Questions and Replies

Filter by year

30 October 2017 - NW2754

Profile picture: Dreyer, Ms AM

Dreyer, Ms AM to ask the Minister of Public Works

Is there a backlog with respect to any of his department’s (a) essential, (b) major and/or (c) other projects; if so, (i) which projects are affected and (ii) what are the full reasons for the delay in each case?

Reply:

1. Yes, the Department has identified and programmed backlog in the area of construction infrastructure projects deemed essential to be cleared year on year basis.

2. Definition of backlog:

Backlog in terms of infrastructure projects is defined as a number of projects that remained on planning phase for a period exceeding two years after issuing of procurement instruction and construction projects on construction phase for a period exceeding two years of construction period.

3. Essential and/or Major

The department has no classification of projects. It works according to prioritisation from client departments. Statistics of backlog are as follows:

3.1 Projects on planning stage for 2016/17

  • Planned Maintenance = 432
  • DPW Capital = 172
  • Client Capital = 530

Total = 1134 (Annual target was 15% of 1134)

(a) Performance reported in 2016/17 was 159 representing 14% of 1134. That implies that 94% of the annual target was achieved.

(b) Annual target for 2017/18 remain 15% (146) of the 975 remaining backlog in line with availability of budget from clients for the construction phase.

3.2 Projects on Construction Phase for 2017/18

  • Planned Maintenance = 24
  • DPW Capital = 3
  • Client Capital = 17

Total = 44

4. The annual target for 2017/18 is 75% (32) of 44 backlog projects identified and programmed.

5. Backlog projects in construction phase is caused by under-performance of contractors appointed for execution of the work, heritage compliance requirements, litigation processes, contract disputes and subsequent cancellations. Normal process of sourcing the replacement contractor had to be followed without deviation. In terms of CIDB regulation the department can only initiate the appointment of a replacement contractor after six months of cancellation. This waiting period contributes to backlog statistics.

6. These challenges will be addressed by the infrastructure delivery management system (IDMS) which the department is in the process of institutionalising and establishment of pre-approved panels of contractors and consultants.

7. Please find attached hereto a list of projects identified as infrastructure backlog of projects in construction phase for 2017/18 and projects that were on planning phase in 2016/17 and full reasons for the delay in each case.

30 October 2017 - NW2345

Profile picture: Mileham, Mr K

Mileham, Mr K to ask the Minister of Cooperative Governance and Traditional Affairs

(1)(a) Which municipalities declared local disasters due to water shortages caused by drought (i) in each of the past three municipal financial years and (ii) since 1 July 2017, (b) on what date was each disaster (i) declared and (ii) gazetted, (c) what action(s) has been taken by his department to address the local disasters and (d) what amount has been spent on addressing the local disasters in each case; (2) What amount in funding has been made available to assist municipalities where local disasters have been declared at (a) national and (b) provincial levels of government?

Reply:

(1) (a) (i) The local state of disasters declared by municipalities due to water shortages caused by drought during the past three municipal financial years, that have been reported to my department, are listed in a table below. All the other states of disasters during the indicated period were provincial states of disasters, declared by respective provinces.

For the past three municipal financial years:

Provinces and Municipalities

Financial Year

Eastern Cape Province

Joe Gqabi District Municipality

2014/15 (January 2014)

Western Cape Province

Central Karoo (Prince Albert)

Eden District (Knysna, Bitou, Oudtshoorn)

Cape Winelands (Witzenburg)

2015/2016 (November 2015)

(ii) Since 01 July 2017, the following municipalities were declared a local state of disaster:

Provinces and Municipalities

Period

Eastern Cape Province

Sarah Baartman District Municipality

Nelson Mandela District Municipality

Amathole District Municipality

August 2017

August 2017

September 2017

(b) The dates for the (i) declarations and (ii) gazettes are as follows:

Provinces and Municipalities

(b) dates for the (i) declarations and (ii) gazettes

Eastern Cape Province

Joe Gqabi District Municipality

 

30 January 2014, GN3115 - 6 EC 2014

Western Cape Province

Central Karoo (Prince Albert)

Eden District (Knysna, Bitou, Oudtshorn)

Cape Winelands (Witzenburg)

25 November 2015, GN632-365 WC 2015

 

Provinces and Municipalities

(b) dates for the (i) declarations and (ii) gazettes

Eastern Cape Province

Sarah Baartman District Municipality

Nelson Mandela Metro Municipality

Amathole District Municipality

11 August 2017, LAN3893-118 EC2017

14 August 2017, GN13895-19 EC2017

04 September 2017, GN3908-180 EC2017

(c) Where applicable, the department performs the following roles:

  • Conducts assessments and classification of disasters as per section 23 of the Disaster Management Act (Act No. 57 of 2002);
  • Facilitates the provision of technical support and guidance through the Municipal Infrastructure Support Agent (MISA);
  • Coordinates the funding allocation to address the situation; and
  • Monitors the implementation of intervention measures as per the Division of Revenue Act and applicable grant conditions.

(d) The amounts spent on addressing drought and water shortages in all the municipalities that were declared a state of disaster were provided through reprioritisation process by affected municipalities, Provincial Treasuries as well as relevant provincial and national government departments. The bulk of the funds that were made available by the provincial and national spheres of government were for implementation of drought intervention measures with regard to declared provincial state of disasters. With regard to the recent state of disasters declared by Amathole, Sarah Baartman District Municipalities and Nelson Mandela Metro Municipality respectively, there are no amounts allocated by the department and spent so far, as the process for the drought assessments and disaster classification are underway.

The bulk of the funds that were made available by the provincial and national spheres of government were for implementation of drought intervention measures with regard to declared provincial state of disasters. However, it should be noted that the indicated municipalities also benefitted from the funding that was allocated due to the declaration of a provincial state of disaster as a result of drought, since they were incorporated within the provincial declarations.

2. (a) The relevant national departments contributed funding to assist the affected provinces whereby the municipalities that declared a local state of disaster also benefitted. The details below are as per the reports from sector departments as well as where my department facilitated funding:

Table 1: Funding facilitated by different national sector departments to address the drought situation

Province that benefitted

National department that facilitated and contributed funding

Amount and source of funding

Financial year

Type of Assistance

Eastern Cape

COGTA through National Treasury

R29 million

Contingency Reserve

2016/17

  • Provision and transportation of livestock feed for agriculture sector
 

Department of Agriculture, Forestry and Fisheries (DAFF)

R37.4 million

Reprioritization from the Comprehensive Agricultural Support Programme (CASP)

2015/16

  • Provision and transportation of livestock feed
 

COGTA through National Treasury

R8.6 million

Contingency Reserve

2016/17

  • Water tankering and storage for human consumption
 

Department of Water and Sanitation (DWS)

R4.9 million

Reprioritisation from existing programmes

2015/16

  • Water tankering and storage for human consumption

Total Amount - EC : R79.9 million

Western Cape

COGTA through National Treasury

R12 million

Contingency Reserve

2016/17

  • Provision and transportation of livestock feed for agriculture sector
 

Department of Agriculture, Forestry and Fisheries

R6 million

Reprioritization from the Comprehensive Agricultural Support Programme (CASP)

2015/16

  • Provision and transportation of livestock feed
  • Inputs costs to small grain
 

COGTA through National Treasury

R8.6 million

Contingency Reserve

2016/17

  • Water tankering and storage for human consumption for the water sector
 

Department of Water and Sanitation

R8 million

Reprioritisation from existing programmes

2015/16

  • Drilling of boreholes for human consumption

Total Amount – WC : R34.6 million

(b) The following provinces reprioritised within their internal resources to address the impacts of drought. The details below on Table 2 are as per the reports received from the sector departments in the provinces:

Table 2: Funding facilitated by different provincial sector departments to address the drought situation.

Province that made contribution

Amount contributed and source of funding

Financial year

Type of Assistance

EASTERN CAPE PROVINCE

Eastern Cape

R95 million

Equitable share

2016/17

Livestock feeds, refurbishment and drilling of boreholes (Agriculture Sector)

 

R5.9 million

Equitable share

2015/16

  • Provision and transportation of livestock feed
  • Inputs costs to small grain (Agriculture Sector)
 

About R200 million

Equitable share

2015/16

  • Water infrastructure for human consumption (Water Sector)

Total Amount – EC : R 300.9 million

WESTERN CAPE PROVINCE

Western Cape

R40.9 million

 

CASP, Equitable share & AgriSA donations

2016/17

  • Provision and transportation of livestock feed
  • Inputs costs to small grain
 

R5.1 million Equitable share

2015/16

  • Provision and transportation of livestock feed
  • Inputs costs to small grain

Total Amount – WC : R46 million

30 October 2017 - NW3113

Profile picture: Walters, Mr TC

Walters, Mr TC to ask the Minister of Rural Development and Land Reform

(1)With reference to portion 0 which is the remaining extent of the farm Haakdoornkuil, KR 323, in Mookgophong in Limpopo and portion 9 of the farm Klipfontein KR 322 in Mookgophong, Waterberg District, in Limpopo, (a) who were the successful claimants of the Haakdoornkuil farm, (b)(i) was a certain person (name and details furnished) one of the beneficiaries and (ii) what communications took place between the specified person and his department with regard to the specified claim, (c) what commercial venture is currently happening on the specified land and (d) who are the beneficiaries who own shares in it; (2) whether all beneficiaries are benefiting from the specified commercial venture; if not, why not; (3) whether the property was subsequently sold or leased; if not, who is benefiting or benefited from such a sale or lease; (4) (a) what amount of funding did his department spend on the property and (b) under which programme?

Reply:

1. According to our database, we do not have any records of land claim lodged on the farm Haakdoornkuil 323 KR and the Office of the Regional Land Claims Commissioner: Limpopo received a land claim lodged by Kekana Matsobane Petrus on behalf of Motekwana Community on the farm Klipfontein 322 KR.

The said land claim was received on the 20th of November 2014, such land claims are not being processed due to the outcome of the Constitutional Court ordered that the claims that were lodged between 1 July 2014 and 27 July 2016 are validly lodged, but it interdicted the Commission from processing those claims until the Commission has finalised the claims lodged by 31 December 1998 or until Parliament passes a new law providing for the re-opening of lodgement of land claims. Parliament was given until 27 July 2018 to pass such a law.

(b)(i)(ii) Falls away;

(c) Falls away;

(d) Falls away.

 

2. Falls away.

3. Falls away.

4. (a)(b) Falls away.

30 October 2017 - NW3131

Profile picture: Groenewald, Mr HB

Groenewald, Mr HB to ask the Minister of Police

(1) (a) What number of vehicles from the Boksburg North Police Station are currently at the mechanical workshop, (b) how long has each specified vehicle been at the mechanical workshop and (c) what are the reasons for each vehicle being at the mechanical workshop; (2) what number of operational vehicles does the specified police station currently have?

Reply:

(1)

a. Number of vehicles at the mechanical workshop.

Six.

b. Time frame (from which date).

1. BSW236B: 2017-08-14.

2. BRW840B: 2017-08-15.

3. BSY701B: 2017-08-28.

4. BTG221B: 2017-09-06.

5. BSN321B: 2017-10-05.

6. BTC806B: 2017-10-05.

c. Mechanical problem.

1. Brake system, steering, suspension overhaul and wheel alignment.

2. Accident damages.

3. Engine, minor repairs.

4. For inspection, cooling system and cylinder head.

5. Repairs.

6. Repairs.

(2) 36.

30 October 2017 - NW3123

Profile picture: Figlan, Mr AM

Figlan, Mr AM to ask the Minister of Police

(1) (a) How many suspects have escaped from the Tembisa South police station (i) in the (aa) 2015-16 and (bb) 2016-17 financial years and (ii) from 1 April 2017 up to the latest specified date for which information is available, (b) on what date did each person escape and (c) which police officers were on duty at the time of each escape; (2) whether a case of escape was registered in each case; if not, (a) why not and (b) what (i) is the name of the officer that failed to register such a case and (ii) action was taken against each officer in each case?

