Questions and Replies

Filter by year

07 March 2023 - NW222

Profile picture: Breedt, Ms T

Breedt, Ms T to ask the Minister of Water and Sanitation

(1)What are the reasons that work continued on the multi-million Rand sewage project in Deneysville, Free State, while the existing license has apparently expired in 2021; (2) whether there is a new application to continue the project; if not, what is the position in this regard; if so, what are the relevant details. (3) what are the reasons that public participation (a) was not done before embarking on the project, as is required with a project of this nature, (b) is only scheduled for the end of February, a month before planned completion and (c) is not to be held in the town affected, but in a neighbouring town; (4) whether, considering that the project is set to be completed by end of March 2023, posts have been advertised for the plant; if not, why not; if so, (a) which posts have been advertised and (b) what are the (i) requirements and (ii) financial implications of the positions; (5) whether the plant will open on time with relevant employed staff; if not, why not; if so; what are the relevant details?

Reply:

(1) The construction of the Refengkgotso (Deneysville) Wastewater Treatment Works (WWTW) commenced in 2017/2018 with the Contractor appointed on 9 May 2017, after the Water Use License (WUL), (14/C83M/CFGI/4681) was issued on 7 June 2016. The effluent discharge pipeline was constructed in 2017 and halted in 2017 when it was at 95% towards completion. At the time, the outstanding scope of work included the construction of the discharge end and the connection to the WWTW.

The WUL which expired and for which a new application is in process, is for the discharging of treated effluent into a water course, not for the construction of the WWTW. Currently, no effluent from the Refengkgotso (Deneysville) WWTW is being discharged into either the Vaal Dam or the Vaal River. Furthermore, no treated effluent will be discharged from the Refengkgotso WWTW before a WUL is in place.

(2) An application for the WUL which expired on 7 June 2021, was submitted, and is expected to be finalised by 31 May 2023. It should be noted that a Public Participation Process is not required for an application for a previously authorized WUL. However, a public participation meeting is scheduled to be held at the Deneysville Municipal Offices on 23 February 2023 at 17h00.

(3)(a) A Public Participation Process was convened before the project construction commenced at the Deneysville Primary School in Tank Street on 08 October 2015.

(b) The public participation meeting which was scheduled for 28 November 2022 could not take place due to the Engineer on the project passing on. Furthermore, the contractual arrangements between the Consultant and Metsimaholo had to be resolved first before the project activities could resume.

(c) The meeting was originally planned to be held in Refengkgotso, the residential area where the Deneysville WWTW is located. Refengkgotso is not a neighbouring town, it is a residential area of Deneysville. As indicated above, the meeting has been moved to the municipal offices of Metsimaholo in Deneysville.

(4)(a-b) The Deneysville WWTW will be owned and operated by the Metsimaholo LM once the construction and commissioning of the infrastructure has been concluded. Therefore, the municipality will be responsible for the advertising of posts and the appointment of the required personnel to operate the plant. The municipality has reported that it is already in the process of advertising the relevant posts. The DWS is not aware of further relevant details relating to the nature of posts to be advertised, the requirements and financial implications thereof. It is however estimated that the Deneysville WWTW will be classified as a Class C plant which will require the following operational staff according to Government Gazette No. 36958 of 23 October 2013 (Schedule 2 for Class of Works Rating, Schedule IV for Supervisor and Process Controller):

  • 1 x Supervisor - Class V
  • 4 x Process Controllers - Class III

(5) The Department has included an operational contract in the project in terms of which the Consultant will be assisting the Metsimaholo LM with the operation of the plant for 12 months after completion of the project.

---00O00---

07 March 2023 - NW320

Profile picture: Madokwe, Ms P

Madokwe, Ms P to ask the Minister of Water and Sanitation

What role has his department played in holding the mine accountable for (a) the slimes dam disaster in Jagersfontein in the Free State and (b) enforcing safety regulations, given that it has been nearly five months since the disaster and that victims have been left stranded with family members in nearby towns and those whose homes are being rebuilt are receiving subpar housing that is not close to the houses that were destroyed?

Reply:

a) The Department of Water and Sanitation issued a directive to Jagersfontein Developments (Pty) Ltd on 12 September 2022, in terms section 20 (4) of the National Water Act (NWA), 1998 (Act No. 36 of 1998), relating to control of emergency incidents. Amongst other issues, the directive requested rehabilitation of all the affected areas from the Wolwas dam in the Proses Spruit and from the dam downstream towards the confluence of the Proses Spruit and Kromellenboog, downstream to the confluence of the Kromellenboog and Riet Rivers and into the Kalkfontein Dam.

Jagersfontein Developments (JD) has since submitted the incident and rehabilitation plans to DWS which were evaluated and sent back for corrections and improvements in October 2022. The rehabilitation action plan was resubmitted to DWS in December 2022 and DWS has provisionally accepted the plan with the view that the updated plan will be submitted after the appointment of additional specialists as stated in the response submitted in December 2022 by JD. The DWS is continuing to monitor progress regarding the implementation of the rehabilitation plan which has already commenced.

Further to that, the department has opened a criminal case with the Jagersfontein South African Police Services (SAPS) against the owners of Jagersfontein Mine, Jagersfontein Development, for possible contraventions of Section 151(1) (f) & (i) read with Section 1 and 151(2) of the NWA. The DWS is also in the process of appointing a panel of tailings experts to carry out an independent forensic investigation on the causes of failure of the tailings storage facility (TSF). The final report of the forensic investigation will be made available to Parliament.

b) The Department issued a Dam Safety directive in terms of section 118 of the NWA, compelling Jagersfontein Development (JD) to decant Compartment 2 which still had fine tailings to prevent a secondary failure of the TSF. In addition, JD was directed to appoint an Approved Professional Person (APP) to oversee and advise the mine on the safety and operations, including but not limited to decanting Compartment 2 of the TSF at an appropriate rate to safeguard the risk of failure of the said compartment. The APP appointment was approved by the department’s Dam Safety Office (DSO). The DWS is not able to respond on the query regarding the rebuilding of the houses. We are requesting the Honourable Member to redirect this question to the Department of Human Settlements.

---00O00---

15 December 2022 - NW4594

Profile picture: Groenewald, Mr IM

Groenewald, Mr IM to ask the Minister of Water and Sanitation

(1) With reference to his reply to question 2335 on 17 July 2022, what (a) total number of the 77 Water Services Authorities who initially failed to comply with the non-compliance letters issued by his department submitted corrective action plans since June 2022 and (b) are their names. 2) whether he will make a statement on the matter; if not, why not; if so, what are the relevant details?

Reply:

(a) Fifteen (15) of the remaining 77 Water Services Authorities (WSAs) have submitted action plans since June 2022.

(b) The following fifteen (15) WSAs have submitted action plans:

  • O R Tambo DM
  • Sunday River Valley LM
  • Kouga LM
  • Beaufort West LM
  • Kannaland LM
  • Matzikama LM
  • Prince Albert LM
  • Swellendam LM
  • Siyacuma LM
  • Tsantsabane LM
  • Merafong LM
  • Lesedi LM
  • Rand West LM
  • Pixley Ka Seme LM
  • Ngaka Modiri Molema DM

Four (4) additional WSA have requested support for the development of the action plan as indicated below:

  • Msukaligwa LM
  • Thaba Chweu LM
  • Emalahleni LM
  • Chris Hani DM

The Department is implementing the Water Services Improvement Programme (WSIP) to strengthen its support and intervention at municipal level based on actual data or most available data, the aim of the programme is to ensure that support and intervention at municipal level is proactive, consistent, and systematic. There has also been concerted effort with SALGA and MISA to assist remaining municipalities with the development and implementation of the action plans.

---00O00---

15 December 2022 - NW4589

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Water and Sanitation

Considering that the total surface water available in the Republic averages about 49 200 million m3 annually, of which about 4 800 million m3 annually originates from the Kingdom of Lesotho, a portion of this runoff known as the Ecological Reserve needs to remain in the river in order to maintain the natural environment along the watercourse, (a)(i) what total amount in water bill does the Republic pay to the Kingdom of Lesotho on annual basis and (ii) which areas benefit more from this water agreement, (b)(i) what is the nature of contract between the Kingdom of Lesotho and the Republic regarding water and (ii) by what date will the contract lapse and (c) what is the Republic doing to ease the burden on the Kingdom of Lesotho such that it is self-sufficient on water?,

Reply:

a)(i) The allocated budget for royalties for the period 1 Jan to 31 Dec 2022 is R 1 330 million.

(ii) Article 4 of the Treaty describes the purpose as follows: “The Project shall be to enhance the use of water of the Senqu/Orange River by storing, regulating, diverting and controlling the flow of the Senqu/Orange River and its affluents in order to effect the delivery of specified quantities of water to the Designated Outlet Point in the Republic of South Africa and by utilizing such delivery system to generate hydro-electric power in the Kingdom of Lesotho.” The water is transferred into the Vaal River system to mainly supply water users in Gauteng.

a) The implementation, operations and commitments to deliver water to South Africa from the Lesotho Highlands Water Project (LHWP) are governed by the Treaty of 1986 and its Protocols and the Phase II Agreement of 2011. The purpose of the Treaty and Agreement is to provide the legal basis for the implementation of Phases I and II of the LHWP as well as for the operation and maintenance of infrastructure.

i) There is no date by when the obligations of the Treaty in respect of water deliveries to South Africa will lapse.

ii) There are extensive programs in place as part of Phases I and II, including:

  • Water supply for affected communities
  • Sanitation programs for affected communities.
  • Releases of water from the LHWP tunnel system for purposes of augmenting the Lesotho Lowlands Water Scheme that delivers water to Maseru and urban areas in the lowlands of Lesotho.

---00O00---

15 December 2022 - NW4588

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Water and Sanitation

With reference to the estimation that, based on current usage trends, water demand will exceed availability of economically usable fresh water resources in the Republic by 2025, and in view of the fact that the continuing trend in industrialisation and urbanisation of the population is expected to place further pressure on the Republic’s sources of water supply unless appropriate corrective action is taken, (a) what is his department currently doing to ease the pressure as alluded to, (b) what are the key specific workable strategies to deal with the envisaged water demand and (c)(i) which areas will be the most affected when it comes to water demand and (ii) why?

Reply:

a) The Department of Water and Sanitation (DWS) undertakes planning studies over different planning horizons, to develop interventions that are implemented to ensure water security for the country. These interventions comprise of enablers like governance, financing, human capacity building as well as science and innovation which facilitate implementation of water projects at National, Provincial and District and Local Municipality level.

b) The interventions implemented to ensure water security are contained in the National Water Resource Strategy (NWRS), through which the minister gives effect to the National Water Act, as well as the National Water and Sanitation Master Plan (NWSMP). Additional interventions include the following:

  • Planning and implementing a range of major projects to augment national bulk water resource infrastructure and
  • Establishing the National Water Resource Infrastructure Agency (NWRIA) to finance and implement the large-scale investments in national water resource infrastructure that are required to ensure that South Africa has sufficient bulk water supply now and in future.
  • The department is prioritising increased but sustainable use of groundwater
  • The department is also exploring seawater desalination.
  • Strengthening the department’s its role in supporting and intervening in municipalities where water and sanitation services are failing, in conjunction with provinces, COGTA, National Treasury and SALGA.
  • The Department is updating the National and sectoral Water Conservation and Water Demand Management strategies. This is to ensure effective performance of WCWDM practices by the sector.
  • The DWS has also developed the Water Services Improvement Programme (WSIP) to strengthen its support and intervention at municipal level based on actual data or most available data. The aim of the programme is for the Department to ensure that support and intervention at municipal level is proactive, consistent, and systematic.
  • In line with the WSIP, the department has further established the Water Partnership Office (WPO) within the Development Bank of Southern Africa (DBSA). The WPO has developed five standardized National Programmes for private sector participation in municipal water and sanitation services,
  • One of the five National Programmes within the WPO is Non- Revenue Water (NRW) programme aimed at implementing the Water Conservation and Water Demand Management and cost recovery programme focusing on reducing losses, reducing over consumption, and improving cost recovery

The various studies that inform the NWRS are available on the DWS website, at http://www6.dwa.gov.za/iwrp/projects.aspx, and the National Water and Sanitation Master Plan (NW&SMP) is available at http://www.dwa.gov.za.

c) (i-ii) All provinces are affected by the growing demand for water due to:

  • Demand outstripping supply due to extensive growth of urban settlements
  • Extension of services to previously serviced rural settlements
  • Poor maintenance of ageing infrastructure - at a municipal level - that has also reached the end of its lifespan
  • Non-revenue water is currently sitting at 45.1% (31,9 % is losses through physical leakages)
  • The management of water treatment plants adds to the crisis as many of the municipal treatment plants are operating below average standards and a third are critical based on the Blue Drop reports.
  • Shortage of bulk water (owing to droughts, delayed planning for and delivery of bulk water infrastructure such as dams and associated infrastructure)

---00O00---

15 December 2022 - NW4533

Profile picture: Sithole, Mr KP

Sithole, Mr KP to ask the Minister of Water and Sanitation

Whether his department has any alternative plans put in place to provide (a) rural households and (b) persons with disabilities living in rural areas in KwaZulu-Natal with bulk water supply; if not, why not; if so, what are the details of the alternative plans?

Reply:

The Department of Water and Sanitation is funding various bulk water supply projects which benefit rural househols as well as persons with disabilities in KwaZulu-Natal. The following are the projects which are being implemented in the various municipal areas:

Project name

Municipality

Estimated project cost

No. of beneficiaries

Overall progress

Nongoma BWS

Zululand DM

R822 m

153 236

100%

Greytown BWS

uMzinyathi DM

R523.4 m

27 824

92%

Driefontein BWS

uThukela DM

R536.2 m

204 306

99%

Ngcebo BWS

iLembe DM

R1 096.7 m

585 900

100%

Greater Bulwer BWS

Harry Gwala DM

R339.6 m

113 256

80%

Maphumulo BWS

iLembe DM

R649.9 m

112 320

76%

Mandlakazi BWS Phases 5&6

Zululand DM

R2 988.0 m

279 297

61%

Middledrift BWS

King Cetshwayo DM

R290.9 m

177 576

54%

Greater Mthonjaneni BWS

King Cetshwayo DM

R2 025.5 m

99 612

65%

Greater Mpofana BWS

UMgungundlovu DM

R954.9 m

181 590

87%

uMshwathi BWS

uMgungundlovu DM & iLembe DM

R2 308.7 m

362 682

50%

15 December 2022 - NW4344

Profile picture: Van Zyl, Ms A M

Van Zyl, Ms A M to ask the Minister of Water and Sanitation

Whether his department has been informed of any sewerage spillages into natural water sources in the (a) Walter Sisulu Local Municipality and (b) Senqu Local Municipality; if not, what is the position in this regard; if so, what (i) is the location of each spillage and (ii) steps has his department taken to assist the Joe Gqabi District Municipality to (aa) fix the infrastructure and (bb) rehabilitate the specified natural water sources?

