Questions and Replies
24 November 2021 - NW2254
Ceza, Mr K to ask the Minister of Water and Sanitation
What is his department’s current (a) national backlog for the installation of boreholes in rural municipalities and (b) time frame for completing the (i) installation of boreholes and (ii) building of dams in this regard?
Reply:
a) The installation of boreholes falls under the mandate of municipalities in line with Section 84(1)(d) of the Municipal Structures Act which mandates that municipalities are responsible for the provision of potable water within their areas of jurisdiction.
(b) (ii) As per the Department of Water and Sanitation Annual Performance Plan and funding for the 2021/22 financial year, progress for the following construction of the following dams is as follows:
No |
Project |
Progress |
Estimated date of completion |
1 |
Raising of Hazelmere Dam |
96% construction |
August 2022 |
2 |
Raising of Clanwilliam Dam |
12% construction |
April 2026 |
3 |
Raising of Tzaneen Dam |
10% construction |
June 2023 |
4 |
Mzimvubu Water Project |
20% construction (Advanced Works-Access Roads) |
Completion to be confirmed on finalisation of construction drawings |
5 |
New Nwamitwa Dam |
|
Completion to confirmed on sequencing of the work packages and availability of long term funding |
6 |
Lusikisiki Regional Water Supply Scheme: Zalu Dam |
|
Date of completion to be confirmed on finalisation of specialist services appointment |
6 |
Algoa Water Supply System: Corney Dam |
0% Design stage |
October 2022 for completion of designs |
7 |
Umkhomazi Water Project |
Project preparation stage |
2027 |
---00O00---
24 November 2021 - NW2156
Mohlala, Ms MR to ask the Minister of Water and Sanitation
(1)Whether he has disbanded the advisory committee that was set up by the former Minister of Human Settlements, Water and Sanitation; if not, what is the position in this regard; if so, (2) whether the progress reports which had been compiled by the advisory committee were collected, given that these were compiled from taxpayers’ money; if not, why not; if so, what are the relevant details?
Reply:
1. The contracts of the advisory committees that were set up by the former Minister of Human Settlements, Water and Sanitation, were linked to her term of office in the Department of Water and Sanitation. Due to the fact that the tenure of the former Minister ended on 5 August 2021, the advisory committees was given 30 days’ notice from this date and terminated on 4 September 2021.
2. The Chairpersons of the respective committees were requested to prepare and submit close-out reports. The Water Services Advisory Committee has submitted its close-out report. The other Committees will table their reports when they meet with the Minister.
---00O00-
04 November 2021 - NW2158
Mohlala, Ms MR to ask the Minister of Water and Sanitation
In light of the fact that water boards such as the Amatola Water Board have in the past five years been riddled with issues of corruption and political interference surrounding the appointment of board members, what strategies of intervention have been devised to strengthen governance at water boards?
Reply:
Honorable Member, the Department of Water and Sanitation (the Department) is implementing the following interventions to strengthen governance at Water Boards:
a) The Minister had 5 Provincial engagements in the Free State, Eastern Cape, Limpopo, Gauteng and KwaZulu- Natal. These provincial engagements were attended by the DWS Provincial Office, Provincial Government, Water Boards, Water Service Authorities and broader water and sanitation Committees and Forums.
b) The engagements with Water Boards were mainly around issues of governance, financial viability and accountability and broader service delivery issues as per their mandate.
c) The Minister, during the engagement in the Eastern Cape between 31 August to 2 September 2021, interacted with Amatola Water Board. The Minister noted with concern the issues of lack of stability both in the Board and Executive Management. The situation is exacerbated by a number of allegations including allegations of political interference.
d) To stabilize Amatola Water Board the following decisions were made:
- The Department obtained a legal opinion on the Board Appointment process of Amatola Water.
- Probity Check was conducted on all new Board Members
- The Minister is currently implementing the outcomes of the legal opinion and probity Check.
- The Minister has processed a Cabinet Memorandum to appoint the permanent Chief Executive Officer of Amatola Water
---00O00---
29 September 2021 - NW1369
Mohlala, Ms MR to ask the Minister of Water and Sanitation
What total amount has been paid to AURECON for their involvement in the Lesotho Highlands Water Project?
Reply:
The total paid to AURECON SA thus far is R 236 205 932.
AURECON SA is participating in various Consulting Joint Ventures for the Lesotho Highlands Water Project as per shares and figures indicated in the schedule below.
Contract LHDA No. |
Description |
Contracted Party |
Total Contract Amount (R) |
Aurecon SA Share of Total Contract Amount (%) |
3020 |
Design and Supervision of Major Bridges |
Aurecon Consortium |
123 892 049 |
30% |
3022 |
Design and Supervision of Polihali Diversion Tunnels |
Metsi a Senqu Khubelu Consultants (MSKC) |
82 460 577 |
19.6% |
3007 |
Design and Supervision of Polihali Transfer Tunnel |
Metsi a Senqu Khubelu Consultants (MSKC) |
914 276 029 |
20% |
TOTAL |
21% |
09 September 2021 - NW1222
Mohlala, Ms MR to ask the Minister of Human Settlements, Water and Sanitation
In view of the fact that a number of Lesotho citizens were uprooted from their land during phase 1 of the Lesotho Highlands Water Project, what steps has she taken to ensure that (a) compensation is paid to the specified persons and (b) there will be no further disenfranchisement of the citizens of Lesotho as a result of the specified project?
Reply:
All persons affected by the project were either relocated, resettled and/or had their assets compensated in accordance with the Lesotho Highlands Water Project (LHWP) Compensation Policy as well as the Treaty between the Republic of South Africa and Lesotho. Ccompensation was paid to the affected persons by adopting the following measures:
- The LHWP’s legal obligations to the people and communities affected by Project works are based on: The Lesotho Constitution, the LHWP Treaty - Article 7, the LHDA Order of 1986 and the LHWP Compensation Regulations, Legal Notice No. 50 of 1990, and specifically for the implementation of Phase II, the Phase II Agreement – Article 15.
- The LHWP Compensation Policy covers compensation for: Loss of assets, Uprootment (including resettlement), Income Restoration, Rural Development, Natural Environment and Heritage and in addition the implementation of Public Health plans with Lesotho.
The implementation and the execution of the Compensation Policy is also regularly monitored by an Independent Panel of Experts.
Complaints relating to compensation, relocation and resettlement issues are dealt with through various Lesotho Highlands Development Agency (LHDA) field officers, the Social Development and Environment Division, and the Public Relations Office. All queries that arise are dealt with by the LHDA on a case-by-case basis and captured on a database. Complainants also have access to the Compensation Ombudsman.
---00O00---
07 September 2021 - NW1649
Powell, Ms EL to ask the Minister Water and Sanitation
Whether she will provide Ms E L Powell with the full, relevant details on the (a) dates, (b) destinations and (c) costs of all flights boarded by a certain person (Mphumzi Mdekazi) (i) between 1 May 2019 and 1 October 2020 and (ii) during the National State of Disaster period; if not, why not; if so, what are the relevant details
Reply:
The Department incurred the following costs in relation to Mr Mdekazi for the period 1 May 2019 and during the National State of Disaster period :
Category |
Cost |
Accommodation/ domestic air travel/ Car hire and transfers |
R 1 763 878.00 |
---00O00---
07 September 2021 - NW1650
Powell, Ms EL to ask the Minister of Water and Sanitation
Whether she will provide Ms E L Powell with the full, relevant details of (a) all travel and (b) additional expenses incurred by each member of the National Rapid Response Task Team (i) between 1 March and 1 October 2020 and (ii) during the National State of Disaster period; if not, why not; if so, what are the relevant details in each specified case?
Reply:
The following expenses were incurred by the Members of the National Rapid Response Task Team for the period 1 March 2019 and during the National State of Disaster period.
Name of official |
Category |
Cost |
Mr Zolile Burnsncamashe |
Accommodation/ domestic air travel/ Car hire and transfers |
R 306 296
|
Mr Lekgotla Dichoetlise |
Car hire and transfers |
R 116 709 |
Mr Mahle Khuzani |
Accommodation/ domestic air travel/ Car hire and transfers |
R 283 800
|
Ms Dudu Manana |
Accommodation/ Car hire |
R 48 319 |
Mr Mzwakhe Masoue |
Accommodation/ domestic air travel/ Car hire and transfers |
R 468 446 |
Mr Maxwele Chumani |
Accommodation/ domestic air travel/ Car hire and transfers |
R 335 875 |
Mr Mogomotsi Mogodiri |
Car hire/domestic accommodation |
R 53 216 |
Dr Mandisa Mokwena |
Accommodation/ domestic air travel/ Car hire and transfers |
R 27 709 |
Ms Carla Motau |
Car Hire |
R 59 801 |
Mr Likhaya Ngqezana |
Accommodation/ domestic air travel/ Car hire and transfers |
R 543 363 |
Mr Simphiwe Ngxakeni |
Accommodation/ domestic air travel/ Car hire and laundry |
R 386 727 |
Ms Nolonwabo Quanta |
Accommodation/ domestic air travel/ Car hire and transfers |
R355 622 |
Ms Debbie Raphuthi |
Accommodation/ domestic air travel/ Car hire and transfers |
R 112 742.00 |
Ms Suliwe Shilwayi |
Accommodation/ domestic air travel/ Car hire and transfers |
R 488 736 |
Mr Samuel Thembani |
Car hire and domestic accommodation |
R 144 422 |
TOTAL |
R 3 732 795 |
---00O00---
16 April 2019 - NW722
Matsepe, Mr CD to ask the Minister of Water and Sanitation
What is the (a) make, (b) model, (c) price and (d) date on which each vehicle was purchased for use by (i) him and/or the former minister and (ii) his deputy and/or the former deputy minister (aa) in the (aaa) 2016-17 and (bbb) 2017-18 financial years and (bb) since 1 April 2018?
Reply:
a) Make of vehicle purchased for use |
b) Model of vehicle purchased for use |
c) Price of each vehicle purchased for use |
d) (aaa) Date on which each vehicle was purchased for use in the 2016/17 FY |
e) (bbb) Date on which each vehicle was purchased for use in the 2017/18 FY |
|
Minister, Nkwinti G came with his vehicle from Rural Development |
Audi |
Q7 |
R1 039 872.66 |
January 2017 |
None |
The former Minister, Mokonyane N moved with her vehicle to Environmental Affairs |
Audi |
Q7 |
R910 714.90 |
None |
January 2018 |
The Deputy Minister, Tshwete P |
Audi |
Q7 |
R951 713.04 |
None |
May 2017 |
---00O00---
16 April 2019 - NW796
Alberts, Mr ADW to ask the Minister of Water and Sanitation
(1)What is the total number of mines with a water licence in each province that (a) meet the licensing requirements and (b) do not comply with the licensing requirements; (2) what (a) is the name of each mine with a water licence that does not comply with the licensing requirements, (b) is the area and province in which each mine is located, (c) are the reasons why the mines do not comply with the water licensing requirements and (d) steps does he intend to take to address the deficiencies; (3) with reference to operational mines in each province that are not in possession of water licences, what are the full relevant details of the (a) name of each mine, (b) area and province in which each mine is located, (c) reasons why the mines are operational without water licenses having been awarded to them and (d) steps he intends to take to address these deficiencies?
Reply:
(1)(a) The total number of mines with a water use licence in each province authorized to use water are 712.
(1)(b) Refer to Annexure A for the total number of mines authorized but non- compliance.
(2) Refer to Annexure A for the action taken to address the deficiencies by authorized non-compliant mines and Annexure B for the technical and administrative conditions of a licence in terms of the National Water Act, 1998 (Act No 36 0f 1998) (NWA).
(3)(a) A total number of mines operating without authorisation in each province are 115.
(3)(b) The table below reflects the number and province in which each of those mines are located. Refer to Annexure C for list of mines operating without authorisation in each province.
Province |
Number of mines |
Steps to be taken to address |
Gauteng |
13 |
Administrative enforcement action |
Limpopo |
3 |
Administrative enforcement action |
Mpumalanga |
30 |
Administrative and criminal enforcement action |
Kwa Zulu Natal |
37 |
Administrative enforcement action |
Free State |
5 |
Administrative enforcement action |
Northern Cape |
25 |
Administrative enforcement action |
Eastern Cape |
1 |
Administrative enforcement action |
North West |
1 |
Administrative enforcement action |
Total |
115 |
(3)(c) It is not clear why transgressors resort to operation of mines without the requisite authorisation however; the Department continues to intensify activities to protect the water resource as mandated by the National Water Act, (Act No. 36 of 1998).
(3)(d) The Department investigates identified as well as reported non- compliances regularly. These non-compliances are dealt with in accordance with administrative, criminal and civil enforcement tools as prescribed by the National Water Act, (Act No. 36 of 1998).The Department also collaborates with other law enforcement agencies such as the South African Police Services and the National Prosecuting Authority in respect of non-compliance matters which require further criminal enforcement action.
---00O00---
16 April 2019 - NW752
Khawula, Ms MS to ask the Minister of Water and Sanitation
(a) What is the total number of water treatment facilities that are there in each province, (b) what number of the specified facilities are (i) functional and (ii) dysfunctional and (c) for how long have the facilities been dysfunctional?
Reply:
Requesting the Hounorable Member to note that water treatment facilities are the responsibility of the Department of Corporative Governance and Traditional Affairs and that the Department of Water and Sanitation only monitors compliance of the facilities.
Refer to the table below for the total number of water treatment facilities that were monitored by the Department in each province.
Province |
Number of water treatment works per Province |
(b)(i) Number of treatment works functional |
(b)(ii) Number of treatment works dysfunctional |
For how long have these been dysfunctional |
Eastern Cape |
224 |
224 |
0 |
N/A |
Free State |
87 |
83 |
4 |
One (1) Water Treatment Works has been dysfunctional for 3 years due to no raw water from the Lovedale Dam. One (1) Water Treatment Works has been dysfunctional for 3 years due to refurbishment of raw water pump station but is now complete. The Municipality is trying to fill up the Balancing dam with raw water in order to start operating the plant. One (1) Water Treatment Works has been dysfunctional for 6 years due to lack of raw water. One (1) Water Treatment Works has been dysfunctional for 4 years due to lack of raw water. |
Gauteng |
17 |
17 |
0 |
N/A |
KwaZulu Natal |
243 |
196 |
47 |
Thirty nine (39) Water Treatment Works has been dysfunctional for 2 years. Eight (8) Water Treatment Works has been dysfunctional for 4 years. |
Limpopo |
89 |
82 |
7 |
One (1) Water Treatment Works has been dysfunctional for 10 years. Two (2) Water Treatment Works has been dysfunctional for 11 years. Three (3) Water Treatment Works has been dysfunctional for 5 years. One (1) Water Treatment Works has been dysfunctional for 1 year. |
Mpumalanga |
105 |
98 |
7 |
Seven (7) Water Treatment Works has been dysfunctional for 1 year. |
Northern Cape |
166 |
165 |
1 |
One (1) Water Treatment Works has been dysfunctional for 2 years. |
North West |
126 |
126 |
0 |
N/A |
Western Cape |
136 |
132 |
4 |
One (1) Water Treatment Works has been dysfunctional for 5 years. One (1) Water Treatment Works has been dysfunctional for 2 years. Two (2) Water Treatment Works has been dysfunctional for 1 year. |
---00O00---
16 April 2019 - NW513
Khawula, Ms MS to ask the Minister of Water and Sanitation
(a) What number of (i) buildings, (ii) properties and (iii) facilities does his department currently (aa) own and (bb) rent, (b) what is the value and purpose of each (i) owned and (ii) rented property and (c)(i) for how long has each property been rented, (ii) from whom is each property rented and (iii) what is the monthly rental fee for each property?
Reply:
(a)(i) The total number of building rented by the Department is 33 buildings and a total number of buildings owed by the Department are 4948 refer to the table below.
Row Labels |
No. of Assets |
Cost |
Accumulative Depreciation |
Book Value |
Buildings |
4889 |
2,173,677,966.77 |
(1,281,645,620.50) |
892,032,346.27 |
Buildings Auxiliary |
59 |
19,368,099.92 |
(9,456,665.67) |
9,911,434.25 |
Grand Total |
4948 |
2,193,046,066.69 |
(1,291,102,286.17) |
901,943,780.52 |
NB Auxiliary Buildings relates to Boat Houses
(a)(ii) The Minister owns, manages and controls a total of 320 state own dams (government waterworks) country wide and a total of 1175 properties refer to the table below.
Row Labels |
No. of Assets |
Cost |
Accumulative Impairment |
Book Value |
Land |
1174 |
7,791,050,104.60 |
(245,160,780.58) |
7,545,889,324.02 |
Grand Total |
1174 |
7,791,050,104.60 |
(245,160,780.58) |
7,545,889,324.02 |
In addition the following should be noted:
In terms of Section 1(1) (x) of the National Water Act, 1998 (Act no. 36 of 1998) (NWA) the Minister owns the land on which a government waterwork is situated. The extent of the land required is determined scientifically up to the dam boundary line of each dam which includes the full supply level, the 1:100 year flood line and a buffer line. In terms of Government Immovable Asset Management ACT No 19 of 2007 (GIAMA), the disposal policies of the Department of Water and Sanitation (DWS) and the National Department of Public Works (NDPW) all excess land must be transferred to NDPW. The Minister only acquires the minimum land required for the government waterwork in order to manage, operate and maintain the dams. In relation to ownership, the
Minister has exclusive rights on the land within the government waterworks and the water source is regarded as national assets which must be protected in terms of the NWA.
(a)(iii) Refer to (a)(i) above.
(b)(i) The Hounorable Member is requested to note the following. The Value of each property owned by the Minister of Water and Sanitation which falls within a Government Waterwork must be determined by a Professional Registered Valuer. The Department is not in a financial position to determine the value of each property as yet and will need to seek the assistance of the Office of the Valuer-General to assist with the determination of the market related value of each property. The purpose of each property falling within a dam boundary line is to store bulk raw water. Refer to Annexure A for the value and purpose of each owed property.
(b)(ii) The Department is renting a total of 33 buildings. Refer to the table below (c) for the value and purpose of the rented properties.