Reply:

(1)(a)(i)(aa)(bb)(ii)(b)(c)

(i)(aa) 2015/2016

(i)(bb) 2016/2017

(ii)

1 April 2017 to date

(b)

Date of escape

(c)

Officers on duty

0

3

0

2016-11-18

2017-03-03

Capt Novela

Sgt Molefe

(2) Yes, Tembisa South, CAS 184/11/2017 and CAS 78/03/2016.

(2)(b)(i) and (ii) Not applicable.

30 October 2017 - NW3097

Profile picture: Cassim, Mr Y

Cassim, Mr Y to ask the Minister of Police

Has his department or any entity reporting to him offered any reward for information that will lead to the arrest of suspects involved in (a) torture and (b) murder cases (i) in each of the past three financial years and (ii) since 1 April 2017; if so, what are the relevant details?

Reply:

We are sourcing information from our archives, the information that is required is not readily available, as each case must be verified, before the information can be submitted. 

30 October 2017 - NW2802

Profile picture: McLoughlin, Mr AR

McLoughlin, Mr AR to ask the Minister of Public Enterprises

Whether progress had been made with the introduction of the maintenance, repari and overhaul facility for South Africa, as set out in the Strategy Statement of the 2016-17 Annual Report of SA Express; if not, what are the reasons for the failure; if so, what are the full relevant details?

Reply:

The formation of a Maintenance Repair and Overhaul facility to service the aircraft maintenance needs of the state is currently being considered through the development of an Optimal Corporate Structure for the realignment of the State Owned Airlines.


Mogokare Richard Seleke Lynne Brown, MP

Director-General Minister of Public Enterprises

Date: Date:

30 October 2017 - NW3112

Profile picture: Walters, Mr TC

Walters, Mr TC to ask the Minister of Rural Development and Land Reform

With reference to Portion 0 of the Farm Haakdoornkuil, KR 323, in Mookgophong in the Waterberg District in Limpopo, (a) on what basis was (i) a certain person (name furnished) and (ii) the specified person’s group of claimants unsuccessful in their original claim on the specified portion of land, (b) what recourse is available to the claimants to pursue the original claim and (c) what steps will his department take to rectify the ownership of the specified portion of land after the specified recourse has been successful?

Reply:

(a)(i)(ii) According to our database, we do not have any records of land claim lodged on the farm Haakdoornkuil 323 KR.

(b) falls away

(c ) falls away

30 October 2017 - NW3255

Profile picture: Mileham, Mr K

Mileham, Mr K to ask the Minister of Cooperative Governance and Traditional Affairs

(1)      Whether his department keeps repository of data on municipal performance, capacity, viability and sustainability; if not, why not; if so, (a) who maintains this specified repository and (b)(i) how and (ii) how often is the repository updated; (2) Whether the information is accessible to the general public through an open application programming interface; if not, why not; if so, how is access granted

Reply:

1. Yes, the department keeps repositories of data on municipal performance, capacity, viability and sustainability

(a) Various units in the department contribute to the repositories, based on their specific areas of responsibility, e.g. financial information, public participation, MIG spending, service delivery protests, and the appointment of section 56 employees.

(b) (i) information is consolidated into excel spreadsheets;

    (ii) annually as it becomes available.

2. No, the information is not accessible to the general public through an open application programming interface;

(a) The department is still working on designs for such an open interface and is collaborating with National Treasury, DPME and StatsSA in the reporting reforms project to reduce the reporting burden of municipalities in this regard.

30 October 2017 - NW3129

Profile picture: Groenewald, Mr HB

Groenewald, Mr HB to ask the Minister of Police

(1) (a) How many suspects have escaped from the Germiston police station (i) in the (aa) 2015-16 and (bb) 2016-17 financial years and (ii) from 1 April 2017 up to the latest specified date for which information is available, (b) on what date did each person escape and (c) which police officers were on duty at the time of each escape; (2) whether a case of escape was registered in each case; if not, (a) why not and (b) what (i) is the name of the officer that failed to register such a case and (ii) action was taken against each officer in each case?

Reply:

(1)(a)(i)(aa)(bb)(ii)(b)(c)

(i)(aa) 2015/2016

(i)(bb) 2016/2017

(ii)

1 April 2017 to date

(b)

Date of escape

(c)

Officers on duty

3

2

0

2016-09-24

2016-12-12

Lt Col Thapeli

Lt Col Qangase

(2) Yes, Germiston, CAS 243/06/2015, CAS 238/06/2015, CAS 430/08/2015, CAS 709/09/2016 and CAS 348/12/2016.

(2)(a)(b)(i)(ii) Not applicable.

30 October 2017 - NW2211

Profile picture: Kruger, Mr HC

Kruger, Mr HC to ask the Minister of Cooperative Governance and Traditional Affairs

(a) On what date was the last inspection for possible structural damages of the Windsor Water Tower situated in the Ekurhuleni Metropolitan Municipality, (b) who conducted the inspection, (c) what were the findings, (d) by what date will repairs to the tower take place and (e) what is the projected cost of repairs?

Reply:

The following response was provided by the Gauteng Department of Cooperative Governance Human Settlements and Traditional Affairs:

(a) The last inspection was conducted in the previous financial year.

(b) The inspection was conducted by Rod Rankine.

(c) The above mentioned tower is in Sunnyridge and gives supply to all higher laying area in the vicinity. During the assessment of structural defects of Primrose reservoir to allow for repairs, the structural Engineer also gave comments after inspections. The structural engineer confirmed that the tower still has remaining useful life and that there must be structural repairs to improve conditions.

(d) Ekurhuleni Metro Municipality through the quantum leap project intended to increase the storage capacity of most of water reservoirs. It planned that another water tower be built adjacent to the existing tower with greater volumes and retention periods. Consultants have been appointed for the design of critical reservoirs including Sunnyridge and upon completion the Metro will go on tender for the appointment of contractor.

(e) It is projected that the cost for repairs could be 45% of building new water tower, but the Municipality will still have challenges of capacity.

 

30 October 2017 - NW2977

Profile picture: Hadebe, Mr TZ

Hadebe, Mr TZ to ask the Minister of Environmental Affairs

(1)With regard to the court’s dismissal of the application of a certain family (name furnished) to compel a certain bank (name furnished) not to close its  accounts by the end of September, what steps does she intend to put in place to ensure that the rehabilitation funds of mines owned by and/or linked to the specified family do not leave the country; (2) whether she intends to approach the courts to ensure that the rehabilitation funds are frozen to deal with environmental degradation caused by mines owned by and/or linked to the specified family; if not, why not; if so, what are the relevant details?

Reply:

(1) With regard to the question 1 which asks what steps the Minister will take to ensure that funds identified for the rehabilitation of mines do not leave the country, the Minister draws attention to the following legislative requirements:

The National Environmental Management Act, 1998 (Act No. 107 of 1998) requires the following in respect of financial provision:

Section 24P“(5)

(a) The requirement to maintain and retain the financial provision contemplated in this section remains in force notwithstanding the issuing of a closure certificate by the Minister responsible for mineral resources in terms of the Mineral and Petroleum Resources Development Act, 2002 to the holder or owner concerned. “

Further, the competency for these matters has been identified as the Minister of Mineral Resources in the following circumstances:

Section 24C(2A):

“The Minister responsible for mineral resources must be identified as the competent authority in terms of subsection (1) where the listed or specified activity is directly related to-

(a) prospecting or exploration of a mineral or petroleum resource; or

(b) extraction and primary processing of a mineral or petroleum resource.”

Therefore, noting the provisions of the Act, it is the responsibility of the Minister of Mineral Resources to ensure that the legal requirements are implemented.

(2) With respect to question 2 regarding the intention of the Minister to approach the courts to ensure rehabilitation funds remain to deal with remediating degradation caused by mining, please note that section 24C(2A) of the Act, identifies the Minister of Mineral Resources has having the competency with respect to mining, including the provisions surrounding financial provision for rehabilitation of impacts associated with prospecting, exploration, mining and production.

---ooOoo---

30 October 2017 - NW3135

Profile picture: Hoosen, Mr MH

Hoosen, Mr MH to ask the Minister of Police

(1) (a) What number of vehicles from the Norkem Park Police Station are currently at the mechanical workshop, (b) how long has each specified vehicle been at the mechanical workshop and (c) what are the reasons for each vehicle being at the mechanical workshop; (2) what number of operational vehicles does the specified police station currently have?

Reply:

(1)

a. Number of vehicles at the mechanical workshop.

Eight.

b. Time frame (from which date).

1. BRV123B: 2017-10-03.

2. BRV756B: 2017-10-04.

3. BTG809B: 2017-09-21.

4. BTD146B: 2017-08-04.

5. BTC185B: 2017-10-16.

6. BTN358B: 2017-09-07.

7. BSY263B: 2017-10-03.

8. BSZ562B: 2017-10-12.

c. Mechanical problem.

1. Starter.

2. Breaks/fuel.

3. Accident.

4. Accident.

5. Timing belt.

6. Accident.

7. Starter and ignition.

8. Radiator.

(2) 16.

30 October 2017 - NW3132

Profile picture: Hadebe, Mr TZ

Hadebe, Mr TZ to ask the Minister of Police

(1) (a) What number of vehicles from the Sebenza Police Station are currently at the mechanical workshop, (b) how long has each specified vehicle been at the mechanical workshop and (c) what are the reasons for each vehicle being at the mechanical workshop; (2) what number of operational vehicles does the specified police station currently have?

Reply:

(1)

a. Number of vehicles at the mechanical workshop.

Four.

b. Time frame (from which date).

1. BBTC571B: 2017-09-29.

2. BBSR986B: 2017-10-10.

3. BBTW005B: 2017-09-21.

4. BBSV520B: 2017-08-31.

c. Mechanical problem.

1. Starter motor.

2. Engine oil leak.

3. Panel beating.

4. Starter motor.

(2) 10.

30 October 2017 - NW3134

Profile picture: Hadebe, Mr TZ

Hadebe, Mr TZ to ask the Minister of Police

(1) (a) What number of vehicles from the Bedfordview Police Station are currently at the mechanical workshop, (b) how long has each specified vehicle been at the mechanical workshop and (c) what are the reasons for each vehicle being at the mechanical workshop; (2) what number of operational vehicles does the specified police station currently have?

Reply:

(1)

a. Number of vehicles at the mechanical workshop.

Five.

b. Time frame (from which date).

1. BTL287B: 2017-09-04.

2. BSS598B: 2017-09-20.

3. BTD305B: 2017-09-13.

4. BRX515B: 2017-09-13.

5. BTB715B: 2017-10-12.

c. Mechanical problem.

1. Water leak.

2. Air conditioning pump.

3. Electrical problems.

4. Petrol pump.

5. Overheating.

(2) Eight.

30 October 2017 - NW3094

Profile picture: Brauteseth, Mr TJ

Brauteseth, Mr TJ to ask the Minister of Police

What is the total number of cases of (a) murder, (b) assault, (c) rape (d) robbery, (e) armed robbery and (f) attempts to commit the aforementioned crimes that were reported in each province in (i) each of the past three financial years and (ii) since 1 April 2017?

Reply:

(a)(b)(c)(d)(e)(f)(i)(ii)

The national crime figures are attached. However, the figures per province, are available on the South African Police Service (SAPS) website.

The crime figures for 2016/2017 are also on the South African Police service (SAPS)website

30 October 2017 - NW2213

Profile picture: Lotriet, Prof  A

Lotriet, Prof A to ask the Minister of Cooperative Governance and Traditional Affairs

Whether, with reference to his reply to question 1438 on 5 July 2016, the Ekurhuleni Metropolitan Municipality has provided the information; if so, what are the relevant details?

Reply:

The following response was provided by the Gauteng Department of Cooperative Governance Human Settlements and Traditional Affairs:

  1. Lease agreement is in place, there has been billing since January 2017.
  2. Current Rental: R11 700.00 pm (10% escalation).
  3. Lease period: 9 years and 11 months.
  4. SASSA took occupation of the building from the 9th May 2017.
  5. SASSA is currently painting the building internally, and they are in the process of branding the building outside.

