Question NW2963 to the Minister of Water and Sanitation
03 December 2018 - NW2963
Mulaudzi, Adv TE to ask the Minister of Water and Sanitation
With reference to his reply to question 2470 on 8 October 2018, (a) who are the contractors constructing each dam, (b) what is the value of each specified contract and (c) on what date was each contract signed?
Reply:
Refer to the table below for the list of constructors constructing dams in all provinces:
ITEM |
DAM INFORMATION |
||
Name of Dam |
Clanwilliam Dam |
Hazelmere Dam |
Tzaneen Dam |
GPS Location |
32°11'5.1"S 18°52'28.5"E |
29°35'55"S 32°2'36"E |
23°47'57"S 30°09'58"E |
Province |
Western Cape |
KwaZulu Natal |
Limpopo |
River/ Watercourse |
Olifants |
Mdloti |
Letaba |
Size/ Capacity (Million Cubic Meters) |
125Mm³ (existing) 344Mm³ (raised) |
23.9 Mm³ (existing) 43.6Mm³ (raised) |
158Mm³ (existing) 193 Mm³ (raised) |
Purpose |
Irrigation & Domestic Use |
Irrigation & Domestic Use |
Domestic Commercial |
Estimated Construction Cost |
R 2.2 Billion (Raising of existing Dam Only) |
R 600 Million (total project costs, including professional fees, implementing Agent fees, Project Management office on site) |
R367.4 Million (Estimate cost including VAT) R322 Million (Estimate cost excluding VAT) |
Contractors constructing each dam |
DWS Construction Unit |
Group Five |
DWS Construction Unit to be appointed |
The value of each specified contract |
R 3 726 735 402 (inclusive of all project components excluding escalation and VAT |
R498 157 000.00 dam only at tender stage |
R367.4 Million (Estimate cost including VAT, Contingencies & Contract Price Adjustment) R322 Million (Engineer’s Estimate in August 2018 excluding the above costs. |
Date on which each contract was signed |
10 October 2018 (Temporary access granted to DWS Construction) |
01 June 2015 |
Not yet signed (Currently in Evaluation prior to Award) |
---00O00---