(c) Refer to the table below for the rented properties:
(c)(i) for how long has each property been rented |
(c)(ii) from whom is each property rented and |
(c)(iii) what is the monthly rental fee for each property |
SPECTRUM HOUSE 1 8 years |
Grey Jade Trade and Invest 85 (PTY) LTD |
R 1 232 050.68 |
SPECTRUM HOUSE 2 5 years |
Ascession Properties LTD |
R 71 968.37 |
SIGMA HOUSE 9 years |
Cape Horizon Properties (PTY) LTD |
R 852 773.71 |
INTERPARK 5 years |
Interpark |
R 7 410.00 |
9&11 HIGH STREET 28 years |
Quenprop Investment PTY LTD |
R 17 345.33 |
9&11 HIGH STREET 28 years |
Quenprop Investment PTY LTD |
R 26 146.70 |
LIONN ROARS OFFICE PARK 9 years |
Kuper Legh Property Management (PTY) LTD |
R 229 751.86 |
SANPORT 23 years |
Africorp International Properties (PTY) LTD |
R 69 398.44 |
44 SPRIGG STREET 30 years |
M.J Lombard |
R 15 900.46 |
PARK HOMES 14 years |
M. Projects CC |
R 18 700.56 |
PRD2 19 years |
Colliers RMS (PTY) LTD |
R 351 581.37 |
2 HARGREAVES 16 years |
Arrowhead Properties LTD |
R 435 084.24 |
PROROM 26 years |
Ascession Properties LTD |
R 669 760.87 |
26 CENTRAL ROAD KIMBARLEY 8 years |
Albasync (PTY) LTD |
R 420 538.47 |
PRAETOR 11 years |
Centpret Properties (PTY) LTD |
R 284 095.98 |
SANLAM PLAZA EAST 18 years |
Superbia Four (PTY) LTD |
R 742 486.10 |
22 ROOTH STREET CANELLE BLDG 15 years |
Ascession Properties LTD |
R 42 690.16 |
TALANA 13 years |
BASFOUR 3072 (PTY) LTD |
R 54 240.38 |
SOUTHREN LIFE 19 years |
Delta Property Fund (LTD) |
R 674 900.55 |
SANLAM PLAZA 31 years |
Gensec Property services Limited t/a JHB |
R 313 964.06 |
MEGACITY WEST GALARY 4 years |
Combia Falls Properties |
R 712 317.29 |
(c)(i) for how long has each property been rented |
(c)(ii) from whom is each property rented and |
(c)(iii) what is the monthly rental fee for each property |
FACTORY 40-12 15 years |
Limpopo Economic Development Agency |
R 42 643.70 |
OLD SABC 14 years |
South African Broadcasting Corporation Coc limited |
R 152 479.39 |
LEBOWAKGOMO GOV. COMPLEX 14 years |
Department of Public Works |
R 7 508.55 |
AZMO PLACE 23 years |
Delta Properties Fund LTD |
R 676 362.18 |
LIBRARY GARDENS 18 years |
Changing Tides 132 (PTY) LTD |
R 82 539.52 |
38-42 HOOGE STREET 18 years |
Omtay Property Holding Trust |
R 91 835.69 |
SEDIBENG 37 years |
Summermania Seven (PTY) LTD |
R 3 735 404.30 |
EMANZINI 40 years |
Redefine Properties |
R 1 200 273.83 |
ZWAMADAKA 40 years |
Summermania Seven (PTY) LTD |
R 1 695 729.48 |
WATERBRON 10 years |
Dreamfair Properties (PTY) LTD |
R 3 444 465.10 |
FINPARK 17 years |
Servest (Finpark) |
R 110 712.91 |
NDINAYE 2 3 years |
Supperble Four (PTY) LTD |
R 751 451.30 |
CORPORATE 66 7 years |
Faerie Glen Waterpark (PTY) LTD |
R 129 650.93 |
NDINAYE 1 4 years |
Supperble Four (PTY) LTD |
R 474 345.04 |
CONTINENTAL 11 years |
Redefine Properties |
R 490 173.29 |
---00O00---
26 March 2019 - NW106
Waters, Mr M to ask the Minister of Water and Sanitation
(1)With regard to the reply to question 3753 of 12 December 2018, what number of sewerage processing plants (a) were inspected since 1 July to 30 September 2018 and (b) passed the inspection; (2) what number of sewerage processing plants (a) were inspected during (i) 1 January to 31 March 2018, (ii) 1 April to 30 June 2018 and (iii) 1 October to 31 December 2018 and (b)(i) failed and (ii) passed the inspection; (3) with reference to the letter in Annexure B, did the Siyathemba Local Municipality make written representation to his department within the 14-day period providing no compelling reasons for his department not to exercise its powers; if so, what reasons were given; (4) what number of municipalities were given non-compliance letters?
Reply:
(1)(a) The number of sewerage processing plants inspected in relation to question 3573 of 12 December 2018 is a total of forty three (43) see attached Annexure A.
(1)(b) The Inspections referred to are conducted to determine functionality and treatment efficacy of the sewerage processing plants. During the inspections the Inspector looks for any deficiencies in the process and if any are encountered the Inspector makes recommendations for implementation by the Water Services Authorities.
(2)(a)(i) A total of 114 sewerage processing plans were inspected January to March 2018 see attached Annexure A.
(2)(a)(ii) A total of 82 sewerage processing plans were inspected 1 April to June 2018 see attached Annexure A.
(2)(a)(ii) A total of 76 sewerage processing plans were inspected 1 October to 31 December 2018 see attached Annexure A.
(2)(b)(i) Please refer to response in (1)(b).
(2)(b)(ii) Please refer to response in (1)(b).
-2-
(2)(a) Refer to Annexure A.
(2)(b)(i) Please refer to response in (1)(b).
(2)(b)(ii) Please refer to response in (1)(b).
(3) Yes, a written representation from the Siyathemba Municipality was received by the Department’s Northern Cape Regional office within the 14 days. The action plan has time frames and responsible personnel which will enable the Department to monitor progress. Requesting the Honourable Member to refer to Annexure B for details.
(4) A total of thirty two (32) municipalities were given non-compliance letters up to the third quarter of the 2018/2019 financial year and two (2) of these were issued with court interdicts, however these notices are not as a result of the above mentioned inspections. The notices were issued following complaints of pollution received by the Department’s Provincial Operations.
---00O00---
26 March 2019 - NW751
Khawula, Ms MS to ask the Minister of Water and Sanitation
Whether, in light of the current water consumption rates, his department commissioned any study to determine whether the country will have enough water to sustain the population, economic growth and development by (a) 2050, (b) 2075 and (c) 2100; if not, why not; if so, what are the details of the findings of the study?
Reply:
a) The Department undertakes various planning studies over 25-year horizons, including the period to 2050 to ensure water security for the country. Such studies include (i) Water Availability Assessment Studies (WAAS), which generate base input information for planning, (ii) long term water resource reconciliation planning studies for large and small demand centres, and (iii) catchment-based studies. These planning studies culminate in strategies that address water needs for the country, which are then continuously monitored and updated every 3 to 5 years to ensure that they remain current and relevant. The outputs of the studies inform the National Water Resource Strategy (NWRS), the instrument by which the minister gives effect to the National Water Act, as well as the master plans that emanate from the NWRS. The studies are available on the DWS website, at http://www6.dwa.gov.za/iwrp/projects.aspx..
(b) and (c)
For the perspectives 2075 to 2100, the planning horizon is longer, and this is accompanied by a high degree of uncertainty. The studies conducted as mentioned in (a) above provide indicative directions of strategies for the country’s water security, which are continuously firmed up on a progressive basis to make them dynamic high level water resource plans that address uncertainty.
---00O00---
26 March 2019 - NW569
Waters, Mr M to ask the Minister of Water and Sanitation
(1)(a) On what date was the Rand Water project, Palmiet RW-06, started and (b) what (i) still needs to be done before the project is completed, (ii) are the reasons that the project has stalled for over a year and (iii) is the expected completion date; (2) (a) what (i) is the expenditure to date and (ii) was the original costing of the project, (b) who were the contractors and consultants on the original project, (c) who is contracted to complete the project and (d) what penalties have been requested and paid?
Reply:
(1)(a) The Rand Water project Palmiet RW-06 started in March 2014.
(1)(b)(i) The overall project is currently 90% complete. The overall scope of work for this project is the construction of a 15km pipeline and the portion now to be completed is approximately 700m which includes pipelaying together with the associated concrete chambers. Thereafter tie-ins/cross connections of the entire 15km pipeline will be constructed and this is dependent on the shutdowns.
(1)(b)(ii) The project experienced challenges which were beyond Rand Water and the service provider’s control as follows:
- All service providers experienced unsuitable ground conditions which included excessive rock and a high water table. These conditions were not predetermined and as such had to be decided upon within the project time lines which then resulted into delays.
- During implementation, the pipeline route had to be changed to accommodate third party requirements (i.e. restrictions related to working within the vicinity of high voltage ESKOM powerlines and late approval of Water Use Licence (WULA) by the department). This added in the delays experienced by the project.
(1)(b)(iii) The expected completion date is April 2020.
(2)(a)(i) The expenditure to date is R597 396 518.29 excluding Vat.
(2)(a)(ii) The original costing of the project was R668 556 000.00 excluding Vat.
(2)(b) The contractors and consultants on the original project where the following:
Contractors:
- M&D Construction Group (Portion A pipe laying – 8km)
- Lubbe Construction (Pty) Ltd (Portion B pipe laying – 7km)
- Esor / SBM Joint Venture (Portion B pipe jacking)
- Mapitsi Civil Works (Portion A pipe jacking).
Consultants:
- Jeffares and Green (Pty) Ltd.
(2)(c) The service providers listed in question (2)(b) above are all contracted to complete the project. Lubbe Construction (Pty) Ltd is currently completing their scope of work on portion B where they are left with 700m of pipelaying against the scope work of 7km.
(2)(d) Penalties have been applied and are being progressively deducted for all contractor delays.
---00O00---
26 March 2019 - NW494
Khawula, Ms MS to ask the Minister of Water and Sanitation
What is the (a) qualification and (b) total number of artisans employed by each water board?
Reply:
Refer to the table below for the list of qualifications and number of artisans employed by each water board.
Entity |
(a) Qualification |
(b) Total number of artisan |
Amatola Water |
Artisan Building work |
4 |
Artisan Electrical |
6 |
|
Artisan Fitter and Turner |
11 |
|
Artisan Instrumental |
2 |
|
Artisan Mechanical |
4 |
|
Artisan Millwright |
1 |
|
Artisan Plumber |
4 |
|
Artisan Welder |
1 |
|
Bloem Water |
Artisan Electrical |
5 |
Artisan Mechanical |
12 |
|
Artisan Civil |
2 |
|
Artisan Instrumental |
4 |
|
Lepelle Northern Water |
Fitter, Electrician and Motor Mechanic; Maintenance Officers; Instrumentation Technicians |
56 |
Magalies Water |
N4 Electrical Engineering |
14 |
N4 Electrical Engineering |
||
N6 Electrical Engineering |
||
National Technical Certificate 4 |
||
Grade 12 |
||
ND Electrical Engineering |
||
N3 Electrical Engineering |
||
N6 Electrical Engineering |
||
N3 Mechanical Engineering |
||
N4 Mechanical Engineering |
||
N5 Mechanical Engineering |
||
ND Mechanical Engineering |
||
N3 Mechanical Engineering |
||
N2 Mechanical Engineering |
||
Mhlathuze Water |
Trade Test Instrument Mechanic; National Diploma: Electrical Engineering; Trade Test Boiler Maker; Trade Test Electrician; Trade Test Fitter; Trade Test Millwright; Trade Test Plumber; Trade Test Welder |
26 |
Overberg Water |
None in terms of the qualification specified |
9 |
Rand Water |
Dry Trades Electricians Filters and Turners Instrument Mechanicals Millwrights Motor Mechanics Telephone Electrician Welders |
163 |
Wet Trades Painters Plumbers |
39 |
|
Sedibeng Water |
N3 – N6 Certificates |
43 |
National Diploma |
||
Umgeni Water |
Matric; N2 plus Trade Test (Electrical, Civil, Mechanic, Boilermaking, Instruments) |
79 |
---00O00---
26 March 2019 - NW189
Dreyer, Ms AM to ask the Minister of Water and Sanitation
Whether any investigations have been conducted into the continuing sewerage overflow at 25 Quinine Street, Glen Marais, Kempton Park; if not, (a) what steps will be taken to resolve the matter, (b) by what date will the specified matter be resolved, (c) what is the estimated cost, (d) what number of complaints has the Ekurhuleni Metropolitan Council received regarding the matter and (e) why was the matter not resolved earlier given the number of complaints; if so, will he furnish Mrs A M Dreyer with a copy of the findings of the specified investigation?
Reply:
According to information received by the department from the City of Ekurhuleni, findings of an investigation were that the sewerage overflow is as results of storm water ingress, especially when it is raining. Furthermore, building owners in the area have connected rain water gutters and are channelling storm water into sewer lines; which worsened the problem.
a) To resolve the problem at 60 Quinine Street specifically, the CoE has already installed non-return valves to prevent the backflow into the house. The plan is to install valves at all the other properties affected by overflows and back flows in the aftermath of rain.
The City of Ekurhuleni (CoE) is planning to send building inspectors who will assist in investigating illegal connections to the municipal sewer system. Furthermore, the CoE, through its Water and Sanitation Division, will facilitate the disconnection of all illegal connection pipes and also install non-return valves at critical affected areas.
For further information relating to (b), (c), (d) and (e); the Honourable Member is requested to refer the questions to the Minister of Corporative Governance and Traditional Affairs (CoGTA) who will be in a better position to respond to specific details relating to the timelines to resolve the problem, costs and the number of complaints received by the Municipality with regard to this matter.
---00O00---
26 March 2019 - NW818
Khawula, Ms MS to ask the Minister of Water and Sanitation
Since his reply to question 1791 on 14 August 2018, how many households currently use bucket toilets?
Reply:
The following beneficiary towns (see table below) from the Bucket Eradication Programme are still using bucket toilets as the construction of bulk infrastructure that will allow toilets to flush are currently in process.
PROVINCE |
LOCAL MUNICIPALITY |
BUCKET ERADICATION TOWN |
TOILETS NOT YET FLUSHING |
Free State Province |
Setsoto |
Ficksburg |
218 |
Senekal |
2,435 |
||
Clocolan |
3,379 |
||
Nketoana |
Arlington |
1,192 |
|
PetrusSteyn |
960 |
||
Reitz |
739 |
||
Tokologo |
Dealesville |
1,279 |
|
Northern Cape Province |
Siyancuma |
Griekwastad |
387 |
Campbell |
596 |
||
Tsantsabane |
Maranteng |
134 |
|
Postdene |
149 |
||
Sol Plaatjie |
Motswedimosa |
656 |
|
Fraser Moleketi |
97 |
||
TOTAL: |
12 221 |
---00O00---
25 March 2019 - NW638
Khawula, Ms MS to ask the Minister of Water and Sanitation
(1)What (a) total amount of drought relief funding was allocated to each province (i) in the 2017-18 and (ii) for the 2018-19 financial years and (b) amount of the funding has been spent; (2) are any of the funds unaccounted for; if not, what is the position in this regard; if so, what are the relevant details?
Reply:
The Hounorable Member is requested to note that the response provided in NA 242 of 15 February 2019 on drought relief to each province from 2017-2019 was adequately responded to.
---00O00---
25 March 2019 - NW107
Dreyer, Ms AM to ask the Minister of Water and Sanitation
(1)(a) How often must his department inspect dam infrastructure with regard to (i) dam walls and (ii) spillways and (b)(i) who conducts such inspections and (ii) under what statutory provisions is the person or entity authorised; (2) (a) on what date was the last inspection of each dam performed by his department in Gauteng and (b) what number of dams (i) passed and (ii) failed the inspection; (3) with regard to dams situated within the City of Ekurhuleni, (a) what concerns and recommendations were raised in respect of each dam, (b) on what date was the City of Ekurhuleni notified about the concerns and recommendations and (c) by what date was the City of Ekurhuleni expected to rectify all defects in the dam infrastructure, including dam walls and spillways, in each case?
Reply:
(1)(a) All dams classified as dams with a safety risk by the Directorate: Dam Safety Regulation (i.e. Dam Safety Office) and are category II and III in terms of size must be subjected to a compulsory 5 yearly dam safety evaluation by an Approved Professional Person (APP).
(1)(b) The owner of a Category II or III dam must appoint an Approved Professional Person (APP) to conduct a dam safety evaluation at 5 years intervals. This regulatory provision is in terms of Section 118 and 119 of the National Water Act as well as Government Notice R 139 of 24 February 2012 (i.e. Dam Safety Regulations).
(2) Refer to Annexure A for the inspection dates, number of dams that passed or failed the inspection in Gauteng.
(3)(a) Refer to Annexure B for the APP recommendations.
(3)(b) Refer to Annexure C for the letters of acceptance or rejection sent to the City of Ekurhuleni after receipt of the Dam Safety Evaluation report from the APP.
(3)(c) Refer to Annexure C.
--00O00---
25 March 2019 - NW167
Lekota, Mr M to ask the Minister of Water and Sanitation
What (a) are the root causes of the current water crisis in the Makana Local Municipality and (b) steps has he taken to resolve the crisis?
Reply:
a) The root causes of the current water crisis in Makana Local Municipality (LM) are due to aged infrastructure, increased demand and some recent operational deficiencies and the current drought conditions.
The latter has led to electrical failure and therefore disruption of plant operations has affected the town area, but has since been fixed. The Eastern Cape Provincial Office is working very hard to ensure plant operations are restored to the maximum design capacity but it is partly functional and currently produces 50% of its capacity. The work is to be completed by end of March 2019.
b) The following interventions are in place to deal with the crisis:
- The Department has embarked on various Water Conservation and Demand Management Strategies which include rationing of water, dealing with major leaks, tankering to high laying areas and bottle water distribution in partnership with the “Gift of the Givers” a known Non-Governmental Organisation (NGO). In addition, alternative sources are being explored by drilling boreholes which are to be linked to the current systems across Makana LM including Riebeeck East and Alicedale.
- The linkages of both the East and West water supply systems will enable access to reliable controlled/restricted supply to cater for the Makhanda communities during the drought period and will be fully functional by end of March 2019.
- In dealing with the increased demands, the Department has appointed Amatola Water Board to double the current treatment capacity of one of the treatment works from 10 ML/d to 20ML/d to meet current and future demands until 2030. Phase 1 of 4 phases is to be completed in March 2019. This phase will allow pumping of treated water from the eastern side to the western side which is currently at critical storage levels.
- Furthermore, the Department has advised the Municipality to reprioritise its Municipal Infrastructure Grant (MIG) to deal with the replacement of major components in the distribution system .This is due to the fact that the current funding trends and the revenue base of the municipality is inadequate to effectively address the current aged infrastructure and/or asset management in general. The Amatola Water Board is also in partnership with the Department in providing operational support to oversee and guide plant operators.
---00O00---
25 March 2019 - NW242
Khawula, Ms MS to ask the Minister of Water and Sanitation
(a) What is the total amount of drought relief that was allocated to each province in (i) 2016, (ii) 2017 and (iii) 2018, (b) what amount has been spent by each province to date and (c) what have been the most common items on which the money has been spent?