Reply:

a)  The Department is aware of the sewage challenges experience by Joe Gqabi District Municipality. There have been long standing issues at the Burgersdorp sewage system and Steynsburg Waste Water Treatment Works (WWTW). The status regarding progress made is as follows:

  • Contractors are currently at both sites
  • Progress made at the Burgersdorp WWTW is at 95%
  • Progress made with the Steynsburg sewage system is at 80%.

b) (i) Site of pollution

(ii) (aa) steps taken by department to assist through repairs to the infrastructure

(ii) (bb) rehabilitation of the specified natural water sources

Burgersdorp - pollution of the Stormberg Spruit

  • A directive had been issued and funding support was received from Municipal Infrastructure Grant and funding from Joe Gqabi DM
  • Four (4) sewage pumpstations repaired as follows:
    • repairs completed on 2 pumpstations
    • repairs ongoing on 2 pumpstations and are in final stages, planned for completion at end November 2022.

Rehabilitation included removal of any paper and solids for burial and application of chloride of lime to disinfect affected areas

Steynsburg Sewage Ponds in the catchment of Teebus stream

  • Funding support from Water Service Infrastructure Grant
  • Project is about 80% complete with all work due to be completed by end February 2023.

Rehabilitation includes removal of papers, disinfection with chloride of lime and natural attenuation

Sterkspruit Activate Sludge Works

Sterkspruit Activate Sludge Works have been repaired and the works are functioning normally, thus removing the overload on the Sterkspruit Pond System

Overflow from the Sterkspruit sewage ponds had impacted the Sterkspruit Stream, but has since been resolved

---00O00---

15 December 2022 - NW4283

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Water and Sanitation

What is the (a) current backlog in the provision of water and sanitation in the rural areas across the Republic and (b) total cost attached to the backlog?

Reply:

a)  The current backlog in the provision of water in the rural areas across the Republic are as follows:

  • Out of a total of 19,368,622 households in South Africa 6 396 431 households are classified as rural households
  • Out of 6 396 431 rural households 4 760 182 (86%) have access the RDP level of service for water
  • Out of 6 396 431 rural households, only 3 157 091 (61%) have access to a reliable supply of water

b) A funding gap of R33 billion must be closed each year for the next 10 years, through improved revenue generation and reduced costs based on a study undertaken through the National Water and Sanitation Master Plan (NWSMP). The department has embarked on the development of a Five-Year Reliable Water and Sanitation Services Delivery Implementation Plans that will, after completion, produce a pipeline of projects for each WSA with the associated costing. National grant funding programmes will be aligned with these needs.

---00O00---

15 December 2022 - NW4595

Profile picture: Bryant, Mr D W

Bryant, Mr D W to ask the Minister of Water and Sanitation

(1)With reference to Part 9 of the National Water Act, Act 36 of 1998, what measures has his department taken to ensure the compliance of water treatment package plants with their licensing conditions in each province in (a) 2018, (b) 2019, (c) 2020, (d) 2021 and (e) 2022; (2) what (a) punitive measures have been taken against those who contravened their licence agreements in the specified period in each province and (b) additional measures is his department taking to ensure that privately owned water treatment package plants are licensed and compliant for the period under review in each province?

Reply:

1. Part 9 of the National Water Act, Act 36 of 1998 addresses the review and renewal of licenses, and the amendment and substitution of conditions of licenses. Water treatment package plants, either for drinking water treatment or for wastewater treatment, usually have a design capacity range of between 1-2ML/day. This capacity range is small and has a low impact compared to the conventional larger water treatment plants. Lower-risk water uses are generally authorized through Part 6: Section 39 (General Authorization) of the National Water Act, depending on the sensitivity of the catchment. Licenses are issued for larger treatment plants. The table below provides a summary of regulatory requirements for wastewater treatment and drinking water treatment package plants.

Legal requirements

Wastewater Treatment Package plants

Drinking Water Treatment Package Plants

Water use authorization required

  • General Authorization for wastewater discharge.
  • Most privately owned plants discharge into the municipal sewer systems and are regulated through Municipal by-laws.
  • General Authorization for abstraction
  • Storage (where applicable)

Common design Capacity

1-2Ml/day

1-2ML/day

Monitoring for compliance

Part of Green Drop

Part of Blue Drop

Mandate

DWS and Water Services Authorities

DWS and Local government as Water Services Authorities

Measures taken by the Department to ensure the compliance of water treatment package plants between 2018 and 2022 include:

  1. The revival of the Green and Blue Drop certification programs
  2. Monitoring action plans for non-compliant systems
  3. Enforcement actions
  4. Review of the norms and standards for drinking water
  5. Confirmation of general authorizations for new plants
  6. As part of the license conditions, package plants are mandated to submit to the DWS, monthly water quality analysis which should be in line with the applicable limits for each parameter analysed.

2. (a) The Water Services Act, Act 08 of 1997 does not make provisions for penalties. However, the DWS carries out audits to monitor compliance and implements enforcement actions to rectify contraventions related to non-compliance to the conditions of authorizations.

(b) The Department is monitoring compliance of package plants as provided for by legislation. The department undertakes audits as part of regular monitoring activities and where there is non-compliance, issues Notices or Directives to the owners of the package plant. In some cases, investigations are triggered by reports of suspected cases of non-compliance which are followed up by the department. Where administrative enforcement actions are implemented, the department monitors to ensure full compliance with the conditions of authorisations.

The table below indicates instances where the Department has undertaken compliance monitoring audits and investigations triggered by complaints received and the subsequent administrative actions to address non-compliances.

Table 2: Compliance monitoring audits, inspections conducted, and enforcement actions taken

Activities and administrative action taken

Activities and administrative action taken

Activities and administrative action taken

Activities and administrative action taken

Activities and administrative action taken

2022

2021

2020

2019

2018

3x audits and 1x inspection undertaken in Eastern Cape i.e. Mzimvubu / Tsitsikamma

4x audits and 1x inspection undertaken in Eastern Cape i.e. Mzimvubu / Tsitsikamma

1x inspection and 2x audits undertaken in Eastern Cape i.e. Mzimvubu / Tsitsikamma

2x inspections and 1x audit undertaken in Eastern Cape i.e. Mzimvubu / Tsitsikamma

2x inspections undertaken in Eastern Cape i.e. Mzimvubu / Tsitsikamma

2x Notices issued

3x Notices issued

2x Notices issued

3x Notices issued

2x Notices issued

-

3x Directives issued

1x Directive issued

-

-

Complaints received and investigated

1x complaint received from Limpopo regional office (i.e. Limpopo WMA)

2x complaints received from North- West and KwaZulu Natal regional office (i.e. Pongola/Mtamvuna and Limpopo WMA)

3x complaints received from North-West and Limpopo regional office (i.e. Limpopo WMA)

-

-

1x Investigation undertaken

2x investigations undertaken

3x investigations undertaken

-

-

1x Notice issued

Both cases were recommended for administrative action

3x Directives were issued

-

-

---00O00---

06 December 2022 - NW4233

Profile picture: Buthelezi, Ms SA

Buthelezi, Ms SA to ask the Minister of Water and Sanitation

(1)Whether his department has implemented plans to address the serious risks posed to the citizens by the failing water treatment plants in KwaZulu-Natal; if not, why not; if so, what are the relevant details. (2) whether his department will make funds available for the reconstruction of critical infrastructure which was damaged in the floods; if not, why not; if so, what are the relevant details:

Reply:

1.  The Department of Water and Sanitation (DWS) conducted the Green Drop assessment during 2021/22 which culminated in the release of the National Green Drop Report 2022. In KZN, 14 Water Services Authorities (WSAs) and 147 wastewater systems were audited with the following results

  • 47 of the wastewater systems in KwaZulu Natal were found not to be measuring their wastewater inflows
  • 7 wastewater systems were overloaded
  • 76 wastewater systems received Green Drop Score of above 50% (meaning what?)
  • 20 wastewater systems were found to be at critical state
  • 3 wastewater systems received Green Drop certification (scored minimum of 90%).

To mitigate the risk, the DWS has implemented several interventions including the issuance of non-compliance letters, notices, and directives to minimize the pollution impacts on the water resources. In addition, corrective action plans and green drop improvement plan templates have been issued to the WSAs to ensure that their Councils commit funds to address the gaps identified in the assessments. The DWS is assisting the WSAs to compile corrective action plans and improvement plans which will need to be implemented within predetermined timeframe and monitored by the department.

The department has also implemented measures to address pollution of water resources in KwaZulu-Natal. These include:

  1. Undertaking routine inspections of sewerage infrastructure (wastewater treatment works, pumpstations and pipelines).
  2. The DWS also follows up on pollution issues reported by the public.
  3. In cases where pollution to water resources is observed, administrative processes are taken against the non-compliant municipalities in the form of Non-compliance Notices and/or Directives
  4. The Department has also established Water Resource Protection Technical Committee Meetings to address the issues of pollution in different districts

Following the floods in April 2022, the DWS has also implemented the following interventions to support affected municipalities in KZN:

  1. Availed the team of Engineers and Scientists to assist with the assessments of the damage to the water and sanitation infrastructure
  2. Officials of the department participate in WAR Room meetings where repairs of infrastructure and progress thereof are discussed
  3. Three (3) Directives were issued, on 13 May 2022, to the municipalities which were severely affected, namely: eThekwini Metropolitan Municipality, ILembe District Municipality (DM) and Ugu DM
  4. Established the WAR Room through the Minister to address issues of water provisioning and sanitation, as well as to discuss challenges that the municipalities might be facing such as funding, human resources, amongst others

(2) The DWS assisted the Ethekwini, Ugu and Ilembe District Municipalities by reallocating R65 million funding to support immediate relief measures which included provision water tankers for 3 months. The DWS also conducted assessments of the damaged infrastructure and submitted a funding application for disaster relief funding to the National Disaster Management Centre. Damaged infrastructure can also be repaired through reprioritising of the DWS Water and Sanitation Infrastructure Grant (WSIG).

---00O00---

06 December 2022 - NW4417

Profile picture: Engelbrecht, Mr J

Engelbrecht, Mr J to ask the Minister of Water and Sanitation

What is the (a) total number of staff employed and/or provided as departmental support in (i) his and (ii) each of the Deputy Ministers’ private offices and (b)(i) job title and (ii) annual remuneration package of each specified person?

Reply:

The details for the staff employed in offices of the Minister and Deputy Ministers are indicted in the table below:

(i) Office of the Minister (9 officials)

JOB TITLE

ANNUAL REMUNERATION PACKAGE

2 x Ministerial Advisors SL 15 and 16

R1 791 978 all-inclusive package

R2 330 121 all-inclusive package

1 x Chief of Staff SL 14

R1 308 051 all-inclusive package

1 x Private and Appointment Secretary SL 13

R1 105 383 all-inclusive package

1 x Media Liaison Officer SL 13

R1 105 383 all-inclusive package

1 x Parliamentary and Cabinet

Support SL 13

R1 105 383 all-inclusive package

1 x Community Outreach Officer SL 11

R766 584 all-inclusive package

1 x Assistant Appointment and Admin Secretary SL9

R393 711 per annum

1 x Receptionist SL 5

R269 214 per annum

2 x Household Aide SL3

R128 166 per annum

R128 166 per annum

(ii) Office of Deputy Minister (9 officials)

JOB TITLE

ANNUAL REMUNERATION PACKAGE

1 x Head of Office SL 13

R1 105 383 all-inclusive package

1 x Private and Appointment Secretary SL 12

R1 070 169 all-inclusive package

1 x Technical Specialist SL13 (Previous Dispensation)

R1 105 383 all-inclusive package

1 x Parliamentary and Cabinet

Support SL 11

R766 584 all-inclusive package

1 x Community Outreach Officer SL 11

R766 584 all-inclusive package

1 x Driver/Messenger SL 4

R181 599 per annum

1 x Receptionist SL 5

R285 735 per annum

2 x Household Aide SL 3

R128 166 per annum

R128 166 per annum

1x Registry Clerk SL 5 (Previous Dispensation)

R269 214 per annum

(iii) Office of Deputy Minister (8 officials)

JOB TITLE

ANNUAL REMUNERATION PACKAGE

1 x Head of Office SL 13

R1 105 383 all-inclusive

1 x Technical Specialist SL 13 (Previous dispensation0

R1 105 383 all-inclusive package

1 x Private and Appointment Secretary SL 12

R908 502 all-inclusive package

1 x Community Outreach Officer SL 11

R766 584 all-inclusive package

1 x Driver/Messenger SL 4

R181 599 per annum

1 x Food Services Aide SL2

R128 166 per annum

1 x Receptionist SL5

R269 214 per annum

2 x Household Aide SL3

R128 166 per annum

R128 166 per annum

1x Registry Clerk SL 5 (Previous Dispensation)

R269 214 per annum

---00O00---

06 December 2022 - NW4284

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Water and Sanitation

What (a) total number of resolutions has he implemented since the two-day National Water and Sanitation Summit that was held from 18 to 19 February 2022 at Gallagher Convention Centre in Midrand and (b) are the details of the specific milestones that have been reached?

