Questions and Replies

Filter by year

23 April 2018 - NW118

Profile picture: Van Der Walt, Ms D

Van Der Walt, Ms D to ask the Minister of Health

(1)Whether, with regard to the (a) Warmbad (Bela-Bela) Hospital, (b) F H Odendaal Hospital, (c) Thabazimbi Hospital and (d) Ellisras Hospital in Limpopo, the post of chief executive officer (CEO) has been filled at each specified hospital; if not, (i) why not, (ii) since which date is the relevant hospital without a permanent CEO and (iii) by which date will the specified posts be advertised and filled;if so, what are the (aa) names, (bb) qualifications and experience and (cc) term of each CEO’s contract; (2) what are the relevant details with regard to the term, qualifications and experience of the acting CEO in each case?

Reply:

See attached.

23 April 2018 - NW218

Profile picture: Khawula, Ms MS

Khawula, Ms MS to ask the Minister of Water and Sanitation

What is the (a) total number of dams in the country, (b) exact location of each dam, (c) capacity of each dam, (d) date on which each dam became operational, (e) current level of each dam and (f) name of the owner of each dam?

Reply:

THE MINISTER OF WATER AND SANITATION

(a) Table below gives a breakdown summary of total number of dams in the country as well as ownership status as per dam register published on 31 December 2017.

Ownership sector

Total number of registered dams

State

854

Department of Water & Sanitation

322

Municipalities

333

Other state departments

76

Water Boards

123

Private sector

4 657

Mines, industries, business

335

Agriculture

4 322

Total

5 511

(b) Dam location per Province is given in the table below. A detailed location of each dam is supplemented in Columns G to O of the dam register, submitted as Annexure A.

Province

Total number of registered dams

North West

92

Gauteng

187

Limpopo

458

Kwazulu-Natal

1090

Eastern Cape

789

Western Cape

1572

Northern Cape

130

Mpumalanga

675

Free State

518

Total

5 511

(c) The table below gives a cumulative summary of dam capacities per ownership sector. From the table it can be seen that state dams store 94% of all available water resources in the country, whereas private sector store the remaining 6%.

Ownership sector

Total capacity in (m3 x 109)

% total capacity

State

31.35

94

Department of Water & Sanitation

29.35

88.0

Municipalities

1.0

3.0

Other state departments

0.2

0.6

Water Boards

0.8

2.4

Private sector

2.06

6.0

Mines, industries, business

0.5

1.5

Agriculture

1.56

4.5

Total

33.41

100

(d) Dam register is submitted as an Annexure A of this reply, for all practical purpose, the date in which the dam became operational is taken as the date of completion which is given in Column R of the dam register.

(e) Dam levels are submitted as Annexure B of the reply. It should be noted that only dam levels owned by my Department are submitted. My Department is unfortunately not in a position to furnish levels of privately owned dams.

(f) Owner's details are given in Column AD of the register

 

23 April 2018 - NW406

Profile picture: Mente-Nkuna, Ms NV

Mente-Nkuna, Ms NV to ask the Minister of Health

(a)What (i) is the total number of hospitals in the country that offer maternity services and (ii)is the name of each hospital and (b) of those hospitals, how many have fully functional maternity services?

Reply:

(a) (i) The total number of hospitals that offer maternity services is 309.

(ii) See Annexure A for the names of the hospitals.

(b) The 309 of the hospitals have fully functional maternity services.

END.

23 April 2018 - NW752

Profile picture: Thembekwayo, Dr S

Thembekwayo, Dr S to ask the Minister of Health

What are the ten leading causesfor admission to a healthcare facility in the Buffalo City Metropolitan Municipality in the Eastern Cape in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Buffalo City Metropolitan Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW754

Profile picture: Mashabela, Ms N

Mashabela, Ms N to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Amathole District Municipality in the Eastern Cape in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Amathole District Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW755

Profile picture: Dlamini, Mr MM

Dlamini, Mr MM to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Chris Hani District Municipality in the Eastern Cape in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Chris Hani District Municipality for the period 2016/17 by age and gender.