Reply:
Refer to the table below for Main Account Allocated Budget for Drought Relief:
(a) |
(b) |
(c) |
||
Financial Year |
Province |
Adjusted Budget R’000 |
YTD Expenditure R’000 |
Expenditure Items |
2015/16 |
Kwa-Zulu Natal |
50 500 |
50 500 |
Transfers & Subsidies: Water Services Operating Subsidy (WSOS) 5B grant reprioritised for Drought Relief Intervention |
106 270 |
111 836 |
Payments for capital assets: Buildings and other fixed structures |
||
Total |
156 770 |
162 336 |
||
2016/17 |
Eastern Cape |
5 883 |
5 725 |
Goods & Services: Contractors – Water tankering |
Kwa-Zulu Natal |
290 700 |
301 168 |
Payments for capital assets: Buildings and other fixed structure |
|
Free State |
21 100 |
20 363 |
Goods & Services: Contractors – Water tankering |
|
North West |
24 512 |
24 512 |
Goods & Services: Contractors – Water tankering |
|
Total |
342 195 |
351 768 |
||
2017/18 |
Eastern Cape |
17 548 |
17 548 |
Goods & Services: Contractors, Water Tanks and Travel & Subsistence – Water tankering |
Kwa-Zulu Natal |
10 432 |
10 432 |
Goods & Services: Contractors, Water Tanks and Travel & Subsistence – Water tankering |
|
Free State |
11 498 |
11 498 |
Goods & Services: Contractors, Water Tanks and Travel & Subsistence – Water tankering |
|
North West |
545 |
545 |
Goods & Services: Contractors and Travel & Subsistence – Water tankering |
|
Mpumalanga |
1 093 |
10 93 |
Goods & Services: Contractors and Water Tanks– Water tankering |
|
Total |
41 116 |
41 116 |
||
2018/19 |
Eastern Cape |
647 214 |
49 021 |
Payments for capital assets: Buildings and other fixed structures, Transfers & Subsidies |
Kwa-Zulu Natal |
122 366 |
- |
Payments for capital assets: Buildings and other fixed structures |
|
Limpopo |
97 475 |
- |
Payments for capital assets: Buildings and other fixed structures |
|
Mpumalanga |
56 800 |
56 800 |
Buildings and other fixed structures, Transfers & Subsidies |
|
Northern Cape |
9 788 |
- |
Payments for capital assets: Buildings and other fixed structures |
|
North West |
309 649 |
10 000 |
Payments for capital assets: Buildings and other fixed structures, Transfers & Subsidies |
|
Western Cape |
58 919 |
- |
Payments for capital assets: Buildings and other fixed structures |
|
Total |
1 302 211 |
115 821 |
||
Grand Total |
1 815 292 |
671 041 |
Refer to the table below for Water Trading Entity (WTE) Allocated Budget for Drought Relief:
(a) |
(b) |
(c) |
||
Financial Year |
Province |
Adjusted Budget R’000 |
YTD Expenditure R’000 |
Expenditure Items |
2016 |
Kwa-Zulu Natal |
306 278 |
302 910 |
Boreholes, Water Tanker Rental and Programme Management |
2017 |
Kwa-Zulu Natal |
2 961 |
2 597 |
Boreholes, Water Tanker Rental and Programme Management |
2018 |
Kwa-Zulu Natal |
Nil or no budget was allocated |
||
Total |
309 239 |
305 507 |
---00O00---
25 March 2019 - NW271
Khawula, Ms MS to ask the Minister of Water and Sanitation
What number of (a) tender briefings were held in 2018 by (i) his department and (ii) each of the entities reporting to him and (b) the specified briefings were compulsory?
Reply:
(a)(i) A total of four (4) tender briefings were held in 2018 by the Department.
(a)(ii) A total of 187 tender briefing were held in 2018 by the entities reporting to me.
(b) All four (4) tender briefings held by the Department were compulsory and a total of 186 tender briefings were compulsory and only one (1) briefing was non-compulsory for the entities reporting to me.
---00O00---
25 March 2019 - NW372
Lees, Mr RA to ask the Minister of Water and Sanitation
What (a) are the details of the processes followed by the Uthukela District Municipality in KwaZulu-Natal in awarding contracts for the transport and supply of water by road tanker transport to consumers from 1 January 2014, (b) are the (i) names, (ii) identity or company registration numbers and (iii) physical and postal addresses of each person and/or company contracted to deliver water to consumers, (c) is the (i) duration, (ii) value and scope of each contract and (iii) total amount paid in each case and (d) is the number of loads delivered and distances travelled by each contractor?
Reply:
The Hounorable Member is requested to refer the question to the Minister of Cooperative Governance and Traditional Affairs who will be in better position to respond to the awarding contracts for the transport and supply of water by road tanker to consumers by the Uthukela District Municipality in KwaZulu-Natal.
---00O00---
25 March 2019 - NW639
Khawula, Ms MS to ask the Minister of Water and Sanitation
What is the (a) location and (b) capacity of each privately owned dam in the country?
Reply:
Refer to Annexure A for the dams with location and capacity where the information was supplied in full.
---00O00---
20 March 2019 - NW360
Waters, Mr M to ask the Minister of Transport
Whether the bridge structure on the corner of the R25 and M39 situated within the Ekurhuleni Metropolitan Council has been inspected recently; if not, (a) on what date will an inspection be conducted and (b) how often should infrastructure be inspected as provided for by his department’s policy; if so, (i) on what date, (ii) by whom was it inspected and (iii) what were the findings and recommendations of the report?
Reply:
Yes, the bridge structure on the corner of the R25 and M39 situated within the Ekurhuleni Metropolitan Council has been inspected recently;
(a) The inspection is conducted on a going basis
(b) The department’s policy provides that infrastructure be inspected periodically
(i) 6 June 2016,
ii) Mr K Dahlgren from JG Afrika; and
(iii) Erosion at the embankment require backfilling, concrete at the abutments need to be replaced, interlocking paving blocks need to be reinstated, missing sidewalk kerbs need to be replaced, spalling on the parapets to be repaired.
11 March 2019 - NW150
Hugo, Mr RT to ask the Minister of Water and Sanitation
With reference to the reply of the Minister of Public Service and Administration to question 3797 on 21 December 2018, what was the total expenditure incurred by his department relating to the travel privileges contained in the 2007 Ministerial Handbook of former (a)(i) Ministers and (ii) their spouses, (b)(i) Deputy Ministers and (ii) their spouses, (c) Ministers’ widows or widowers and (d) Deputy Ministers’ widows or widowers (i) in each of the past five financial years and (ii) since 1 April 2018?
Reply:
We wish to advise the Honorable member that we are in a process of finalizing the information required, response will be made available within seven working days.
11 March 2019 - NW104
Waters, Mr M to ask the Minister of Water and Sanitation
(1)Whether, with reference to his reply to question 353 for oral reply on 21 November 2018, he will furnish Mr M Waters with copies of the results of each water quality test conducted for each month during 2018 by the Ekurhuleni Metropolitan Municipality; (2) which of the specified water quality tests failed to meet minimum standards?
Reply:
1. The response provided on 21 November 2018 to question 353 by the Department was adequately responded to. The Department monitors the data that is uploaded on the Integrated Regulatory Information System (IRIS) by both the Water Services Authority and Water Services Provider. Refer to the tables below for the compliance results for 2018:
Microbiological: Acute Health
Months |
Compliance |
Failures |
Samples |
January |
98.9% |
4 |
378 |
February |
99.7% |
1 |
351 |
March |
97.6% |
9 |
369 |
April |
98.3% |
6 |
353 |
May |
99.7% |
1 |
379 |
June |
>99.9% |
0 |
398 |
July |
99.5% |
2 |
386 |
August |
>99.9% |
0 |
392 |
September |
>99.9% |
0 |
383 |
October |
99.7% |
1 |
392 |
November |
99.7% |
1 |
390 |
December |
99.4% |
2 |
343 |
Total |
99.4% |
27 |
4 514 |
Chemical: Acute Health
Months |
Compliance |
Failures |
Samples |
January |
>99.9% |
0 |
101 |
February |
>99.9% |
0 |
92 |
March |
>99.9% |
0 |
92 |
April |
>99.9% |
0 |
84 |
May |
>99.9% |
0 |
88 |
June |
>99.9% |
0 |
96 |
July |
>99.9% |
0 |
92 |
August |
>99.9% |
0 |
92 |
September |
>99.9% |
0 |
88 |
October |
>99.9% |
0 |
92 |
November |
>99.9% |
0 |
92 |
December |
>99.9% |
0 |
80 |
Total |
>99.9% |
0 |
1 089 |
Chemical: Chronic Health
Months |
Compliance |
Failures |
Samples |
January |
>99.9% |
1 |
1 068 |
February |
>99.9% |
0 |
981 |
March |
>99.9% |
0 |
1 016 |
April |
>99.9% |
0 |
960 |
May |
>99.9% |
0 |
1 026 |
June |
>99.9% |
0 |
1 087 |
July |
>99.9% |
0 |
1 053 |
August |
>99.9% |
0 |
1 064 |
September |
>99.9% |
0 |
1 032 |
October |
>99.9% |
0 |
1 063 |
November |
>99.9% |
1 |
1 062 |
December |
>99.9% |
0 |
934 |
Total |
>99.9% |
2 |
12 346 |
Chemical -Non Health: Aesthetic
Months |
Compliance |
Failures |
Samples |
January |
99.5% |
3 |
293 |
February |
97.7% |
12 |
286 |
March |
95.8% |
23 |
289 |
April |
95.9% |
21 |
274 |
May |
96.0% |
22 |
287 |
June |
97.9% |
12 |
297 |
July |
99.8% |
1 |
295 |
August |
>99.9% |
0 |
294 |
September |
>99.9% |
0 |
292 |
October |
>99.9% |
0 |
297 |
November |
>99.9% |
0 |
303 |
December |
>99.9% |
0 |
271 |
Total |
98.6% |
94 |
314 |
Operational
Months |
Compliance |
Failures |
Samples |
January |
98.8% |
19 |
1 524 |
February |
99.1% |
13 |
1 428 |
March |
98.9% |
16 |
1 487 |
April |
99.2% |
11 |
1 418 |
May |
99.5% |
8 |
1 531 |
June |
99.7% |
4 |
1 596 |
July |
99.1% |
14 |
1 569 |
August |
99.9% |
2 |
1 591 |
September |
99.5% |
7 |
1 553 |
October |
99.4% |
10 |
1 585 |
November |
99.6% |
7 |
1 581 |
December |
99.4% |
9 |
1 392 |
Total |
99.3% |
120 |
|
2. None, the water quality test as provided above proves that there were no tests that failed to meet minimum standards as they are well above 95% for each test conducted during 2018.
---00O00---
18 December 2018 - NW3513
Wessels, Mr W to ask the Minister of Water and Sanitation
(1)What are the current water levels of the dams that supply water to the Mangaung Metropolitan Municipality; (2) how many litres of water were lost during the 2017-18 financial year in the specified municipality as a result of leakages, (3) whether he has found that the levels at the specified dams justify changing the current water restriction level; if not, why not; if so, what are the relevant details; (4) whether he will make a statement on the matter?
Reply:
(1) Refer to Annexure A for the current water levels of the dams that supply water to the Mangaung Metropolitan Municipality.
(2) The Mangaung Metropolitan Municipality has lost 13 334 248 000 litres of water during the 2017-18 financial year as a result of leakages.
(3) The Caledon-Modder Water Supply System that supply water for the Mangaung Metropolitan Municipality experienced significant drought conditions from around 2015 until 2017 seasons. Although the situation has improved a bit, drought conditions are still lingering into this 2018 season. Hence, some good inflows came into the dams of the system, easing the critical state of total dams’ storage from about 44% in May 2017 to about 57% in May 2018. May is the decision month for the system. Therefore, following the 2018 Annual Operating Analysis, the new system storage level justified changing water restrictions from 20% to 15% level.
(4) The Department held a Stakeholders Operation Forum (SOF) meeting, which involve water users from the system, in Mangaung on 4 October 2018, where results of the annual operation analysis, including the new restriction levels, were presented. Publication of a gazette notice for the new restriction levels is being processed.
---00O00---
18 December 2018 - NW3466
Khanyile, Ms AT to ask the Minister of Water and Sanitation
(1)(a) On what date did his department last conduct an audit of artwork owned by Government which is under his department’s curatorship and (b) what are the details of each artwork under the curatorship of his department according to the Generally Recognised Accounting Practice 103; (2) whether any artworks under his department’s curatorship have gone missing (a) in each of the past five financial years and (b) since 1 April 2018; if so, what are the relevant details?
Reply:
The Hounorable Member is requested to note that the Generally Recognised Accounting Practice 103 (GRAP 103) is applicable to Public Entities in the Arts and Culture sector that prescribes the uniform accounting for classifying and recording Heritage Assets and regulates related disclosure requirements. The Hounorable Member is requested to refer the question to the Minister of Arts and Culture.
---00O00---
18 December 2018 - NW3087
Basson, Mr LJ to ask the Minister of Water and Sanitation
(1)Whether a certain person (name and details furnished) was placed on suspension because the specified person refused to allow other projects of his department to access the R12 billion fund of the unit of the specified person; if not, why was the specified person placed on suspension; if so, (2) whether he supports the suspension of the specified person based on the specified person’s refusal to allow other departmental projects to misappropriate funds from the specified person’s unit; if not, what is the position in this regard; if so, what are the relevant details; (3) whether he has taken any steps to prevent the units of his department from misappropriating funds from each other; if not, why not; if so, what are the relevant details?
Reply:
1. No.
2. Falls away.
3. Yes, compliance with the PFMA is encouraged by the Accounting Officer.
---00O00---
18 December 2018 - NW3273
Khawula, Ms MS to ask the Minister of Water and Sanitation
Whether (a) his department and/or (b) entities reporting to him awarded any contracts and/or tenders to certain companies (names and details furnished) from 1 January 2009 up to the latest specified date for which information is available; if so, in each case, (i) what service was provided, (ii) what was the (aa) value and (bb) length of the tender and/or contract, (iii) who approved the tender and/or contract and (iv) was the tender and/or contract in line with all National Treasury and departmental procurement guidelines?
Reply:
Refer to the table below:
The Department |
None |
|
The Entities |
Amatola Water |
None |
Bloem Water |
None |
|
Lepelle Northern Water |
None |
|
Magalies Water |
None |
|
Mhlathuze Water |
None |
|
Overberg Water |
None |
|
Sedibeng Water |
None |
|
Umgeni Water |
None |
|
Trans Caledon Tunnel Authority (TCTA) |
None |
|
Rand Water |
Yes, Refer below for the response |
|
Water Research Commission (WRC) |
Yes, Refer below for the response |
Rand Water:
Rand Water awarded work to 1 of the 13 companies provided in the list, namely Vox Telecommunications. The work was awarded from 07 March 2013 up to 26 July 2018. The awards were made in accordance with the applicable SCM practices.
-2-
The table below provides the details required for (i) to (iv):
Doc. Date |
Purch.Doc. |
Description |
Net Value |
Duration |
Approver |
26.07.2018 |
4500205144 |
Request for Room Booking Panel |
156,113.66 |
Once-off |
Supply Chain |
19.06.2018 |
4500204614 |
Off Premise Contact Centre 201805 |
278,650.74 |
6 months |
Supply Chain |
30.04.2018 |
4500203783 |
Email Filtering & Security Services |
431,728.00 |
10 months |
Supply Chain |
10.04.2018 |
4500203488 |
Supply & Delivery of Internet Service |
335,738.73 |
10 months |
Supply Chain |
31.01.2018 |
4500202608 |
Internet service for 3 months |
438,129.63 |
3 months |
Supply Chain |
30.01.2018 |
4500202579 |
Internet service |
400,000.00 |
Once-off |
Supply Chain |
01.11.2017 |
4500201570 |
Internet Services for 3 months |
437,481.57 |
3 months |
Supply Chain |
20.10.2017 |
4500201336 |
Call Centre Systems 6 months |
430,701.12 |
6 months |
Supply Chain |
26.07.2017 |
4500199366 |
Internet Services for a period of three months |
306,473.46 |
3 months |
Supply Chain |
31.05.2017 |
4500197701 |
Off Premise Contact Centre for WOL 6mnth |
400,080.05 |
6 months |
Supply Chain |
29.06.2016 |
4500184884 |
WOL-Installation& Configuration Contact c |
486,651.78 |
Supply Chain |
|
12.05.2015 |
4500164350 |
Vox tender cost routing |
2,151,160.88 |
24 months |
BAC |
14.04.2015 |
4500163033 |
Cost Routing Service |
149,658.72 |
6 months |
Supply Chain |
17.03.2015 |
4500161587 |
cost routing telephone |
116,823.68 |
||
25.02.2015 |
4500160456 |
Cost routing for telephones |
127,285.11 |
||
09.02.2015 |
4500159599 |
Cost routing telephone |
127,285.11 |
||
23.01.2015 |
4500158801 |
Cost Routing Telephone |
766,743.82 |
Once-off |
BAC |
06.03.2014 |
4500143226 |
RFP00237/13A Internet service 3yrs |
5,196,449.72 |
36 months |
BAC |
19.06.2013 |
4500131227 |
Audio / Video Conferencing |
204,949.20 |
Once-off |
Supply Chain |
07.03.2013 |
4500126223 |
Cost routing telephones |
2,996,290.64 |
24 moths |
BAC |
TOTAL |
15,938,395.62 |
Water Research Commission (WRC)
b) Water Research Commission
(i) Provision of Cloud Hosting Services to the Water Research Commission (WRC) for a period of twelve (12) months
(ii) (aa) The Contract value amounted to R 493 085.50 (Inclusive of Vat)
(bb) Contract period of twelve (12) months, Contract award date: 10 September 2018
(iii) The contract was evaluated by the Bid Evaluation Committee and approved by the Bid Adjudication Committee in line with their approval delegation
(iv) The approved tender and contract award processes followed was in line with all National Treasury and the WRC procurement policies and procedures.
The contract awarded to Vox Telecommunications (Pty) Ltd (Company registration number: 2011/000797/07) was cancelled on the 22 November 2018 due to the company failing to commence with the contract as per the agreed contract terms and conditions. The contract start date was 01 October 2018, the company failed to commence on that date and the start date was extended to 01 November 2018 and was unable to migrate the WRC data and thus again failed to commence with delivering the contracted services. The company provided the technical reasons why they were unable to provide the services and estimated that the data transfer would take three months this was not acceptable to the WRC. The WRC then served VOX Telecommunications (Pty) Ltd with a contract termination letter on the 22 November 2018, which they accepted and agreed to reimburse the WRC an amount of R 7 509.23 which incurred as a result of the delays during the month of November 2018.
---00O00---
18 December 2018 - NW3861
Mhlongo, Mr TW to ask the Minister of Water and Sanitation
(1)Whether (a) his department and/or (b) any entity reporting to him contracted the services of a certain company (name and details furnished), in each of the past 10 financial years; if so, what (i) number of contracts were signed, (ii) was the date on which each contract was signed, (iii) was the duration of each contract, (iv) services did the company render and (v) was the monetary value of each contract in each case; (2) whether any irregular expenditure relating to the contracts was recorded and/or condoned in each case; if so, what are the relevant details?