Reply:

 

 

The Summit was intended to engage various stakeholders together to form partnerships and identify lasting solutions to the water and sanitation problems facing the country. Based on the outcomes of the summit, the department is working together with SALGA, NT and COGTA, DWS will lead the development and implementation of a range of inter-related and coordinated support measures and interventions. Broadly, interventions that have been identified and are being implemented include the following:

    1. Strengthening and extending the roles, responsibilities, and capacity of water boards so that they are able to provide water and sanitation services in instances where municipalities are failing to provide the services
    2. Reviewing the geographical boundaries of the water boards to make them more sustainable, this already started with the disestablishment of Sedibeng Water
    3. Increasing involvement of private sector financing and management in municipal water and sanitation services through public-private partnerships
    4. Strengthening regulatory interventions based upon the results of monitoring mechanisms such as Blue Drop, Green Drop and No Drop
    5. Strengthening the National Norms and Standards (Water Services Act) and put in place a framework to guide the provision of sanitation services
    6. Introducing longer term interventions through WISP and the DDM programmes, through for example, taking over the management of wastewater treatment works from municipalities for a longer prescribed period where there is continued non-compliance with norms and standards
    7. More effectively link the allocation of municipal water and sanitation grants to enable support and interventions
    8. Use DWS internal construction capacity for rapid deployment to address urgent intervention needs
    9. Put in place appropriate financing frameworks and mechanisms for support and interventions
    10. Improve coordination and linkages of the interventions made in terms of sections of various legislation

Some of these measures will start to have an impact on municipal water and sanitation services in the short term (within 3 months) and others will yield results in the medium term.

---00O00---

06 December 2022 - NW4271

Profile picture: Mogale, Mr T

Mogale, Mr T to ask the Minister of Water and Sanitation

What (a) has he found to be the prevalence of water shedding across the Republic and (b) are the causes thereof?

Reply:

a)  Many of the provinces across the country have been impacted by a combination of factors including:

  • Additional demand and water use owing to population growth and extension of services to previously unserved rural communities
  • Prolonged droughts in certain parts of the country
  • Shortage of bulk water (owing to droughts, delayed planning for and delivery of bulk water infrastructure such as dams and associated infrastructure)
  • Challenges with municipal water service delivery
  • Poor maintenance of municipal infrastructure that results in frequent pipe bursts and unreliable supply of water

To prevent more widespread water interruptions across the country, municipalities have resorted to water restrictions or even scheduled water interruptions to ensure that communities are able to access some water for a few hours.

b) The main challenges impacting reliability of water supply are due to:

  • Demand outstripping supply due to extensive growth of urban settlements
  • Extension of services to previously unserviced rural settlements
  • Poor maintenance of ageing infrastructure - at a municipal level - that has also reached the end of its lifespan
  • Non-revenue water is currently at 45.1% (31,9 % refers to losses through physical leakages)
  • The management of water treatment plants adds to the crisis as half of our treatment plants are operating below average standards and fully a third are critical based on the Blue Drop reports
  • Ongoing load shedding by ESKOM during the last year has also intensified the situation by impeding the ability of Water Boards and municipalities to pump water into reservoirs. This resulted in water levels in the reservoirs being too low to gravity-feed water to high-lying areas across the country.

To address the challenges outlined above, the Department of Water and Sanitation (DWS) is in the process of:

  • Planning and implementing a range of major projects to augment national bulk water resource infrastructure and
  • Establishing the National Water Resource Infrastructure Agency (NWRIA) to finance and implement the large-scale investments in national water resource infrastructure that are required to ensure that South Africa has sufficient bulk water supply now and in future.
  • Strengthening its role in supporting and intervening in municipalities where water and sanitation services are failing, in conjunction with provinces, COGTA, National Treasury and SALGA.
  • The DWS has also developed the Water Services Improvement Programme (WSIP) to strengthen its support and intervention at municipal level based on actual data or most available data. The aim of the programme is for the Department to ensure that support and intervention at municipal level is proactive, consistent, and systematic.
  • In line with the WSIP, the Department has further established the Water Partnership Office (WPO) within the Development Bank of Southern Africa (DBSA). The WPO has developed five standardized National Programmes for private sector participation in municipal water and sanitation services, to make it easier, quicker, and cheaper for municipalities to enter into partnerships, without having to ‘reinvent the wheel’ for each partnership. One of the five National Programmes within the WPO is Non- Revenue Water (NRW) programme aimed at implementing the Water Conservation and Water Demand Management and cost recovery programme focusing on reducing losses, reducing over consumption, and improving cost recovery

---00O00---

06 December 2022 - NW4259

Profile picture: Siwisa, Ms AM

Siwisa, Ms AM to ask the Minister of Water and Sanitation

With reference to his reply to question 753 for oral reply on 2 November 2022 pertaining to the eradication of pit toilets and bucket system and the completion of the projects, and noting that the residents of ward 17 in the Sol Plaatje Local Municipality are still left with half-built and/or dismantled toilets, leaving them with no privacy if they need to relieve themselves, (a) what are the reasons that the project is still not completed and (b) on what date will it resume as residents have been left stranded?

Reply:

The sanitation project in the Sol-Plaatje Local Municipality, Ward 17 is being implemented in Phases. Phase 1 which provided 368 toilets was completed in September 2022. The issues listed above were primarily due to theft of material. In addition, the project was also affected by poor workmanship by the contractor compounded by labour unrest during implementation. The municipality is in the process of developing a business plan for funding of further phases.

---00O00---

06 December 2022 - NW4257

Profile picture: Mokgotho, Ms SM

Mokgotho, Ms SM to ask the Minister of Water and Sanitation

(a) What plans has his department put in place to provide the community of Xikukwane in Giyani with water and (b) how long is it going to take his department to implement the plan?

Reply:

The Xikukwane village receives water from Giyani Water Treatment Works (WTW) through pipeline F1. The design capacity of the Giyani WTW is 30Ml/d.

The Department of Water and Sanitation (DWS) has two (2) projects funded under Regional Bulk Infratructure Grant (RBIG), which are currently under construction in the Greater Giyani Local Municipaty (LM), and the Xikukwane village is one of the beneficiaries. The projects are implemented to address bulk water challenges in the Greater Giyani LM. Lepelle Northern Water was appointed as the Implementing Agent for both projecs which are comprised of the Nandon-Nsami pipeline project; and the Giyani Water Services project.

The background and progress of the projects is indicated below:

The need for the transfer of water from the Nandoni Dam to Giyani arose because of the critical shortage of water in Giyani due to low water levels in the Middle Letaba and Nsami Dams cause by recurring drought.

The department’s intervention is meant to accelerate water services provision in the distressed area of Mopani DM by conveying bulk water from Nandoni Dam to Nsami Water Treatment Works.

Overall progress at end of (November?) 2022 is estimated to be 62,78% with a projected completion date of 22 June 2023.

The Giyani Water Services projects are intended to accelerate water services provision to 55 villages in Giyani and include:

  • Overall refurbishment and upgrade of Giyani WTW.
  • The Giyani reticulation and household connection project. The envisaged completion date is October 2023

The two projects will be implemented by the Mopani DM once procurement processes are completed.

 

---00O00---

06 December 2022 - NW4256

Profile picture: Mokgotho, Ms SM

Mokgotho, Ms SM to ask the Minister of Water and Sanitation

What intervention has been made to ensure that the defects in the newly built houses of the community of Budeli, in Nandoni in the Vhembe district, who have been relocated from their area where the Nandoni dam is built are fixed?

Reply:

The Budeli village is one of the five villages that the residents were affected by the construction of the Nandoni dam. A budget of R 62milllion has been set aside to repair the defects of all the five villages for the 2022/2023 financial year and the project is set to be completed by March 2023.

There were 100 houses that were found to have defects at the Budeli Village. Progress made by the Department is indicated below:

  • Sixty-six (66) houses have been repaired
  • One (1) house re-built due to the extent of the defects
  • Repairs to the remaining thirty-three (33) houses will be completed by 15 December 2022.

---00O00---

06 December 2022 - NW4107

Profile picture: Msane, Ms TP

Msane, Ms TP to ask the Minister of Water and Sanitation

What steps has his department taken to intervene in the water crisis in the Nkowankowa area of the Greater Tzaneen Local Municipality, where reservoirs have been left unmaintained with the homeless using tanks to relieve themselves?

Reply:

Water supply challenges in Nkowankowa are a result of tampering with valves on the outlet of the command reservoir and the bypass line to facilitate illegal connections. This caused low pressure on the bulk pipeline resulting in supply interruptions in some areas of Nkowankowa as water could not reach the furthest points of distribution.

The Mopani District Municipality together with the Greater Tzaneen Local Municipality have identified all the valves that needed to be repaired to supply water at Nkowankowa Township and Dan village.

With the assistance of Mokgolobotho Cooperation, which is a community-led structure, all unauthorized connections to the rising main were identified and removed. Water supply to Mokgolobotho settlement has since been restored. Leakages caused by unauthorised connection were identified and repaired.

---00O00---

06 December 2022 - NW4254

Profile picture: Ceza, Mr K

Ceza, Mr K to ask the Minister of Water and Sanitation

(1)What (a) impact has load shedding had on the proper functioning of water purification plants in the Republic and (b) is the extent of the impact on the ability to make water available to some drought-stricken areas in the Republic; (2) whether he has engaged with Eskom to ensure that critical water infrastructure is exempted from load shedding; if not, why not; if so, what are the further, relevant details?

Reply:

1 a) Severe load shedding affects the ability of Water Boards and Water Service Authorities (WSAs) to pump water into their reservoirs. This resulted in the water levels in the reservoirs being too low to gravity-feed water to high-lying areas. As a result, several high-lying areas have been without water for prolonged periods.

The Department of Water and Sanitation (DWS) has not quantified the amount of production downtime across the country. However, most WSAs have a contingency plan to ensure continuity of water supply. Water Boards and WSAs experienced several electrical and mechanical failures, which also contributed to the difficulty in filling the reservoirs. Some of these failures may have been a result of damage to equipment caused by the frequent load shedding.

Using the Eskom schedule of loading shedding, Treatment Plants can be closed in phases to prevent sudden shutdown of processes at the start of loadshedding that damage infrastructure. It is also possible to store additional treated water in preparation to cater for downtime at the plant. The operating philosophy is to maintain the reservoir levels between 60-80%. This targeted range will enable the system to be resilient and respond to any challenges.

1 b) All treatment plants, rely on electricity in one way or another, and where affordable, WSAs are encouraged to ensure continuous water provision through additional storage such as reservoirs and static tanks or alternative energy supply to cater for loadshedding.

2 The Water Boards, as water service providers to various WSAs, have taken different approaches to manage the impact of ESKOM’s loadshedding on their ability to provide reliable bulk water supply services to users, including:

  • Engaging with the provincial government leadership and ESKOM to negotiate and facilitate for exemption on water infrastructure from frequent load-shedding.
  • Filing applications with ESKOM for exemption in terms of Eskom Regulation NRS048-9. Some applications for exemption have been successful while some have not been due to technical reasons advanced by ESKOM and some are still waiting for outcomes to the applications.
  • Water Boards such as Bloem Water, Rand Water, Umngeni Water, Lepelle Water and Magalies Water are operating water infrastructure that is exempt from loadshedding and are mostly able to continue with operations during loadshedding.
  • Entities such as Bloem Water, Rand Water, Umngeni Water, Lepelle Water and Magalies Water are operating water infrastructure that is exempt from loadshedding and are mostly able to continue with operations.
  • Where affordable, some of the entities have procured back-up generators to continue with operations even when there is loadshedding.

Some municipalities have been able to exempt some of their water and sanitation facilities from load shedding, but this is often not possible because it would require exempting whole areas from load shedding, which in turn would result in Eskom’s load shedding requirements not being met.

---00O00---

24 November 2022 - NW4086

Profile picture: Mokgotho, Ms SM

Mokgotho, Ms SM to ask the Minister of Water and Sanitation

On what date will adequate water supply be provided for the community of Boitekong in Ward 19 in Rustenburg, North West province, which is currently without water and has been requesting the municipality to make provisions since 2016?

Reply:

Due to the current high-water demand exacerbated by the ongoing power outages, the Rustenburg Local Municipality (LM) is implementing water demand management in the greater Boitekong areas including the new stands (Extention 13). According to the Rustenburg LM, the water restrictions schedules have been communicated with relevant Ward Councillors and the affected residents.

In the medium to long term, funds have been made available through the Municipal Infrastructure Grant (MIG) administered by Department of Cooperative Government and Traditional Affairs (COGTA) for the upgrade of Bospoort Water Treatment Works from the 12ML/d to 24ML/d. I have been advised that the outstanding mechanical and electrical works are envisaged to be completed by the end of June 2023. This will ensure adequate water provision to the Boitekong area.

---00O00---

23 November 2022 - NW3872

Profile picture: Myburgh, Mr NG

Myburgh, Mr NG to ask the Minister of Water and Sanitation

With reference to the Auditor-General’s 2021-22 report on his department, (a) what steps are being taken to design and implement a National Action Plan to address the growing scourge of water losses in various parts of the Republic and (b) by what date will the specified plan be ready for implementation?

Reply:

a)  The Department acknowledges the deterioration of water and sanitation services at municipal level. The decline includes a growing trend on water losses and water use inefficiencies. In response to the decline, and along with the requirement by AGSA to develop an action plan, the Department is putting in place a Water Services Improvement Programme (WSIP) to strengthen its support and intervention at municipal level based on actual data or most available data. The aim of the programme is for the Department to ensure that support and intervention at municipal level is proactive, consistent, and systematic as opposed to current ad-hoc approach. In line with the WSIP, the Department has further established the Water Partnership Office (WPO) within the Development Bank of Southern Africa (DBSA). The WPO has developed five standardized National Programmes for private sector participation in municipal water and sanitation services, to make it easier, quicker, and cheaper for municipalities to enter into partnerships, without having to ‘reinvent the wheel’ for each partnership. One of the five National Programmes within the WPO is Non- Revenue Water (NRW) programme aimed at implementing the Water Conservation and Water Demand Management and cost recovery programme focusing on reducing losses, reducing over consumption, and improving cost recovery

b) A part of the programme is being implemented; the intention is to roll it out Nationally in the next Financial Year (2023/24 FY)

---00O00---

21 November 2022 - NW3905

Profile picture: Mokgotho, Ms SM

Mokgotho, Ms SM to ask the Minister of Water and Sanitation

What plans did his department put in place to provide adequate water to residents of new stands at Boitekong in Rustenburg?

Reply:

Due to the current high water demand exacerbated by the ongoing power outages, the Rustenburg Local Municipality (LM) is implementing water demand management in the greater Boitekong areas including the new stands (Extention 13). According to the Rustenburg LM, the water restrictions schedules have been communicated with relevant Ward Councillors and the affected residents.