END.

23 April 2018 - NW756

Profile picture: Ketabahle, Ms V

Ketabahle, Ms V to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the OR Tambo District Municipality in the Eastern Cape in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for OR Tambo District Municipality for the period 2016/17 by age and gender.

END.

23 April 2018 - NW757

Profile picture: Khawula, Ms MS

Khawula, Ms MS to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Alfred Nzo District Municipality in the Eastern Cape in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Alfred Nzo District Municipality for the period 2016/17 by age and gender.

END.

23 April 2018 - NW1035

Profile picture: Xalisa, Mr Z R

Xalisa, Mr Z R to ask the Minister of Environmental Affairs

With reference to her reply to question 266 on 20 March 2018, (a) what is the name of each (i) of the 955 young persons who were incubated in the Groen Sebenza programme, (ii) person who is now employed, (iii) organisation that has employed the specified persons, and (iv) person who is still unemployed; (b) what are the reasons that they are still unemployed and (c) what actions is her Department taking to ensure employment of those who are still unemployed?

Reply:

(a) (i) (ii) (iii) and (iv) Attached find the spreadsheet as an Annexure containing the names of young persons incubated through the Groen Sebenza Programme, including those employed by different organisations and those unemployed.

(b) Some chose to further their studies while others were self-employed at the end of the programme. However, as indicated previpusly, the ongoing Tracer Study will provide the status quo in this regard.

(c) Opportunities are shared with young people as and when they arise through various platforms.

---ooOoo---

23 April 2018 - NW758

Profile picture: Ntlangwini, Ms EN

Ntlangwini, Ms EN to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Nelson Mandela Bay Metropolitan Municipality in the Eastern Cape in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Nelson Mandela Bay Metropolitan Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW760

Profile picture: Tshwaku, Mr M

Tshwaku, Mr M to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Lejweleputswa District Municipality in the Free State in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Lejweleputswa District Municipality in the financial year 2016/17 by age and gender.

END.

23 April 2018 - NW769

Profile picture: Tshwaku, Mr M

Tshwaku, Mr M to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Ugu District Municipality in KwaZulu-Natal in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Ugu District Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW770

Profile picture: Xalisa, Mr Z R

Xalisa, Mr Z R to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the uMgungundlovu District Municipality in KwaZulu-Natal in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for uMgungundlovu District Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW771

Profile picture: Dlamini, Mr MM

Dlamini, Mr MM to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the uThukela District Municipality in KwaZulu-Natal in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for uThukela District Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW773

Profile picture: Khawula, Ms MS

Khawula, Ms MS to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Zululand District Municipality in KwaZulu-Natal in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Zululand District Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW775

Profile picture: Mathys, Ms L

Mathys, Ms L to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the King Cetshwayo District Municipality in KwaZulu-Natal in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Cetshwayo District Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW787

Profile picture: Ntlangwini, Ms EN

Ntlangwini, Ms EN to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Frances Baard District Municipality in the Northern Cape in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Frances Baard District Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW791

Profile picture: Mhlongo, Mr P

Mhlongo, Mr P to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Cape Town Metropolitan Municipality in the Western Cape in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Cape Town Metropolitan Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW792

Profile picture: Moteka, Mr PG

Moteka, Mr PG to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Cape Winelands District Municipality in the Western Cape in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Cape Winelands District Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW793

Profile picture: Mulaudzi, Adv TE

Mulaudzi, Adv TE to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Overberg District Municipality in the Western Cape in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Overberg District Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW1022

Profile picture: Moteka, Mr PG

Moteka, Mr PG to ask the Minister of Basic Education

What (a) number of (i) high schools and (ii) primary schools offer healthcare services, (b) is the (i) location and (ii) name of each specified school, (c) health services are on offer, (d) is the cost of the health services and (e) is the number of employees in each profession who provide the health services at each school?