 

30 October 2017 - NW3124

Profile picture: Figlan, Mr AM

Figlan, Mr AM to ask the Minister of Police

(1) (a) How many suspects have escaped from the Edenvale police station (i) in the (aa) 2015-16 and (bb) 2016-17 financial years and (ii) from 1 April 2017 up to the latest specified date for which information is available, (b) on what date did each person escape and (c) which police officers were on duty at the time of each escape; (2) whether a case of escape was registered in each case; if not, (a) why not and (b) what (i) is the name of the officer that failed to register such a case and (ii) action was taken against each officer in each case?

Reply:

(1)(a)(i)(aa)(bb)(ii)(b)(c)

(i)(aa) 2015/2016

(i)(bb) 2016/2017

(ii)

1 April 2017 to date

(b)

Date of escape

(c)

Officers on duty

0

0

0

Not applicable

Not applicable

(2)(a)(b)(i)(ii) Not applicable.

30 October 2017 - NW3121

Profile picture: Esau, Mr S

Esau, Mr S to ask the Minister of Police

(1) (a) How many suspects have escaped from the Boksburg police station (i) in the (aa) 2015-16 and (bb) 2016-17 financial years and (ii) from 1 April 2017 up to the latest specified date for which information is available, (b) on what date did each person escape and (c) which police officers were on duty at the time of each escape; (2) whether a case of escape was registered in each case; if not, (a) why not and (b) what (i) is the name of the officer that failed to register such a case and (ii) action was taken against each officer in each case?

Reply:

(1)(a)(i)(aa)(bb)(ii)(b)(c)

(i)(aa) 2015/2016

(i)(bb) 2016/2017

(ii)

1 April 2017 to date

(b)

Date of escape

(c)

Officers on duty

0

7

1

19 May 2016 (6)

16 October 2016 (1)

8 May 2017 (1)

Warrant Officer PM Mabuya

Warrant Officer TJ Mdluli

Warrant Officer TZ Nyembe

(2) Yes, Boksburg, CAS 276 to 281/05/2016, CAS 185/10/2016 and CAS 85/05/2017.

(2)(a) Not applicable.

(2)(b)(i)(ii) Not applicable.

30 October 2017 - NW3095

Profile picture: Cassim, Mr Y

Cassim, Mr Y to ask the Minister of Police

(1) What are the relevant details of the shortage of (a) DNA primer kits, (b) sample holders, (c) chemicals and (d) other consumables necessary for DNA analysis at each forensic science laboratory administered by his department; (2) what number of Genetic Sample Processing System (GSPS) machines does his department own; (3) whether each GSPS machine is being utilised at full capacity; if not, why not; if so, what number of samples on average are processed in a week?

Reply:

(1)(a)(b)(c)(d)

a

There is no shortage of DNA reagent kits, for analysing DNA samples. However, there is currently a shortage of DNA buccal sample collection kits, which are used to collect buccal samples from persons arrested and charged for schedule eight offences, in accordance with the DNA Act.

b

There are no shortages of sample holders.

c

There are no shortages of chemicals.

d

There are no shortages of other consumables, necessary for DNA analysis.

(2) and (3) The Forensic Science Laboratory had one functional Genetic Sample Processing System (GSPS), which was installed in 2006, for DNA analysis in the Biology Section, Arcadia. The GSPS reached the end of its life cycle, several years ago and is no longer utilised. The GSPS equipment was decommissioned, due to old technology and unavailability of maintenance/service by service providers. The GSPS has been replaced with semi-automated DNA analysis equipment, to analyse crime scene and buccal samples. The semi-automated equipment is proving to be very effective and is significantly more cost effective than the GSPS.

30 October 2017 - NW3101

Profile picture: Steenkamp, Ms J

Steenkamp, Ms J to ask the Minister of Police

How many (a) analyses of soil and related materials, (b) analyses of ivory samples, (c) print and impressions comparisons, (d) analysis of explosive and propellant residues and (e) specialised forensic photograph sets were finalised by the Forensic Service Division of the SA Police Service (i) in each of the past five financial years and (ii) since 1 April 2017?

Reply:

(a)(b)(c)(d)(e)(i)(ii)

 

(i)

2013/2014

(i)

2014/2015

(i)

2015/2016

(i)

2016/2017

(ii)

Since 1 April 2017

(a) Analyses of soil and related materials.

33

87

57

47

19

(b) Analyses of ivory samples.

24

14

9

20

13

(c) Print and impressions comparisons.

12

6

5

15

4

(d) Analysis of explosive and propellant residues.

100

205

286

318

290

(e) Specialised forensic photograph sets.

122

168

157

130

74

30 October 2017 - NW2991

Profile picture: Mileham, Mr K

Mileham, Mr K to ask the Minister of Cooperative Governance and Traditional Affairs

(1)Whether any former councillors have not yet received the once-off gratuity promised to them since his reply to question 2601 on 5 December 2016; if so, (a) how many councillors are still owed this payment, (b) what are the reasons for the delayed payments, (c) which municipalities are affected and (d) by what date will the specified councillors receive their gratuities; (2) whether each councillor who received this gratuity received a statement reflecting how the specified gratuities were calculated; if not, why not; if so, what are the details contained on those statements?

Reply:

1(a)(b)(c)(d)2

There are 12 councillors which are still not paid by the Department, the reasons varies to tax related challenges, inactive tax numbers, incorrect tax numbers and deceased former councillors. Therefore, the councillors and the families of the deceased councillors need to visit SARS offices to solve these tax problems. The Municipalities which are affected are, Moretele, Cederberg, Mahikeng, Theewaterskloof, Ekurhuleni, Westrand, Mamusa, Randfontein, Amahlathi, Ngwathe, Modimolle, City of Cape Town and Greater Tubatse.

The councillors will be paid immediately upon resolving their tax challenges with SARS and submit a proof thereof.

Majority of the councillors received the gratuity outcome letters indicating how the gratuity amount was calculated, the gross amount due, the tax amount deducted and the net amount paid to the councillor.

 

30 October 2017 - NW3099

Profile picture: Dreyer, Ms AM

Dreyer, Ms AM to ask the Minister of Police

What number of (a) firearm and tool mark identification, (b) identification of firearms and ammunition, (c) restoration of defaced and removed numbers on metal, (d) terminal ballistic reports, (e) vehicle accident scene reconstructions, (f) wheel and tyre examinations, (g) preliminary body fluid tests and (h) blood spatter pattern analyses were finalised by the Forensic Service Division of the SA Police Service in (i) each of the past five financial years and (ii) since 1 April 2017?

Reply:

(a)(b)(c)(d)(e)(f)(g)(h)(i)(ii)

 

2013/ 2014

2014/ 2015

2015/ 2016

2016/ 2017

1 April 2017 to date

a) Firearm and tool mark identification.

13 917

13 995

17 007

19 662

10 014

b) Identification of firearms and ammunition.

11 318

11 197

10 230

1 174

6 552

c) Restoration of defaced and removed numbers on metal.

5 958

5 547

5 384

5 563

2 774

d) Terminal ballistic reports.

445

485

448

405

106

e) Vehicle accident scene reconstructions.

445

485

448

405

77

f) Wheel and tyre examinations.

52

50

63

61

29

g) Preliminary body fluid tests.

26 684

25 239

25 007

32 527

15 073

h) Blood spatter pattern analyses.

The Forensic Science Laboratory Administration System, does not have a specific function for capturing blood spatter pattern analysis separately. This analysis is done by the Ballistics and Victim Identification Centre Section, when attending crime scenes.

30 October 2017 - NW2803

Profile picture: McLoughlin, Mr AR

McLoughlin, Mr AR to ask the Minister of Public Enterprises

(1)What are the (a) relevant details of all aircraft forming part of the SA Express fleet as at 31 August 2017 and (b) which of the aircraft are serviceable; (2) Were any of the SA Express’ aircraft out of service in the 2016-17 financial year; if so, what are the reasons for the unserviceability in each case; (3) (a) On how many occasions did the SA Express charter aircraft from other airlines honour its commitments from 1 April 2015 to 31 August 2017, (b) what are the details of (i) the type of aircraft chartered and (ii) the airline from which the aircraft was chartered and (c)(i) for what period and (ii) at what cost was each aircraft chartered

Reply:

(1)

SA Express Aircraft

Reg. No

Aircraft Type

Status

ZS - NMI

CRJ200

In Service

ZS - NML

CRJ200

In Service

ZS – NMM

CRJ200

Out of Service

ZS - NMN

CRJ200

In Service

ZS – NMC

CRJ200

Out of Service

ZS - NMD

CRJ200

In Service

ZS - NME

CRJ200

In Service

ZS - NMF

CRJ200

In Service

ZS – NBF

CRJ700

Out of Service

ZS - NBG

CRJ700

In Service

ZS- NMO

Q400

Out of Service

ZS – NMS

Q400

Out of Service

ZS - YBP

Q400

In Service

ZS - YBR

Q400

In Service

ZS - YBT

Q400

In Service

ZS – YBU

Q400

Out of Service

ZS - YBW

Q400

In Service

ZS - YBX

Q400

In Service

ZS – YBY

Q400

Out of Service

ZS - YBZ

Q400

In Service

(2)The following aircraft were out of service:

Aircraft

Aircraft Type

Reason for Out of Service

NMO

Q400

NLG, Engines, Propellers, Engine mounts and robbed spares

NMS

Q400

NLG, Engines, Propellers, Engine mounts and robbed spares

YBU

Q400

NLG, Engines, Propellers, Engine mounts and robbed spares

YBY

Q400

NLG, Propellers, Engine mounts and robbed spares

NMC

CRJ200

Engines, Spares

NMM

CRJ200

Aircraft is robbed spares beyond economic repair.

(3) See below the link for  Annexure A.

 

http://pmg-assets.s3-website-eu-west-1.amazonaws.com/RNW2803Annexure-171030.pdf

 

Mogokare Richard Seleke Lynne Brown, MP

Director-General Minister of Public Enterprises

Date: Date:

 

30 October 2017 - NW3090

Profile picture: Bara, Mr M R

Bara, Mr M R to ask the Minister of Police

(1) (a) How many forensic science laboratories are currently (i) owned and/or (ii) administered by the SA Police Service (SAPS) in each province and (b) where is each laboratory located; (2) (a) how many forensic science laboratories does his department plan to set up in each province in the (i) 2017-18, (ii) 2018-19 and (iii) 2019-20 financial years, and (b) (i) where will each laboratory be set up and (ii) what are the projected costs in each case?

Reply:

(1)(i)(ii)(b)

FORENSIC SCIENCE LABORATORY: PRETORIA

Services provided

Location

Owned/Leased

Ballistics

Silverton

Owned

Scientific Analysis

Silverton

Owned

Chemistry

Silverton

Owned

Questioned Documents

Pretoria CBD

Leased

Victim Identification Centre

Tulbagh Park(Hatfield)

Leased

Biology

Acardia

Owned

FORENSIC SCIENCE LABORATORY: WESTERN CAPE

Forensic Science Laboratory

Plattekloof

Owned

FORENSIC SCIENCE LABORATORY: EASTERN CAPE

Forensic Science Laboratory

Port Elizabeth

Owned

FORENSIC SCIENCE LABORATORY: KWAZULU-NATAL

Ballistics

Amanzimtoti (Kingscrest building)

Leased

Biology and Chemistry

Amanzimtoti (Nedbank building)

Leased

Questioned Documents

Durban South

Leased

Scientific Analysis

Durban Central

Leased

(2)(a)(i)(ii)(iii)(b)(i)(ii)

 

2017/2018

2018/2019

2019/2020

Where

None

Mpumalanga (Chemistry & Ballistics)

None

Cost

None

Renovations: R11 468 616,00

Access control systems: R20 005 178,00

Recruitment and training: R500 000,00

Procurement of Laboratory and office furniture: R11 540 420,00

Procurement of Laboratory equipment:

R16 000 000,00

Procurement of Information and Communication Technology (ICT) equipment: R21 159 066,00

Official launch: R300 000,00

Total: R80 973 280,00

The cost of planning the Forensic Services facility in Pinetown, to support the National Forensic Strategy, is unknown at this stage.