In the medium to long term, funds have been made available through Municipal Infrastructure Grant (MIG) administered by Department of Cooperative Government and Traditional Affairs (COGTA) for the upgrade of Bospoort Water Treatment Works from the 12ML/d to 24ML/d. I have been advised that the outstanding mechanical and electrical works is envisaged to be completed by the end of June 2023. This will ensure adequate water provision to the Boitekong area.

---00O00---

21 November 2022 - NW3904

Profile picture: Mokgotho, Ms SM

Mokgotho, Ms SM to ask the Minister of Water and Sanitation

(1)By what date will his department install a sewer system for residents of Ward 40, Extension 8 in Rustenburg, who had put in a request for installation to his department in 2019 without any response to their application to date. (2)whether he will furnish Mrs S M Mokgotho with the relevant details regarding the installation; if not, why not; if so, on what date?

Reply:

The extension 8 housing development in Ward 40 was funded by the erstwhile Department of Housing in 2005. Two hundred (200) houses were constructed and handed over to beneficiaries. Whereas there was a sewer pipeline network in the areas at the time of construction, some of the houses were not connected to the sewer pipe network. According to the Municipality, the area is fully equipped with a sewerage conveyances system, the only challenge that exists is to connect the few houses to the sewer line.

The Department of Water and Sanitation allocated R70 million from the Water Services Infrastructure Grant for 2022/23 to the Rustenburg Local Municipality. The municipality indicated that it has prioritised the refurbishment of the Boitekong sewer pump station and the outfall sewer. The current budget allocation for WSIG is fully committed, however, the municipality is in the process of reprioritising the Municipal Infrastructure Grant to address the Boitekong sanitation backlog.

---00O00---

18 November 2022 - NW3913

Profile picture: Tafeni, Ms N

Tafeni, Ms N to ask the Minister of Water and Sanitation

(a) What is the total number of water boards that dissolved in the current financial year and (b) on what date will the new boards be appointed?

Reply:

a)  To date, two (2) Boards for Water Boards, have been dissolved. The Board for Amatola Water was dissolved in March 2022 and the Interim Board of Sedibeng Water was automatically dissolved as a result of the disestablishment of Sedibeng Water in July 2022.

b) The process of appointing the new board for Amatola Water has commenced, and it should be finalised before the end of the current financial year.

---00O00---

18 November 2022 - NW3577

Profile picture: Buthelezi, Ms SA

Buthelezi, Ms SA to ask the Minister of Water and Sanitation

(1)Given that parts of the Republic are experiencing water shedding at present, what significant progress has been made in the water sector under Operation Vulindlela in relation to the water shortages in certain parts of the Republic; (2) (a) how has his department contributed to modernising and transforming the outdated bulk water infrastructure of the Republic and (b) what proactive measures are in place to prevent water shedding from becoming a semi-permanent fixture similar to load shedding in South African households?

Reply:

1. The main purpose of the Operation Vulindlela is to accelerate the implementation of structural reforms and support economic recovery, as such the Department of Water and Sanitation (DWS) is implementing following projects under Operation Vulindela:

  • Revival of the Green Drop, Blue Drop and No Drop Assessment Programme: The asessment programmes are aimed at improving the wastewater quality, water supply quality and water use efficiency in all the 144 Water Service Authorities. The Department published the Green Drop report in March 2022 and will publish the Blue and No Drop programme in next financial year.
  • Improvement of Water Use Authorisation: The Department is revising the water use authorisation process with the intention being able to process all water use applications within 90 days to ensure economic development and access to water.
  • Independent Economic Regulator: The Minister has appointed the Regulator Commission for the period of 3 years. The aim of an independent economic regulator to regulate tariffs, standards, and performance in the water services sector.

2. (a)The department is funding refurbishment of infrastructure through its Water Services Infrastructure Grant (WSIG) programme. Regional Bulk Infrastructure Grant (RBIG) facilitates achievement of targets for access to bulk water and sanitation through successful execution and implementation of bulk projects of regional significance. The main purpose of this grant amongst others is to:

  • To develop new, refurbish, upgrade and replace ageing bulk water and sanitation infrastructure of regional significance that connects water resources to infrastructure serving extensive areas across municipal boundaries or large regional bulk infrastructure serving numerous communities over a large area within a municipality
  • To implement bulk infrastructure with a potential of addressing Water Conservation and Water Demand Management (WC/WDM) projects or facilitate and contribute to the implementation of local WC/WDM projects that will directly impact on bulk infrastructure requirements. This is achieved through project planning, where diversification of water resources is encouraged as part of calculating the Water Balance to ensure sustainability of supply

(b)The Department undertakes planning studies over different planning horizons, to derive interventions that are implemented to ensure water security for the entire country. These interventions cover the enablers like governance, financing, human capacity building and science and innovation which facilitate implementation of water projects at National, Provincial and District and Local Municipality level. The interventions implemented for our water security are contained in the National Water Resource Strategy (NWRS), the instrument by which the Minister gives effect to the National Water Act, as well as the master plans that emanate from the NWRS. The various studies informing the NWRS are available on the DWS website, at http://www6.dwa.gov.za/iwrp/projects.aspx and the National Water and Sanitation Master Plan (NW&SMP) is available at http://www.dwa.gov.za

The DWS also monitors the capacity of municipalities to deliver water and sanitation through the Municipal Strategic Self-Assessment (MuSSA); a web-based system that enables municipalities to conduct their self-assessment on critical aspects service delivery performance. The outcomes of the assessment position the Department and other sector role players to provide targeted support to local government through various support and intervention programmes aimed at improving services delivery, governance and business health. Priority areas are identified and addressed through the development of a Municipal Priority Action Plan (MPAP).

Lastly, Five-Year Reliability Water and Sanitation Plans will soon be rolled out in all forty-four (44) District Municipalities. The plans are meant to:

  • Ensure sustainable and reliable water services with the service-standard yardstick that has a 100% compliance to functionality, water security and effective governance to maintain appropriate levels of service delivery
  • Conduct primary situational assessments of the water services and infrastructure supply conditions and classify each situation into a reliability category. The solution options are then integrated to proposed projects, specifically integrating all funding programmes to alleviate new infrastructure needs and achieve reliability of water services.

Recently the Department has developed the Water Services Improvement Programme (WSIP). The aim of WSIP is to guide Department in initiating and leading the national support and regulatory interventions to reverse the decline in the provision of water and sanitation services in all municipalities. The programme consists of the following four key elements:

  • In terms of the Water Services Act, DWS will issue updated and more comprehensive norms and standards for water and sanitation services.
  • DWS will publish a National Regulatory Dashboard showing the extent of compliance with national norms and standards for water services for all Water Service Authorities, drawing on existing monitoring information, including from the Drop reports, NT, and COGTA reports (no new additional reporting requirements will be put on municipalities).
  • DWS will develop rolling regional support and intervention plans based on the evidence in the Regulatory Dashboard, managed by its regional offices, in consultation with provincial governments, municipalities and DDM structures.
  • The support and intervention plans will draw on a range of support programmes which will be developed at national level.

---00O00---

18 November 2022 - NW3801

Profile picture: Van Dyk, Ms V

Van Dyk, Ms V to ask the Minister of Water and Sanitation

(1) (a) What water sources do the mining companies in Koingnaas in the Kamiesberg Local Municipality use for mining purposes and (b) do the mining companies use any water from the Somnaas-Noup aquifer in the specified municipality. (2) what companies applied for water licences in the specified area. (3) whether any water licences were granted to the mining companies; if not, why not; if so, (a) to whom were the licences granted, (b) what were the specifications of each licence and (c) on what date was each licence granted. (4) whether an environmental impact study has been conducted to ensure what the effect of mining will be on the (a) water tables of the area, specifically Somnaas-Noup aquifer and (b) town of Koingnaas; (5) whether he will furnish Mrs V van Dyk with a copy and/or copies of the licence(s) issued; if not, why not; if so, what are the relevant details?

Reply:

1a)  Groundwater is the main source of water for domestic supply in the region. The settlements of Koingnaas, Hondeklip Bay and Samson Bak derive water from the Somnaas Noup aquifer located about 20 km north of Koingnaas. Two boreholes, BH 12 and BH 14, are currently in use. A third borehole, BH15 adjacent to BH 12, is equipped and used as a standby borehole.

b) the mining companies use water from the Somnaas-Noup aquifer in the specified municipality.

(2) West coast Resources Pty Ltd: Namaqualand Mine applied for a water use licence which was issued on 23 June 2017. Conditions of the licence includes the following:

  • Monitoring: The licensee should establish ground water network monitoring within 1 year from the date of issuance of licence.
  • Water Conservation and Water Demand management (WC/WDM): The licensee shall develop WC/WDM and submit to Provincial Head or responsible authority, which amongst other should quantify the water use efficiency of the activity.
  • The WC/WDM shall be updated annually and submitted to Provincial Head or responsible authority.
  • The licensee shall provide any water user whose water supply is impacted by use with potable water

(3) Please refer to the response above.

(4) It is a prerequisite for any mining licence holder to conduct an environmental impact study to ensure what the effect of mining will be on the water resources. A report on geohydrological impact assessment for West Coast Resources Diamond mining operations along the west coast around Koingnaas, Northern Cape province: was concluded in 2016 with a Ref number: 2016/ENV008, dated July 2016, amongst others the report made the following reference “Groundwater represents the main source of water for domestic supply in the region. The settlements of Koingnaas, Hondeklip Bay and Samson Bak derive water from the Somnaas Noup aquifer located about 20 km north of Koingnaas. Two boreholes, BH 12 and BH 14, are currently in use. A third borehole, BH15 adjacent to BH 12, is equipped and used as a standby borehole”.

a-b) For the town of Koingnaas, the report made the following reference:

  • Available water quality data indicate that the entire area proposed for mining is characterised by highly saline groundwater with electrical conductivity of above 1000 mS/m. This is supported by the fact that there are no water supply boreholes around, and south of Koingnaas. Potable groundwater is currently sourced from the Somnaas Noup aquifer located about 20 kilometres north of Koingnaas.

(5) A copy of the licence is attached as Annexure A.

18 November 2022 - NW3886

Profile picture: Buthelezi, Ms SA

Buthelezi, Ms SA to ask the Minister of Water and Sanitation

Following reports that the residents of the Amathole District Municipality, which includes the towns Peddie, Stutterheim, Kei Mouth and Haga Haga have been without water for weeks, and noting that the water issues are due to a lack of maintenance, whilst the specified municipality has not spent the allocated funds (details furnished) set aside for maintenance and infrastructure repairs, what intervening steps does he intend to take to (a) assist the municipality to (i) spend the allocated funds for maintenance and (ii) perform maintenance on ageing infrastructure and (b) avoid a water crisis as a result of ageing infrastructure?

Reply:

Amathole District Municipality (ADM) is receiving the Water Services Infrastructure Grant (WSIG), Regional Bulk Infrastructure Grant (RBIG) and the Municipal Infrastructure Grant (MIG) to implement water services infrastructure development projects within their area of jurisdiction for accessibility of water and sanitation services and to reduce backlogs.

RBIG and WSIG are administered by the Department of Water and Sanitation and MIG is administered by the Department of Cooperative Governance.

In terms of section 227 of the Constitution, local government is entitled to an equitable share of national revenue to enable it to provide basic services and perform its allocated functions. The local government equitable share is an unconditional transfer that supplements the revenue that municipalities can raise themselves (including revenue raised through property rates and service charges). The equitable share provides funding for municipalities to deliver free basic services indigents and subsidises the cost of administration and other core services for those municipalities with the least potential to cover these costs from their own revenues.

The operations and maintenance of water services infrastructure is the responsibility of the Municipalities and should be funded by the equitable share and the revenue that the Municipalities can raise.

Recent challenges across this municipality have been as a result of labour issues which were resolved about two weeks ago. This we believe this will ensure full operations of the systems across the district.

During the 2021/22 financial year the DWS allocated a total of R 172,2 million funding through RBIG and WSIG to the ADM, as follows:

Grant

Allocation

R’ 000

Revised allocation

Expenditure

R’ 000

Expenditure

%

Balance

R’ 000

WSIG 5B

75 000

75 000

20 147

27

54 853

RBIG 6B

153 715

97 162

88 503

91

8 660

Total

228 715

172 200

108 650

63%

63 513

ADM applied to National Treasury for a rollover of the unspent WSIG allocation to the amount of R49,5 million. National Treasury did not approve the rollover application as the Municipality did not meet the set criteria in terms of section 21(2) of the 2021 Division of Revenue Amendment Act, (Act No. 17 of 2021).

During the 2022/23 financial year, a total revised allocation of R 172,2 million funding was allocated by DWS through RBIG and WSIG to the ADM, as follows:

Grant

Allocation

R’ 000

Revised allocation

Transferred

Expenditure

R’ 000

Expenditure

%

Balance

R’ 000

WSIG 5B

86 000

86 000

15 200

0

0

86 000

RBIG 6B

222 935

110 000

N/A

36 689

33

73 311

Total

228 715

172 200

 

108 650

63%

159 311

a) The intervention steps are as follows:

i) Peddie – This area is one of the areas having inadequate bulk water supply. Bulk water in Ngqushwa Municipal area is supplied by Amatola Water (AW). AW is continuously engaged in trying to come up with a Long-Term Plan for this area and have promised to be developing a plan. The ADM is also currently implementing interventions where boreholes are currently being drilled and equipped for the following villages, Ntilini, Hamburg, Upper Gwalana and Celetyume through WSIG funding budgeted in the 2022/23 Financial Year benefiting about 24 000 people. ADM is also busy implementing the Bulk and Reticulation Phase 2 project funded through MIG in the current MIG 3-year Capital Plan. The whole Peddie Town and surrounding areas will benefit from the project (about 24 000 people). ADM continues to cart water as and when required utilising its Equitable Share.

ii) Stutterheim – This town is supplied with water through the Gubu Dam as well the Kubusie River and Scotchmans Weir. ADM operates and maintains its infrastructure efficiently while continuing to cart water as and when required. To improve service delivery, ADM is also implementing the Stutterheim Water Pipe Replacement Programme funded through WSIG also in this financial year.

iii) Kei mouth - This town is supplied with water through the Cwili Dam. The ADM is also in the process of upgrading the Kei Bridge Komga Water Treatment Works funded through MIG also prioritised the current financial Year.

iv) Haga haga - This town is supplied with water through the Haga Haga Dam. ADM has also prioritised Upgrading of the Haga Haga Water Treatment Works which is currently at implementation stage funded through MIG and also prioritised this current 2022/23 Financial Year.