Reply:

(a), (b) and (c) The Integrated School Health Programme (ISHP) is implemented by school health teams employed by the Department of Health (DoH) in provinces. The reach of the services and the package provided, is dependent on the availability and composition of these school health teams in each geographic area. The Department of Basic Education receives signed off collated data on the number of learners that have received services in the preceding quarter from the national Department of Health. The list of schools is not provided.

(d) and (e) The cost of the school health services as well as the number of employees are the responsibility of each respective Provincial Education Department. This information is not available at DBE.

23 April 2018 - NW1002

Profile picture: Vos, Mr J

Vos, Mr J to ask the Minister of Water and Sanitation

How much land does (a) his department and (b) the entities reporting to him (i) own, (ii) have exclusive rights to and/or (iii) lease from the State to (aa) use and/or (bb) occupy?

Reply:

a) (i) In terms of Section 1(1)(x) of the National Water Act, 1998 (Act no. 36 of 1998) (NWA) the Minister owns the land on which a Government Waterwork is situated. The Minister owns, manages and controls 322 dams (Government Waterworks) country wide. The extent of the land is determined scientifically up to the dam boundary line of each dam which includes the full supply level, the 1:100 year flood line and a buffer line. All excess land must in terms of Government Immovable Asset Management Act (GIAMA) and the disposal policies of the Department of Water and Sanitation (DWS) and the National Department of Public Works (NDPW) fall back to the NDPW.

(ii) In terms of ownership the Minister has exclusive rights on the land mentioned as above. No other Custodian Departments have any right over the mentioned land because Government Waterworks are National Assets and the water source must be protected in terms of the NWA.

(iii) None, due to the fact that the Minister acquires the minimum land needed for a Government Waterwork.

(aa) Refer to (a)(1)

(bb) Refer to (a)(1)

b) Refer to Annexure A for information regarding entities reporting to the Department.

ANNEXURE A

(b) How much land does the entities reporting to him

(i) own

(ii) have exclusive rights to and/or

(iii) lease from the State to

(aa) use and/or

(bb) occupy

Amatola Water

6 Lancaster Road Vincent East London-

R2 372 250.00

3 Lancaster Road Vincent East London-

R1 332 220.17

Albany Coast-

R1 705 213.00

Nahoon WTW (and related land and dwellings on site)

Laing WTW (and related land and dwellings on site)

Craighead Pumping Station (and related land and dwellings on site)

Glenmore WTW (and related land and dwellings on site)

Peddie Regional WTW (and related land and dwellings on site)

Gubu Dam (and related land and dwellings on site)

Wriggleswade Dam  (and related land and dwellings on site)

Rooikrantz WTW (and related land and dwellings on site)

Binfield WTW (and related land and dwellings on site)

Debe Nek WTW (and related land and dwellings on site)

Masincedane WTW (and related land and dwellings on site)

Upper Mnyameni WTW (and related land and dwellings on site)

Sandile WTW (and related land and dwellings on site

None

Public Works Port Elizabeth workshop – Harrower Road

Public Works Port Elizabeth workshop – Harrower Road

Bloem Water

44509.1479 Hectare

75338.89 hectare

There are no properties leased from the state

None

None

Lepelle Northern Water

2 hectares valued at R6.4 million situated in Polokwane area

2 hectares valued at R6.4 million situated in Polokwane area

There are no properties leased from the state

None

None

Magalies Water

24 properties, of which covers the area of 169 hectares, 15 of the properties own by Magalies Water are still registered with Department Public Works, and Magalies Water is in the process of transferring ownership.