None

30 October 2017 - NW3128

Profile picture: Gqada, Ms T

Gqada, Ms T to ask the Minister of Police

(1) (a) How many suspects have escaped from the Bedfordview police station (i) in the (aa) 2015-16 and (bb) 2016-17 financial years and (ii) from 1 April 2017 up to the latest specified date for which information is available, (b) on what date did each person escape and (c) which police officers were on duty at the time of each escape; (2) whether a case of escape was registered in each case; if not, (a) why not and (b) what (i) is the name of the officer that failed to register such a case and (ii) action was taken against each officer in each case?

Reply:

(1)(a)(i)(aa)(bb)(ii)(b)(c)

(i)(aa) 2015/2016

(i)(bb) 2016/2017

(ii)

1 April 2017 to date

(b)

Date of escape

(c)

Officers on duty

0

1

0

2016-12-07

Capt SJ Nkosi

(2) Yes, Bedfordview, CAS 78/12/2016.

(2)(a)(b)(i)(ii) Not applicable.

30 October 2017 - NW3192

Profile picture: Khawula, Ms MS

Khawula, Ms MS to ask the Minister of Water and Sanitation

With reference to her reply to question 1987 on 9 October 2017, (a) in which municipality and (b) ward are most of the leaks located in (i) Gauteng and (ii) KwaZulu-Natal provinces?

Reply:

(a) Municipalities with most leaks are located in Gauteng and KwaZulu-Natal. The Department does not assess location of water leaks by wards system. Instead, Municipalities provide information on water leaks as per distribution/ reticulation systems in accordance with either the number of households, total reservoir supply area and/or systems operating pressure regime.

(b)(i) In Gauteng Province, the municipality with the most leaks is the Johannesburg Metropolitan Municipality.

(b)(ii) In KwaZulu-Natal Province, the municipality with most leaks is the EThekwini Metropolitan Municipality.

---00O00---

30 October 2017 - NW1576

Profile picture: Motau, Mr SC

Motau, Mr SC to ask the Minister of Police

Whether he has started the process for the appointment of a permanent Head of the Directorate for Priority Crimes Investigation (DPCI) unit; if not, (a) why not and (b) by what date does he envisage the process to be started; if so, (i) what are the relevant details and (ii) by what date does he expect to appoint a new Head of the DPCI?

Reply:

Yes

a) Not applicable

b) Mid November 2017

Section 17CA (1 of SAPS Act) provides as thus:

(i) Minister of Police, with concurrence of cabinet, appoints National Head of DPCI for a non-renewable fixed term of not shorter than 7 years but not exceeding 10 years.

(ii) End of January 2018

30 October 2017 - NW3102

Profile picture: Breytenbach, Adv G

Breytenbach, Adv G to ask the Minister of Police

With reference to the escape of a certain prisoner (name and details furnished) from police custody due to alleged negligence by the SA Police Service officers on or around March 2010, what steps have been taken to ensure that the specified person is rearrested and prosecuted for the crimes committed in respect of CAS 17/03/2010 opened at Dorset in Vaalwater, Waterberg in Limpopo?

Reply:

The details of the accused were circulated, as wanted, on 4 October 2010 and the circulation number is 2010/W/41973. Members of the Directorate for Priority Crime Investigation (DPCI) and informers were tasked to trace the suspect.

30 October 2017 - NW3126

Profile picture: Gqada, Ms T

Gqada, Ms T to ask the Minister of Police

(1) (a) How many suspects have escaped from the Tembisa police station (i) in the (aa) 2015-16 and (bb) 2016-17 financial years and (ii) from 1 April 2017 up to the latest specified date for which information is available, (b) on what date did each person escape and (c) which police officers were on duty at the time of each escape; (2) whether a case of escape was registered in each case; if not, (a) why not and (b) what (i) is the name of the officer that failed to register such a case and (ii) action was taken against each officer in each case?

Reply:

(1)(a)(i)(aa)(bb)(ii)(b)(c)

(i)(aa) 2015/2016

(i)(bb) 2016/2017

(ii)

1 April 2017 to date

(b)

Date of escape

(c)

Officers on duty

2

1

0

2015-04-30

2015-05-11

2016-10-12

Const Chauke

WO Kanyane

Capt Lamola (deceased)

(2) Yes, Tembisa, CAS 750/04/2015, CAS 272/08/2015 and CAS 237/10/2016.

(2)(a)(b)(i)(ii) Not applicable.

30 October 2017 - NW3125

Profile picture: Figlan, Mr AM

Figlan, Mr AM to ask the Minister of Police

(1) (a) How many suspects have escaped from the Primrose police station (i) in the (aa) 2015-16 and (bb) 2016-17 financial years and (ii) from 1 April 2017 up to the latest specified date for which information is available, (b) on what date did each person escape and (c) which police officers were on duty at the time of each escape; (2) whether a case of escape was registered in each case; if not, (a) why not and (b) what (i) is the name of the officer that failed to register such a case and (ii) action was taken against each officer in each case?

Reply:

(1)(a)(i)(aa)(bb)(ii)(b)(c)

(i)(aa) 2015/2016

(i)(bb) 2016/2017

(ii)

1 April 2017 to date

(b)

Date of escape

(c)

Officers on duty

3

0

1

2015-08-06

2017-05-25

Capt Sukula

Capt Fakude

(2) Yes, Primrose, CAS 309/05/2017, 54/08/2015, 55/08/2015 and 56/08/2015.

(2)(a)(b)(i)(ii) Not applicable.

30 October 2017 - NW3216

Profile picture: Lees, Mr RA

Lees, Mr RA to ask the Minister of Finance

Whether the SA Airways (SAA) has a contract with the publisher of a certain newspaper (New Age Newspapers) for the supply of newspapers; if so, (a) what amount does the specified contract cost SAA each month, (b) on what date (i) was the contract signed and (ii) does the contract expire and (c) what are the details of price escalation clauses included in the contract?

Reply:

SAA does not have a direct contract with New Age Newspaper for the supply of newspapers. However, SAA has a month-to-month contract with Press Support, which provides for the supply of a variety of readership material including the New Age newspaper to our passengers.

(a) The contract with Press Support in respect of the New Age newspaper costs R165 690 per month excluding VAT. The New Age newspaper supply costs covers Johannesburg, Durban and Cape Town stations.

(b)(i) The contract with Press Support was signed in April 2009.

(b)(ii) This is a month-to-month contract and SAA may terminate the agreement by giving a one months’ notice with no penalties.

(c) The contract provides for general inflationary increase in March/April of every year.

30 October 2017 - NW2231

Profile picture: Figg, Mr MJ

Figg, Mr MJ to ask the Minister of Public Works

Whether there were any renovations conducted in any Ministerial residence in the 2015-16 financial year; if not, when last were any renovations of Ministerial residences conducted; if so, (a) what was the (i) nature and (ii) total cost of such renovations and (b) which Ministerial house was renovated?

Reply:

Item No

Project Name

Nature of renovations

2015/16

2016/17

1

Bryntirion No. 19

WCS 053319

BUILDING WORKS:

Replace portion of corrugated roof sheets with new, Replace burnt roof timber purlins with new, Repaint entire roof & walls, Replace study ceiling with new, New wall tiling, vinyl flooring, vanities, sanitary fittings to bathrooms, New ceiling in passage, Replace partitioning in study with new, Replace front door with new, Replace study door, New cabinetry to study, Replace broken glazing, Sand and seal existing timber flooring, Termite treatment to all floors and issue certificate, Install ironmongery where missing, New plumbing to bathrooms and Service plumbing, Investigate and repair all damaged electrical installation, Rewire the whole house, Allow for the installation of fire extinguishers, Replace patio paving and edging, New aprons around the house

Scope for the outbuilding:

Repainting of interior & exterior, Replacement of gutters and downpipes, Replacement of damaged ceilings, Repaint of roof ( Including replacement of sheets allowance)

Replacement of two Doors. Allow glazing to broken panes, Replacement of skirting’s.

New Ceramic tiles to toilet, Repainting of Windows and doors

ELECTRICAL WORKS:

Total rewire of the entire house – which will result in issuing a certificate of compliance (C.O.C) as the primary function. Servicing of existing generator

R 158 301.19

R 2 107 035.90

2

331 Olivier, Brooklyn

WCS 053347

BUILDING WORKS:

Fix cracks on walls, place loose paving, Remove all pergolas and replace with new, Replace existing built in gas braai unit, Re-slope existing carport roof structure, Paint existing steel balustrades, Replace existing asbestos components, Realignment, replacement of existing slate roof tiles, Paint existing timber eaves, fascia, badge boards, Replace gutters and downpipes with new where applicable, Replace rotten roof timber with new where applicable, Waterproof existing concrete flat roof, High pressure wash face bric, surface, New walk-way canopy/overhang, New coat/hat hooks and built in bench, Paints to walls, ceilings, New painted ceilings where applicable, Replace existing counter tops with new where applicable, Re-varnish existing clad existing timber wall panels, Re-putty and repaint existing painted steel window frames where applicable, Replace internal flooring with new where applicable, Clean existing wall to wall carpets, Clean existing floor tiles, Paint garage floor, Service sanitary fittings, Replace walls tiles where applicable, Install new vanity where applicable, Replace existing coloured whb with new white, Replace existing coloured bath with new white, Replace existing coloured wc with new white, Replace shower with new where applicable, Replace missing/damaged ironmongery

ELECTRICAL AND MECHANICAL WORKS:

Replacement of damaged light fitting, Replacement of faulty light fittings and lamps

Repair of external light fittings, Repair of faulty electrical connections, Replacement of damaged light switches, Replacement of faulty socket outlets (plugs), Installation of wiring where required, Replacement of all old circuit breaker with new, Upgrade of electrical supply from dual phase to three phase. Testing of the existing generator as well as the changeover system, To that the entire electrical installation complies with the latest regulations, Issuing of certificate of compliance. Installation of new air conditioning, Ensured that air-conditioning system complied with latest regulation.

 

R 1 835 818.72

3

375 Lawley

WCS 053574

BUILDING WORKS:

Replace damaged ceiling, Replace damaged floor and wall tiles, Replace gutters and downpipes, Uplift and relay paving, Fix cracks on walls, Repair leaks to roof and balconies, Waterproof to walls and floors, Repair broken doors, Repair damaged cupboard bases in the kitchen, Replace toilet seat and base in the main bedroom, Replace wash basin in the main bedroom, Replace shower head and stop tap in the main bedroom, Replace broken glazing in the main bedroom, Replace bathtub in the main bedroom, Paint walls, ceilings, doors and windows, Service drainage system. Replace broken glass pane, Replace the skylight

ELECTRICAL

Repair of Main incoming supply Distribution point that is corroded, Servicing of Swimming pool Distribution Board, Replace main DB in house with new surface mounted DB. Minor electrical repairs including replacing or damaged missing cover plates, TV points, isolators, plug points etc. Replace garden area outlet box with new waterproof termination box and re-connect cables. Install new conduit in enclosed Garage area to house existing loose cabling in the area. Remove guard house DB face plate, install a 16A SP circuit breaker for the UPS feed, surge arresters, manufacture a new face plate, re install the face plate and install legend card and labelling, Install new Pratley joint box, joint the new supply cable and existing supply cable outside the Guard house, New dedicated supply breaker for electric fence energizer to be installed at Guard house.

Install new 10kVA UPS at guard house.

SECURITY

Reposition Electric Fence energizer to Guard house.Install new 8 Strand/ 4 Zone Electric Fence including all accessories e.g. strobe lights, sirens, gate contactors, surge arrestors and earth rods. Connect electric Fence to Intruder Alarm system, Install new 4 x Static Cameras, Install new 2 x PTZ Cameras, Install new 1 x CCTV Recording System including all network switched, racking, monitors, keyboards, patches and panels

Connect CCTV system to Intruder Alarm system, Install new IP Intercom system including 1 x Master, 3 x slave points and surge protection. Install new gooseneck intercom stand for vehicular gate access, Connect new Intercom system to existing system. Install new Intruder Alarm system including door contacts, PIR detectors, outdoor dual beam detectors, keypads, alarm sounders, strobes and surge protection.