---00O00---

18 November 2022 - NW3908

Profile picture: Langa, Mr TM

Langa, Mr TM to ask the Minister of Water and Sanitation

What (a) has he found are the main causes of water shortages in the cities of (i) Johannesburg and (ii) Tshwane and (b) action has he and/or his department taken to deal with the specified water shortages?

Reply:

Several negative factors occurred simultaneously in Gauteng, which resulted in the recent supply problems. These included:

Severe load shedding affected the ability of both Rand Water and Joburg Water to pump water into their reservoirs. This resulted in the water levels in the reservoirs being too low to gravity-feed water to high-lying areas. As a result, a number of high-lying areas were without water for prolonged periods.

A heat water wave which resulted in increased watering of gardens by residents. In addition, the summer rains arrived late, meaning that residents did not swich off their sprinkler systems as they usually do when the summer rains start. These factors combined to result in a spike in water demand. This spike in water demand also made it difficult for the reservoirs to be filled adequately.

Both Rand Water and Joburg Water experienced several electrical and mechanical failures, which also contributed to the difficulty in filling the reservoirs. Some of these failures may have been a result of damage to equipment caused by the frequent load shedding. Two of Rand Water’s purification plants, namely, Zuikerbosh and Vereeniging as well as two major pumps stations (Palmiet and Eikenhof) supplying large parts of the city were affected by power failures. The equipment has since been repaired.

Rand Water’s operating philosophy is to maintain the reservoir levels between 60-80%. This targeted range is intended to enable the system to be resilient and respond to any challenges. Historically, during September to January, water consumption increases exponentially in Gauteng. It was with this understanding that Rand Water wrote to the high consumers, i.e. City of Tshwane, City of Johannesburg, and City of Ekurhuleni; to encourage reduced consumption in anticipation of the increased demand for water.

Despite these efforts, water consumption continued to increase significantly, and Rand Water’s overall water storage declined from 52% to 38%. Stemming from this decline, a high-level meeting was convened with the Metros to notify them of the intention to apply Stage 1 restrictions. Despite these efforts, water storage levels continued to decline and that prompted Rand Water to apply Stage 2 restrictions. The heatwave also informed the decision to escalate from Stage 1 to 2. The restrictions are necessary to stabilize the system and are aimed at restoring the overall reservoir storage capacity to 60%.

The Department is in the process of temporarily increasing the allocation of water to Rand Water from the Vaal River System, to ensure that the availability of raw water does not become a constraint to Rand Water’s ability to provide treated water during this difficult period.

---00O00---

18 November 2022 - NW3932

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Water and Sanitation

What total amount has his department spent on replacing and/or refurbishing water infrastructure in the past five financial years, as 37% of drinking water was lost through pipe leakages and other infrastructure failures?

Reply:

The amounts spent by the Department of Water and Sanitation to replace and refurbish water infrastructure in the past five financial years were spent on Water Trading Entity infrastructure and not municipal infrastructure where these losses are occuring.

The following amounts have been spent on replacing and/or refurbishing water infrastructure by the Water Trading Entity (WTE):

Financial Year

Total

 

R'000

2017/18

390 787

2018/19

177 123

2019/20

164 457

2020/21

137 315

2021/22

227 250

 Grand Total

1 096 932

The following amounts have been spent on replacing and/or refurbishing water infrastructure by the Main Account:

Financial Year

RBIG

WSIG

Total

 

5B

6B

5B

6B

 

2017/18

1 829 002

3 747 243

3 305 237

819 416

9 700 899

2018/19

1 963 000

3 061 848

4 777 267

578 398

10 380 514

2019/20

2 028 516

2 768 746

3 669 319

548 284

9 014 865

2020/21

2 005 605

2 998 971

3 360 456

330 186

8 695 218

2021/22

2 237 370

2 246 121

3 620 327

404 797

8 508 615

Grand Total

10 063 493

14 822 930

18 732 606

2 681 081

46 300 110

---00O00---

18 November 2022 - NW3817

Profile picture: Weber, Ms AMM

Weber, Ms AMM to ask the Minister of Water and Sanitation

(1) How will he assist the community of Doornkop in the Steve Tshwete Local Municipality in Mpumalanga, who lack service delivery of water and are in serious need for boreholes as there is no infrastructure. (2) whether he will intervene as the existing bore holes cannot meet the demand as the supply is not enough to provide water to the entire area and occupants are connecting pipes to the main supply water line and they use all the water before it reaches the community; if not, what is the position in this regard; if so, (a) on what date and (b) how; (3) whether he has been informed that on 19 September 2020 a notice was going to be delivered to those occupiers of Doornkop that illegally connected to the borehole and /or main supply; if not, what is the position in this regard; if so, (a) was the notice served, (b) will he furnish Ms A M M Weber with a copy of the notice and (c) how will he ensure that the notice will be enforced; (4) whether he intends to assist the Steve Tshwete Local Municipality to have a security company to take guard over the pump station and borehole area where the illegalities are taking place in order for the community to have access to their basic human right to water; if not, why not; if so, what process needs to be followed?

Reply:

1)  It should be noted that Doornkop is illegally occupied as the land is owned by Doornkop Communal Property Association (CPA). The area is not yet formalised by the municipality as it is still subject to a land claim. The area is supplied with water through six boreholes which are utilized as the main water source. However, one borehole is not operational due to vandalism. The municipality is in the process of fixing the borehole and is supplementing water supplies through water tankering.

2) The municipality has intervened by providing thirty-five water storage tanks that are servicing Doornkop Village, the tanks are placed in strategic areas across the Doornkop Village. The municipality has seven water tankers that are allocated to supply water to Doornkop Village daily to supplement the boreholes.

3) The municipality is not aware of any notice that was circulated on19 September 2020. On 22 September 2021 the municipality arranged a stakeholder engagement meeting with the community including political parties to try and address the issue of illegal connections through public engagement.

The Municipality officials with the support of the former Member Mayoral Council (MMC) for infrastructure Mr Johannes Matshiane were chased away by the community. The community clearly indicated that they will not allow the municipality to disconnect those who are illegally connected as they need water in their yards not from communal standpipes or tankers. The municipality has put on hold their long term plans due to the pending litigation of the land dispute by the CPA.

4) The existing infrastructure which are boreholes are secured, they are equipped with locks and cannot be tampered with. Currently, the municipality has no intention of hiring security personnel as this is a privately owned land and this would require permission from the CPA.

---00O00---

14 November 2022 - NW3773

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Water and Sanitation

Whether he has engaged with Eskom to exclude water treatment works from load shedding in the various municipalities, as it has a negative impact on service delivery; if not, why not; if so, what are the relevant details?

Reply:

Engagement is ongoing with the respective Water Service Authorities regarding the need to provide alternative energy supply mechanisms that can minimize the impact of loadshedding, to ensure the citizens constitutional right of access to clean drinking water.

Supported by the department, Water Boards, in their roles as water service providers to water service authorities, have taken different approaches to manage the impact of ESKOM’s loadshedding on their ability to provide reliable bulk water supply services to users, including:

  • Engaging with the provincial government leadership and ESKOM in an attempt to negotiate and facilitate for exemption on water infrastructure from frequent load-shedding
  • Filing applications with ESKOM for exemption in terms of Eskom Regulation NRS048-9. Some applications for exemption have been successful while some have not been due to technical reasons advanced by ESKOM and some are still waiting for outcomes to the applications.
  • Entities such as Bloem Water, Rand Water, Umngeni Water, Lepelle Water and Magalies Water are operating water infrastructure that is exempt from loadshedding and are mostly able to continue with operations.
  • Where affordable, some of the entities have procured back-up generators to continue with operations even when there is loadshedding

---00O00---

14 November 2022 - NW3617

Profile picture: Phillips, Ms C

Phillips, Ms C to ask the Minister of Water and Sanitation

Whether he has been informed of the extended water outages experienced by many residents in Rustenburg in the North West due to load shedding at the water purification plant, the sewerage treatment plant that provides grey water to some of the platinum mines and at the pump stations pumping water to both the command and supply reservoirs; if not, what (a) is the position in this regard and (b) mitigating measures will he urgently implement to ensure that residents and businesses do not continue to be deprived of their basic human right of access to water; if so, what mitigating measures has he put in place to prevent the outages from continuing?

Reply:

I am aware of the water supply interruptions at the Rustenburg Local Municipality (LM). An urgent notice was issued by the municipality on 27 September 2022, informing consumers of the expected water interruptions due to load shedding implemented by ESKOM. This has resulted in Water Treatment Plants not operating optimally. The municipality also reported a 40% reduction within the Magalies Water supply system, which has since recovered and is currently operating at 100%. However, the Bospoort system is still operating at 40% supply.

As a relief measure, the municipality began implementing a Water Demand Management Strategy on 14 October 2022. Based on the strategy, water supply is isolated and rotated to specific areas at a time. A schedule of water supply has been issued, detailing the supply times for different areas.

I have been advised that the municipality requested Eskom to exempt the Bospoort area from load shedding to mitigate water supply challenges and meet the current demand. However, Eskom only approved the Bospoort Water Treatment Plant to be exempted for a total of two days. The municipality has since committed to equip the Bospoort Water Treatment Plant with backup power.

I am also aware of the grey water that is supplied to the mines. The supply of treated effluent from the Rustenburg Wastewater Treatment Works to Anglo American and Impala Platinum mines was authorised in the water use authorisations for the mines as a way of promoting the wate re-use. At no point is the treated effluent pumped to any water supply reservoirs.

---00O00---

14 November 2022 - NW3427

Profile picture: Tito, Ms LF

Tito, Ms LF to ask the Minister of Water and Sanitation

Whether he has been informed that residents of Wards 10 and 5 in Mkhondo in Mpumalanga have been drinking muddy water for the past couple of weeks; if not, why not; if so, what immediate plans of intervention have been taken to provide communities with clean water?

Reply:

The Department of Water and Sanitation engaged with Mkhondo Local Municipality on 10 and 19 October 2022 respectively. The Municipality reported that there has never been a point where there has been muddy water supplied to the community except when the team is busy with pipe repairs and only for a few hours not days or weeks. The Municipality has never received any complaints regarding muddy water in both Wards mentioned above.

Eskom’s load shedding affects the water supply and the low-level water in the reservoirs causes sediments to flow from the reservoirs into the pipeline, and this affects the quality supplied to the community. When the water treatment plants are not operating, water storage reservoirs drop significantly to an extent that remaining water at the water storage reservoirs remain with sediments that are flushed out when water supply is restored.

On occasions when the municipality experiences muddy water, their water quality team collects water samples for analysis to confirm compliance with the drinking water quality standard.

The DWS has been engaging with the municipality on the 2022 Blue Drop Risk Assessment Report published in April 2022. The DWS has requested the municipality to improve on the following:

  • The WTW Microbiological report
  • Develop water storage reservoirs cleaning programme to all water supply systems within the municipality to prevent sediments in tap water.
  • Flush water following major pipe burst to prevent supply of muddy water.

---00O00---

11 November 2022 - NW3702

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Water and Sanitation

(a) How was the budget for the R3 billion bulk water project in Giyani spent and (b) what total number of (i) officials and (ii) politicians have been arrested for corruption relating to the specified project?

Reply:

a)  The budget for the R3 billion bulk water project in Giyani was spent as indicated in the table below.

     

PROJECT NAME 

LTE

SOUTH ZAMBEZI

KHATO CIVILS

TOTAL SPEND

Giyani Intervention

181,534,525.82

171,737,633.33

2,544,327,974.52

2,897,600,133.67

Nandoni

52,195,702.16

22,779,243.65

0

74,974,945.81

Nwamitwa

104,559,644.15

60,678,623.86

0

165,238,268.01

Makoxa

2,446,636.00

0.00

0

2,446,636.00

Total

338,289,872.13

255,195,500.84

2,544,327,974.52

3,140,259,983.49

(i) The Special Investigation Unit (SIU) made a referral to the National Prosecution Authority (NPA) and the Directorate for Priority Crime Investigation (the HAWKS) on 3 April 2018 for criminal charges against the former Chief Executive Officer of Lepelle Northern Water for contravening the provisions of the Public Finance Act (PFMA). Another referral was made to the NPA for charges against the manager responsible for Planning GIS on 20 September 2018 for collusion, and fraud. The investigation is in progress and no arrests have been made so far.

(ii) No referral was made to the NPA for charges against any politician.

---00O00---

10 November 2022 - NW3772

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Water and Sanitation

What steps of intervention has his department taken to address the trend which reflects that it manages to spend a large part of its appropriations, but the actual achievement of its targets is far below?

Reply:

The correlation between performance information and expenditure is a complex matter as the annual performance plan (APP) that is designed to track performance does not necessarily monitor all expenditure items of the Department. The APP is designed to measure activities of strategic importance within a given period even though some activities may have little cost implications.

In an effort of aligning the performance with expenditure, the departmental activities that have the highest budget have several indicators, for example the Regional Bulk Infrastructure and Water Services Infrastructure Grants. The Department is continually improving processes that result in inefficiencies and contribute to the low performance (a case in point is the procurement processes).

---00O00---

10 November 2022 - NW3770

Profile picture: Msane, Ms TP

Msane, Ms TP to ask the Minister of Water and Sanitation

What steps has he taken in reducing the struggles of the communities who are subjected to inhumane conditions of having no clean water supply and proper sanitation in the Mopani District Municipality that is riddled with corruption?

Reply:

The Mopani District Municipality (DM) is a Water Service Authority (WSA) in its area of jurisdiction comprising of five local municipalities (Greater Tzaneen, Ba-Phalaborwa, Greater Letaba, Maruleng and Greater Giyani). The district area has been experiencing water shortages due to various causes, namely:Raw Water Shortages (low level dams)

  • Dilapidated and aging infrastructure
  • Population growth

The Mopani DM receives funding from the Department through the Regional Bulk Infrastructure Grant (RBIG) and Water Services Infrastructure Grant (WSIG) schedule 6B and under schedule 5B. The municipality utilises these grants to provide short- and long-term water provision interventions.