Magalies Water has 226 servitudes endorsement in different properties, of which it covers 54 163M2 and 105 servitudes not registered, which covers the area of 307 hectares

There are no properties leased from the state

None

None

Mhlathuze Water

Portion 6 ERF 6724 Richards Bay Registration Division GU in the Richards Bay Transitional Local Council area, Province of KwaZulu-Natal on sub-divisional diagram S.G no. 2118/1997 in extent 2 5012 hectares;

Sub 4 of Lot 8723 Richards Bay (Extension No. 28) situated in the Richards Bay Transitional Local Council Area, Administrative District of Natal, Province of KwaZulu-Natal, in extent Three comma Three Five Nought One ( 3, 3501) hectares;

Portion 41 of Reserve 6 No.15 825 Registration Division GU Province of KwaZulu-Natal in extent 44,4332 ( Forty Four , Four Three Three Two) hectares;

ERF 960 Eshowe ( Extension Number 9 Registration Division GU Province of KwaZulu-Natal in extent 1534( One Thousand Three Hundred and Thirty Four) square metres;

Portion of ERF 1413 Eshowe Registration Division GU Province of KwaZulu-Natal in extent 1441( One Thousand Four Hundred and Forty One) square metres; and

Portion 1 of the farm Richards Bay No. 16990 GU situated in the Township of Richards Bay, Administrative District of KwaZulu- Natal in the extent 3 542(Three Thousand Five and Forty Two) square metres as indicated on SG Diagram 2009/1999.

Mhlathuze Water does not have land that it has exclusive right to use.

Mhlathuze Water does has have land that it is leasing from the State:

None

None

Overberg Water

No land is owned except the wastewater treatment works in three schemes and houses.

Servitude to access infrastructure in someone property such as the adjacent farm.

None

None

None

Rand Water

7778.798ha land owned

4072.006ha Servitudes

None

None

None

Sedibeng Water

R142,440,370.95 (Both Land and Buildings for Office and Plant Operations: Total value of all regions combined as at 31 March 2018. Land used for Offices, Purification Plants and Pump station area is 144.9H but government owned).

R1,088,122.85 (Servitudes where the pipeline is laid. Right to use the land-Estimated area is 5.17657 km²).

None

Refer to response in (b) (i) & (ii) above

Refer to response in (b) (i) & (ii) above

Umgeni Water

Properties own by Umgeni Water are 451

Umgeni Water has exclusive right over 473 properties

Umgeni Water is leasing no land from the State

None

None

Trans Caledon Tunnel Authority (TCTA)

Total freehold land owned: 1318.35 hectares

Land with exclusive rights: 675.39 hectares;

State Land: 1115.63 hectares

None

State Land: 1115.63 hectares

Water Research Commission (WRC)

Through its subsidiary ERF 706 Pty (Ltd) WRC is currently the registered owner of a property with a building situated in Gezina, Pretoria. This property together with the building was sold during the 2017/18 financial year and the transfer of ownership in the Deeds office is underway.

Yes, the WRC own the building and the land and at this stage has exclusive right of use until the transfer to the new owners occur and this should happen soon

The WRC does not lease land from the state

The WRC is currently leasing and using office space in 4 Daventry Street, Lynnwood Bridge, Pretoria as it has sold the property ERF706 in Gezina.

See response (aa) above

23 April 2018 - NW545

Profile picture: Matiase, Mr NS

Matiase, Mr NS to ask the Minister of Health

(a) What is the (i) name, (ii) location and (iii) patient capacity of each clinic which does not offer pharmaceutical services and (b) why?

Reply:

There is no clinic that does not offer pharmaceutical services in this country.

END.

23 April 2018 - NW706

Profile picture: Vos, Mr J

Vos, Mr J to ask the Minister of Communications

(1) Whether her department has a sexual harassment and assault policy in place; if not, (a) why not and (b) by what date will her department have such a policy in place; if so, (i) how are reports investigated and (ii) what are the details of the consequence management and sanctions stipulated by the policy; (2) (a) what is the total number of incidents of sexual harassment and assault that have been reported in her department (i) in each of the past three financial years and (ii) since 1 April 2017, (b) what number of cases were (i) opened and concluded, (ii) withdrawn and (iii) remain open based on the incidents and (c) what sanctions were issued for each person who was found to have been guilty?

