Question NW822 to the Minister of Water and Sanitation

Share this page:

30 March 2023 - NW822

Profile picture: Buthelezi, Ms SA

Buthelezi, Ms SA to ask the Minister of Water and Sanitation

(1)What total number of large water projects are currently running in each province; (2) what total number of the specified projects are still (a) undergoing planning and (b) under construction; (3) (a) what total number of the projects are currently behind schedule and (b) how far behind is each such project?

Reply:

The Department currently has 14 large water projects running across different provinces. A total of 10 infrastructure projects are under planning, whilst 4 are in construction phase. In terms of progress, 11 projects are behind schedule. Details are tabulated below:

(1) PROJECTS PER PROVINCE

(2) PROJECT PHASE

(3) PROJECT SCHEDULE

Province

Number of Projects

Name of Project

(a) Planning

(b) Construction

(a) Behind Schedule

(b) How Far Behind Schedule

Eastern Cape

5

Gcuwa Weir

X

 

No

N/A

   

Mzimvubu Water Project

 

X

Yes

N/A

   

Lusikisiki Zalu Dam

X

 

Yes

1 Year

   

Coerney Dam

X

 

No

N/A

   

Foxwood Dam

X

 

Yes

1 Year

Free State

0

-

-

-

 

 

Gauteng

0

-

-

-

 

 

Kwa-Zulu Natal

4

Raising of Hazelmere Dam

 

X (Complete)

No

N/A

   

uMkhomazi Water Project

X

 

Yes

4 years

   

Cwabeni Off-Storage Channel Dam

X

 

Yes

9 months

   

Stephen Dlamini Dam

X

 

Yes

9 months

Limpopo

4

Raising of Tzaneen Dam

 

X

Yes

28 months

   

ORWRDP: Olifants Management Model

X

 

No

N/A

   

New Nwamitwa Dam

X

 

Yes

7 Years

   

Mokolo Crocodile River (West) Augmentation Scheme - Phase 2A

 

X

Yes

3 years

Mpumalanga

0

-

-

-

 

 

Northern Cape

0

-

-

-

 

 

Northwest

0

-

-

-

 

 

Western Cape

2

Raising of Clanwilliam Dam

 

X

Yes

3 years

   

Berg River-Voelvlei Augmentation Scheme

X

 

Yes

6 months

TOTALS

14

 

10

4

11

 

---00O00---