The municipality also receives Municipal Infrastructure Grant (MIG) from the Department of Cooperative Governance which they utilise for their water and sanitation projects.

Table 1: Water Provisioning Status and Backlogs in Mopani

NUMBER OF HOUSEHOLDS PER MUNICIPALITY

MUNICIPALITY

BPM

GGM

GLM

GTM

MLM

MDM

Total No. of HH

41 115

63 548

58 261

108 925

24 469

296 320

HH with access

39 889

54 003

52 838

82 552

20 101

249 384

HH without access

1 226

9 545

5 423

26 373

4 368

46 935

% Backlog

2.98%

15.02%

9.31%

24.21%

17.85%

16%

% HH with access

97.02%

84.98%

90.69%

75.79%

82.15%

84%

The following are projects that are currently being implemented by the Mopani DM through funding from DWS and COGRA (MIG, RBIG and WSIG) to improve water supply services in the short, medium to long term:

  • Tours Water Scheme: Bulk Lines refurbishment and Reticulation
  • Hoedspruit Bulk Water Supply
  • Thapane Regional Water Scheme (Upgrading of Water Reticulation and Extensions)
  • Sefofotse to Ditshosine Bulk Water Supply/Ramahlatsi Bulk and Reticulation
  • Lulekani Water Scheme (Benfarm)
  • Rural Household Sanitation (Maruleng)
  • Rural Household Sanitation (Greater Tzaneen LM)
  • Rural Household Sanitation (Greater Giyani LM)
  • Rural Household Sanitation (Greater Letaba LM)
  • Rural Household Sanitation (Ba-Phalaborwa LM)
  • Ritavhi 2 Water Scheme (Sub-Scheme 1)
  • Giyani Water Reticulation to the outstanding villages
  • Refurbishment of the Giyani Water Treatment Works
  • Mametja Sekororo RWS Phase 1
  • Mametja Sekororo RWS Phase 1A (Edlin)
  • Mametja Sekororo RWS Phase 1B (Eternity)
  • Mametja Sekororo RWS Phase 2

---00O00---

10 November 2022 - NW3701

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Water and Sanitation

(a) What measures of intervention have been put in place to prevent the projected water deficit by the year 2040, (b) to what extent will the plan benefit rural communities in small rural municipalities and (c) what are the timelines for implementing the specified intervention measures?

Reply:

a)  The Department undertakes planning studies over different planning horizons to derive interventions that are implemented to ensure water security for the entire country. These interventions incorporate enablers like governance, financing, human capacity building and science and innovation that facilitate implementation of water projects at National, Provincial and District and Local Municipality level.

The interventions implemented for our water security are contained in the National Water Resource Strategy (NWRS), the instrument by which the minister gives effect to the National Water Act, as well as the master plans that emanate from the NWRS. The various studies informing the NWRS are available on the DWS website, at http://www6.dwa.gov.za/iwrp/projects.aspx, and the National Water and Sanitation Master Plan (NW&SMP) is available at http://www.dwa.gov.za.

Some of the work done by the department in relation to long term planning includes the development of the:

  • Water Reconciliation Strategies
  • Five-year Water and Sanitation Reliability Plans for all District Municipalities in South Africa.

The key outputs of the scenario planning are strategies to reconcile water requirements and availability for all large integrated systems in the country as well for localised water resource systems that secure water for small towns, villages, or clusters of settlements. Reconciliation strategies inform water security perspectives into national, provincial, and local planning instruments such as the National Development Plan, NWRS, Provincial Growth and Development Strategy, Water Service Development Plans and vice-versa

The objective of the Five-year Water and Sanitation Reliability Plans for all District Municipalities is to develop a Water and Sanitation Services Situational Assessment of the current service levels and infrastructure referenced to households at community level. The situational assessment information knowledge base is then interpreted into a needs perspective that categorises each supply need and gap analysis into a reliability category. Projects are then identified to address each of the reliability needs classification categories and a funding model developed that enables a five-year pipeline of projects implementation plan that integrates all grant funding. The full development of the plans for all 44 District Municipalities is scheduled to be completed by March 2024.

b) The identified interventions cover the whole country and benefit all the municipalities and communities in the country.

c) The plans extend cover continuous daily and weekly monitoring of water levels, to the Annual Operating Analyses which optimise annual water management, to at least 25-year planning horizons for the water resource reconciliation studies and beyond. The plans conducted as indicated in (a) above provide the direction of strategies for the country’s water security, which are continuously firmed up on a progressive basis to make them dynamic. The plans are continuously monitored and updated every 3 to 5 years to ensure that they remain current and relevant.

---00O00---

09 November 2022 - NW3858

Profile picture: Buthelezi, Ms SA

Buthelezi, Ms SA to ask the Minister of Water and Sanitation

(1)What are the relevant details of how his department intends to balance the repairing and maintenance of water supply infrastructure with the plans of his department to expand access to water. (2) considering the magnitude of the irregular expenditure in his department, what are the relevant details of how his department will implement the initiatives to balance the two aspects without the implementation contributing to further wasteful expenditure by his department?

Reply:

1.  The Department of Water and Sanitation (the Department) has a maintenance plan in place for government water schemes which includes all activities to ensure adherence to routine, planned and unplanned maintenance requirements. The maintenance plan is informed by the Asset Management Plan of the Department. Furthermore, the Department has entered into agreements with some Water User Associations (WUAs) and Irrigation Boards (IB) to operate and maintain water schemes to ensure increased water security or sustainable bulk raw water supply for economic and social water users.

2. The Department has, through a competitive bidding process, appointed sixteen (16) mechanical and electrical engineering maintenance contractors for a period of three (3) years, to augment existing capacity.

02 November 2022 - NW3347

Profile picture: Wilson, Ms ER

Wilson, Ms ER to ask the Minister of Water and Sanitation

(1)With reference to the sewerage plants in Musina, Makhado and Ephraim Mogale Local Municipality in Limpopo being altogether dysfunctional and spewing raw sewerage into rivers and water supplies in the towns and surrounding areas, resulting in the contamination of rivers, drinking water, irrigation dams and affecting the health of livestock in all areas, what (a) number of complaints has his department received with regard to the crisis and (b) actions have been taken against the municipalities, district municipalities and Lepelle Northern Water, to hold them accountable for the health risks, damage to the environment and losses of exportable crops and livestock; (2) what actions have been taken to ensure that the (a) crisis is immediately rectified and that sewerage plants are made properly functional and (b) rehabilitation of surrounding areas including underground water, rivers, irrigation dams, is urgently attended to; (3) what funds have been made available to compensate for losses and/or health issues of members of the public and businesses as a result of the incompetence of the municipalities and Lepelle Northern Water?

Reply:

1.  The Musina and Makhado Local Municipalities (LM) fall within the jurisdiction of Vhembe District Municipality (VDM). The VDM is the Water Service Authority (WSA) and Water Service Provider (WSP) to the two local municipalities. A total of three (3) complaints were received regarding (i) two (2) sewer spillages from manholes in the Makhado and Musina and; (ii) uncontrolled discharge of effluent from the Harper wastewater treatment works (WWTW) which is disturbing the construction of a nearby road. Both incidents from the manholes have since been resolved.

The 2022 Green Drop Report raised concerns regarding the overall poor state of wastewater services at Biaba, Waterval, Hlanganani, Makhado, Malamulele, Mhinga, Musina, Mutale, Nancefield, Rietvlei, Tshifulanani, Vleifontein and Vuwani systems and the consequential impact on respective water resources. A letter of non-compliance has been issued for the Water Services Authority to submit a detailed corrective action plan within 60 days of publishing the Green Drop Report. The plan must map the activities, responsible persons, timelines, and expected improvements as outlined in the Regulations. To date, no report has been received to date and the Department is engaging the WSA together with MISA and SALGA as indicated below.

In addition, the Department of Water and Sanitation (DWS) conducted compliance monitoring Inspections at Musina WWTW Nancefield (08 March 2022) and Rietvlei WWTW (07 March 2022) to check compliance against the conditions of issued water use licences for these WWTWs. An investigation was also conducted on the 18 August 2022 at the Campbell sewage package plant an to ensure compliance of National Water Act.

  • The DWS has issued directives to VDM for non-compliance of the following wastewater systems that are under Musina and Makhado LMs:Musina WWTW and Nancefield WWTW - issued on the 25 March 2022
  • Harper WWTW and Makhado WWTW - issued on the 06 September 2021
  • Campbell sewage package plant - issued on the10 August 2022In response to the directives issued by the DWS, the Vhembe District Municipality has developed the corrective action plans to address challenges with the WWTWs. Actions to be taken by the VDM include:refurbishment of the WWTW systems
  • Improvement operation and maintenance of the existing infrastructure

Furthermore, the DWS has approved business plans to fund the refurbishment projects through the Water Service Infrastructure Grant (WSIG) within the current financial year. The department is monitoring the implementation of the projects which are still at initiation stage and expected to be completed by end of municipal financial year 2022/23.

(2) Ephraim Mogale Local Municipality falls within the jurisdiction of Sekhukhune District Municipality (SDM) which assume responsibility of water and sanitation services as the WSA and WSP. Four complaints were received from Ephraim Mogale Local Municipality regarding pollution emanating from Wastewater Treatment Works (WWTW). Administrative actions were taken against Sekhukhune District Municipality as a Water Service Authority for Ephraim Mogale Local Municipality.

  • Moganyaka Oxidation Ponds for which the DWSissued notice of intention to issue a directive dated 29 October 2021;– a follow up inspection was conducted on 15 June 2022 by the department who found that the issues identified in the notice had not been addressed. A directive is being prepared.
  • Dennilton WWTW for which the DWS issued notice of intention to issue a directive dated 31 July 2019; the department conducted a follow up inspection on 08 June 2022 to ascertain compliance with the provisions of the NWA. The municipality was further non-compliant with the directive in terms of Sections 19(3) and 53(1) of the National Water Act, 1998 which is an offence in terms of Section 151(1)(d) of the NWA. The case has been referred for an interdict against Sekhukhune District Municipality to ensure compliance with the directive for the Dennilton WWTW. Therefore, the Department has opened a criminal case for offences outlined in Section 151(1)(d), (i) and (j)) of the NWA. The criminal case will be opened against the Sekhukhune DM.

 

  • Nebo Oxidation Ponds in relation to a directive dated 04 May 2021; - DWS officials conducted a follow up inspection was conducted on 13 August 2020 and 05 November 2021 to ascertain compliance with a directive issued by the DWS. Most of the non-compliances had been rectified and the ponds were empty. The municipality indicated that the Oxidation Ponds will be utilized soon. The department officials recommended that the facility should be monitored continuously to ensure compliance with the directive issued to Greater Sekhukhune Municipality.
  • Ephraim Mogale WWTW in relation to a notice of intention to issue a directive dated 29 December 2021; DWS officials conducted a follow up inspection on 15 June 2022 to ascertain compliance with the provisions of NWA. A directive will be issued.
  • The 2022 Green Drop Report indicates that Marble Hall Wastewater system declined from a 62.3% score in 2013 to a 52% score in 2022. The inspectorate observed a lack of co-ordination amongst Lepelle Water (which is responsible for the Operation and Maintenance of four (4) WWTWs including Burgersfort, Groblersdal, Marble Hall, Steelpoort) and the WSA, which was noticeable during assessments. Plants operated by Lepelle Water achieved Green Drop scores of between 46% and 58% indicating a decline from 2013 Green Drop scores.

There were no compensation claims submitted to Vhembe DM regarding loss and/or health issues however the department availed funds to Vhembe DM through the Water Services Infrastructure Grant (WSIG) to refurbish and improve operations and maintenance of the wastewater systems.

---00O00---

02 November 2022 - NW3364

Profile picture: Buthelezi, Ms SA

Buthelezi, Ms SA to ask the Minister of Water and Sanitation

(1)Whether his department has conducted recent investigations into the state of water and sanitation infrastructure in the municipalities that have either collapsed or are close to collapse; if not, why not; if so, what are the relevant details; (2) whether his department has made additional funding available for the maintenance of the water and sanitation infrastructure for the specified municipalities; if not, why not; if so, what are the relevant details?

Reply:

1.  The Department of Water and Sanitation (DWS) carries out a number of assessments into the state of water and sanitation infrastructure in the municipalities. These assessments enable the DWS to monitor the condition of municipal water and sanitation infrastructure through three incentive-based regulatory mechanisms:

  • The Green Drop Report, which focuses on sanitation (waste-water treatment systems and effluent quality)
  • The Blue Drop Report, which focuses on water (water treatment and water quality)
  • The No Drop Report, which focuses on non-revenue water and water losses through leakages

Findings of the 2022 Green Drop report 2022 indicated that 334 Wastewater Treatment Systems have been identified to be at critical state by achieving less than 30% during Green Drop Assessment. Letters of non-compliance in terms of green drop report audit findings have been sent to respective water services institutions responsible for the systems at critical state, requiring them to submit a detailed corrective action plans. To date, eighteen (18) municipalities responsible for 81 wastewater treatment systems have submitted action plans. The Department has also collaborated with SALGA and MISA to assist municipalities on the development of action plans.

In line with the National Water Resource Strategy and National Water and Sanitation Masterplan, the Department has also revived the No Drop Programme to facilitate the reduction of Non-Revenue Water and Actual Water Losses. Findings of the No Drop progress report will be published in March 2023. The department is also currently in the process of undertaking blue drop assessments in 1186 water supply systems. The final Detailed Blue Drop Report is targeted for release in March 2023.

The DWS also monitors the capacity of municipalities to deliver water and sanitation through the Municipal Strategic Self-Assessment (MuSSA); a web-based system that enables municipalities to conduct their self-assessment on critical aspects service delivery performance. The outcomes of the assessment position the Department and other sector role players to provide targeted support to local government through various support and intervention programmes aimed at improving services delivery, governance and business health. Priority areas are identified and addressed through the development of a Municipal Priority Action Plan (MPAP).

Lastly, Five-Year Reliability Water and Sanitation Plans will soon be rolled out in all forty-four (44) District Municipalities. The plans are meant to:

  • Ensure sustainable and reliable water services with the service-standard yardstick that has a 100% compliance to functionality, water security and effective governance to maintain appropriate levels of service delivery
  • Conduct primary situational assessments of the water services and infrastructure supply conditions and classify each situation into a reliability category. The solution options are then integrated to proposed projects, specifically integrating all funding programmes to alleviate new infrastructure needs and achieve reliability of water services.