Install new 3 x Panic Buttons, Connect new Intruder Alarm system to new CCTV system.

MECHANICAL

Service existing air conditioner units, Service existing generator.

 

R 1 319 303.55

4

321 Rigel

WCS 054033 & 048576

BUILDING WORKS:

Phase 1- was confirmed as the following:

HVAC – Main bedroom; Lounges; Study; Proposed Guardhouse (Equipment room)

Generator – Behind guardhouse. Noise/Decibels to be reduced to comply.

Security – Electric fence; Cameras; Alarm; Gate motor; Intercom system; security Equipment to be placed in proposed guardhouse. Floor level/storm water drainage problems – Identified areas require existing floor (paving/concrete floors) removed, fill re-compacted then new paving finish (re-use if possible). Cracked Garage floor – floor to be demolished. Replaced with new

Evidence of water seepage into building on identified walls. Leakages to be rectified and walls to be filled/repainted. All interior walls to be re-painted to have consistent colour. Damaged ceilings and cornice to be replaced. Damaged/lifted roof flashing to be rectified. Towel rails/Toilet roll holders to be replaced new. Damaged blinds to be replaced with new. Damaged curtain rails to be rectified. All locks to be services (replaced where necessary) Steam clean all carpets

New skirting in Study, Interior levels inconsistent and cracking. To be rectified. All rubber traps to be replaced with new bottle traps. Rusted light fitting to be replaced with new. Door stoppers to all doors/Cupboards. New keys for cupboards. External doors to receive new weather bars.

Outbuilding – Replace existing Whb and WC. New shower doors to be installed. Main bedroom – fix mirror onto wall. Repaint internal door frames, Cover places for taps where necessary

Cupboard edge strips to be replaced. Repair existing door hinges, Repair existing bedroom cupboards, Pergola to receive new hurricane clips.

ELECTRICAL WORKS:

Allow for electrical repairs – which will result in issuing a certificate of compliance (C.O.C) as the primary function. Install security measures for close circuit surveillance (CCTV) installation, refers: ( all connected to UPS power): 10 Static Cameras;2 PTZ;3 screens for viewing;

1 Recording System for 30 days; Repair / replace an 8 strand electric fence installation including a certificate of compliance (C.O.C) Add new A/C units for main bedroom, lounge, sun room and guard house.

Servicing existing A/C units; New intruder alarm installation with indoor and outdoor passives, including 3 Panic Buttons to increase security measures

New intercom system for communication between guard house to outside and from guardhouse to the inside of the house.

R 2 398 350.77

R 89 124.35

5

313 Edward, Waterkloof

WCS 054031

BUILDING WORKS:

Fix cracks on walls,Paint walls, Fix/re-a line loose, replace broken/missing slate roof tiles by specialist, Paint existing steel balustrades, Service all trelly security sliding windows/doors

Reputy and repaint painted steel window frame where needed, Replace existing asbestos components if any, Replace damaged & paint existing closed eaves, Replace gutters and downpipes with new where needed, Paints to walls, ceilings, Replace internal vinyl flooring with new tiled flooring in the cottage room, Clean existing floor tiles, Clean existing wall to wall carpets

Remove existing wall to wall carpets & restore existing parquet flooring underneath.

Service sanitary fittings, Replace walls tiles were damaged, Replace coloured whb with new white

Replace existing coloured bath with new white, Replace coloured wc with new white, Install shower with new where needed, Replace missing/damaged ironmongery,Service existing bathroom extract fan, Replace formica counter tops in guard house, Retile existing vanity slab & repaint vanity cupboards.

Roofs : reinstate damaged roof tiles, reinstate waterproofing, reinstate damaged truss members,

reinstate waterproofing, reinstate and repaint ceiling boards to match existing

ELECTRICAL WORKS:

Allow for electrical repairs:Distribution Boards, Security Lighting,Switches and socket outlets,Power points for air-conditioning, Earthling and bonding, Allow for Mechanical repairs: Replacing damage geysers, Replacing air-conditioning, Additional air-conditioning, Toilet extraction and ventilation

R 0.00

R 2 597 583.51

6

273 Eridunus, Waterkloof

WCS 053575

BUILDING WORKS:

Demolish existing structurally damaged old guard house on south boundary wall, Fix cracks on walls, Service/fix sewer and storm water pipes, Varnish existing exterior doors where applicable

Remove existing wall tiles and replace with new where applicable, Re-net existing steel carport with new shade netting, Replace drop in stove and oven with new, Refurbish existing squash court walls and floor, Service existing sauna room, Repaint existing steel balustrades, Repaint existing painted walls, Re-vanish existing timber eaves, Replace gutters and downpipes with new where applicable, Replace rotten roof timber with new where applicable, Paints to walls, ceilings

Retile existing tiled skirting, risers and treads to match existing finish were applicable, Replace broken brass coat and hat hooks, Add mirrors where applicable, Re-putty and repaint existing painted steel window frames where applicable, Replace missing window stays where applicable

Clean existing wall to wall carpets, Replace existing carpets where stains cannot be removed by cleaning, Clean existing floor tiles, Repair or replace existing garage doors where applicable

Replace broken stoep/balcony tiles to match existing, Service sanitary fittings, Replace walls tiles

Replace coloured whb with new white at the small bathroom, Replace existing coloured bath with new white at the small bathroom

Replace coloured wc with new white at the small bathroom, Replace shower with new at the small bathroom, Repaint existing painted skirting where applicable,Replace missing/damaged ironmongery, Relay existing paving

ELECTRICAL WORKS:

Allow for electrical repairs: Replace interior and exterior lighting, Replace power points, Rewiring of distribution boards, Replace gate motor, Replace garage doors motors, Earthing and lightning protection

MECHANICAL WORKS:

Mechanical: Installation of air conditioning

R 0.00

R 2 828 604.88

7

286 Albertus, Waterkloof

WCS 053584

BUILDING WORKS:

Remove steel door frame and replacing with new, Fix sliding gear of timber sliding double doors

Repair and waterproof concrete roof ridge capping, Remove aluminum adjustable louvered awnings and replace with new, Remove aluminum roof gutters and downpipes and replace with new, Remove portion of damaged flush plastered gypsum plasterboard ceilings and replace with new, Remove damaged acoustic suspended ceiling and replace with new, Replace missing acoustic suspended ceiling tiles, Remove portion of damaged fibre-cement suspended eaves soffit coverings replace with new, Remove fibre-cement fascias and barge boards and replace with new, Remove existing roof waterproofing and replace with new, Remove damaged timber laminate skirtings and replace with new, Remove wall cupboard and replace with new, Remove sink cupboards and replace with new, Remove BIC and replace with new, Remove timber counters and replace with new, Remove timber trap door and frame and replace with new

Remove rubber tile floor covering and skirtings and replace with ceramic tiles, Remove carpet floor covering and replace with new, Remove door closer and mortice lockset and replace with new, Remove bathroom towel rail and toilet roll holder and replace with new, Remove steel floor grating, galvanize and re-instate existing, Hack off internal and external plaster due to dampness, waterproof and replace with new plaster as per engineer’s instructions, Hack off wall and floors tiles including tile skirting’s and replace with new, Remove ceramic soap dishes and replace with new, Remove corroded pipes and replace with new uPVC pipes. Remove Sink, WC pan , wash hand basin, shower trays and shower cubicle and replace with new next to the kitchen

Remove wallpaper, plaster and paint wall

Remove grout between floor tiles and clean out joints to receive new grout were damaged, Steam clean existing carpet floor covering, Clean down window panes and make good putty to glazing

Fix window mechanism for easy operating, Demolish existing concrete apron and replace with new, Remove and replace steel rotary dryer, Cart away existing loose rubble from site

Brick seal face brick walls and stone wall cladding, Remove shrubs and plants against building and replace with apron slab were necessary, Paint all new and existing walls and concrete surfaces, Paint all new and existing plasterboard suspended or nailed-up ceilings boards and bulkheads, Paint all new and existing fiber-cement suspended or nailed-up ceiling boards

Paint fibre-cement fascias and barge boards, Varnish new and existing timber doors, frames, skirtings and shelving, Varnish existing timber ceilings (Kitchen), Paint all new and existing metal doors, frames, windows, gates, burglar bars, screens, balustrades, rails, bars and pipes

Paint existing metal gazebo, Paint existing IBR roof sheeting, Remove existing courtyard brick paving, level, re-compact and replay existing brick paving on new sand layer, Remove brick pavers and replace with new were necessary,Break out portion of existing concrete storm water channels and replace with new, Waterproofing of Roof

ELECTRICAL WORKS:

Allow for electrical repairs, Replace interior and exterior lighting, Replace power points, Rewiring of distribution boards, Replace gate motor, Replace garage doors motors, Earthing and lightning protection, Cameras

MECHANICAL WORKS:

Installation of air conditioning, Service generator

R 0.00

R 2 784 102.34

8

13, 1st Avenue Houghton*

WCS 050773 & 054581

BUILDINGS WORKS:

All rooms to be painted. New carpets to Ground Floor passage, All existing carpets to be deep cleaned, All Bathrooms to be upgraded as per drawings, New tiling and to bathrooms, New ceiling to Guest toilet, Door to be repaired. New tiling to toilet, Kitchen to be upgraded as per drawings.

New cabinetry to kitchen and scullery, New tiling to kitchen and scullery, Repairs to pantry cabinetry, Study cabinetry to be repaired. New shelving to Ground Floor store, New plumbing to be installed. Balcony tiling to be re-grouted, Balcony balustrading to be repainted. External timber doors and windows to be re-varnished with new putty to glazing. All internal timber to be retained as is.

All walls to be prepared and repainted. Garage walls to be prepared and repainted. New storm water channel around the buildings, Bath tub to be re enamelled, New taps to existing freestanding tub. Repaint existing front boundary wall

ELECTRICAL WORKS:

Allow for electrical repairs – which will result in issuing a certificate of compliance (C.O.C) as the primary function.

Install security measures for close circuit surveillance (CCTV) installation, refers: ( all connected to UPS power): 10 Static Cameras; 2 PTZ;3 screens for viewing;1 Recording System for 30 days;

Repair / replace an 8 strand electric fence installation including a certificate of compliance (C.O.C)

Add new A/C units for main bedroom, lounge, sun room and guard house. Servicing existing A/C units;New intruder alarm installatio, New intercom system for communication between guard house to outside and from guardhouse to the inside of the house.

The new electrical installation to allow for a future Generator(supplied and installed by the client)

Servicing existing lift

R 3 133 499.05

R 333 263.99

9

21A Killarney Road, Sandhurst

WCS 052038

BUILDING WORKS:

Replacement of cracked marble tiles

Painting of external walls including timber windows (Removal and replacement of timber windows damaged by dry rot).

New Drywall and paint and new door to guardhouse for server room.

Replacement of damaged gutters and installation of leaf guard mesh.

Installation of frosted vinyl to bathroom widows 6.

Repair to carpet

Maintenance of skylights

New stainless steel balustrading.

Repair of wall cracks as per engineers specifications

Repair of precast concrete architrave to outbuilding door.

Repair external doors on outbuilding

Replace 2 external doors on outbuilding

Please note that all internal painting and internal damp proofing to be done by DPW maintenance.

ELECTRICAL WORKS:

Allow for electrical repairs – for achieving the issuing of a certificate of compliance (C.O.C) as the primary function.

Install security measures for close circuit surveillance (CCTV) installation, refers: ( all connected to UPS power)

10 Static Cameras;

1 PTZ;

3 screens for viewing;

1 Recording System for 30 days;

Repair / replace an 8 strand electric fence installation including a certificate of compliance (C.O.C)

Add new A/C unit for main bedroom.

Servicing existing A/C units;

New intruder alarm installation with indoor and outdoor passives, including 3 Panic Buttons to increase security measures

New intercom system for communication between guard house to outside and from guardhouse to the inside of the house.