Reply:
(1)(a) No.
(1)(b) No.
(2) Falls away.
---00O00---
18 December 2018 - NW3753
Waters, Mr M to ask the Minister of Water and Sanitation
(1)Â Â Â Â Â Â (a) How often does her department conduct inspection visits to sewerage processing plants throughout the country, (b) what are the dates of the latest inspections at each sewerage plant, (c) which plants failed to meet minimum standards and (d) what action was taken in each regard; (2) whether she has been informed of the allegation that 50 000 litres of sewerage flows into our rivers every day (details furnished); if not, what is the position in this regard; if so, (a) what action is her department taking in this regard and (b) which municipalities are the biggest culprits in this regard?
Reply:
(1)(a) The Department prioritizes sewerage plants that were found to be critical in terms of their operation and monitors them quarterly.
(1)(b) The latest inspections were done in the previous quarter.
(1)(c) Refer to Annexure A for the list of plants that failed to meet the minimum standards in the last quarter (July-September 2018).
(1)(d) Refer to Annexure B for the Non-Compliance letter issued by Northern Cape Provincial operations for Siyathemba LM associated with the following WWTW refer to:
- Prieska WWTW
- Marydale WWTW
- Niekerkshoop WWTW
2. The Department is aware of these media reports; and, is dealing with this non-compliance through routine inspections of these wastewater treatment works and through administrative action where non-compliance occurs.
---00O00---
Annexure A
List of Plants which failed to meet the minimum standards in the last quarter (July-September 2018):
- Tugela Ferry WWTW
- Rosendaal (Mautse)WWTW
- Winburg WWTW
- Steynsrus WWTW
- Wesselsbron WWTW
- Heilbron WWTW
- Ekangala WWTW
- Rooiwal East WWTW
- Rooiwal North WWTw
- Flip Human WWTW
- Zongesien WWTW
- Senwamokgope WWTw
- Elandskraal WWTW
- Groblersdal WWTW
- Jane Furse WWTW
- Moroke Mecklenberg WWTW
- Motetema WWTW
- Tubatse WWTW
- Musina Singelela WWTW
- Thohoyandou WWTW
- Balfour WWTW
- Grootvlei Eskom WWTW
- Grootvlei Mine WWTW
- Siyabuswa WWTW
- Ferrobank WWTW
- Riverview WWTW
- Kriel WWTW
- Ruitspruit WWTW
- Delmas WWTW
- Botleng WWTW
- Waterval Boven WWTW
- Belfast WWTW
- Kwazamokuhle WWTW
- Blinkpan WWTW
- Brits WWTW
- Lethlabile WWTW
- Delareyville WWTW
- Atamelang WWTW
- Wolmaranstad WWTW
- Leeudoringstad WWTW
- Rulaganyang WWTW
- Warrenton WWTW
- Jankempsdorp WWTW
- Douglas WWTW
- Griekwastad WWTW
- Hopetown New WWTW
18 December 2018 - NW3476
Johnson, Mr M to ask the Minister of Water and Sanitation
Despite the many challenges confronting his department, what are the details of the achievements of his department since 27 April 1994?
Reply:
The Department is in the process of compiling the summary of all the Annual Reports since 1994/1995 to date, where the challenges and achievements are outlined. As soon as this information is ready the information will be made available.
---00O00---
18 December 2018 - NW3908
Khawula, Ms MS to ask the Minister of Water and Sanitation
Whether, with reference to the reply of the Minister of Public Service and Administration to question 141 for oral reply on 7 September 2018, his department and the entities reporting to him implemented the Public Service Coordinating Bargaining Council resolution that all persons employed in the Public Service as Assistant Directors must have their salary level upgraded from level 9 to level 10, and that all Deputy Directors must have their salary level upgraded from level 11 to level 12; if not, why not; if so, what are the relevant details?
Reply:
No, it should be noted that not all the Assistant Director and Deputy Director posts in this Department are on level 10 and 12. There are some that have been originally graded on post levels 9 and 11. The Job Evaluation information (generated through the Job Evaluation system) has been used to determine the grading of these jobs. Subsequently, the Job Evaluation results are factored into the approved organizational structure of the Department. Hence, the Job Evaluation database is created to reflect all the jobs, inclusive of all the Assistant Directors and Deputy Directors which are on 9, 10, 11 and 12.
---00O00---
03 December 2018 - NW2963
Mulaudzi, Adv TE to ask the Minister of Water and Sanitation
With reference to his reply to question 2470 on 8 October 2018, (a) who are the contractors constructing each dam, (b) what is the value of each specified contract and (c) on what date was each contract signed?
Reply:
Refer to the table below for the list of constructors constructing dams in all provinces:
ITEM |
DAM INFORMATION |
||
Name of Dam |
Clanwilliam Dam |
Hazelmere Dam |
Tzaneen Dam |
GPS Location |
32°11'5.1"S 18°52'28.5"E |
29°35'55"S 32°2'36"E |
23°47'57"S 30°09'58"E |
Province |
Western Cape |
KwaZulu Natal |
Limpopo |
River/ Watercourse |
Olifants |
Mdloti |
Letaba |
Size/ Capacity (Million Cubic Meters) |
125Mm³ (existing) 344Mm³ (raised) |
23.9 Mm³ (existing) 43.6Mm³ (raised) |
158Mm³ (existing) 193 Mm³ (raised) |
Purpose |
Irrigation & Domestic Use |
Irrigation & Domestic Use |
Domestic Commercial |
Estimated Construction Cost |
R 2.2 Billion (Raising of existing Dam Only) |
R 600 Million (total project costs, including professional fees, implementing Agent fees, Project Management office on site) |
R367.4 Million (Estimate cost including VAT) R322 Million (Estimate cost excluding VAT) |
Contractors constructing each dam |
DWS Construction Unit |
Group Five |
DWS Construction Unit to be appointed |
The value of each specified contract |
R 3 726 735 402 (inclusive of all project components excluding escalation and VAT |
R498 157 000.00 dam only at tender stage |
R367.4 Million (Estimate cost including VAT, Contingencies & Contract Price Adjustment) R322 Million (Engineer’s Estimate in August 2018 excluding the above costs. |
Date on which each contract was signed |
10 October 2018 (Temporary access granted to DWS Construction) |
01 June 2015 |
Not yet signed (Currently in Evaluation prior to Award) |
---00O00---
03 December 2018 - NW3138
Mkhaliphi, Ms HO to ask the Minister of Water and Sanitation
What contingency measures are currently in place or are being planned for the citizens affected by the incompletion of the Giyani Water Project?
Reply:
The Interim measure includes refurbishment of the boreholes with treatment package plants, several communities are already benefiting from the boreholes. The construction of the bulk pipeline is underway and it is anticipated that that 55 communities with 46 607 households will benefit from the project once it is completed.
A Recovery Plan has been designed; and will be taken to the Community and Municipal Leaders for concurrence in the next few days.
---00O00---
03 December 2018 - NW3199
Hugo, Mr RT to ask the Minister of Water and Sanitation
(a) What is the current status of the official vehicle that was purchased for his predecessor, Ms N P Mokonyane, (b) where is the specified vehicle being housed, (c) what is the cost of the vehicle and (d) on what date was it purchased; (2) Whether the vehicle is currently in use; if so, (a) who is using the vehicle and (b) for what purpose?
Reply:
(1)(a) The Vehicle was transferred to the Department of Communications.
(1)(b) I do not know.
(1)(c) The cost of the vehicle was R 910 714, 90.
(1)(d) The vehicle was procured in January 2018.
(2) Falls away.
---00O00---
03 December 2018 - NW3255
Mbabama, Ms TM to ask the Minister of Water and Sanitation
What (a) amount did (i) his department and (ii) each entity reporting to him borrow from any entity in the People’s Republic of China (aa) in each of the past three financial years and (bb) since 1 April 2018, (b) is the name of the lender of each loan, (c) conditions are attached to each loan and (d) are the repayment periods for each loan in each case?
Reply:
Neither the Department nor Entities reporting to the Minister of Water and Sanitation borrowed any monies from the People’s Republic of China.
---00O00---
03 December 2018 - NW3480
Hugo, Mr RT to ask the Minister of Water and Sanitation
How much water is being saved across the country each month due to his department’s War on Leaks programme?
Reply:
The consolidated water balance for the first 9 months of the 2017/18 within the eight large water supply systems based on the data as at Dec 2017 indicates a savings achievements of 25,2 million m3/a which translates to a savings of 12,6%.
---00O00---
03 December 2018 - NW3600
Basson, Mr LJ to ask the Minister of Water and Sanitation
(1)(a) What is the (i) name and (ii) current safety status of each dam under the control of his department, (b) when last did the dam safety office of his department conduct safety inspections on each dam and (c) what was the outcome of the inspection in each case; (2) what mechanisms has his department put in place to deal with dams that pose safety risks?
Reply:
(1) Refer to Annexure A for the details on current safety status of each dam. In Part (1). Table 1 of the annexure explains the condition rating of the dam based on the most recent Dam Safety Evaluation (DSE) report by an Approved Professional Person (APP). Table 2 contains a list of category 2 and 3 dams which must be subjected to a five yearly DSE (category 1 dams are excluded). Condition rating system based on the outcome of a Dam Safety Evaluation (DSE) was implemented in 2016, which explains why only 72 dams on the list have a condition rating indicating their safety status as reviewed by the Dam Safety Office. Table 2 also indicates the dams that have been rehabilitated to improve their safety and will only be evaluated at least 5 years after construction completion as well as 41 dams that are currently been evaluated by APP’s.
(2) The outcomes of dam safety evaluations determine the type of intervention/mechanism required to address the safety risk. These interventions/mechanisms could either be maintenance related or capital intensive where dam rehabilitation is required. For maintenance related issues the Cluster or Operation Managers are usually tasked to address these as part of routine maintenance as prescribed in the operations and maintenance manuals. For capital intensive safety risks are addressed through Dam Safety Rehabilitation Programme (DSRP).
---00O00---
Annexure A
Table 1: Dam Safety: Proposed Score Card for the Condition of a Dam
Symbol /Score |
Analysis of condition from the Recommendations and Findings of a Dam Safety Evaluation Report by an APP |
A |
Dam in good condition and routine maintenance are acceptably up to date. An evaluation interval of longer than 5 years can be recommended (if the owner request it or for farmers/ smaller municipalities.) |
B |
Dam in reasonable condition but not complying to modern standards. Only routine maintenance and routine inspections recommended. An evaluation interval of longer than 5 years cannot be recommended. |
C |
Significant outstanding maintenance by the normal operation and maintenance staff recommended restoring dam to a functional state. Elementary monitoring systems like settlement beacons and flow monitoring included here. |
D |
Significant rehabilitation recommended to restore dam components to its original state for example repair major erosion or cavitation’s, repair slope protection, reinstate crest level, refurbish outlet works or gates. Work is considered significant rehabilitation if it is outside the capacity of the normal operation and maintenance staff and the appointment of a contractor is necessary and the work should be done under guidance of an APP. Drafting of an Operation and Maintenance Manual and or Emergency Preparedness Plan and install sophisticated monitoring instruments under guidance of an APP also included here. |
E |
Upgrading recommended for example increase spillway capacity, increase freeboard, provide buttress / thicken dam to improve stability or install stress cables, install slope protection, install additional drainage or grouting or water seals to reduce leakage. A licence to alter and the services of an APP will be required. |
F |
Dam unsafe. Restrictions on operation recommended, for example water level may not exceed a specified level. |
Table 2: List of DWS owned dams (Category II and III only)
No. |
Name of dam |
Size Class |
Hazard Rating |
Category |
Date Last DSE |
Condition / Status |
1 |
RAMAH CANAL BALANCING NO 1 |
Small |
Significant |
2 |
1-Jan-91 |
|
2 |
BISSETSDRIFT CROSSING DAM |
Small |
Significant |
2 |
1-Jun-96 |
|
3 |
JAN TSHATSHU DAM |
Small |
Significant |
2 |
24-Aug-99 |
Rehab |
4 |
WOBURN 3 DAM |
Small |
Significant |
2 |
25-Oct-05 |
|
5 |
LIMIETSKLOOF DAM |
Medium |
Significant |
2 |
3-Dec-99 |
|
6 |
ELANDSDRIFT STUDAM |
Medium |
High |
3 |
28-May-01 |
|
7 |
MAJOLA DAM |
Medium |
Low |
2 |
31-May-01 |
|
8 |
MAGWA DAM |
Medium |
Significant |
2 |
31-May-01 |
|
9 |
GCUWA DAM |
Medium |
High |
3 |
1-Jun-01 |
|
10 |
NSAMI DAM |
Medium |
High |
3 |
1-Sep-02 |
Rehab |
11 |
RUST DE WINTER DAM |
Large |
High |
3 |
29-Jan-03 |
Rehab |
12 |
TAUNG DAM |
Large |
High |
3 |
11-Aug-03 |
Rehab |
13 |
PONGOLAPOORT DAM |
Large |
High |
3 |
3-Oct-03 |
DSE In progress |
14 |
HAMMARSDALE DAM |
Small |
High |
2 |
21-Jan-04 |
Rehab |
15 |
DIMBAZA DAM |
Small |
Significant |
2 |
10-Sep-04 |
DSE In progress |
16 |
BOSPOORT DAM |
Medium |
High |
3 |
10-Dec-04 |
Rehab |
17 |
NKADIMENG DAM |
Medium |
Significant |
2 |
24-Jan-05 |
Rehab |
18 |
CATA DAM |
Large |
High |
3 |
1-Feb-05 |
Rehab |
19 |
THABINA DAM |
Large |
High |
3 |
16-Feb-05 |
|
20 |
DONNY BROOK 1 DAM |
Medium |
Low |
2 |
6-Aug-05 |
|
21 |
GLENBROCK DAM |
Medium |
High |
3 |
19-Aug-05 |
|
22 |
KLEIN MARICOPOORT DAM |
Medium |
High |
3 |
4-Oct-05 |
DSE In progress |
23 |
MNYAMENI DAM |
Large |
High |
3 |
25-Oct-05 |
|
24 |
WOBURN 2 DAM |
Small |
Significant |
2 |
25-Oct-05 |
|
25 |
RIETSPRUIT DAM |
Medium |
Significant |
2 |
1-Feb-06 |
|
27 |
SINGIZI DAM |
Medium |
Significant |
2 |
22-Aug-06 |
|
28 |
DAMANI DAM |
Medium |
High |
3 |
28-Sep-06 |
|
29 |
GRASSRIDGE DAM |
Medium |
High |
3 |
21-Nov-06 |
|
30 |
ROXENI DAM |
Medium |
Significant |
2 |
24-Nov-06 |
DSE In progress |
31 |
SHESHEGU DAM |
Medium |
Low |
2 |
24-Nov-06 |
DSE In progress |
32 |
DABI DAM |
Medium |
Low |
2 |
27-Nov-06 |
DSE In progress |
33 |
NQWELO |
Medium |
Significant |
2 |
27-Nov-06 |
DSE In progress |
34 |
RURA DAM |
Medium |
Significant |
2 |
27-Nov-06 |
DSE In progress |
35 |
METSIMATSHO (SWARTWATER) |
Medium |
Significant |
2 |
10-Jan-07 |
DSE In progress |
36 |
NQADU DAM |
Medium |
Significant |
2 |
26-Jan-07 |
|
37 |
NOOITGEDACHT DAM |
Small |
Significant |
2 |
30-Jan-07 |
DSE In progress |
38 |
JAGERSRUST DAM |
Small |
Significant |
2 |
28-May-07 |
DSE In progress |
39 |
KASTEEL DAM |
Medium |
Significant |
2 |
18-Aug-07 |
|
40 |
INJAKA DAM |
Large |
High |
3 |
18-Sep-07 |
|
41 |
BELFORT DAM |
Medium |
Significant |
2 |
26-Sep-07 |
DSE In progress |
42 |
NTENETYANA DAM |
Medium |
Significant |
2 |
26-Sep-07 |
|
43 |
CAMDEN RESERVOIR NO.3 |
Small |
Significant |
2 |
31-Oct-07 |
DSE In progress |