Reply:

1. Yes, the department has a Sexual Harassment Policy in place.

a) Not Applicable

b) (i) and (ii) not applicable

2. The department did not have any incidents of sexual harassment and assault reported in each of the past three financial years, including 1 April 2017.

a) (i) and (ii) not applicable

b) (i), (ii) and (iii) not applicable

c) Not Applicable

23 April 2018 - NW777

Profile picture: Nolutshungu, Ms N

Nolutshungu, Ms N to ask the Minister of Health

What are the ten leading causes for admission to a healthcare facility in the Harry Gwala District Municipality in KwaZulu-Natal in the 2016-17 financial year?

Reply:

Attached is the latest detailed Burden of Disease profile for Harry Gwala District Municipality for the period 2010 to 2015 by age and gender.

END.

23 April 2018 - NW925

Profile picture: Madisha, Mr WM

Madisha, Mr WM to ask the Minister of Justice and Correctional Services

Whether he has been informed that Advocate (details furnished) continues to serve as the Interim Board Chairperson of the Passenger Rail Agency of South Africa (Prasa) after being appointed as a Judge of the High Court; if not, what is the position in this regard; if so, what are the relevant details; (2) Whether he has found that Advocate (details furnished) service on the Interim Board of Prasa constitutes a breach of the Judicial Code of Conduct?

Reply:

1. I have been advised that the Judge was appointed as the Chairperson of the Interim Board of the Passenger Rail Agency of South Africa (PRASA) in October 2017 prior to her appointment by the then President of the Republic of South Africa as a Judge of the Gauteng Division of the High Court. Her appointment as a Judge was effective from 01 January 2018 but due to her position as the Chairperson of the Interim Board of PRASA, the Judge did not assume her position as a Judge of the Gauteng Division of the High Court. She requested the Judge President of the Gauteng Division of the High Court, to request me to approach the President with a request that her appointment date be deferred to 1 April 2018. Whilst she was the Chairperson of the Interim Board of PRASA, the Judge never sat nor carried any judicial functions. I have been informed that she has subsequently resigned as Chairperson of the Interim PRASA Board with effect from 16 March 2018.

2. It is not within my purview to determine whether a conduct of a Judge constitutes a breach of the Code of Judicial Conduct. The responsibility to determine whether a Judge has committed a breach of the Code of Judicial Conduct is vested upon the Judicial Conduct Committee established in terms of section 8 of the Judicial Service Commission Act, 1994 (Act no 9 of 1994) (JSC Act). Additionally, Article 2 of that Code of Judicial Conduct is clear as it provides that ‘any wilful or gross negligent breach of the Code is a ground upon which a complaint against a Judge may be lodged in terms of section 14(4)(b) of the JSC Act. This simply means that if any determination has to be made about the conduct of the Judge, a complaint that complies with the provisions of section 14 of the JSC Act, must first be lodged with the Judicial Conduct Committee setting out the grounds upon which the complaint is based. There is currently no complaint lodged with the Judicial Conduct Committee about Judge’s conduct.

23 April 2018 - NW532

Profile picture: De Freitas, Mr MS

De Freitas, Mr MS to ask the Minister of Transport

(1)With reference to the construction of the N1 bypass through extension 4 Nancefield outside Musina to Beitbridge, what (a) is the (i) budget and (ii) timeframe of the contract and (b) are the names of the contractors; (2) (a) what is the total number of households that are affected, (b) where are the affected households being relocated to and (c) what other compensation was offered to the affected households?

Reply:

(1) (a) (i) Construction contract award value is R487 279 565,59 excluding CPA and VAT.

(ii) The 30 month construction contract commenced on 16 March 2016 and was scheduled to be completed by 15 September 2018. The contractor is however currently behind schedule and now only forecasts to complete in November 2019, with associated applicable contractual penalties to be applied by SANRAL.

(b) The contractor is Basil Read Limited

(2) (a) A total of 30 households in Musina Nancefield Ext 4 are affected due to their houses been within the new road reserve.