R 197 826.19

R 2 501 531.73

10

79 Bogey

WCS 052425

BUILDING WORKS:

Install new aprons, Cut trees, Demolish existing perimeter walls replace with new

Fix cracks on walls, Replace existing pool surround with new, Paint existing paving, Replace loose paving, Remove all pergolas, Install timber decking, Paint existing timber eaves

Replace gutters and downpipes with new

Paints to walls, ceilings, Replace internal flooring with new, Clean existing floor tiles, Replace stoep tile with new, Service sanitary fittings, Replace walls tiles, Install new vanity cupboards

Replace whb with new , Replace existing bath with new, Replace wc with new, Replace shower with new , Replace missing/damaged ironmongery

ELECTRICAL WORKS:

Allow for electrical repairs – for achieving the issuing of a certificate of compliance (C.O.C) as the primary function.

Install security measures for close circuit surveillance (CCTV) installation, refers: ( all connected to UPS power)

10 Static Cameras;

1 PTZ;

3 screens for viewing;

1 Recording System for 30 days;

Repair / replace an 8 strand electric fence installation including a certificate of compliance (C.O.C)

Add new A/C unit for main bedroom.

Servicing existing A/C units;

New intruder alarm installation with indoor and outdoor passives, including 3 Panic Buttons to increase security measures

New intercom system for communication between guard house to outside and from guardhouse to the inside of the house.

R 920 961.98

R 1 200 680.99

11

205 Sterlitzia Street

WCS 054730

ELECTRICAL WORKS:

Repair exterior and interior lighting, Rewiring and distribution boards, Repair power points

Installation of Earthing and lightning protection, Repair gate and garage motors

MECHANICAL WORKS:

Servicing of air conditioning

BUILDING WORKS:

New Boundary walls: Removal of existing fencing,Trench excavations,Reinforced concrete foundations, Construct Masonry walls , Backfilling, Covered entertainment area, Repair and reinstate timber rafters, brandering etc Replace ceiling boards, Repair roof

Paving: Remove and reinstate to match existing, Backfill to required density, Painting , Preparation and Waterproofing, Repair and seal cracks, Repaint (colours to be confirmed)

Roof, Identify leaks and repair , Replace/repair ceiling damaged ceiling boards, Repaint to match existing

R 0.00

R 2 658 529.98

     

R 6 808 939.18

R 20 255 579.94

30 October 2017 - NW2750

Profile picture: Bergman, Mr D

Bergman, Mr D to ask the Mr D Bergman

1) What was the reason for the recent replacement of the blinds in the houses at the parliamentary villages; (2) whether a tender process was followed to appoint the service provider who installed the blinds; if not, why not; if so, what are the details of the (a) date(s) when the tender was placed, (b) place where the tender was placed, (c) bidders who submitted tenders, (d) the winning bidder and (e) cost incurred to replace the blinds?

Reply:

1. The reason for the recent replacement of blinds in houses at the parliamentary villages were because the aluminium perforated blinds in most residences were damaged, tenants complained about not being able to clean the blinds because they bend easily and get damaged, resulting in them being unable to open and close smoothly and secure locking because of the piled dust. Furthermore, doors and fanlights did not have blinds.

2. Yes, an open tender process was followed to appoint the service provider who installed the blinds at the parliamentary villages.

(a) The tender was advertised on 02 September 2016 and closed on 23 September 2016.

(b) The following are the places where the said tender was placed:

      • www.publicworks.gov.za

     • www.etenders.gov.za

     • www.treasury.gov.za

    • www.info.gov.za/documents/tenders

    • Public Works tender noticeboard

(c) There were nine (9) bidders who submitted tenders, as follows:

1. DBEC PTY LTD

2. Earl-Nique Decorators CC

3. Louise Mulholland Interiors

4. Mosebetsi Interiors

5. MTF Consultants

6. Belinda’s Creative Interior Décor

7. Business by Numbers

8. Posh Curtain Designer CC

9. Azis Interior Designs CC

(d) The winning bidder was Belinda’s Creative Interior Décor.

(e) The cost incurred to replace the blinds amounted to R1, 586 890.45.

30 October 2017 - NW2210

Profile picture: Kruger, Mr HC

Kruger, Mr HC to ask the Minister of Cooperative Governance and Traditional Affairs

(a) By what date will the Ekurhuleni Metropolitan Municipality upgrade the generator at the Windsor pump station in order to prevent more water outages and (b) what is the cost of the new generator; (2) How much was budgeted for the new generator;

Reply:

The following response was provided by the Gauteng Department of Cooperative Governance Human Settlements and Traditional Affairs:

1. (a) The Ekurhuleni Metro Municipality installed the new generator at the Windsor Pump Station on 21 July 2017 and it was commission on 22 July 2017.

     (b) The cost of the new generator is R1 313 304 excluding VAT.

2. The budget for the new generator was R1 500 000.

30 October 2017 - NW3010

Profile picture: James, Ms LV

James, Ms LV to ask the Minister in the Presidency

(1)What is the (a) total amount that was paid out in bonuses to employees in his Office and (b) detailed breakdown of the bonus that was paid out to each employee in each salary level in the 2016-17 financial year; (2) what is the (a) total estimated amount that will be paid out in bonuses to employees in his Office and (b) detailed breakdown of the bonus that will be paid out to each employee in each salary level in the 2017-18 financial year?

Reply:

During the 2016/17 financial year, four (4) employees received bonuses in the Ministry as follows:

Ministry

Salary Level

# of qualifying employees

Amount

Level 12

1

R47 957.49

Level 13

1st official

R52 629.12

Level 13

2nd official

R54 418.06

Level 13

3rd official

R55 858.50

 

Total

R 210 863.17

The total amount paid during the 2016/17 financial year to other employees of DPME according to salary levels was as follows:

Salary Band

Qualifying employees

Amount

3 to 5

1 out of 15

R 12 000.00

6 to 8

18 out of 52

R 252 000.00

9 to 12

49 out of 119

R1 656 000.00

Salary level 13

7 out of 41

R 384 000.00

Salary level 14

1 out of 14

R 64 000.00

Salary level 15

4 out of 14

R 317 000.00

 

Total

R 2 685 000.00

The estimated amount to be paid to qualifying employees in the 2017/18 financial year is R2 015 417.00.

30 October 2017 - NW3061

Profile picture: McLoughlin, Mr AR

McLoughlin, Mr AR to ask the Minister of Rural Development and Land Reform

With reference to the under expenditure of R759,7 million in respect of his department’s Programme 4 in the first quarter of the 2017-18 financial year, why have no appropriate and effective steps been implemented by his department to ensure that its target setting and budget forecasting are in alignment with each other, given that his department must be aware of the lengthy verification process involved in the establishment of who the rightful owners of land are; (2) what steps, if any, have been put in place to streamline the process to ensure that prospective claimants are not left waiting needlessly when a budget for the settling of claimant’s claims is available but unspent; (3) what (a) percentage of the lengthy verification process of establishing who the rightful owners of the land are is caused by the lack of urgency, capacity or application on the part of his department’s staff and (b) steps are in place to eradicate such unnecessary delays?

Reply:

1. With the implementation of the new BAS version delays in the processing of payments were experienced. All entities not registered on the National Treasury central database system were not converted to the new BAS version. Suppliers and claimants had to resubmit their banking details in order to process payments. These issues have been resolved and payments are now flowing.

2. Monthly review of expenditure and projections are in place to ensure a streamlined process. Regular meetings with provincial offices to determine the status of projects and the settlement of claims are in place.

3. (a) The Restitution Business is broad and labour intensive. The verification process requires extensive consultation with claimants who at times leave in different areas far apart from each other. Households have also multiplied since the time of dispossession and the verification has to be done in collaboration and in agreement with the community representatives. This process is also intended to prevent fraud in the process.

 (b) The Commission is also engaged through a process of review of its business processes with the intent to find more efficient and effective ways to settle claims.

30 October 2017 - NW2119

Profile picture: Gardee, Mr GA

Gardee, Mr GA to ask the Minister of Cooperative Governance and Traditional Affairs

How many municipalities across the country have municipal-owned entities; (2) Do the specified municipal-owned entities have boards in place; (if so (a) who appoints the board members, (b) how long is the term of each specified board, (c) when was each current board appointed and (d) how many members of each board are female?

Reply:

The information is not readily available in the department and requests were made to the Provincial Departments of Cooperative Governance and Traditional Affairs. However, only six provinces provided information in this regard:

PROVINCE

How many municipalities across the country have municipal owned entities

(2)

   

(a)

Who appoints the board members

(b)

how long is the term of each specified board

(c)

When was each current board appointed

(d)

How many members of each board are female

Western Cape

City of Cape Town

City of Cape Town and Western Cape Government

It’s presumed to be a fixed term board

Various dates – see list attached

5 of 11 members are female

Gauteng

City of Tshwane

The Board is appointed by the City of Tshwane as the shareholder

The appointment of the Board is aligned to the five-year political term of Council

1 October 2012

Tshwane Economic Development Agency – 3 female members

       

10 April 2012

Housing Company Tshwane – 1 female member

 

City of Johannesburg

City of Joburg

1 year

16 March 2017

City Power – 3 female members

         

Joburg Water- 4 female members

         

Pikitup – 4 female members

         

Johannesburg Social Housing Company – 1 female member

         

Joburg Development Agency – 2 female members

         

Joburg Market – 2 female members

         

Joburg Property Company – 3 female members

         

Joburg Roads Agency – 5 female members

         

Metrobus – 3 female members

         

Joburg City Parks & Zoo – 3 female members

         

Joburg City Theatres – 7 female members

         

Metro Trading Company – 5 female members

 

City of Ekurhuleni

Council

3 years

1 May 2015

Brakpan Bus Company – 1 female member (resigned)

         

Ekurhuleni Housing Company – 4 female members

         

East Rand Water Care Company – 2 female members

 

West Rand DM

Executive Mayor

3 years

April 2017

West Rand Development Agency – 2 female members

 

Sedibeng DM

Council

Not specified

February 2015

Vaal River City Tourism Promotion Company – 1 female member

North West

Dr KKDM Economic Agency (SOC) Ltd.

The Council of the Parent Municipality

3 years

1 January 2016

2 female members (1 resigned)

 

Rustenburg LM

Executive Mayor or the Council after an advertisement in the local newspapers

2 years

-

1 female member

 

Lekwa-Teemane Development Agency

Council

3 years

In the process of appointing new board (recently terminated board was appointed Nov 2010 and term expired Oct 2013, however they remained an interim board until July 2017)

-

Mpumalanga

The City of Mbombela inherited the Umjindi Local Economic Development Agency after the amalgamation of Mbombela LM and Umjindi LM

City of Mbombela

24 months

New board in process of being appointed

New board in process of being appointed

 

Thabachweu Local Economic Development Agency (THALEDA)

Council

3 yrs

20th October 2014 (An extension for a further one year was granted after the term of office expired in September 2017)

1 female member

Free State

No response from the province

       

Northern Cape

No municipality in the Northern Cape has a municipal-owned entity

N/A

N/A

N/A

N/A

KwaZulu-Natal

Umhlosinga Development Agency

The respective District Municipality

5 years

26 March 2013

0

 

Zululand Development Agency

 

3 years

01 April 2016

3 female members

 

Uthungulu Fresh Produce Market (King Cetshwayo)

 

5 years

2015

3 female members

 

ILembe Management Development Enterprise

 

3 years

02 October 2015

3 female members

 

UGu South Coast Development Agency

 

3 years

10 July 2015

3 female members

 

Harry Gwala Development Agency

 

3 years

01 April 2015

0

 

UMgungundlovu Development Agency

 

3 years

01 July 2016

3 female members

 

Umzinyathi Development Agency

 

3 years

16 October 2016

2 female members

 

UThukela Development Agency

 

3 years

14 July 2017

1 female member

 

Amajuba Development Agency (The Municipal Council is yet to Endorse the Board and conduct the inauguration)

 

Nil - Awaiting Council Endorsement

2015

0

 

Durban ICC

 

5 years

2014

1 female member

 

Durban Marine Theme Park trading as Ushaka Marine world

 

5 years

2013

2 female members

 

Safe City Pietermaritzburg

 

5 years

2015

2 female members

 

Ugu South Coast Tourism

 

5 years

2015

3 female members

 

Uthukela Water

 

5 years

2014

unknown

Limpopo

No response from the province

       

Eastern Cape

No response from the province

       

30 October 2017 - NW3098

Profile picture: Dreyer, Ms AM

Dreyer, Ms AM to ask the Minister of Police

For each laboratory administered by Forensic Service Division of the SA Police Service, how many entries were (a) received and (b) finalised by the (i) ballistics unit, (ii) scientific analysis unit, (iii) questioned documents unit, (iv) biology unit, (v) victim identification unit and (vi) chemistry unit in (aa) each of the past three financial years and (bb) since 1 April 2017?