44 |
STOMPDRIFT DAM |
Large |
High |
3 |
15-Nov-07 |
Rehab |
45 |
BALANSEERDAM S2 ORANJE RIET KANAAL |
Small |
Significant |
2 |
10-Dec-07 |
|
46 |
KRUGERSDRIFT DAM |
Medium |
High |
3 |
9-Jan-08 |
|
47 |
ROOIFONTEIN DAM |
Small |
Significant |
2 |
27-Jan-08 |
|
48 |
RAMAH CANAL BALANCING NO 2 |
Small |
Significant |
2 |
10-Apr-08 |
DSE In progress |
49 |
BOEGOEBERG DAM |
Medium |
Low |
2 |
24-Jun-08 |
DSE In progress |
50 |
WELTEVREDE DAM |
Small |
Significant |
2 |
29-Sep-08 |
|
51 |
VAALKOP NO.II DAM |
Small |
High |
2 |
20-Oct-08 |
Rehab |
52 |
NZHELELE DAM |
Large |
High |
3 |
21-Oct-08 |
|
53 |
SEDIBA DAM |
Small |
Significant |
2 |
27-Oct-08 |
|
54 |
FELOANA DAM |
Small |
Significant |
2 |
27-Oct-08 |
|
55 |
WOODBRIDGE DAM |
Small |
Significant |
2 |
27-Oct-08 |
|
56 |
SEROALO DAM |
Small |
Significant |
2 |
27-Oct-08 |
|
57 |
AMABELE DAM |
Small |
Significant |
2 |
27-Oct-08 |
DSE In progress |
58 |
MADIKWE DAM |
Medium |
Significant |
2 |
3-Nov-08 |
DSE In progress |
59 |
BULSHOEK DAM |
Small |
Significant |
2 |
2-Dec-08 |
DSE In progress |
60 |
KLEINPLAAS DAM |
Medium |
High |
3 |
3-Dec-08 |
DSE In progress |
61 |
THEEWATERSKLOOF DAM |
Large |
High |
3 |
3-Dec-08 |
|
62 |
LINDLEYSPOORT DAM |
Large |
High |
3 |
4-Dec-08 |
|
63 |
BARTELSFONTEIN RESERVOIR |
Small |
Significant |
2 |
5-Dec-08 |
|
64 |
GROOTDRAAI DAM |
Large |
High |
3 |
26-Jan-09 |
|
65 |
DRIEKLOOF DAM |
Large |
High |
3 |
27-Jan-09 |
DSE In progress |
66 |
STERKFONTEIN |
Large |
High |
3 |
28-Jan-09 |
|
67 |
BLOEMHOF DAM |
Large |
High |
3 |
9-Feb-09 |
|
68 |
WATERDOWN DAM |
Large |
High |
3 |
13-Apr-09 |
|
69 |
CAPES THORNE DAM |
Medium |
Significant |
2 |
18-Jun-09 |
DSE In progress |
70 |
ROOIKRANS DAM |
Medium |
High |
3 |
8-Jul-09 |
|
71 |
WRIGGLESWADE DAM |
Large |
High |
3 |
9-Jul-09 |
DSE In progress |
72 |
DRIEL BARRAGE |
Medium |
High |
3 |
26-Aug-09 |
|
73 |
QEDUSIZI DAM |
Large |
High |
3 |
27-Aug-09 |
|
74 |
RIETFONTEIN WEIR |
Small |
Significant |
2 |
10-Sep-09 |
DSE In progress |
75 |
ONVERWACHT RESERVOIRS NO.1,2 & 3 |
Small |
Significant |
2 |
10-Sep-09 |
|
76 |
ROODEPOORT DAM |
Small |
Significant |
2 |
29-Sep-09 |
|
78 |
WELTEVREDEN WEIR |
Small |
Significant |
2 |
19-Nov-09 |
DSE In progress |
79 |
ROOIKRAAL DAM |
Medium |
Significant |
2 |
19-Nov-09 |
DSE In progress |
80 |
VAAL DAM |
Large |
High |
3 |
21-Dec-09 |
|
81 |
BOSKOP DAM |
Medium |
High |
3 |
23-Dec-09 |
|
82 |
KOUGA DAM |
Large |
High |
3 |
14-Jan-10 |
|
83 |
DARLINGTON DAM |
Large |
High |
3 |
14-Jan-10 |
|
84 |
IMPOFU |
Large |
High |
3 |
15-Jan-10 |
|
85 |
HLUHLUWE DAM |
Large |
High |
3 |
1-Feb-10 |
DSE In progress |
86 |
GOEDERTROUW DAM |
Large |
High |
3 |
3-Feb-10 |
|
87 |
XONXA DAM |
Large |
High |
3 |
12-Apr-10 |
|
88 |
MACUBENI DAM |
Medium |
High |
3 |
12-Apr-10 |
DSE In progress |
89 |
BUSHMANSKRANTZ DAM |
Large |
High |
3 |
13-Apr-10 |
|
90 |
SHILOH DAM |
Medium |
High |
3 |
13-Apr-10 |
|
91 |
OXKRAAL DAM |
Large |
High |
3 |
13-Apr-10 |
|
92 |
SANDILE DAM |
Large |
High |
3 |
14-Apr-10 |
|
93 |
DEBE DAM |
Large |
High |
3 |
14-Apr-10 |
DSE In progress |
94 |
OUKLOOF DAM |
Large |
High |
3 |
4-Jun-10 |
DSE In progress |
95 |
GLEN MELVILLE DAM |
Large |
High |
3 |
20-Jul-10 |
DSE In progress |
96 |
GLEN BOYD BALANCING DAM |
Medium |
Significant |
2 |
22-Jul-10 |
|
97 |
DER BROCHEN DAM |
Large |
High |
3 |
27-Jul-10 |
DSE In progress |
98 |
NANDONI DAM |
Large |
High |
3 |
10-Aug-10 |
|
99 |
ROODEFONTEIN DAM |
Medium |
High |
3 |
16-Aug-10 |
|
100 |
KLIPFONTEIN DAM (W4) |
Medium |
High |
3 |
16-Aug-10 |
|
101 |
BRONKHORSTSPRUIT DAM |
Large |
High |
3 |
17-Aug-10 |
DSE In progress |
102 |
INANDA DAM |
Large |
High |
3 |
31-Aug-10 |
|
103 |
HAZELMERE DAM |
Large |
High |
3 |
31-Aug-10 |
|
104 |
POORTJIESKLOOF DAM |
Large |
High |
3 |
7-Sep-10 |
|
105 |
CLANWILLIAM DAM |
Large |
High |
3 |
8-Sep-10 |
Raising |
106 |
MTATA DAM |
Large |
High |
3 |
1-Oct-10 |
|
107 |
MHLANGA DAM |
Large |
High |
3 |
1-Oct-10 |
|
108 |
NTSHINGWAYO DAM |
Medium |
High |
3 |
1-Jan-11 |
|
109 |
VAALKOP DAM |
Large |
High |
3 |
26-Jan-11 |
Rehab |
110 |
KALKFONTEIN DAM |
Large |
High |
3 |
2-Feb-11 |
Rehab |
111 |
MANKWE DAM |
Medium |
Significant |
2 |
3-Feb-11 |
|
112 |
MARICO-BOSVELD DAM |
Medium |
High |
3 |
3-Feb-11 |
|
113 |
ROODEKOPJES DAM |
Medium |
High |
3 |
9-Feb-11 |
|
114 |
GROOTHOEK DAM (MOUTLOATSI SETLOGELO) DAM |
Medium |
High |
3 |
15-Feb-11 |
|
115 |
ROODE ELSBERG DAM |
Large |
High |
3 |
18-Apr-11 |
|
116 |
BEN ETIVE DAM |
Medium |
Significant |
2 |
19-Apr-11 |
|
117 |
FLORISKRAAL DAM |
Medium |
High |
3 |
19-Apr-11 |
DSE In progress |
118 |
LEEU-GAMKA DAM |
Medium |
High |
3 |
20-Apr-11 |
DSE In progress |
119 |
KLIPBERG DAM |
Medium |
High |
3 |
20-Jun-11 |
|
120 |
BUFFELJAGS DAM |
Medium |
High |
3 |
20-Jun-11 |
|
121 |
KAMMANASSIE DAM |
Large |
High |
3 |
20-Jun-11 |
DSE In progress |
122 |
KLIPHEUWEL DAM |
Medium |
High |
3 |
21-Jun-11 |
|
123 |
MIERTJIESKRAAL DAM |
Medium |
High |
3 |
22-Jun-11 |
|
124 |
MAKOTSWANE DAM |
Medium |
Significant |
2 |
12-Jul-11 |
|
125 |
DISANENG DAM |
Medium |
Significant |
2 |
3-Aug-11 |
|
126 |
BEVENSON DAM |
Medium |
Significant |
2 |
10-Aug-11 |
DSE In progress |
127 |
BUFFELSPOORT DAM |
Large |
High |
3 |
15-Aug-11 |
|
128 |
ROODEPLAAT DAM |
Large |
High |
3 |
15-Aug-11 |
|
129 |
DORINGRIVIER DAM |
Medium |
High |
3 |
15-Aug-11 |
|
130 |
LUBISI DAM |
Large |
High |
3 |
15-Aug-11 |
|
131 |
KWENA DAM |
Large |
High |
3 |
30-Aug-11 |
|
132 |
MIDDEL LETABA DAM |
Large |
High |
3 |
31-Aug-11 |
|
133 |
NCORA DAM |
Large |
High |
3 |
1-Sep-11 |
|
134 |
CRAIGIE BURN |
Large |
High |
3 |
7-Sep-11 |
|
135 |
KLIPDRIFT DAM |
Small |
Significant |
2 |
16-Sep-11 |
|
136 |
ALLEMANSKRAAL DAM |
Large |
High |
3 |
16-Sep-11 |
|
137 |
NAHOON DAM |
Large |
High |
3 |
19-Sep-11 |
|
138 |
XILINXA DAM |
Medium |
High |
3 |
19-Sep-11 |
|
139 |
LOERIE DAM |
Medium |
High |
3 |
20-Sep-11 |
|
140 |
BEERVLEI DAM |
Large |
High |
3 |
22-Sep-11 |
|
141 |
TZANEEN |
Large |
High |
3 |
28-Sep-11 |
Raising |
142 |
VERGELEGEN DAM |
Medium |
Significant |
2 |
28-Sep-11 |
|
143 |
BOSSIESPRUIT DAM |
Medium |
High |
2 |
12-Oct-11 |
|
144 |
DREISELEN DAM |
Medium |
Significant |
2 |
25-Oct-11 |
|
145 |
LEPELLANE DAM |
Medium |
Significant |
2 |
25-Oct-11 |
|
146 |
MOLATEDI DAM |
Medium |
High |
3 |
31-Jan-12 |
|
147 |
LOTLAMORENG DAM |
Small |
Significant |
2 |
1-Apr-12 |
|
148 |
LAKENVALLEI DAM |
Large |
High |
3 |
1-Apr-12 |
|
149 |
GXETU DAM |
Medium |
Significant |
2 |
14-May-12 |
|
150 |
GUBU DAM |
Large |
High |
3 |
15-May-12 |
|
151 |
KROMELLENBOOG DAM |
Medium |
High |
3 |
1-Aug-12 |
Rehab |
152 |
GAMKAPOORT DAM |
Large |
High |
3 |
18-Oct-12 |
|
153 |
GAMKA DAM |
Large |
High |
3 |
19-Oct-12 |
|
154 |
CROSS DAM |
Medium |
Significant |
2 |
30-Oct-12 |
|
155 |
LUPHEPHE DAM |
Large |
High |
3 |
30-Oct-12 |
|
156 |
NWANEDZI |
Large |
High |
3 |
30-Oct-12 |
|
157 |
RUSTFONTEIN DAM |
Large |
High |
3 |
26-Nov-12 |
|
158 |
KNELLPOORT DAM |
Large |
High |
3 |
26-Nov-12 |
|
159 |
ERFENIS DAM |
Large |
High |
3 |
27-Nov-12 |
|
160 |
KOPPIES DAM |
Medium |
High |
3 |
27-Nov-12 |
|
161 |
DOORNDRAAI DAM |
Medium |
High |
3 |
23-Jan-13 |
|
162 |
GLEN ALPINE DAM |
Medium |
High |
3 |
23-Jan-13 |
|
163 |
KLERKSKRAAL DAM |
Medium |
High |
3 |
25-Jan-13 |
|
164 |
TRICHARDTSFONTEIN DAM |
Medium |
High |
3 |
2-Feb-13 |
|
165 |
RHENOSTERKOP DAM |
Large |
High |
3 |
7-Feb-13 |
|
166 |
WOODSTOCK DAM |
Large |
High |
3 |
20-Feb-13 |
|
167 |
KILBURN DAM |
Large |
High |
3 |
20-Feb-13 |
DSE In progress |
168 |
WITKLIP DAM |
Medium |
High |
3 |
27-Feb-13 |
|
169 |
VLUGKRAAL DAM |
Medium |
Significant |
2 |
14-May-13 |
DSE In progress |
170 |
TONTELDOOS DAM |
Medium |
Significant |
2 |
14-May-13 |
|
171 |
SESHEGO DAM |
Medium |
Significant |
2 |
20-Jun-13 |
|
172 |
KORENTEPOORT DAM |
Large |
High |
3 |
28-Aug-13 |
|
173 |
CALIFORNIA DAM |
Medium |
Significant |
2 |
30-Sep-13 |
|
174 |
BLYDERIVIERSPOORT DAM |
Large |
High |
3 |
13-Jan-14 |
|
175 |
MAGOEBASKLOOF DAM |
Large |
Significant |
3 |
14-Jan-14 |
|
176 |
VONDO DAM |
Large |
High |
3 |
15-Jan-14 |
|
177 |
PIETERSFONTEIN DAM |
Medium |
High |
3 |
21-Jan-14 |
|
178 |
FIKA-PATSO DAM |
Large |
High |
3 |
10-Mar-14 |
|
179 |
KILBURN-OMGEWINGS NO.3DAM |
Medium |
Significant |
2 |
11-Mar-14 |
|
180 |
VLAKBULT DAM |
Small |
Significant |
2 |
11-Mar-14 |
|
181 |
TOURS DAM |
Medium |
Significant |
2 |
19-Mar-14 |
|
182 |
HARTBEESKUIL DAM |
Medium |
High |
3 |
19-Mar-14 |
|
183 |
EBENEZER DAM |
Large |
High |
3 |
24-Mar-14 |
|
184 |
KATRIVIER DAM |
Large |
High |
3 |
24-Mar-14 |
|
185 |
HARTBEESPOORT DAM |
Large |
High |
3 |
26-Mar-14 |
|
186 |
ALBASINI DAM |
Large |
High |
3 |
26-Mar-14 |
|
187 |
VYGEBOOM DAM |
Large |
High |
3 |
26-Mar-14 |
|
188 |
KLASERIE |
Medium |
High |
3 |
28-Mar-14 |
|
189 |
BERGRIVIER DAM |
Large |
High |
3 |
28-Mar-14 |
|
190 |
OHRIGSTAD DAM |
Large |
High |
3 |
29-Mar-14 |
|
191 |
LAING DAM |
Large |
High |
3 |
29-Mar-14 |
|
192 |
KWAGGASKLOOF DAM-PART OF GROTER BRANDVLEI 12/2/H100/08 |
Medium |
High |
3 |
14-May-14 |
D |
193 |
EGMONT DAM |
Medium |
High |
3 |
22-May-14 |
|
194 |
ARMENIA DAM |
Medium |
High |
3 |
23-May-14 |
|
195 |
MOKOLO |
Large |
High |
3 |
4-Jul-14 |
D |
196 |
VOELVLEI DAM |
Small |
High |
2 |
19-Aug-14 |
|
197 |
TIERKLOOF DAM |
Medium |
Significant |
2 |
16-Sep-14 |
D |
198 |
NGWEKAZI DAM |
Medium |
Significant |
2 |
12-Nov-14 |
D |
199 |
GEMSBOKHOEK |
Medium |
Low |
2 |
25-Nov-14 |
B |
200 |
VERGELEGEN DAM |
Medium |
Significant |
2 |
30-Jan-15 |
D |
201 |
BALURADAM |
Medium |
Low |
2 |
7-Feb-15 |
C |
202 |
KLIPVOOR DAM |
Medium |
High |
3 |
25-Feb-15 |
|
203 |
TURFLOOP DAM |
Medium |
Significant |
2 |
27-Feb-15 |
E |
204 |
DOUGLAS WEIR |
Small |
Significant |
2 |
1-Mar-15 |
|
205 |
ROCKVIEW DAM |
Large |
High |
3 |
1-Mar-15 |
E |
206 |
BRANDVLEI DAM & GROTER BRANDVLEI RESERVOIR |
Medium |
High |
3 |
1-Mar-15 |
D |
207 |
BIZANA DAM |
Medium |
Significant |
2 |
11-Mar-15 |
C |
208 |
VAALHARTS-STUWAL |
Small |
High |
2 |
13-Mar-15 |
D |
209 |
WENTZEL DAM |
Small |
High |
2 |
16-Mar-15 |
D |
210 |
BONNIEBROOK DAM |
Medium |
Significant |
2 |
18-Mar-15 |
C |
211 |
PIETGOUWS DAM-LEBOWA |
Medium |
Significant |
2 |
20-Mar-15 |
D |
26 |
NONDWENI STUWAL |
Medium |
Significant |
2 |
24-Mar-15 |
|
212 |
ELANDSKUIL DAM |
Small |
High |
2 |
29-Mar-15 |
D |
213 |
TENTERGATE |
Small |
Significant |
2 |
30-Mar-15 |
C |
214 |
BUFFELSKLOOF DAM |
Large |
Significant |
3 |
31-Mar-15 |
B |
215 |
LAKESIDE DAM |
Small |
High |
2 |
31-Mar-15 |
|
216 |
WELBEDACHT DAM |
Large |
High |
3 |
1-Apr-15 |
C |
217 |
GARIEP DAM |
Large |
High |
3 |
1-Apr-15 |
C |
218 |
KOGELBERG DAM |
Large |
High |
3 |
1-Apr-15 |
C |
219 |
ELANDSKLOOF DAM |
Large |
High |
3 |
1-Apr-15 |
C |
220 |
TSOJANA DAM |
Medium |
Significant |
2 |
1-Apr-15 |
E |
221 |
CORANA |
Medium |
Significant |
2 |
1-Apr-15 |
D |
222 |
ALBERT FALLS DAM |
Large |
High |
3 |
1-Apr-15 |
C |
223 |
SPIOENKOP DAM |
Small |
High |
3 |
1-Apr-15 |
C |
224 |
KOSTER DAM |
Medium |
High |
3 |
29-May-15 |
|
225 |
HOUTRIVIER DAM |
Medium |
Significant |
2 |
31-May-15 |
C |
226 |
MITFORD DAM |
Small |
Significant |
2 |
6-Jul-15 |
E |
227 |
LOSKOP DAM |
Large |
High |
3 |
30-Jul-15 |
C |
228 |
NOOITGEDACHT DAM |
Large |
High |
3 |
30-Jul-15 |
B |
229 |
WESTOE DAM |
Medium |
High |
3 |
1-Nov-15 |
C |
230 |
JOZANASHOEK DAM |
Large |
High |
3 |
2-Nov-15 |
C |
231 |
KOMMANDODRIFT DAM |
Large |
High |
3 |
2-Nov-15 |
A |
232 |
DE MISTKRAAL |
Medium |
High |
3 |
21-Jan-16 |
C |
233 |
JERICHO DAM |
Medium |
High |
3 |
30-Jan-16 |
C |
234 |
PATENSIE BALANCING DAM |
Medium |
Significant |
2 |
29-Feb-16 |
C |
235 |
SCHEEPERSVLAKTE DAM |
Medium |
High |
3 |
7-Mar-16 |
A |
236 |
THRIFT DAM (MOUNTHOPE) |
Medium |
Significant |
2 |
7-Mar-16 |
E |
237 |
ZAAIHOEK DAM |
Large |
High |
3 |
7-Mar-16 |
A |
238 |
MUTSHEDZI DAM |
Medium |
Significant |
2 |
14-Mar-16 |
C |
239 |
WOLWEDANS DAM |
Large |
High |
3 |
15-Mar-16 |
C |
240 |
SCHEEPERS DAM |
Small |
Significant |
2 |
15-Mar-16 |
C |
241 |
MIDMAR DAM |
Large |
High |
3 |
25-Mar-16 |
C |
242 |
XIKUNDU STUWAL |
Medium |
Significant |
2 |
29-Mar-16 |
C |
243 |
DUTHUNI DAM |
Small |
Significant |
2 |
29-Mar-16 |
B |
244 |
PHIPHIDI |
Medium |
Significant |
2 |
29-Mar-16 |
C |
245 |
MODJADJI DAM |
Medium |
High |
3 |
29-Mar-16 |
C |
246 |
SPITSKOP DAM |
Medium |
High |
3 |
29-Mar-16 |
C |
247 |
D-DAM |
Medium |
Significant |
2 |
29-Mar-16 |
C |
248 |
MANKAZANA DAM |
Medium |
Significant |
2 |
29-Mar-16 |
A |
249 |
BINFIELD PARK DAM |
Large |
High |
3 |
29-Mar-16 |
C |
250 |
TOLENI DAM |
Small |
Significant |
2 |
29-Mar-16 |
A |
251 |
MEARNS WEIR-OU |
Small |
Significant |
2 |
29-Mar-16 |
C |
252 |
KUDUBE DAM (LEEUKRAAL DAM) |
Small |
Significant |
2 |
30-Mar-16 |
E |
253 |
TSHAKHUMA DAM |
Large |
High |
3 |
30-Mar-16 |
|
254 |
BOTLOKWA DAM |
Small |
Significant |
2 |
30-Mar-16 |
C |
255 |
SETUMO DAM |
Medium |
Significant |
2 |
30-Mar-16 |
B |
256 |
BLUECRANE DAM |
Small |
Significant |
2 |
30-Mar-16 |
C |
257 |
WAGENDRIFT DAM |
Large |
High |
3 |
30-Mar-16 |
C |
258 |
HEYSHOPE DAM |
Medium |
High |
3 |
30-Mar-16 |
C |
259 |
MORGENSTOND DAM |
Large |
Significant |
3 |
30-Mar-16 |
D |
260 |
SPITSKOPKRAAL DAM |
Medium |
Significant |
2 |
31-Mar-16 |
D |
261 |
VANDERKLOOF DAM |
Large |
High |
3 |
31-Mar-16 |
C |
77 |
FLAG BOSHIELO |
Large |
High |
3 |
3-May-16 |
|
262 |
BOTTERKLOOF DAM |
Medium |
Significant |
2 |
30-Mar-17 |
B |
263 |
MOLEPO DAM |
Medium |
Significant |
2 |
31-Mar-17 |
D |
264 |
PELLA DAM |
Medium |
High |
3 |
19-Jun-17 |
C |
265 |
MAHLANGU DAM |
Medium |
Significant |
2 |
6-Jul-17 |
D |
266 |
MIDDELKRAAL DAM |
Small |
Significant |
2 |
7-Jul-17 |
|
267 |
MASHASHANE DAM |
Medium |
Significant |
2 |
12-Jul-17 |
|
268 |
THAPANA DAM |
Medium |
Significant |
2 |
27-Jul-17 |
|
269 |
NEUSBERG WEIR |
Medium |
Low |
2 |
8-Sep-17 |
B |
270 |
DUIVENHOKS DAM |
Large |
High |
3 |
18-Sep-17 |
C |
271 |
PLEASANTVIEW DAM |
Medium |
Significant |
2 |
20-Sep-17 |
B |
272 |
SINQUMENI DAM |
Medium |
Low |
2 |
22-Sep-17 |
D |
273 |
MABELENI DAM |
Medium |
Significant |
2 |
26-Sep-17 |
C |
274 |
NGOTWANE DAM |
Medium |
Significant |
2 |
23-Oct-17 |
|
275 |
ACORNHOEK DAM |
Medium |
Low |
2 |
31-Oct-17 |
D |
276 |
MISVERSTAND-STUWAL |
Medium |
Significant |
2 |
18-Jan-18 |
|
277 |
CHUNIESPOORT DAM |
Medium |
Significant |
2 |
11-May-18 |
|
278 |
SEHUJWANE DAM |
Medium |
Significant |
2 |
24-May-18 |
|
279 |
EDINBURGH DAM |
Medium |
High |
3 |
8-Aug-18 |
|
280 |
LOLA MONTES DAM |
Medium |
Significant |
2 |
27-Aug-18 |
|
281 |
DE HOOP DAM |
Large |
High |
3 |
|
DSE In progress |
282 |
HK BALANCING DAM |
Small |
Significant |
2 |
|
|
283 |
KORHAANSDRIFT WEIR |
Small |
Significant |
2 |
|
|
284 |
LUDEKE DAM |
Large |
High |
3 |
|
DSE In progress |
285 |
SPRING GROVE DAM |
Large |
High |
3 |
|
|
286 |
MUNDTS CONCESSION DAM |
Medium |
High |
3 |
|
|
03 December 2018 - NW3617
Dreyer, Ms AM to ask the Minister of Water and Sanitation
(a) What strategy is in place to rehabilitate the (i) Vaal Dam and (ii) Vaal River, (b) what will be the cost of rehabilitation in each case and (c) by what date is the rehabilitation envisaged to be completed in each case?