2. According to Division of Revenue Act and grants frameworks, the Regional Bulk Infrastructure and Water Services Infrastructure Grants; managed by the DWS; do not fund any works related to operation and maintenance.

The department is looking at the current conditions of certain infrastructure and approached National Treasury to repurpose some portion of Regional Bulk Infrastructure and Water Services Infrastructure Grants to assist in the operation and maintenance of infrastructure.

---00O00---

02 November 2022 - NW3464

Profile picture: Buthelezi, Ms SA

Buthelezi, Ms SA to ask the Minister of Water and Sanitation

(1)Whether his department has conducted recent investigations into the state of water and sanitation infrastructure in the municipalities that have either collapsed or are close to collapse; if not, why not; if so, what are the relevant details; (2) whether his department has made additional funding available for the maintenance of the water and sanitation infrastructure for the specified municipalities; if not, why not; if so, what are the relevant details?

Reply:

1.  The Department of Water and Sanitation (DWS) carries out a number of assessments into the state of water and sanitation infrastructure in the municipalities. These assessments enable the DWS to monitor the condition of municipal water and sanitation infrastructure through three incentive-based regulatory mechanisms:

  • The Green Drop Report, which focuses on sanitation (waste-water treatment systems and effluent quality)
  • The Blue Drop Report, which focuses on water (water treatment and water quality)
  • The No Drop Report, which focuses on non-revenue water and water losses through leakages

Findings of the 2022 Green Drop report 2022 indicated that 334 Wastewater Treatment Systems have been identified to be at critical state by achieving less than 30% during Green Drop Assessment. Letters of non-compliance in terms of green drop report audit findings have been sent to respective water services institutions responsible for the systems at critical state, requiring them to submit a detailed corrective action plans. To date, eighteen (18) municipalities responsible for 81 wastewater treatment systems have submitted action plans. The Department has also collaborated with SALGA and MISA to assist municipalities on the development of action plans.

In line with the National Water Resource Strategy and National Water and Sanitation Masterplan, the Department has also revived the No Drop Programme to facilitate the reduction of Non-Revenue Water and Actual Water Losses. Findings of the No Drop progress report will be published in March 2023. The department is also currently in the process of undertaking blue drop assessments in 1186 water supply systems. The final Detailed Blue Drop Report is targeted for release in March 2023.

The DWS also monitors the capacity of municipalities to deliver water and sanitation through the Municipal Strategic Self-Assessment (MuSSA); a web-based system that enables municipalities to conduct their self-assessment on critical aspects service delivery performance. The outcomes of the assessment position the Department and other sector role players to provide targeted support to local government through various support and intervention programmes aimed at improving services delivery, governance and business health. Priority areas are identified and addressed through the development of a Municipal Priority Action Plan (MPAP).

Lastly, Five-Year Reliability Water and Sanitation Plans will soon be rolled out in all forty-four (44) District Municipalities. The plans are meant to:

  • Ensure sustainable and reliable water services with the service-standard yardstick that has a 100% compliance to functionality, water security and effective governance to maintain appropriate levels of service delivery
  • Conduct primary situational assessments of the water services and infrastructure supply conditions and classify each situation into a reliability category. The solution options are then integrated to proposed projects, specifically integrating all funding programmes to alleviate new infrastructure needs and achieve reliability of water services.

2. According to Division of Revenue Act and grants frameworks, the Regional Bulk Infrastructure and Water Services Infrastructure Grants; managed by the DWS; do not fund any works related to operation and maintenance.

The department is looking at the current conditions of certain infrastructure and approached National Treasury to repurpose some portion of Regional Bulk Infrastructure and Water Services Infrastructure Grants to assist in the operation and maintenance of infrastructure.

---00O00---

02 November 2022 - NW3703

Profile picture: Mohlala, Ms MR

Mohlala, Ms MR to ask the Minister of Water and Sanitation

(1)What are the reasons that the north and southwest areas of Johannesburg are experiencing inconsistent water supply; (2) whether the Government still has water agreements with Lesotho; if not, what is the position in this regard; if so, (a) what are the reasons that the City of Johannesburg is experiencing shortage of water supply and (b) what measures of intervention have been taken to rectify the anomaly?

Reply:

1.  According to City of Johannesburg (COJ), two of Rand Water’s purification plants, namely, Zuikerbosh and Vereeniging as well as two major pumps stations (Palmiet and Eikenhof) supplying large parts of the city were affected by power failures. The municipality’s entity, Joburg Water, reported that Eikenhof system was not being operated to full capacity to boost the Palmiet system which was at a critical level. This has resulted in portions of the Eikenhof system, which supplies Crosby, Brixton, Hurst Hill, Crown Gardens and Eagles Nest systems to collapse completely on 4 October 2022.

During engagements with Rand Water, it was agreed that the Eikenhof system should be operated at full capacity and to no longer sustain the Palmiet system. This resulted in flows to Crosby, Brixton and Hurst Hill reservoirs being improved.

2. Yes, the Treaty between South Africa and Lesotho remains in force. The project generates hydroelectricity for the benefit of Lesotho citizens, while water is transferred to meet the water needs of South Africans. This water meets 60% of Gauteng’s water demand.

a) Rand Water’s operating philosophy is to maintain the reservoir levels between 60- 80%. This targeted range is intended to enable the network system to be resilient and respond to any challenges. Historically, during September to January, water consumption increases exponentially in Gauteng. It was with this understanding that wrote to the high consumers; City of Tshwane, City of Johannesburg, and City of Ekurhuleni; to encourage and plead for reduced consumption in anticipation of the increased demand for water. Despite these efforts, water consumption continued to increase significantly.

Rand Water’s overall water storage declined from 52% to 38%. Stemming from this decline, a meeting was convened with the Metros to notify them of the intention to apply Stage 1 restrictions. Despite these efforts, water storage levels continued to decline and that prompted Rand Water to apply Stage 2 restrictions. The anticipated heatwave informed the decision to escalate from Stage 1 to 2 (. The restrictions are necessary to stabilize the system and avoid total collapse of the systems.

b) It must be noted that Rand Water’s water treatment plants and booster sites are exempt from loadshedding. However, there are two (2) tertiary booster sites in the network that are subjected to loadshedding where diesel generators are used to manage the impact of loadshedding.

The approach for implementing restrictions involves communication on implementation of restrictions to all municipalities that are supplied by Rand Water and to implement restrictions to the three Metros which utilise approximately 80% of Rand Water’s supply, as well as:

    • Identifying major meters under each municipality that will be restricted (53 meters under Johannesburg, 57 under Ekurhuleni and 28 under Tshwane).
    • These meters are monitored over a period of two weeks to assess and review progress to achieve the desired results. As for the current stages two (30%) water supply restrictions that has been implemented effective from 04 October 2022, will be reviewed
    • If the performance of Rand Water’s supply has not improved after two weeks, the review of the implemented water supply restrictions will dictate if other municipalities will be included
  • If the performance of Rand Water’s supply does improve after two weeks, the review of the implemented water supply restrictions will dictate reduction to stage one (10%) or removal of restrictions.

These restrictions are aimed at restoring the overall reservoir storage capacity to approximately 60%. Rand Water has formally consulted with the affected municipalities to inform them of its intention to implement the restrictions. The situation is reviewed on an hourly basis and where improvements are made, Rand Water lifts the restrictions to provide reprieve. Rand Water’s consultation with the customers is designed to ensure that no areas are left without water for a prolonged period.

---00O00---

02 November 2022 - NW3687

Profile picture: Motsepe, Ms CCS

Motsepe, Ms CCS to ask the Minister of Water and Sanitation

What are the reasons that the Bela-Bela community in Limpopo experiences disruptions in water supply during load shedding, often three times in a day, without any notification?

Reply:

The Bela-Bela Local Municipality has been experiencing water supply disruptions owing to the impact of load shedding by ESKOM. The water purification plant is dependent on electricity to pump water from the source to the treatment plant and from the reservoirs to the network reticulation system.

Ageing infrastructure creates also exacerbates the problem of water shortages due to regular pipe bursts which contributes to water losses and shortages in the area.

The municipality is currently implementing water restrictions as and when necessary, because of high-water demand. Availability of water depends on the reservoir levels to avoid a situation where the taps would run dry.

The Bela-Bela Local Municipality has indicated that steps are taken to notify the community timeously about water supply interruptions.

--00O00---

02 November 2022 - NW3619

Profile picture: Phillips, Ms C

Phillips, Ms C to ask the Minister of Water and Sanitation

Whether, in light of the increasing demand for both potable and grey water, he will consider reintroducing the project that was shelved in 2021 which would have seen grey and potable water produced from the Acid Mine Drainage that is currently posing a threat to many buildings and homes in the eastern, central and western basins of the Witwatersrand; if not, why not; if so, what are the relevant details?

Reply:

The Department of Water and Sanitation completed a feasibility study in 2013 for a long-term solution for Acid Mine Drainage (AMD) in the Witwatersrand as per recommendation of the 2011 Inter-Ministerial Committee (IMC) report. The long-term solution that was recommended involved further treatment of the partially treated water currently produced in the AMD treatment plants through desalination for beneficial socio-economic uses. The department commenced with preparations towards implementation of the long-term solution in 2017, but this was later put on hold due to budget constraints.

The department recognises that a significant amount of time has passed from when the feasibility study was first finalised, and for this reason is currently completing other studies to ensure the relevance of the recommendations made in 2013. This work will culminate in a revised long-term solution to be considered for implementation.

Although financial constraints remain a major challenge, the Department is also in the process to re-establish the Technology Demonstration Programme (TDP) which was also put on hold with the long-term solution in 2017. The programme is being undertaken in partnership with other stakeholders such as Water Research Commission and Department of Science and Technology and is exploring alternative technologies which can provide solutions for the AMD problem in the long-term. The TDP will be integrated with the work done by the Development Bank of South Africa through the National Water Programme.

This process will take time as proper technology selection is imperative in ensuring the most cost-effective, technologically sound, and environmentally friendly solution is implemented.

---00O00---

02 November 2022 - NW3618

Profile picture: Phillips, Ms C

Phillips, Ms C to ask the Minister of Water and Sanitation

Whether he will implement mitigating measures and/or introduce national legislation to ensure that water purification plants and sewerage treatment plants throughout the Republic, including Rustenburg, can supply both potable water to residents and businesses and grey water to businesses that use grey water to lessen the burden on our scarce water resources?

Reply:

The Department aims to publish compulsory National Water and Sanitation norms and standards for public consultation drafted under Section 9 of the Water Services Act, No 108 of 1997. In the draft norms and standards, there is a provision for grey water management. It is therefore critical for the public and various stakeholders to provide comments once the regulations are published to shape these regulations to provide necessary guidance on how water and sanitation can be managed and provided efficiently.

Mitigation measures can be addressed by various water services authorities (WSAs) as prescribed in the Municipal Systems Act, Act 32 of 2000 under section 76 which prescribes mechanisms for provision of services. This section empowers the WSAs to provide these services based on the situation in a particular municipality on how water and sanitation services can be provided, and these includes grey water management, water reclamation, decentralised systems such as septic tanks among others.

---00O00---

02 November 2022 - NW3556

Profile picture: Mey, Mr P

Mey, Mr P to ask the Minister of Water and Sanitation

(1)Whether his department has been informed that the residents of Ward 59, Ogunjini, Verulam in the eThekwini Metropolitan Municipality in KwaZulu-Natal, have been without water supply for a number of years and that the water supplied by water tankers is insufficient to meet the requirements of the households of the specified community; if not, why not; if so, what measures is his department taking to intervene in the matter. (2) what is the average cost (a) per tanker to supply the community with water and (b) to sink boreholes to supply sufficient fresh water to the community. (3) whether his department would consider sinking boreholes to address the community’s water crises, should it prove to be cost beneficial; if not, why not; if so, what are the relevant details. (4) whether he will make a statement on the matter?

Reply:

(1)  The residents of Ogunjini in Ward 59 of eThekwini Metro have been receiving water supply from a 1Ml/day Ogunjini water treatment works. A project implemented by the eThekwini Metro to upgrade the treatment plant to 2Ml/day is planned for completion by September 2023.

Eight 16 000 litre water tankers with a minimum of two loads per day, have been permanently deployed to the area by the eThekwini Metro. It is expected that this current deployment plan will remain in force until the completion of the treatment works upgrade.

(2) a) The current average cost per tanker to supply the community with water is estimated at R4 000 per day.

b) The cost to sink a borehole is estimated at R331,000 per borehole at varying capacity outputs to be determined upon testing.

(3) The municipality is currently implementing an emergency borehole rehabilitation and installation programme while a full roll-out of the programme is at tender stage. The Ogunjini areas have also been considered for this programme.

(4) The Department of Water and Sanitation will continue to monitor the water services supplied to the area by the Ethekwini Metro and provide support if required.

---00O00---

02 November 2022 - NW3549

Profile picture: Clarke, Ms M

Clarke, Ms M to ask the Minister of Water and Sanitation

(1)Whether, with reference to the report on Gravelotte Mines Geotechnical Concerns Pertaining to Flooding in April 2022, his department has been advised that ingress water is decanting anywhere else other than where the Trans-Caledon Tunnel Authority (TCTA) and his department are aware of; if not, what is the position in this regard; if so, (2) whether the ingress water has been tested; if not, why not; if so, what quantity of water is being treated by TCTA; (3) whether any water is prevented from coming in due to the pump failure; if not, what is the position in this regard; if so, what steps is TCTA taking in this regard at the moment; (4) what (a) are the reasons that the information has not been made available, (b) are the interim plans for mitigation while the pumps cannot be made functional soon enough, (c) is the level of the water at the moment and (d) are the financial costs involved?

Reply:

1.  There have been no reports to the Department of Water and Sanitation that there are currently any decants elsewhere. There are also no decants at the Eastern Basin plant where the TCTA is abstracting and pumping from.

The water level in the void is monitored daily and was 43.06 metres below ground level as of 17 October 2022. The DWS has scheduled a site visit on 25 October 2022 to Gravelotte Mines to assess the situation

It should be noted that each mine is responsible for pumping and treating water within its own mining area and ensuring the safety of its personnel and the environment it holds a mining right for.