Reply:

(a)(b)(i)(aa)(bb)

(i) Ballistics

2014/2015

2015/2016

2016/2017

2017-04-01 to 2017-10-15

a) Received

66152

60635

80015

33620

b) Finalised

65813

58467

80301

32454

(a)(b)(ii)(aa)(bb)

(ii) Scientific Analysis

2014/2015

2015/2016

2016/2017

2017-04-01 to 2017-10-15

a) Received

6 063

6 642

6 961

4 116

b) Finalised

6 313

6 552

7 070

3 442

(a)(b)(iii)(aa)(bb)

(iii) Questioned Documents

2014/2015

2015/2016

2016/2017

2017-04-01 to 2017-10-15

a) Received

29 705

24 723

27 624

8 922

b) Finalised

29 512

25 486

27 607

9 035

(a)(b)(iv)(aa)(bb)

(iv) Biology

2014/2015

2015/2016

2016/2017

2017-04-01 to 2017-10-15

a) Received

112 575

165 852

505 257

243 180

b) Finalised

112 132

136 090

475 486

237 971

(a)(b)(v)(aa)(bb)

(v) Victim Identification Centre

2014/2015

2015/2016

2016/2017

2017-04-01 to 2017-10-15

a) Received

3 336

9 325

5 172

2 782

b) Finalised

3 248

9 349

5 188

2 815

(a)(b)(vi)(aa)(ab)

 

(vi) Chemistry

2014/2015

2015/2016

2016/2017

2017-04-01 to 2017-10-15

a) Received

82 078

89 215

100 185

55 999

b) Finalised

82 621

84 739

101 663

54 128

30 October 2017 - NW3065

Profile picture: Topham , Mr B

Topham , Mr B to ask the Minister of Finance

What are the full details of all sponsorships in cash or kind that the SA Airways (SAA) awarded and/or paid to any person and/or entity from 1 April 2014 to 30 September 2017, including the (a) name of each person or entity, (b) amount of each sponsorship, (c) reason for awarding each sponsorship and (d) benefits that accrued to the SAA as a result of each sponsorship?

Reply:

(1) South African Airways has not offered any cash sponsorship from 1 April 2014 to 30 September 2017. The Value-In-Kind (VIK) sponsorships offered between 1 April 2014 and 30 September 2017 are listed below:

Sponsorship Property

Right Holder

Value

Period

 

SA Olympic Teams

SASCOC

R6m per annum

2014-15

Springboks

SA Rugby

R22.5m per annum

2014-15

 

SA Olympic Teams

SASCOC

R6m per annum

2015-16

Springboks

SA Rugby

R22.5 per annun

2015-16

Miss South Africa

Sun International

R594k

2015-16

World Routes

UBM

R1.5m

2015-16

NBA Africa Games

NBA Africa

R1.3m

2015-16

International Jazz Extravaganza

Teacup Projects

R1.1m

2015-16

 

Bafana Bafana

SAFA

R10m first year

2016 - 17

SA Olympic Teams

SASCOC

R8m per annum

2016 -17

Miss South Africa

Sun International

R596k

2016 -17

 

Bafana Bafana

SAFA

R25m per annum

2017 - 2018

International Jazz Extravaganza

Teacup Projects

R1.2m

2017 - 2018

The sponsorships are offered with the purpose of deriving marketing and commercial benefits for SAA. All these sponsorships were approved in accordance with the company’s Delegation of Authority Framework (“DOA”) and have followed internal approval process.

In return for the sponsorships, SAA is afforded sponsorship rights, which include: (i) platform to promote sales on SAA; (ii) media exposure and adverting; and (iii) branding opportunities.

30 October 2017 - NW3122

Profile picture: Esau, Mr S

Esau, Mr S to ask the Minister of Police

(1) (a) How many suspects have escaped from the Boksburg North police station (i) in the (aa) 2015-16 and (bb) 2016-17 financial years and (ii) from 1 April 2017 up to the latest specified date for which information is available, (b) on what date did each person escape and (c) which police officers were on duty at the time of each escape; (2) whether a case of escape was registered in each case; if not, (a) why not and (b) what (i) is the name of the officer that failed to register such a case and (ii) action was taken against each officer in each case?

Reply:

(1)(a)(i)(aa)(bb)(ii)(b)(c)

(i)(aa) 2015/2016

(i)(bb) 2016/2017

(ii)

1 April 2017 to date

(b)

Date of escape

(c)

Officers on duty

0

0

0

Not applicable

Not applicable

(2)(a)(b)(i)(ii) Not applicable.

30 October 2017 - NW3100

Profile picture: Dreyer, Ms AM

Dreyer, Ms AM to ask the Minister of Police

What number of (a) DNA profile analyses, (b) facial reconstructions, (c) mummified fingerprinting, (d) microscopic hair comparisons, (e) arson chemistry reports, (f) poison analyses, (g) crime scene toxicology reports and (h) gunshot residue analyses were finalised by the Forensic Service Division of the SA Police Service in (i) each of the past five financial years and (ii) since 1 April 2017?

Reply:

(a)(b)(c)(d)(e)(f)(g)(h)(i)(ii)

 

(i)

2013/2014

(i)

2014/2015

(i)

2015/2016

(i)

2016/2017

(ii) Since 1 April 2017

(a) DNA profile analyses

95 814

86 885

75 560

89 467

49 894

(b) Facial reconstructions

103

71

93

347

144

(c) Mummified fingerprinting

963

1 583

534

2 292

1 129

(d) Microscopic hair comparisons

765

5

10

11

0

(e) Arson chemistry reports

314

268

305

300

133

(f) Poison analyses

511

409

408

356

205

(g) Crime scene toxicology reports

2

1

2

0

0

(h) Gunshot residue analyses

2 686

2 561

2 583

2 671

1 253

30 October 2017 - NW3096

Profile picture: Cassim, Mr Y

Cassim, Mr Y to ask the Minister of Police

(a) What number of vacancies exist at each forensic science laboratory that is administered by his department and (b) in each case, (i) what is the title of the position Friday, to be filled, (ii) how long has the position been vacant, (iii) what steps were taken to fill the vacancy and (iv) on what date does his department expect the vacancy to be filled?

Reply:

(a) It needs to be noted that forensic analysts are appointed in terms of the South African Police Service Act, in the Division: Forensic Services, at the Criminal Record and Crime Scene Management, Forensic Science Laboratory and Quality Management. The following vacancies exist:

CRIMINAL RECORD AND CRIME SCENE MANAGEMENT

ACT OF APPOINTMENT

SALARY LEVEL

NATIONAL OFFICE: PRETORIA

WC

EC

KZN

NC

MP

FS

NW

LP

GP

TOTAL

POLICE ACT

SALARY LEVEL 13: BRIGADIER

1

0

1

0

0

0

0

0

0

0

2

POLICE ACT

SALARY LEVEL 12: COLONEL

1

4

2

1

4

4

3

7

4

7

37

POLICE ACT

SALARY LEVEL 10: LIEUTENANT COLONEL

14

13

19

28

15

22

19

11

15

19

175

POLICE ACT

SALARY LEVEL 8: CAPTAIN

22

13

30

55

16

10

19

16

26

48

255

POLICE ACT

SALARY LEVEL 7: WARRANT OFFICER

2

10

9

11

4

3

2

13

6

7

67

POLICE ACT

SALARY LEVEL 6: SERGEANT

1

0

2

0

1

1

5

2

0

0

12

POLICE ACT

SALARY LEVEL 5: CONSTABLE

0

1

0

0

1

1

1

0

0

3

7

PUBLIC SERVICE ACT

SALARY LEVEL 7

3

1

0

0

0

0

0

0

0

1

5

CRIMINAL RECORD AND CRIME SCENE MANAGEMENT

ACT OF APPOINTMENT

SALARY LEVEL

NATIONAL OFFICE: PRETORIA

WC

EC

KZN

NC

MP

FS

NW

LP

GP

TOTAL

PUBLIC SERVICE ACT

SALARY LEVEL 6

2

0

2

0

0

1

0

2

0

0

7

PUBLIC SERVICE ACT

SALARY LEVEL 5

0

2

7

2

1

1

2

1

2

3

21

PUBLIC SERVICE ACT

SALARY LEVEL 4

0

0

0

0

0

0

0

0

0

1

1

PUBLIC SERVICE ACT

SALARY LEVEL 3

1

4

1

1

1

0

0

1

0

0

9

PUBLIC SERVICE ACT

SALARY LEVEL 2

0

0

0

0

1

0

0

0

0

0

1

TOTAL

47

48

73

98

44

43

51

53

53

89

599

FORENSIC SCIENCE LABORATORY

ACT OF APPOINTMENT

SALARY LEVEL

PTA

WC

EC

KZN

TOTAL

POLICE ACT

SALARY LEVEL 13: BRIGADIER

0

0

0

0

0

POLICE ACT

SALARY LEVEL 12: COLONEL

2

1

1

3

7

POLICE ACT

SALARY LEVEL 10: LIEUTENANT COLONEL

4

7

6

13

30

POLICE ACT

SALARY LEVEL 8: CAPTAIN

31

26

19

25

101

POLICE ACT

SALARY LEVEL 7: WARRANT OFFICER

16

4

2

4

26

POLICE ACT

SALARY LEVEL 6: SERGEANT

1

0

0

0

1

POLICE ACT

SALARY LEVEL 5: CONSTABLE

1

1

0

0

2

PUBLIC SERVICE ACT

SALARY LEVEL 7

0

0

0

0

0

PUBLIC SERVICE ACT

SALARY LEVEL 6

0

0

0

0

0

PUBLIC SERVICE ACT

SALARY LEVEL 5

1

1

0

4

6

PUBLIC SERVICE ACT

SALARY LEVEL 4

0

0

0

0

0

PUBLIC SERVICE ACT

SALARY LEVEL 3

1

0

0

0

1

PUBLIC SERVICE ACT

SALARY LEVEL 2

1

0

0

0

1

TOTAL

58

40

28

49

175

QUALITY MANAGEMENT

ACT OF APPOINTMENT

SALARY LEVEL

PTA

WC

EC

KZN

NC

GP

TOTAL

POLICE ACT

SALARY LEVEL 13: BRIGADIER

1

0

0

0

0

0

1

POLICE ACT

SALARY LEVEL 12: COLONEL

13

0

2

0

0

0

15

POLICE ACT

SALARY LEVEL 10: LIEUTENANT COLONEL

28

1

2

1

0

0

32

POLICE ACT

SALARY LEVEL 8: CAPTAIN

21

2

1

2

1

0

27

POLICE ACT

SALARY LEVEL 7: WARRANT OFFICER

1

0

0

0

0

0

1

POLICE ACT

SALARY LEVEL 6: SERGEANT

0

0

0

0

0

0

0

POLICE ACT

SALARY LEVEL 5: CONSTABLE

0

0

0

0

0

0

0

PUBLIC SERVICE ACT

SALARY LEVEL 7

0

0

0

0

0

1

1

PUBLIC SERVICE ACT

SALARY LEVEL 6

0

0

0

0

0

0

0

PUBLIC SERVICE ACT

SALARY LEVEL 5

1

0

0

0

0

0

1

PUBLIC SERVICE ACT

SALARY LEVEL 4

0

0

0

0

0

0

0

PUBLIC SERVICE ACT

SALARY LEVEL 3

0

0

0

0

0

0

0

PUBLIC SERVICE ACT

SALARY LEVEL 2

0

0

0

0

0

0

0

TOTAL

65

3

5

3

1

1

78

 