Reply:
a) Currently the Department does not have a river rehabilitation programme for the Vaal Dam and the Vaal River; however we have the following programmes that are aimed at managing the quality of water as follows:
- River ecosystatus monitoring programme to determine the status of the river health with the following objectives:
- Measure, assess and report on the ecological state of aquatic ecosystems (river health data);
- Detect and report on spatial and temporal trends;
- Identify and report on emerging problems regarding aquatic ecosystems;
- Ensure that reports provide scientifically and managerially relevant information.
- Six (6) rivers are monitored in the Upper Vaal
- Six (6) rivers also monitored in the Middle Vaal Water Management Area; namely the Vaal, Renoster, Vals, Vet and Sand Rivers. This monitoring is done on a quarterly basis.
- Two (2) rivers (Harts and Lower Vaal) are monitored in the Lower Vaal.
- Surface water monitoring programme to determine the quality of surface water. The programme analyses chemical and microbiological variables. 28 surface monitoring points monitored in the Middle Vaal Water Management Area, of which six (6) points are on the Vaal River mainstream, four (4) on the Renoster River, three (3) on the Vals River, five (5) on the Schoonspruit, five (5) on the Sand and five (5) on the Vet Rivers.
- Resource Quality Objectives (RQOs) are used to determine compliance.
- Surface water quality samples taken are analyzed at an internal laboratory which is not accredited, therefore the results cannot be used for prosecution purposes but only for audit purposes.
- This sampling is taking place twice a year.
- Water use license authorisation process to ensure that water users comply with the water quality standards.
- Routine inspections on various water users (agriculture, industries, mines, local government) and implementation of enforcement action to ensure compliance with water use license conditions
- Infrastructure development, operation and maintenance with the following objectives:
- Minimise the pollution of water resources;
- Improve operation and maintenance of the waste water infrastructure;
- Reduce sewage spillages;
- Improve the capacity and quality of the waste water infrastructure.
b) Falls away.
c) Falls away.
---00O00---
03 December 2018 - NW2784
Basson, Mr LJ to ask the Minister of Water and Sanitation
(a) Why has his department not furnished the National Treasury with the required paperwork to approve the appointment of a certain law firm (name furnished) to conduct the forensic investigation into allegations of corruption and maladministration in his department, (b) who is responsible for providing such paperwork to the National Treasury and (c) by what date will the specified paperwork be sent to the National Treasury?
Reply:
(a) The Honorable member is advised to note that the process for the appointment of Werksman was handled by the former employee, who was the then Acting Director-General, Mr Sifiso Mkhize alone. The Legal Services advised against the manner in which Werksman was appointed and for that reason could not participate in the appointment process. Since there is no handover report of Mr Mkhize on this matter, it will be difficult for the current Acting Director-General to provide the required responses.
(b) As indicated above, Mr Mkhize as the then Acting Director-General was expected to request the approval of any deviation from or report the financial irregularity to the National Treasury.
(c) Falls away.
---00O00---
03 December 2018 - NW2480
Hugo, Mr RT to ask the Minister of Water and Sanitation
How much water is being saved across the country each month due to his department’s War on Leaks programme?
Reply:
The consolidated water balance for the first 9 months of the 2017/18 within the eight large water supply systems based on the data as at Dec 2017 indicates a savings achievements of 25,2 million m3/a which translates to a savings of 12,6%.
---00O00---
03 December 2018 - NW2322
Khawula, Ms MS to ask the Minister of Water and Sanitation
(1)(a) What number of labour disputes are currently being faced by (i) his department and (ii) the entities reporting to him, (b) what is the cause of each dispute, (c) what is the nature of each dispute and (d) on what date was each dispute (i) reported and (ii) resolved; (2) (a)(i) what number of employees have been dismissed by his department in the past five years and (ii) for what reason was each employee dismissed and (b)(i) what number of the specified employees were paid severance packages and (ii) what was the monetary value of each severance package?
Reply:
Refer to the tables below for the number of labour disputes and the number of employees dismissed by the Department and the entities reporting to me for the past five years.
- Refer to the table below for the number of labour disputes:
Department / Entity |
(1)(a)(ii) What number of labour disputes are currently being faced |
(1)(b) what is the cause of each dispute |
(1)(c) what is the nature of each dispute |
(1)(d)(i) on what date was each dispute reported |
(1)(d)(ii) on what date was each dispute resolved |
The Department |
A total of 244 |
Employee dismissed for Fraud |
Unfair dismissal |
31 March 2015 |
18 March 2016 |
Employee dismissed for fraud |
Unfair dismissal |
25 February 2014 |
25 June 2015 |
||
The department did absorb the employee to Higher OSD position |
Unfair labour practice: Promotion |
09 February 2016 |
09 February 2018 |
||
Failure by the department to upgrade employees(56 x1) |
Unfair labour practice: benefits |
09 June 2017 |
10 January 2018 |
||
Employee dismissed for being involved in a serious accident with a state vehicle without permission |
Unfair dismissal |
3 April 2018 |
28 June 2018 |
||
Employee dismissed for sexual harassment |
Unfair dismissal |
11 April 2016 |
25 April 2016 |
||
Failure by the department to upgrade employees to salary level 10 & 12 ( 46X1) |
Interpretation of the Public Service Co-ordinating Bargaining Council: Clause 18.1: Resolution no 1 of 2012 |
4 December 2017 |
30 May 2018 |
||
Unfair discrimination (41X1) |
Equal pay for equal value ( One Senior Messenger upgraded to salary 4 in 2010 whereas the others upgraded in 2016 |
22 May 2018 |
18 September 2018 |
||
Unfair labour Practice: Benefits: Failure by the department to job evaluate the applicants (15X1) |
Unfair labour Practice: Benefits: Failure by the department to job evaluate the applicants |
4 June 2018 |
23 July 2018 |
||
Withdrawal of maximum engine category of 3000cc on official vehicle kilometers claims (2x1) |
Unfair labour practice benefits |
3 April 2018 |
28 June 2018 |
||
Amatola Water |
Illegal strike by 28% of workforce |
Over wages in respect of 2017/18 and 2018/19. |
Illegal strike |
Dispute declared via deadlock on wages effective 23 October 2017 and illegal strike from 2 August 2018 |
Not as yet resolved |
Bloem Water |
3 current disputes |
Matter referred back from labour appeal court to be heard on the merits. |
Alleged Unfair dismissal |
29 June 2017 |
Pending |
Resolved at arbitration; dismissal confirmed as fair. Matter taken on review. |
Review Application |
20 October 2016 |
Pending |
||
Employee resigned and later claimed constructive dismissal. |
Alleged constructive dismissal. Late submission: arbitration in favor of employer. Review application |
March 2018 |
Pending |
||
Lepelle Northern Water |
Four (4) current disputes |
The employee is undergoing a disciplinary enquiry for violating the disciplinary code, the case is at the CCMA: MM Masipa. |
Misconduct |
December 2015 |
Pending |
The employee is undergoing a disciplinary enquiry for violating the disciplinary code: T Monnathebe. |
Misconduct |
April 2018 |
Pending |
||
The employee is undergoing a disciplinary enquiry for violating the disciplinary code: K Kganane. |
Misconduct |
July 2018 |
Pending |
||
The dispute is about non-renewal of fixed term contract: M Phokanoka. |
Unfair labour practice |
July 2018 |
Pending |
||
Magalies Water |
Seven (7) labour disputes |
Salary disparity. |
Unfair labour practice related to benefits |
30 August 2018 |
Pending |
Suspension of employee for disrupting interviews. |
Unfair Suspension |
14 March 2018 |
Resolved |
||
Suspension of employee for leaking of confidential information. |
Unfair Suspension |
29 November 2017 |
Resolved |
||
Failure by employer to shortlist employee for a higher advertised position. |
Unfair labour practice related to promotion |
27 July 2018 |
Resolved |
||
Failure by employer to shortlist employee for a higher advertised position. |
Unfair labour practice related to promotion |
6 April 2018 |
Resolved |
||
Theft of scrap material from the plant. |
Unfair dismissal |
17 March 2015 |
Resolved |
||
Failure by employee to follow instructions from line manager. |
Unfair dismissal |
4 April 2015 |
Resolved |
||
Mhlathuze Water |
Two (2) labour disputes |
Chief Executive Officer is on suspension pending a disciplinary enquiry. The employee made an application for an interdict against the disciplinary action, the matter is awaiting a court date at the Supreme Court of Appeal. |
Unfair suspension |
20 November 2015 |
Both matters are not yet resolved. |
K Kruger - CCMA referral - Conciliation – Unfair Dismissal arising out of misconduct. |
Unfair dismissal |
31 July 2018 |
|||
Overberg Water |
Three (3) registered labour disputes at Overberg Water |
The causes are mainly administrative processes. |
Former employee filed a dispute on the 7th March 2017 after being dismissed on 16 January 2017 and stated the nature of the dispute as “Reasons for dismissal not known”. The dispute was resolved at the CCMA arbitration on 24 July 2017. |
7th March 2017 |
Resolved |
Another former employee filed a dispute on 9 March 2018 after being dismissed on 07 February 2018 and stated the nature of dispute as “Dismissal related to unfair discrimination”. The dispute was resolved at the CCMA Arbitration on 4 June 2018. |
9 March 2018 |
Resolved |
|||
The last one the current employee has filed a dispute on 4th July 2018 after his request for transfer from one scheme to another scheme was rejected about a year ago and stated that the nature of dispute as “Unfair conduct-Promotion/Probation/Training/Benefits”. The dispute has been referred for arbitration on 29 August 2018. |
4th July 2018 |
In progress |
|||
Sedibeng Water |
Total number 16 |
Alleged conduct of the employee. |
Misconduct |
21 February 2017 |
Resolved on 21 February 2017 |
Alleged conduct of the employee. |
Misconduct |
30 January 2017 |
Resolved on 28 March 2017 |
||
Alleged conduct of the employee. |
Misconduct |
02 March 2018 |
Resolved on 09 March 2017 |
||
Alleged conduct of the employee. |
Misconduct |
29 June 2017 |
Resolved on 07 August 2017 |
||
Alleged conduct of the employee. |
Misconduct |
10 February 2016 |
Resolved on 10 February 2016 |
||
Alleged conduct of the employee. |
Misconduct |
13 March 2016 |
Resolved on 13 March 2016 |
||
Dismissal on the basis of ill-health. |
Incapacity |
N/A |
Resolved on 15 March 2018 |
||
Alleged conduct of the employee. |
Misconduct |
13 March 2016 |
Resolved on 09 May 2017 |
||
Alleged conduct of the employee. |
Misconduct |
12 June 2017 |
Resolved on 26 September 2017 |
||
Alleged conduct of the employee. |
Misconduct |
19 May 2017 |
Resolved on 03 November 2017 |
||
Alleged conduct of the employee. |
Misconduct |
30 November 2015 |
Resolved on 30 November 2015 |
||
Alleged conduct of the employee. |
Misconduct |
07 August 2015 |
Resolved on 16 October 2015 |
||
Alleged conduct of the employee. |
Misconduct |
14 September 2015 |
Resolved on Resolved on 04 November 2015 |
||
Alleged conduct of the employee. |
Misconduct |
26 December 2015 |
Resolved on 24 February 2016 |
||
Alleged conduct of the employee. |
Misconduct |
03 February 2016 |
Resolved on 13 April 2016 |
||
Alleged conduct of the employee. |
Interpretation of the Collective Agreement |
The matter is scheduled to be heard on the 28 August 2018 at the CCMA. |
In progress |
||
Rand Water |
Total number of labour Dispute: 25 |
Grievance (1). |
Volume of work should be equal to the rate of pay |
28 Aug 2017 |
Pending |
Grievance (1). |
Disallowed to use company provided utensils |
8 Nov 2017 |
11 Dec 2017 |
||
Dismissal (1). |
Found in possession of the company property without permission |
14 Mar 2018 |
28 Jun 2018 |
||
Dismissal (1). |
Leaving the workplace without permission |
16 Jun 2018 |
Pending |
||
Grievance (1). |
Unfair treatment by the supervisor |
16 May 2018 |
28 May 2018 |
||
Grievance (1). |
To be paid back the difference between current rate after adjustment and the previous rate |
19 Jun 2018 |
Pending |
||
Unfair Discrimination (1). |
Transfer from one site to the other |
10 Mar 2016 |
Matter is pending at the Labour Court |
||
Unfair Labour Practice (1). |
Written warning issued |
28 Aug 2017 |
2 Feb 2018 |
||
Unfair Dismissal (1) |
None Renewal of fixed term contract |
3 Feb 2016 |
10 Mar 2016 |
||
Dismissal (1) |
Misconduct |
16 Apr 2018 |
Arbitration ongoing |
||
Dismissal (1) |
Misconduct |
Pending set down |
|||
Remuneration (1) |
Pay discrimination |
Conciliation failed |
|||
Misconduct (1) |
Conflict of interest |
Feb 2018 |
On-going |
||
Misconduct (1) |
Gross negligence – over payment to supplier |
May 2018 |
On-going |
||
Misconduct (1) |
Gross negligence |
Jun 2018 |
On-going |
||
Misconduct (1) |
•Gross insubordination and •Insolence towards Line Manager for refusing to carry out instructions |
09 Sept 2015 |
|||
Misconduct (1) |
Committed deliberate act which causes potential prejudice for failing to take appropriate disciplinary Action against subordinates for fraudulent activities |
Apri2016 |
27 Jun 2016 |
||
Misconduct (1) |
Gross Negligence and violation of procurement policies resulting in overpayment to supplier |
Nov 2017 |
|||
Grievances (7) |
Employees requesting for Hay band and position upgrade |
15 Mar 2018 |
Resolved on the 12 Apr 2018 |
||
Query regarding overtime pay for an employee who is above the threshold. |
8 Jul 2017 |
26 Jan 2018 the matter was settled in employers favour after the employee went to the CCMA |
|||
Unfair treatment by the line manager |
17 Jan 2017 |
16 Feb 2017 resolved at the next level of management |
|||
Umgeni Water |
None |
None |
None |
None |
None |
TCTA |
Two (2) cases at Labour court stage and four (4) at CCMA stage |
Labour court cases: TCTA//C Bleeker -Unfair labour practice TCTA// J Nhlapo -Unfair labour practice |
Labour court cases: TCTA//C Bleeker -Non-renewal of five-year fixed term contract and non-payment of incentive bonus TCTA//J Nhlapo - Unlawful reinstatement |
Labour court cases: TCTA//C Bleeker -CCMA referral November 2015, and awarded in May 2016. Labour Court review of award heard May 2018 and ruling issued August 2018. TCTA// J Nhlapo - April 2018 |
In progress |
CCMA cases: TCTA// H. Mhlongo - Unfair labour practice TCTA// N. Nkosi -Unfair labour practice TCTA// N. Mageza - Unfair labour practice TCTA// C. Mageda - Unfair labour practice |
CCMA cases: TCTA// H. Mhlongo - Unfair dismissal based on the inconsistent application of internal policies TCTA// N. Nkosi - Non-renewal of fixed term contract TCTA// N. Mageza - Non-payment of variable pay TCTA// C. Mageda -Non-payment of goodwill gesture (equivalent of one months’ salary) |
CCMA cases: TCTA// H. Mhlongo - May 2018 TCTA// N. Nkosi -March 2018 TCTA// N. Mageza - June 2018 TCTA// C. Mageda - July 2017 and June 2018 |
In progress |
||
WRC |
Two (2) disputes |
The dispute relates to a dismissal subsequent to misconduct of an employee |
The dispute has been referred to the CCMA and subsequently to the Labour Court for review. |
The dispute was reported to the CCMA on 28 July 2017 |