2. Mine impacted water / acid mine drainage water in the void is tested daily when the plant is operating, and groundwater tests are conducted quarterly through the use of boreholes. Due to the plant being offline, the frequency of ground water testing has been increased from quarterly to monthly.

Depending on the results, the frequency may be increased to ensure the DWS and TCTA monitors possible ground water contamination closely. As the Eastern Basin AMD Treatment plant is offline, no water is currently being treated.

3. Ingress control measures are the mandate of DMRE and as such, DMRE would be in a better position to provide more clarity regarding the projects it is currently working on to reduce the total amount of water flowing into the Witwatersrand voids.

4. (a) The information is made available to the various forums on a regular basis and the Department and TCTA further responds to all stakeholder queries as and when needed.

(b)TCTA in partnership with Gold-One has procured 3 new motors in July 2022 and the factory acceptance tests for the new motors were conducted successfully on 29 September 2022 in China. The motors will be shipped to RSA on 21 October 2022.

A service provider is busy servicing the pump and will also make the modifications to the pump to be compatible with the new motor from China. It is expected that the plant will be operational early December 2022.

(c) The level at the Eastern Basin AMD Treatment plant was 43.06 metres below surface as of 17 October 2022.

(d) The cost of operations and maintenance in the Eastern Basin for the financial year 2021-2022 was R72 million while the cost of repairing the motors to date is R15.5 million.

---00O00---

21 October 2022 - NW2691

Profile picture: Hendricks, Mr MGE

Hendricks, Mr MGE to ask the Minister of Water and Sanitation

Whether he has been advised that 5 000 standpipes and water meters were installed in 2018 in 40 villages in Bushbuckridge, Mpumalanga, but that the treated water does not reach the reservoir as farmers and residents, including those persons who recently obtained land from chiefs, unlawfully tap into the bulk water pipe of 62 km; if not, why not; if so, what are the relevant details. (2) whether he has been advised that half of the potable water is regarded as captured and that the municipality says that they cannot stop this damage to state infrastructure and theft of water that is treated at a high cost; if not, why not; if so, what are the relevant details. (3) On what date (a) is it anticipated that water would reach the standpipes and asbestos bulk pipe that was replaced, as it now has over 5 000 illegal connections and (b) will he ensure that criminal charges are laid?

Reply:

(1-2) The Bushbuckridge Local Municipality (LM) has advised the Department of Water and Sanitation (DWS) that there are villages that do not have reliable access to water due to leakages caused by illegal connections, which results in the the supply system not being able to cater for all villages. The municipality has implemented a rationing programme to ensure that all residents have access to water. The Bushbuckridge Local Municipality is implementing a project to replace the asbestos pipeline which is due for completion during the 2024/25 financial year.

(3)(a) It is anticipated that the project to replace the asbestos pipeline will be completed during the 2024/25 financial year. The municipality is currently implementing a project to install an additional clear water pump at the Hoxane WTW which will increase the volumes pumped by the plant from 22 Ml/day to 31 Ml/day to the Ndonga reservoir that supplies all the villages being enquired about.

(b) The municipality has a duty to ensure that the farmers and residents are connected legally and to take legal actions against individuals that are vandalising infrastructure.

---00O00---

21 October 2022 - NW3488

Profile picture: Clarke, Ms M

Clarke, Ms M to ask the Minister of Water and Sanitation

(1)Regarding the report on Gravelotte Mines Geotechnical Concerns Pertaining to Flooding in April 2022, what (a) is the reason that his department did not resolve the issue of pumps that were not functioning for the duration of all the respective months, (b)(i) are the details of the service-level agreement for the maintenance of the pumps, (ii) steps were taken in this regard and (iii) were the costs and (c) entity is tasked with restoring the pumps; (2) whether any local companies have been given tenders for the restoration of the pumps; if not, why not; if so, (a)(i) who are the companies and (ii) what are the details and/or terms of reference of the tenders, (b) what is the timeline of the process at the moment and (c) on what date can pumping resume; (3) what quantity of acid mine drainage has he found is being released into the Blesbokspruit at the moment?

Reply:

1.  The department of Water and Sanitation (DWS) is aware of water from the mine void in the Eastern Basin entering an opencast pit. It should be noted that mining operations are responsible for dewatering their own operations, not the DWS. This responsibility has been recognised by Gold One who are procuring pumps to assist in the pumping and treatment of acid mine drainage in the Eastern Basin.

The Trans-Caledon Tunnel Authority (TCTA) is the implementing agent for DWS on this project. The pumps were procured from Andritz in Germany. Andritz had a proven track record in the supply of these submersible pumps worldwide and the first 2 pumps were donated by Central Rand Gold, who at that stage wished to mine to a depth of 450 m in the Central Basin. Additional pumps were sourced from the same supplier to ensure compatibility and to allow the pumps to be moved between the basins as required.

(a) Due to Covid-19 and the related global supply chain challenges, TCTA was not able to secure all the spares from Andritz in time to enable the continued pumping at the Eastern Basin AMD Plant. A decision was made to concentrate pumping and treatment in the Western and Central Basins as once the Eastern Basin becomes operational again it has the capacity to recover.

(b) (i)Nafasi Water Technologies (Pty) Ltd was appointed by the TCTA through a competitive process, on a 5-year contract to operate and maintain the AMD Plants for the Central and Eastern Basins including the AMD pumps.

(ii) The spares for the first motor were received in June 2022 (planned for December 2021) and the refurbishment of the first motor commenced in July 2022 by Marthinus and Coutts and was completed mid-August 2022 as planned. The motor was installed and commissioned by Carl Harm in August 2022 but was only in operation for 1 week before it started stalling and this necessitated the motor to be taken back to the workshop for a detailed inspection.   

(iii) The cost of operations and maintenance in the Eastern Basin for the financial year 2021-2022 was R72 million

2. The TCTA is responsible for the sourcing of critical spares from the original equipment suppliers in order to maintain the warranties for the various installed equipment.  

((i)In addition, the refurbishment of the motors and pumps is being done locally through the following service providers:

  • Marthinus & Coutts based in Cleverland, Johannesburg.
  • Sulzer - Local Branch
  • Carl Harm (Andritz local installer)

(ii-iii) The TCTA in partnership with Gold-One has procured 3 new motors in July 2022 and the factory acceptance tests for the new motors were conducted successfully on 29 September 2022 in China and the motors will be shipped to RSA on 7 October 2022. TCTA is evaluating the option to airfreight one of these motors so that it can be delivered to site within 10 days. Parallel to this process, Sulzer is busy reassembling the pump to be compatible with the new motor from China. If successful, these plans will enable the TCTA to commission one pump by the end of October 2022 and the other two pumps will be commissioned early December 2022.  

3. TCTA has not released any non-treated acid mine water to the Blesbokspruit since the commencement of operations.

---00O00---

21 October 2022 - NW3286

Profile picture: Mey, Mr P

Mey, Mr P to ask the Minister of Water and Sanitation

(1)Whether his department has been informed that the residents of some suburbs in the Polokwane Local Municipality have been without water supply since the first week of August 2022 and that the specified municipality has apparently informed residents that water supply would probably only be restored by December 2022; if not, why not; if so, what measures is his department taking to intervene in the specified matter; (2) whether he will make a statement on the matter?

Reply:

1. The Minister of Water and Sanitation is aware of the water supply shortages of water supply within the Polokwane Local Municipality particularly within the Polokwane City, the surrounding suburbs and Seshego township.

Polokwane LM receives daily water supply from three major sources comprising of the Ebenezer Water Treatment Works (WTW), Olifantspoort WTW and Dalmada WTW. The Ebenezer and Olifasproot plants are operated by the Lepelle Northern Water Board (LNWB) while Dalmada WTW is operated by Polokwane LM.

Polokwane City and Seshego has a total demand of 96.5 Ml/d and all possible sources can only supply the city with 88.4Ml/d and currently there is a deficit of 8.1 Ml/d. The city is authorized to abstract and or to treat 29.4 Ml/d while LNWB supplies 27 Ml/d from Olifastsproot WTW and 32 Ml/d from Ebenezer WTW.

Water supply to the Polokwane LM is also augmented through boreholes, some of which are non-operation and require repairs as indicated below:

  • Sand River North: all fifteen (15) Boreholes are operational. Polokwane LM is pumping the boreholes in alternative to allow some of the boreholes to recharge and the total yield of the boreholes is 4.8 Ml/d
  • Seshego Boreholes (Direct to Reticulation): out of six (6) boreholes, two (2) are not operational due to vandalism and the municipality is currently repairing the borehole.
  • Marshall Boreholes: all five (5) boreholes are operational and currently producing 3.8 Ml/d

The WTWs supplying Polokwane are faced with challenges that impact on the ability of the municipality to supply water consistently to all residents as follows:

  • The Ebenezer WTW
    • The plant is operated by LNWB and is highly affected by general interruption of electricity, currently affecting optimal water supply countrywide, which is supplied by the Greater Tzaneen LM
    • Greater Tzaneen LM is currently upgrading electricity infrastructure which supplies the Ebenezer WTW and discussions to explore whether Greater Tzaneen LM can isolate Ebenezer WTW from load shedding are underway
  • Olifanspoort WTW
    • The plant is operated by LNWB is impacted negatively by the Olifantspoort ageing bulk water supply network contributes significantly to the interruption of water supply in the City of Polokwane.
    • The main cause of the water supply challenges in Polokwane City was due to deficiencies of the pumping systems of the Olifantspoort scheme. There were mechanical breakdowns within Pump Station No 2 and Pump Station No 3 which have since been repaired.
      • The LNWB has already commissioned Phase 1 for the upgrade and refurbishment of this bulk pipeline, a cost of R 32 million. Phase 2 which has been allocated R 38 and is meant to refurbish aging infrastructure will be completed by the end of October 2022
  • The Dalmada WTW
    • This plant, which is operated by the City of Polokwane, has a pipeline that conveys raw water from Dap Naude sections of which is critically dilapidated.
    • A study that was done in 2019 has confirmed a need for refurbishment and upgrade of the pipeline to enable Polokwane LM to safely abstract of 14Ml/d from the dam, which would add 4.1Ml to the supply
    • The Implementation Readiness Studies for the refurbishment and upgrades is under consideration by the department.
  • Seshego WTW
    • There is a 1.8 Ml/d deficiency in the system due to the new Seshego WTW Plant currently being non-operational while under construction.

To ensure proper resolution of the water supply plaguing the Polokwane LM, a task team led by both Deputy Ministers, the Executive Major of Polokwane and Chairperson of the Board of LNWB has been set up to resolve water supply challenges in the Polokwane LM. A technical task team led by the Municipal Manager of Polokwane LM, the Chief Executive Officer of LNWB and DWS officials has also been established. The task team will meet weekly to track progress on the restoration of water supply to Polokwane City including the Seshego township. The implementation of the action plan is at 85% and all major challenges are being resolved.

2. A joint media briefing was held by both Polokwane LM, LNWB and the department on 5 September 2022. Furthermore, the Polokwane LM continues to update residents of Polokwane City including Seshego township on any development regarding the state of water supply.

---00O00---

21 October 2022 - NW3300

Profile picture: Buthelezi, Ms SA

Buthelezi, Ms SA to ask the Minister of Water and Sanitation

Given that the Green Drop report indicates that half of the wastewater treatment works in the Republic fail to treat sewage properly and, in many cases, fail to treat it at all, (a) what steps have been taken by his department to capacitate Water Service Authorities in the Republic and (b)(i) which key focus areas has his department isolated from the specified report and (ii) how will they be addressed?

Reply:

The Department of Water and Sanitation (DWS) recently published the 2022 Green Drop Report which gives a detailed overview of the state of Wastewater Management in the country. The report presents an extremely concerning situation across the country, and that wastewater management has deteriorated notably since 2014.

a) The Department of Water and Sanitation has taken steps to capacitate Water Service Authorities in collaboration with the South Africa Local Government Association (SALGA) through:

  • Capacitating the Water and Sanitation Portfolio based Councillors throughout their term.
  • Ensuring adequate wastewater operations and maintenance capacity through the training of Process Controllers. The department will, in collaboration with the Energy and Water Sector Training Authority (EWSETA) facilitate training of Process Controllers in order to comply with the required Wastewater Quality Management regulations.
  • Ensuring that all wastewater management environmental hazards are mapped and mitigated

Furthermore, the department together with SALGA embarked on the Water and Sanitation Councillor Induction from May to August 2022 across the country. Wastewater Quality Management and Drinking Water Management themes were part of the inductions.

b) (i) Key focus areas identified in the report include the following:

  • Technical competence
  • Treatment capacity
  • Wastewater monitoring and compliance
  • Operation, Maintenance and Refurbishment of Assets

(ii) Key areas of concern identified during the Green Drop Assessments will be addressed in the following ways:

  • The DWS is in the process of finalising the amendments to regulations relating to compulsory national standards for process controllers and water services works. The regulations seek to ensure that the water services works are classified according to their technology type to determine the level of skill required for operations by process controllers.
  • Process controllers who are skilled in both qualifications and years of experience must be registered to operate a relevant water service works based on their class of certificate.
  • The DWS is putting in place a Water Services Improvement Programme (WSIP) to strengthen its support and intervention at municipal level based on actual data or most available data. The aim of the programme is to ensure that support and intervention at municipal level is proactive, consistent, and systematic.
  • Maintenance and refurbishment of Wastewater Treatment Works is the primary responsibility of the responsible Water Service Authorities (WSAs). However, the Department of Water and Sanitation (DWS) works together with the Department of Cooperative Governance and Traditional Affairs (COGTA) and the South African Local Government Association (SALGA) to ensure that municipalities receive the necessary support and grant funding to refurbish and maintain their assets.
  • The DWS also funds certain refurbishment and upgrading projects that meet the criteria of the different funding programs such as Regional Bulk Infrastructure Grant (RBIG) and Water Services Infrastructure Grant (WSIG). Some of the specified WWTW have been gradually included in these programs depending on availability of funds availed to the Regions.
  • COGTA also supports WSAs through the Municipal Infrastructure Grant (MIG) for water and sanitation services, amongst other. Some of the funding has been allocated for the refurbishment of some of WWTW.

---00O00---