SUPPORT SERVICES

ACT OF APPOINTMENT

SALARY LEVEL

NATIONAL OFFICE: PRETORIA

POLICE ACT

SALARY LEVEL 13: BRIGADIER

0

POLICE ACT

SALARY LEVEL 12: COLONEL

0

POLICE ACT

SALARY LEVEL 10: LIEUTENANT COLONEL

1

POLICE ACT

SALARY LEVEL 8: CAPTAIN

13

POLICE ACT

SALARY LEVEL 7: WARRANT OFFICER

0

POLICE ACT

SALARY LEVEL 6: SERGEANT

0

POLICE ACT

SALARY LEVEL 5: CONSTABLE

0

PUBLIC SERVICE ACT

SALARY LEVEL 7

0

PUBLIC SERVICE ACT

SALARY LEVEL 6

0

PUBLIC SERVICE ACT

SALARY LEVEL 5

1

PUBLIC SERVICE ACT

SALARY LEVEL 4

0

PUBLIC SERVICE ACT

SALARY LEVEL 3

1

PUBLIC SERVICE ACT

SALARY LEVEL 2

0

PUBLIC SERVICE ACT

SALARY LEVEL 1

0

TOTAL

16

DIVISION: FORENSIC SERVICES

ACT OF APPOINTMENT

SALARY LEVEL

NATIONAL OFFICE: PRETORIA

POLICE ACT

SALARY LEVEL 13: BRIGADIER

3

POLICE ACT

SALARY LEVEL 12: COLONEL

59

POLICE ACT

SALARY LEVEL 10: LIEUTENANT COLONEL

238

POLICE ACT

SALARY LEVEL 8: CAPTAIN

396

POLICE ACT

SALARY LEVEL 7: WARRANT OFFICER

94

POLICE ACT

SALARY LEVEL 6: SERGEANT

13

POLICE ACT

SALARY LEVEL 5: CONSTABLE

9

PUBLIC SERVICE ACT

SALARY LEVEL 7

6

PUBLIC SERVICE ACT

SALARY LEVEL 6

7

PUBLIC SERVICE ACT

SALARY LEVEL 5

29

PUBLIC SERVICE ACT

SALARY LEVEL 4

1

PUBLIC SERVICE ACT

SALARY LEVEL 3

11

PUBLIC SERVICE ACT

SALARY LEVEL 2

2

TOTAL

868

(b)(i) The table below, reflects the posts that are to be filled:

ACT OF APPOINTMENT

SALARY LEVEL

TOTAL

POLICE ACT

SALARY LEVEL 13: BRIGADIER

1

POLICE ACT

SALARY LEVEL 12: COLONEL

13

POLICE ACT

SALARY LEVEL 10: LIEUTENANT COLONEL

28

POLICE ACT

SALARY LEVEL 8: CAPTAIN

21

POLICE ACT

SALARY LEVEL 7: WARRANT OFFICER

1

PUBLIC SERVICE ACT

SALARY LEVEL 5

1

TOTAL

 

65

(b)(ii) The posts are vacant from the 2015/2016, 2016/2017 and 2017/2018, financial years.

(b)(iii) The vacant posts were identified and submitted to the Divisional Commissioner: Personnel Management, for approval to advertise and fill the posts.

       

(b)(iv) A total of 304 SAPS Act posts, on salary level seven, Warrant Officer/Forensic Analyst, have been approved and allocated to the Division: Forensic Services, for the 2017/2018 financial year. The approval to advertise and commence with the filling of the posts on the other levels, is pending the upliftment of the moratorium, on the filling of vacant posts.

 

30 October 2017 - NW3127

Profile picture: Gqada, Ms T

Gqada, Ms T to ask the Minister of Police

(1) (a) How many suspects have escaped from the Sebenza police station (i) in the (aa) 2015-16 and (bb) 2016-17 financial years and (ii) from 1 April 2017 up to the latest specified date for which information is available, (b) on what date did each person escape and (c) which police officers were on duty at the time of each escape; (2) whether a case of escape was registered in each case; if not, (a) why not and (b) what (i) is the name of the officer that failed to register such a case and (ii) action was taken against each officer in each case?

Reply:

(1)(a)(i)(aa)(bb)(ii)(b)(c)

(i)(aa) 2015/2016

(i)(bb) 2016/2017

(ii)

1 April 2017 to date

(b)

Date of escape

(c)

Officers on duty

0

0

0

Not applicable

Not applicable

(2)(a)(b)(i)(ii) Not applicable.

30 October 2017 - NW2746

Profile picture: Figg, Mr MJ

Figg, Mr MJ to ask the Minister of Public Works

(1) Whether he has found that there are monies paid by his department for leases where it was subsequently established that no property was in fact leased, used or even existed; if not, what is the position in this regard; if so, what (a) are the relevant details of each case and (b) action has been taken in this regard; (2) whether his department suffered any financial losses as a result of paying money for leases where it was subsequently established that no property was in fact leased, used or even existed; if not, why not; if so, what plans have been put in place to recover these funds?

Reply:

1. (a) & (b) No monies were paid for leases where it was established that no property was in fact leased, used or did not exist.

2. The department has not suffered any financial losses in this regard.

30 October 2017 - NW2955

Profile picture: Van Dyk, Ms V

Van Dyk, Ms V to ask the Minister of Police

In each province, (a) what is the total number of (i) hot spots and (ii) vulnerable communities that were identified in rural areas through the partnership between the SA Police Service and each specified community, as envisioned in Pillar 1 of the National Rural Safety Strategy and (b) in each case, (i) what are the further relevant details and (ii) is an operational plan compiled to combat crime in the specified area?

Reply:

Sourcing the information from our archives, as each case must be verified, before the information can be submitted.

30 October 2017 - NW2209

Profile picture: Kruger, Mr HC

Kruger, Mr HC to ask the Minister of Cooperative Governance and Traditional Affairs

How many power outages have the suburbs of (a) Marlands and (b) Sunnyridge in the Ekurhuleni Metropolitan Municipality experienced (i) in the (aa) 2015 and (bb) 2016 and (ii) in the period 1 January to 31 July 2017; (2) What (a) were the reasons for the power outages in each case, (b) was the duration of the outage and (c) time of day did the outages take place; (3) By what date (i) will the Ekurhuleni Metropolitan Municipality upgrade the infrastructure in the area to prevent further outages and (ii) will work commence on the upgrade, (b) what is the projected cost of the upgrade and (c) what amount has been budgeted for the upgrade?

Reply:

The Gauteng Department of Cooperative Governance Human Settlements and Traditional Affairs provided the response in this regard:

#

AREAS AFFECTED

NUMBER OF POWER OUTAGES PER FINANCIAL YEAR

   

(aa) 2015-2016

(bb) 2016-2017

a

Marlands

4

21

2

Sunnyridge

19

20

3

Both Areas Affected at the same time (upstream substation trip)

18

9

Summary for 2015/2016

Marlands areas affected by power outages 22 times (4+18=22)

Sunnyridge areas affected by power outages 37 times (19+18=37)

Summary for 2016/2017

Marlands areas affected by power outages 30 times (21+9=30)

Sunnyridge areas affected by power outages 29 times (20+9=29)

Therefore, Marlands areas were affected 52 times in 24 months while Sunnyridge areas were affected 66 times in the same period. It must however be noted that not all customers were always affected at the same time. The customers were only affected as-and-when the circuit feeding them faulted which differed in frequency.

2. (a)

#

Financial Year

CAUSE OF POWER OUTAGES

   

Equipment Failure

Operational Causes

3rd Party Cause

Eskom

TOTAL

1

2015/2016

22

12

6

1

41

2

2016/2017

33

8

8

1

50

3

TOTAL

55

20

14

2

91

  • Equipment Failure refer to mainly medium voltage cable faults and switchgear failure
  • Operational Causes refer to overload caused by limited number of available cables during repairs and failure of protection equipment.
  • 3rd Party Causes refer to cable theft and damages by contractors
  • Eskom refer to power outages imposed by Eskom network.

(b) Average hours for power restorations = 6 hours. The shortest power outage took around 0.25 hours and the longest around 41.5 hours.

(c) The power outages randomly happens across all days and hours.

(3) (a)

(i) The main substation (Germiston North Intake Substation) supplying the areas is being upgraded at the moment. The project started in January 2017 and is expected to run until the end of 2018. The substation is being completely upgraded with new transformers and switchgear. In addition to the upgrading of the main substation, the Municipality has identified ageing and frequently failing equipment (mainly medium voltage underground cables) to be refurbished this financial year. Tenders for underground cables (supply and install) are in place. Material already ordered in July 2017 and projects expected to run from October 2017 to June 2018.

(ii) Upgrading of main substation started in January 2017 and is expected to run until the end of 2018. Refurbishment of ageing and frequently failing medium voltage underground cables expected to run from October 2017 to June 2018.

(b) The upgrading of the main substation (Germiston North Intake Substation) is projected at R120 million. The refurbishment of ageing and frequently failing equipment (medium voltage underground cables) for the area is projected at R25 million for the 2017/2018 financial year.

(c) The upgrading of the main substation (Germiston North Intake Substation) is budgeted at R120 million. The refurbishment of ageing and frequently failing equipment (medium voltage underground cables) for the area is budgeted at R25 million for the 2017/2018 financial year.

 

30 October 2017 - NW3130

Profile picture: Groenewald, Mr HB

Groenewald, Mr HB to ask the Minister of Police

(1) (a) How many suspects have escaped from the Elsburg police station (i) in the (aa) 2015-16 and (bb) 2016-17 financial years and (ii) from 1 April 2017 up to the latest specified date for which information is available, (b) on what date did each person escape and (c) which police officers were on duty at the time of each escape; (2) whether a case of escape was registered in each case; if not, (a) why not and (b) what (i) is the name of the officer that failed to register such a case and (ii) action was taken against each officer in each case?

Reply:

(1)(a)(i)(aa)(bb)(ii)(b)(c)

(aa) 2015/2016

(bb) 2016/2017

(ii)

1 April 2017 to date

(b)

Date of escape

(c)

Officers on duty

0

0

0

Not applicable

Not applicable

(2)(a)(b)(i)(ii) Not applicable.

30 October 2017 - NW3223

Profile picture: Steyn, Ms A

Steyn, Ms A to ask the Minister of Rural Development and Land Reform

Whether his department currently has a programme in place aimed at transferring title deeds to farmers; if not, why not; if so, (a) what is the name of the programme and (b) under which circumstances would land transfers take place in this regard?

Reply:

Yes.

a) Land Tenure Reform: Land acquisition for farm dwellers and labour tenants.

b) All land acquired to secure tenure for farm dwellers in terms of Section 4 of the Extension of Security of Tenure Act (Act No. 62 of 1997) and settlement of labour tenants in terms of Section 16 and 17 of the Land Reform (Labour Tenants) Act (Act No. 3 of 1996).

30 October 2017 - NW3133

Profile picture: Hadebe, Mr TZ

Hadebe, Mr TZ to ask the Minister of Police

(1) (a) What number of vehicles from the Primrose Police Station are currently at the mechanical workshop, (b) how long has each specified vehicle been at the mechanical workshop and (c) what are the reasons for each vehicle being at the mechanical workshop; (2) what number of operational vehicles does the specified police station currently have?

Reply:

(1)

a. Number of vehicles at the mechanical workshop.

Six.

b. Time frame (from which date).

1. BTH884B: 2017-09-14.

2. BTN498B: 2017-08-14.

3. BTG005B: 2017-08-14.

4. BRW842B: 2017-08-14.

5. BTK376B: 2017-09-14.

6. BSC840B: 2017-10-14.

c. Mechanical problem.

1. Accident damage.

2. Accident damage.

3. Accident damage.

4. Accident damage.

5. Mechanical (gearbox and engine head gasket blown).

6. Mechanical (gearbox and engine head gasket blown).

(2) 30.