The dispute has not been resolved yet as it has been referred to the Labour Court for review. |
Inkomati-Usuthu Catchment Management Agency |
None |
None |
None |
None |
None |
Breede-Gouritz Catchment Management Agency |
None |
None |
None |
None |
None |
2. Refer to the table below for the number of employees dismissed:
Department / Entity |
(2)(a)(i) what number of employees have been dismissed |
(2)(a)(ii) for what reason was each employee dismissed |
(2)(b)(i) what number of the specified employees were paid severance packages |
(2)(b)(ii) what was the monetary value of each severance package |
The Department |
18 employees were dismissed |
3 were due to Fraud & Dishonesty |
None |
None |
5 were due to Theft |
||||
1 was due to Assault |
||||
3 were due to Mismanagement and embezzlement of state funds |
||||
1 was due to Fraudulent qualification |
||||
1 was due to Sexual harassment |
||||
2 were due to Gross dishonesty |
||||
1 was due to Absenteeism |
||||
1 was due to Irregular appointment in the recruitment processes |
||||
Amatola Water |
11 employees were dismissed |
10 were due to misconduct and 1 was due to incapacity |
No severance packages were offered by Amatola Water |
None |
Bloem Water |
2 Employees were dismissed |
Misconduct relating to abuse of sick leave/dishonesty and Abscondment. |
No severance packages were paid by Bloem Water |
None |
Lepelle Northern Water |
Six (6) employees |
|
None |
None |
Mhlathuze Water |
Nine (9) employees |
8 were due to Misconduct and 1 was due to Incapacity. |
None |
None |
Sedibeng Water |
15 Employees were dismissed |
14 due to Misconduct and 1 due to incapacity (ill-health) |
No, payment in lieu of notice |
None |
Rand Water |
Total number of dismissed employees in the past 5 years is 57 |
2018/19 falsifying documents (1) Misconduct (1) |
No Employees were retrenched, hence no severance payments made. |
None |
2017/18 Found in possession of the company property without permission (1) Leaving the workplace without permission (1) Bribery (1) Misconduct: one relating acts of witchcraft and the other assault (2) Wilfully leaving a place of work without permission (2) Assault (1) Gross negligence (2) Giving untrue info (2) AWOP (4) Employee found guilty as charged for AWOL for a substantial number of days and was subsequently dismissed in absentia (1) |
||||
2016/17 Found in possession of the company property without permission (1) Unauthorized possession for all (3) dismissals Wilfully leaving a place of work without permission (1) Employees were found guilty as charged for AWOL for a substantial number of days and was subsequently dismissed in absentia (2) Misconduct (1) |
||||
2015/16 Found in possession of another employee’s property without permission (1) Gross negligence (1) Absent without official leave (1) Absenteeism forming a trend (1) AWOL (1) Committed Sexual Harassment against 3 female employees. (1) Absent without official leave (1) |
||||
2014/15 Found in possession of the company property without permission(1) Absent without official leave (1) Reporting on duty being under the influence of alcohol(1) Absenteeism forming a trend (1) Bribery (1) Wilfully leaving a place of work without permission (5) Being in possession of RW property(1) Three dismissed for being absent without official leave (3) Six Charges of gross negligence and mismanagement of the Project resulting in procedural and unauthorized payment of invoices amounting to R 31m (1) Employee was charged for incompatibility for causing disharmony in the workplace (1) Failure to comply with procurement policies and failure to comply with recruitment policy-employment of next of kin (1) |
||||
2013/14 Found in possession of another employee’s property without permission(1) Driving RW vehicle without authority(1) Wilfully leaving a place of work without permission (2) Falsifying documents (1) Insubordination(1) |
||||
Umgeni Water |
Fifteen (15) employees |
Gross Negligence in appointing a candidate who did not meet the minimum requirements. |
Three (3) employees |
|
Insubordination, Absence without leave or permission and Dereliction of duty. |
||||
Unauthorized removal and or possession of company property without proper authorization. Gross negligence and or dishonesty. Misrepresentation of facts and or falsifying of information. |
||||
Unlawful possession of company property which culminates to theft. Misrepresentation of facts in that the employee said he picked up the flanges in Umlaas Road Chamber whereas he took them from stores which culminate to gross dishonesty. |
||||
Unlawful possession of company property which culminates to theft. Misrepresentation of facts in that the employee said he picked up the flanges in Umlaas Road Chamber whereas he took them from stores which culminate to gross dishonesty. |
||||
Stored and/or caused to be stored photographs depicting nudity of himself and another person on an Umgeni Water property. Accessing confidential information without proper authorization. Deleted his administrative account which was linked to a senior official’s mailbox account in order to deliberately disguise/mask your access to that person’s mailbox account which amounts to gross dishonesty. Failure to follow or adhere to Umgeni Water’s prevailing ICT practice. Failure and/or omitted and/or neglected to register each of the following Umgeni Water assets in your possession or control contrary to the reasonable expectations. |
||||
Gross insubordination/disobeying a lawful and reasonable instruction and gross insolence. |
||||
Gross Negligence in that you failed to follow an acceptable due diligence process when you realized that the page that declares CPG was understated. Gross Dishonesty in that you misrepresented facts in order to influence the evaluation process by submitting a report confirming that all is order. |
||||
Abusive, derogatory insulting language/conduct and/or harassment. Assault/Attempted Assault/Violence. |
||||
Abusive, derogatory insulting language/conduct and/or harassment unlawfully, intentionally or negligently failed to comply with prescribed procedures, rules and/or instructions. |
||||
Absence without leave for 7 consecutive days (Dismissal without notice after the employee had failed to report for duty after one month suspension without pay for similar offence). |
||||
Negligent and reckless driving which resulted into an accident. Absconded from the accident scene before the arrival of the police. |
||||
Negligence driving which resulted into an accident. Gross dishonesty and or using UW vehicle without authorization. Gross misconduct by leaving the accident scene before the Traffic Police, emergency and SAPS services could arrive. Bringing Umgeni Water’s name into disrepute by controversially disappearing from the accident scene. |
||||
Usage of UW vehicle without authorization. Failure to comply with ISO procedures. Falsely declaring information on vehicle log sheet checklist. |
||||
Unauthorized use of Umgeni Water vehicle for private reasons. Negligent driving which resulted into an accident. |
||||
WRC |
None |
None |
None |
None |
Inkomati-Usuthu Catchment Management Agency |
Two (2) employees were dismissed |
The employees were dismissed for dishonesty, fraud and non-disclosure |
None |
None |
Breede-Gouritz Catchment Management Agency |
None |
None |
None |
None |
---00O00---
03 December 2018 - NW2959
Khawula, Ms MS to ask the Minister of Water and Sanitation
Whether certain persons (names furnished) are employees of his department?
Reply:
Yes, Ms DG Mochotlhi, Mr AB Singh, Ms ZY Makhathini, Ms ONV Fundakubi and Mr JD Mahlangu are still employees of the Department. Mr MJ Mofokeng resigned from the Department.
---00O00---
03 December 2018 - NW2927
Khawula, Ms MS to ask the Minister of Water and Sanitation
How many kilometres of water and sanitation piping were laid (a) in 2017 and (b) since 1 January 2018, in each province?
Reply:
(a) Kilometers of water and sanitation piping laid in 2017. The table below illustrates the kilometers of water and sanitation per province.
Table 1:
NO |
Province |
No. Kilometres (KM) |
1 |
Gauteng |
65, 56 |
2 |
Eastern Cape |
216,939 |
3 |
Limpopo |
247,9 |
4 |
Mpumalanga |
60 |
5 |
Northern Cape |
7.8 |
6 |
Kwa Zulu Natal |
638 |
7 |
North West |
46 |
8 |
Free State |
43.1 |
9 |
Western Cape |
18,2 |
(b) Kilometers of water and sanitation piping laid since 1 January 2018, in each province? The table below illustrates the kilometres of water and sanitation per province.
Table 2:
NO |
Province |
No. Kilometres (KM) |
1 |
Gauteng |
19 |
2 |
Eastern Cape |
31,828 |
3 |
Limpopo |
72,29 |
4 |
Mpumalanga |
6 |
5 |
Northern Cape |
2.5 |
6 |
Kwa Zulu Natal |
260 |
7 |
North West |
0 |
8 |
Free State |
20,29 |
9 |
Western Cape |
0 |
---00O00---
03 December 2018 - NW2833
Steyn, Ms A to ask the Minister of Water and Sanitaiton
Whether his department (a) issued any new water rights and/or (b) transferred any water rights in the Vhembe District in Limpopo in the past three financial years; if so, (i) what are the relevant details of each affected farm, including its GPS location, (ii) who were the beneficiaries, (iii) from whom were the water rights transferred, (iv) for what purposes were (aa) new water rights issued and (bb) existing water rights transferred and (v) what are the relevant details of any other relevant information?
Reply:
(a) Yes, the Department has issued new water use entitlement.
(b) Yes, the Department has transferred water rights in the Vhembe District in Limpopo in the past three financial years.
(b)(i) See Table 1 and 2 attached.
(b)(ii) Baobab Mining and Exploration: Makhado Colliery Project.
(b)(iii) See Table 2 attached.
(b)(iv)(aa) See Table 1, column titled sector.
(b)(iv)(bb) The existing water rights were transferred for Coal Mining.
(b)(v) See Table 1 and 2 attached.
---00O00---
Table 1: List of authorizations granted during financial years 2015/16, 2016/17, 2017/18 to date
NO. |
APPLICANT |
FILE/ REGISTER/ LICENSE NUMBER |
SECTOR |
PURPOSE |
PROPERTY DETAILS |
EQUITY STATUS |
APPLICA-TION DATE |
FINALISA-TION DATE |
QUATER-NARY |
|
1 |
African Caribean Aloe Product (PTY)LTD |
27/2/1/A72B/427MS |
Agriculture |
Irrigation |
Remainder of Wintersveld |
BBBEE |
12 September 2013 |
18 December 2015 |
A72B |
|
2 |
Baobab Mining and Exploration: Makhado Colliery Project |
16/2/7/A480/1/4 |
Mining |
Coal |
Fripp 645 MS and others |
BBBEE |
10 December 2012 |
24 December 2015 |
A80F |
|
3 |
Brother and sisters fresh vegetables Cop LTD |
27/2/1/A91J |
Agriculture |
Irrigation |
Tshivhilwi |
B:BBBEE |
09-May-17 |
02-Oct-17 |
A91G |
|
4 |
Chatleka Communal Property Association |
27/2/1/A71D/LS434/0 |
Agriculture |
Irrigation |
Dassieshoek 432 LS /3, Ontevreden 358LS/0, Ontevreden 358LS/0 |
HDI |
21 September 2011 |
30 August 2015 |
A71D |
|
5 |
COGHSTA |
27/2/2/A171/9/4 |
LG &Devt |
Construction of drainage channel |
Doornkraal 680 LS |
LG/Govt |
27 September 2013 |
18 December 2015 |
A71A |
|
6 |
Davhana F |
27/2/1/A91C |
Agriculture |
Irrigation |
Elim village |
HDI |
04 April 2014 |
21 October 2015 |
A91C |
|
7 |
Dr. JJ Uys |
27/2/1/A1171/5/1 |
Agriculture |
Irrigation |
Tovey 154 MS |
HAI |
20 July 2014 |
10 February 2016 |
A71K |
|
8 |
Dream World Investments 170 |
27/2/2/A171 |
LG &Devt |
river crossings |
portion 51 of Doornkraal 680 LS |
HAI |
04 December 2014 |
17 July 2015 |
A71A |
|
9 |
Dzevhe S. |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
10 |
Fletcher W A |
27/2/1/A71B |
Agriculture |
Irrigation |
Portion 1 of Songloed 857LS |
HAI |
13 May 2014 |
28 March 2015 |
A71B |
|
11 |
Gemeli M. |
21/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
12 |
Goba G.J |
27/2/1/A80C |
Agriculture |
Irrigation |
HalishibaDzanani |
HDI |
09 November 2012 |
16 June 2015 |
A80C |
|
13 |
Godzwana I.S |
27/2/1/A380/9/1 |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
17 July 2015 |
A80C |
|
14 |
House on the Mountain Farming Co-Operative Ltd |
27/2/1/A691/1 |
Agriculture |
Irrigation |
Hasani Dakari Village |
HDI |
06-Julu-15 |
18 December 2015 |
A91F |
|
15 |
IkagengBalemibaMankweng |
27/2/1/A71B |
Agriculture |
Irrigation |
Mankweng |
HDI |
12 November 2014 |
18 December 2015 |
A71B |
|
16 |
Jika Farm |
27/2/A791/10/1 |
Agriculture |
Irrigation |
Xigalo |
B:BBBEE |
19-May-17 |
15-Sep-17 |
A91F |
|
17 |
Khaloshe NT |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
18 |
Khalushi MP |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
16 June 2015 |
A80C |
|
19 |
Khangala ND |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
16 June 2015 |
A80C |
|
20 |
Khangale KT |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
21 |
Khomola NC |
27/2/1/A891/18/1 |
Agriculture |
Irrigation |
Tshaulu-Dopeni |
HDI |
03 May 2013 |
20 October 2015 |
A91H |
|
22 |
Khuba TG |
27/2/1/A591/1 |
Agriculture |
Irrigation |
Tsianda Village |
HDI |
23 June 2015 |
21 October 2015 |
A91E |
|
23 |
Khunwana T.G |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
24 |
Khwashaba AI |
27/2/1/B582/2/1 |
Agriculture |
Irrigation |
Ngovhela-Maembeni |
HDI |
20/02/2015 |
04 October 2015 |
A91G |
|
25 |
Kotihle Trust |
27/2/1/A71A |
Agriculture |
Irrigation |
Doornbuilt 624LS |
HDI |
30 July 2014 |
20 October 2015 |
A71A |
|
26 |
Kwinda M |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
16 June 2015 |
A80C |
|
27 |
Kwinda NJ |
27/2/1/A380/35/1 |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
17 July 2015 |
A80C |
|
28 |
Limpopo Coal Company: Vele colliery Mine |
16/2/7/A1171/c1/1 |
Mining |
industry |
Erfrust 123MS,Bergen op zoom 124 MS,onvervlakte 125 MS |
BBBEE |
24 September 2014 |
18 December 2015 |
A71L |
|
29 |
Limpopo Coal Company: Vele Colliery: River Diversion |
27/2/2/A171/1/4 |
Mining |
Mining |
Overvlakte 125 MS portions 3,4 & 5 AND Bergen Op Zoom 124 MS |
W:BBBEE |
19-Dec-16 |
16-Jan-18 |
A71L |
|
30 |
Lishiba M. |
27/2/1/A380/28/1 |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
17 July 2015 |
A80C |
|
31 |
LushuthaAgric Co-Operation |
27/2/1/A292/10/1 |
Agriculture |
Irrigation |
Vhurivhuri |
HDI |
12 June 2015 |
21 October 2015 |
A92B |
|
32 |
Luvhani RP |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
33 |
M.J. Munyai |
27/2/1/A791/27/1 |
Agriculture |
Irrigation |
Khubvi Village |
HDI |
29 August 2011 |
17 July 2015 |
A91G |
|
34 |
Mac Group of Companies/ Mactransco railway siding |
16/2/7/A71K/B102/3 |
Industry |
Industry |
Portion 68 of Messina 4 MT |
HAI |
01 October 2011 |
12 January 2015 |
A71K |
|
35 |
Magadani M.A |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
16 June 2015 |
A80C |
|
36 |
Magwayini Agricultural |
27/2/1/A691/37/1 |
Agriculture |
Irrigation |
Shigalo-Ndlhazini village |
HDI |
05 June 2013 |
30 August 2015 |
A91F |
|
37 |
Maitakhole RC |
27/2/1/A591/27/1 |
Agriculture |
Irrigation |
Tsianda Village |
HDI |
23 June 2015 |
20 October 2015 |
A91E |
|
38 |
Maluta ME |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
39 |
Mamabolo MC |
27/2/1/A71B |
Agriculture |
Irrigation |
Portion 218 of Kalkfontein 1001LS |
HDI |
24 February 2014 |
28 March 2015 |
A71B |
|
40 |
Mamadi H.J |
27/2/1/A380/39/1 |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
17 July 2015 |
A80C |
|
41 |
Mami group Pty ltd |
27/2/2/A591/6/1 |
Development |
Development |
CHIBASE 312 MT |
B:BBBEE |
12 May 2017 |
13-Nov-17 |
A91E |
|
42 |
MamphodoMushasha CPA |
27/2/1/A91B |
Agriculture |
Irrigation |
Melkhoutkopjes 314 LS |
HDI |
03 July 2014 |
02-Oct-17 |
A91B |
|
43 |
Manenzhe M. |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
44 |
Maroroma Agricultural Primary Co-operative |
27/2/1/A691/43/1 |
Agriculture |
Irrigation |
Hasani Dakari Village |
HDI |
15 June 2015 |
19 November 2015 |
A91F |
|
45 |
Masindi I.M |
27/2/1/A891/1/1 |
Agriculture |
Irrigation |
Lambani village |
HDI |
19 January 2015 |
04 October 2015 |
A91H |
|
46 |
MatambaLungisani |
27/2/1/A591/23/1 |
Agriculture |
Irrigation |
Dzwerani village |
HDI |
21 February 2013 |
20 October 2015 |
A91E |
|
47 |
Mathala I |
27/2/1/A380/29/1 |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
17 July 2015 |
A80C |
|
48 |
Mathala RL |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
49 |
Mathivha TS |
27/2/1/A80C |
Agriculture |
Irrigation |
Tshitwi Village |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
50 |
Matidza TS |
27/2/1/A380/36/1 |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
17 July 2015 |
A80C |
|
51 |
Matshavha M.D |
27/1/1/A71H |
Agriculture |
Irrigation |
Sinthumule 291 LS/1 |
HDI |
13 May 2013 |
30 August 2015 |
A71H |
|
52 |
Mavhetha N.P |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
16 June 2015 |
A80C |
|
53 |
Mavhungu M |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 April 2015 |
A80C |
|
54 |
Mavhungu R.S |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
16 June 2015 |
A80C |
|
55 |
Messina Border Properties (PTY)LTD |
27/2/1/A71A/LS634/0 |
Agriculture |
Irrigation |
Newgate 802MS/0 |
HDI |
05 December 2012 |
20 October 2015 |
A80E |
|
56 |
Mfana Farming |
27/2/1/A72A |
Agriculture |
Irrigation |
Overdyke CPA |
HDI |
12 November 2014 |
19 April 2015 |
A72A |
|
57 |
Mokobi T.M |
21/2/1/A80C |
|
Irrigation |
Dzanani |
HDI |
09 November 2012 |
16 June 2015 |
A80C |
|
58 |
Moletjie Farming |
27/2/1/A671/3/1 |
Agriculture |
Irrigation |
Ga-Maleka |
HDI |
19/06/2015 |
04 October 2015 |
A71F |
|
59 |
Mopani District Munipality: Nandoni |
27/2/2/A691/1 |
LG &Devt |
Gov |
Nandoni |
LG/Govt |
03 March 2014 |
16 August 2015 |
A91F |
|
60 |
Motlokwa T.S |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
61 |
Mpfuni A.A |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
62 |
Mpfuni KJ |
27/2/1/A80C |
Agriculture |
Irrigation |
Tshitwi-Nzhelele village |
HDI |
09 November 2012 |
16 June 2015 |
A80C |
|
63 |
Mphohoni I K |
|
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
16 June 2015 |
A80C |
|
64 |
Mposi MR |
27/2/1/A691/49/1 |
Agriculture |
Irrigation |
Ha-Mangilasi |
HDI |
10-Feb-17 |
13-Jun-17 |
A91F |
|
65 |
Mudau N.E |
27/2/1/A380/60/1 |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
17 July 2015 |
A80C |
|
66 |
Mudau NG |
27/2/1/A591/26/1 |
Agriculture |
Irrigation |
Tsianda Village |
HDI |
23 June 2015 |
20 October 2015 |
A91E |
|
67 |
Mudau SM |
27/2/1/A580/3/1 |
Agriculture |
Irrigation |
Mamvuka Village |
HDI |
26 September 2014 |
18 December 2015 |
A80E |
|
68 |
Mudzunga Aquaculture Agricultural primary cooperative LTD |
27/2/1/A91G |
Agriculture |
Irrigation |
Makwarela |
HDI |
13 March 2014 |
17 March 2016 |
A91G |
|
69 |
Mulaudzi M.N |
27/2/1/A80C |
Agriculture |
Irrigation |
Maranikwe village |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
70 |
Mungomeni A.E |
27/2/1/A80C |
Agriculture |
Irrigation |
Maranikwe village |
HDI |
09 November 2012 |
16 June 2015 |
A80C |
|
71 |
Munyai MM |
27/2/1/A380/37/1 |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
17 July 2015 |
A80C |
|
72 |
Munyai MW |
27/2/1/A591/1/1 |
Agriculture |
Irrigation |
Ha-Mutsa village |
HDI |
13 March 2014 |
10 February 2016 |
A91E |
|
73 |
Musandiwa AP |
27/2/1/A180/1 |
Agriculture |
Irrigation |
Khalavha village |
HDI |
09 May 2014 |
13 March 2016 |
A80A |
|
74 |
Musekwa M.N |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
75 |
Muvhango R.P. |
27/2/1/A192/20/1 |
Agriculture |
Irrigation |
Mbahela Abstraction |
HDI |
13 March 2015 |
20 October 2015 |
A92A |
|
76 |
Muvhulawa MW |
27/2/1/A871/7/1 |
Agriculture |
Irrigation |
Remaining extent of the Farm Spruithoek 249 LS |
HDI |
12 June 2015 |
18 December 2015 |
A71H |
|
77 |
Ndizwenezwo Business Enterprise |
27/2/1/A91F |
Agriculture |
Irrigation |
Tshitomboni village |
HDI |
15 June 2015 |
17 March 2016 |
A91F |
|
78 |
Ndwamato MA |
27/2/1/A91F |
Agriculture |
Irrigation |
Dovheni village |
HDI |
23 September 2013 |
17 July 2015 |
A91F |
|
79 |
Nedambane TA |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 April 2015 |
A80C |
|
80 |
Nefale K.J. |
27/2/1/A180/9/1 |
Agriculture |
Irrigation |
Dopeni Village(Ndzhelele) |
HDI |
15 June 2015 |
17 March 2016 |
A80A |
|
81 |
Nefolovhodwe AS |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
82 |
Nekuvule M.S |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
83 |
Neluheni MO |
27/2/1/A591/31/1 |
Agriculture |
Irrigation |
Manamani village |
HDI |
24/03/2015 |
24 December 2015 |
A91E |
|
84 |
Nemaangani P.A |
27/2/1/A80B |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80B |
|
85 |
Nemadandila TS |
27/2/1/A891/19/1 |
Agriculture |
Irrigation |
Tshifudi-Dimani village |
HDI |
09 June 2015 |
20 October 2015 |
A91H |
|
86 |
Nemangwele KJ |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
87 |
Nemangwele T.L |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
88 |
Nengovhela T.S. |
27/2/1/A580/7/1 |
Agriculture |
Irrigation |
Portion3 of the farm Nooitgedacht 72/MS |
HDI |
12 June 2015 |
17 March 2016 |
A80E |
|
89 |
Nenzhelele M.A |
27/2/1/A380/18/1 |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
17 July 2015 |
A80C |
|
90 |
Nesane MS |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
91 |
Nesani T.W |
27/2/1/A380/58/1 |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
17 July 2015 |
A80C |
|
92 |
Netshifhefhe ND |
27/2/1/A691/40/1 |
Agriculture |
Irrigation |
Gunyula |
HDI |
21 October 2013 |
19 November 2015 |
A91F |
|
93 |
Netshitanini NG |
|
Development |
Brickyard |
Site no.2429 Muledane |
HDI |
18-Jul-16 |
13-Jun-17 |
A91E |
|
94 |
Nevondo T.G |
27/2/1/A791/44/1 |
Agriculture |
Irrigation |
Vondo Village |
HDI |
12 June 2015 |
18 December 2015 |
A91G |
|
95 |
Ngwana ME |
27/2/1/A380/10/1 |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
17 July 2015 |
A80C |
|
96 |
Nthangeni AC |
27/2/1/A591/24/1 |
Agriculture |
Irrigation |
Muledane |
HDI |
07 May 2015 |
20 October 2015 |
A91E |
|
97 |
Nwabubha Agricultural Primary Co-Operative |
27/2/1/A691/47/1 |
Agriculture |
Irrigation |
Vuwani |
HDI |
15 June 2015 |
17 March 2016 |
A91F |
|
98 |
Octane Dew 106 cc |
27/2/A171/7/1 |
Industry |
filling station |
portion 42 of Rondebosch 287 LS |
HAI |
13 November 2014 |
18 December 2015 |
A71H |
|
99 |
Palm Tree Agricultural Cooperative Limited |
27/2/1/A161/49/1 |
Agriculture |
Irrigation |
Portion 48, 49 & 50 of the farm Kalkfontein 1001LS |
B:BBBEE |
22-Feb-17 |
13-Jun-17 |
A71B |
|
100 |
Panlemn Agricultural Cooperative LTD |
27/2/1/A92B |
Agriculture |
Irrigation |
Tshitavha |
B:BBBEE |
24-Feb-17 |
02-Oct-17 |
A91G |
|
101 |
PEB Properties (PolokwaneEsternBouleved) |
27/2/2/A171/6/4 |
LG &Devt |
Construction of stormwater |
Krugersberg 993 LS |
BBBEE |
31 July 2013 |
17 July 2015 |
A71A |
|
102 |
PH Storm |
27/2/1/A971/2/1 |
Agriculture |
Irrigation |
Barron 622 |
HAI |
25 September 2014 |
21 October 2015 |
A71J |
|
103 |
Phalandwa T.E |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
104 |
PMC(PolokwaneMeturlargical Complex)Anglo Platinum |
16/2/7/A700/C01/3 |
Industry |
Industry |
ReboileCommunuty Trust |
BBBEE |
01 November 2012 |
25 August 2015 |
A700 |
|
105 |
Radana TS |
|
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
106 |
Raedani N.S |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
107 |
Ramaano AE |
27/2/1/A691/38/1 |
Agriculture |
Irrigation |
Dzwerani village |
HDI |
04 November 2013 |
17 July 2015 |
A91F |
|
108 |
Ramannzi LM |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
109 |
Ramatamela N.P |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
110 |
Ramatshimbila H |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
111 |
Ramatshimbila SM |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 April 2015 |
A80C |
|
112 |
Ramuthaga MT |
27/2/1/A192/19/1 |
Agriculture |
Irrigation |
Matangari-Tshiombo |
HDI |
04 November 2013 |
18 December 2015 |
A92A |
|
113 |
Razwinani JN |
27/2/1/A192/21/1 |
Agriculture |
Irrigation |
Matangari |
HDI |
08 October 2014 |
20 October 2015 |
A92A |
|
114 |
RembanderAgri Business Primary Copr LTD |
27/2/1/A591/30/1 |
Agriculture |
Irrigation |
Reubander 21 LT |
HDI |
14 July 2015 |
18 December 2018 |
A91E |
|
115 |
Rothodzani Agricultural Co-operative Limited |
27/2/1/A292/9/1 |
Agriculture |
Irrigation |
Mangaya village |
HDI |
23 September 2014 |
17 July 2015 |
A92B |
|
116 |
Sazm Trading & Projects (Pty) Ltd |
27/2/1/A691/50/1 |
Agriculture |
Irrigation |
Shigalo Village |
B:BBBEE |
09-Feb-17 |
13-Jun-17 |
A91F |
|
117 |
Shovhas Valley cooperative |
27/2/1/A391/1/1 |
Agriculture |
Irrigation |
Mashau Village |
HDI |
17 April 2015 |
20 October 2015 |
A91C |
|
118 |
Silicon smelters |
27/2/2/A171/8/1 |
Industry |
Smelter |
Weltevreden 746 LS |
BBBEE |
22 July 2013 |
04 February 2017 |
A71A |
|
119 |
Silicon smelters |
27/2/2/A191/8/1 |
Industry |
Smelting process |
Weltevreden 746 LS |
W:BBBEE |
17 January 2017 |
08-Dec-17 |
A71A |
|
120 |
Simba RZ |
27/2/1/B891/20/1 |
Agriculture |
Irrigation |
Buluni Village(Farmer 263MT) |
HDI |
10 June 2015 |
20 October 2015 |
A91H |
|
121 |
Singo MF |
27/2/1/A591/28/1 |
Agriculture |
Irrigation |
Tsianda Village |
HDI |
22 June 2015 |
18 December 2015 |
A91E |
|
122 |
Splendid Sunset Investment |
27/2/1/A600 |
Agriculture |
Irrigation |
Portion268 Farm Avon LS |
HDI |
19 June 2015 |
20 October 2015 |
A71H |
|
123 |
Steady Rain Farming |
27/2/1/A71F |
Agriculture |
Irrigation |
Ga- Mokibelo |
HDI |
19/06/2015 |
20 October 2015 |
A71F |
|
124 |
ThabaChueu Mining (Pty) LTD-Silicon Smelters |
27/2/1/A71A/LS852/13 |
Mining |
Mining |
Fort Klipdam |
HDI |
18 December 2012 |
20 October 2015 |
A71A |
|
125 |
Thulamela Municipality: Dzwerani Bridge |
27/2/1/A591/1 |
LG &Devt |
Construction of bridge |
Dzwerani village |
LG/Govt |
10 July 2015 |
17 March 2016 |
A91E |
|
126 |
Timeti NA |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 April 2015 |
A80C |
|
127 |
Tseisi N.S |
27/2/1/A80C |
Agriculture |
Irrigation |
Dzanani |
HDI |
09 November 2012 |
30 August 2015 |
A80C |
|
128 |
Tshibalo NA |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
129 |
TshidawofaraAgr. Primary Cooperative |
27/2/1/A791/43/1 |
Agriculture |
Irrigation |
Mbilwi village |
HDI |
23/01/2015 |
04 October 2015 |
A91G |
|
130 |
TshihulimathemaAgr. Primary cooperative |
27/2/1/A691/1/1 |
Agriculture |
Irrigation |
Mphego village |
HDI |
20/02/2015 |
17 March 2016 |
A91F |
|
131 |
Tshirema T |
27/2/1/A591/22/1 |
Agriculture |
Irrigation |
Lwamondo |
HDI |
04 November 2013 |
20 October 2015 |
A91E |
|
132 |
Tshirundu AJ |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
133 |
Tshirundu MJ |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
134 |
Tshirundu RA |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
135 |
Tshirundu S |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
136 |
Tshisikule NP |
27/2/1/A691/42/1 |
Agriculture |
Irrigation |
Tshififi village |
HDI |
13 March 2014 |
04 October 2015 |
A91F |
|
137 |
Tshitangoni M |
27/2/1/A380/13/1 |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
17 July 2015 |
A80C |
|
138 |
Tshotheli MD |
27/2/1/A80C |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
30 August 2015 |
A80C |
|
139 |
Tsiligi P |
27/2/1/A380/14/1 |
Agriculture |
Irrigation |
Sane |
HDI |
03 December 2013 |
17 July 2015 |
A80C |
|
140 |
Twin City Development |
27/2/1/A91C/1 |
LG &Devt |
Development |
Elim Mall |
BBBEE |
09 November 2014 |
18 December 2015 |
A91C |
|
141 |
VersamelBoerdery (Pty) Ltd |
27/2/1/A71H/A/2980 |
Agriculture |
Irrigation |
Nebo |
HDI |
03 July 2014 |
28 March 2015 |
A71H |
|
142 |
Vhembe District Municipality |
27/1/2/A92B |
LG &Devt |
Development |
Tshikundamalemavilage |
LG/Govt |
06/02/2015 |
20 October 2015 |
A92B |
|
143 |
Vhugala River Queen Agricultural Hospitality |
27/2/1/A871/4/1 |
Agriculture |
Irrigation |
Farm Rondebosch 287 LS Portion 10 |
HDI |
12 June 2015 |
04 October 2015 |
A71H |
|
144 |
Vhumatshelo Crop Farming Co-operative Ltd |
27/2/1/A91C |
Agriculture |
Irrigation |
Elim village |
HDI |
28 July 2014 |
18 December 2015 |
A91C |
|
145 |
Vica Investments and Trading Eighteen |
27/2/1/A191/7/1 |
Agriculture |
Irrigation |
Vreemdeling 236 MT Portion 4 HDI |
HAI |
20 July 2015 |
21 October 2015 |
A91C |
|
146 |
Willy Maseka's Farming & Projects |
27/2/1/A871/3/1 |
Agriculture |
Irrigation |
Machaba village |
HDI |
12 December 2013 |
16 July 2015 |
A71D |
|
147 |
Makuya Traditional Healers Organization |
|
Agriculture |
Irrigation |
MakuyaMusanda Village |
B:BBBEE |
26 March 2012 |
06-Sep-18 |
A91J |
|
148 |
Vhembe Municipality: Makhado waste water treatment |
|
Government |
WWTW |
PORTION 1 OF FARM RIETVLY 276 LS |
Govemenrt |
01 May 2013 |
06-Apr-18 |
A700 |
|
149 |
Rolivhuwa Farming and Multi-Purpose Co-operative Limited |
Agriculture |
Irrigation |
Mphego village(vhembe district) |
HDI |
18-Jul-16 |
04-Apr-18 |
A91F |
||
150 |
Mhangwane MM |
|
Agriculture |
Irrigation |
ELIM |
HDI |
30-Jun-17 |
04-Apr-18 |
A91C |
|
151 |
Oor Die MuurBoerdery CC |
27/2/1/A191/3/1 |
Agriculture |
Irrigation |
Remainder of the farm Geluk no 240 MT portion 3 and portion 2 of the Farm KleinPlaats 241 MT |
W:BBBEE |
25-Jul-17 |
05-Jul-18 |
A91A |
|
152 |
Mr NetshandamaDivhani |
27/2/A791/55/1 |
Agriculture |
Irrigation |
Vondwe Village |
HDI |
09-Oct-17 |
24-May-18 |
A91G |
|
153 |
Mr Netshandama TG |
|
Agriculture |
Irrigation |
Vondwe Village |
HDI |
09-Oct-17 |
05-Jul-18 |
A91G |
|
154 |
Mphathele Farming and Projects |
|
Agriculture |
Irrigation |
Thengwes 255 MT Portion 0 |
HDI |
06-Feb-18 |
02-Aug-18 |
A92B |
Table 2: List of Properties that surrendered water in favour of to Baobab Mining and Exploration: Makhado Colliery Project
No |
Customer Name |
Farm name |
1 |
MaswiriBoerdery (Pty) Ltd |
Schuitdrift 179 |
|
|
Skullpoint 132 |
|
|
Lotsieus |
|
|
Kranspoort |
2 |
Jan Fourie Trust |
Naus Ptn2 |
|
|
Naus Ptn3 |
|
|
Tshipise Ptn14 |
3 |
Johan Nell Trust |
Tshipise Ptn31 |
|
|
Hardevlakte |
4 |
Mount Stuart Boerdery |
Mount Stuart |
|
|
Mount Stuart Ptn 2 |
5 |
Xmas Boerdery Trust |
Meteor |
|
|
Xmas |
6 |
Alicedale Estates (Pty) Ltd |
Alicedale |
|
|
Beckmans |
|
|
TshipisePtn 1 |
|
|
TshipisePtn 2 |
|
|
TshipisePtn 3 |
|
|
TshipisePtn 4 |
|
|
TshipisePtn 5 |
7 |
Ronelle & Bennie Nicholson |
TshipisePtn 6 |
|
|
TshipisePtn 7 |
|
|
TshipisePtn 8 |
8 |
A P Cronje |
TshipisePtn 15 |
9 |
Kumbelo Trading 102 CC |
Hope Ptn 1 |
10 |
Nzhelele Valley Estate (Pty) Ltd |
Hope |
11 |
Peter Knott Investment Trust |
Doreen |
|
|
KroomdraaiPtn 1 |
12 |
H B Knott |
Howard |
13 |
Maremani Nature Reserve (Pty) Ltd |
Bosbokpoort |
|
|
Solitude |
|
|
Stoffel |
14 |
Gordonia Estates Trust |
Tshipise Ptn9 |
|
|
Tshipise Ptn13 |
---00O00---
03 December 2018 - NW3686
Khawula, Ms MS to ask the Minister of Water and Sanitation
With reference to his reply to question 2700 on 20 November 2018, what number of litres of water were lost through leaks (a) nationally and (b) in each (i) province and (ii) municipality in the 2016-17 financial year?
Reply:
It should be noted by the Hounorable Member that the response provided in the reply to question 2700 published on 7 September 2018 was adequately responded to.
---00O00---
03 December 2018 - NW2960
Matiase, Mr NS to ask the Minister of Water and Sanitation
(a) Which of the recommendations of the report of the Public Service Commission, titled Investigation into the Irregularity of the Appointment of DDGs at the Department of Water and Sanitation (i) were and (ii) were not implemented and (b) in each instance that the recommendation was not implemented, why was it not implemented?
Reply:
(a) (i) None
(ii) All
(b) The matter is still under consideration by Parliamentary committees.
---00O00---