(b) The affected households are provided with new houses in Musina Nancefield Ext 10.

(c) Ownership of the affected stands vests with Musina local municipality. SANRAL compensated the municipality for the affected stands as well as for the new stands identified by the municipality. SANRAL is in the process of constructing new houses to all applicable national standards on the new stands at SANRAL’s cost. Compensation values per affected property have been determined by independent Professional Valuers appointed by SANRAL through negotiations with households and the municipality. The affected households also agreed to R3000 per household compensation for relocation costs to be paid by SANRAL.

23 April 2018 - NW122

Profile picture: King, Ms C

King, Ms C to ask the Minister of Health

Whether, with reference to the research conducted by the University of Cape Town’s molecular endrinologist which found that the contraceptive Depro Provera increases the risk of HIV, his department has conducted its own study to find out whether the synthetic hormone could affect the body’s immune system and increase the risk of contracting HIV; if not, why not; if so, what were the findings?

Reply:

The National Department of Health is aware of the study that was published in January 2018 which were based on animal studies. The possibility of DMPA being associated with HIV acquisition has been discussed by the World Health Organisation since 2012. South African experts have been part of these discussions. The studies presented at meetings of the World Health Organisation were not based on randomised clinical trials but on observational studies. In order to get conclusive evidence that DMPA definitely facilitates HIV acquisition, a number of donors, with the support of the National Department of Health commissioned the ‘Evidence for Contraceptive Options and HIV Outcomes’ Study (ECHO) in 2016 with results expected in 2019.

As well, in April 2017, the Department convened a group of experts in contraception to review the data on DMPA and HIV acquisition. These experts recommended the following: (a) that women must be provided with the full range of contraceptives and they must be counselled on the advantages and disadvantages of each to enable them to make the best possible decision; and that (b) regardless of which contraceptive method women chose, they must be informed about the importance of dual protection – this means consistent use of male or female condoms together with a contraceptive of their choice. This reinforced the policy decision taken earlier and included in the National Contraception and Fertility Planning Policy and Service Delivery Guidelines which the Department has been implementing since 2014.

The Department is committed to continue to monitor the research as well as World Health Organisation guidance on the use of DMPA and take appropriate decisions based on evidence.

END.

23 April 2018 - NW97

Profile picture: Hadebe, Mr TZ

Hadebe, Mr TZ to ask the Minister of Communications

With reference to the reply to question 1958 on 16 October 2017, (a) which trade exchanges are currently in dispute, (b) what amounts are associated with each trade exchange and (c) which trade exchanges are currently before the courts?

Reply:

a) Currently there are no trade exchanges before the courts, but there exists a dispute which is not before the courts yet.

The background briefly:

The South African Broadcasting Corporation SOC Limited (“SABC”) through Metro FM concluded a Trade Exchange Agreement (“Agreement”) with RBA Developments JHB (Proprietary) Limited (“RBA”) for the exchange of value added services set out in Annexure “A” and Schedules II, III and IV of the Agreement. The salient terms of the Agreement are as follows:

  • The Agreement commenced on 08 August 2016;
  • The Agreement will terminate on 08 October 2016;
  • The parties to the Agreement are the SABC and RBA;
  • In terms of the Agreement the parties would perform the obligations set out in Annexure “A” including the deliverables set out in the trade exchange items schedule. A copy of the Agreement is attached herewith and marked as “Annexure A”.

b) The trade exchange value is R3 450 749.68 including VAT.

In terms of the Agreement, the parties agreed to jointly work together in delivering a fully furnished house as a prize giveaway pursuant to a competition to be run by Metro FM for its listeners. To this end each of the parties undertook to perform certain obligations to ensure the successful implementation of the competition and delivery of the house to the competition winner. The dispute is therefore that RBA was liquidated and MSP, which took over and agreed to step in and assist in completing the house and handing it over to the completion winner is now reneging on its initial undertaking.  This has resulted in the house not having been handed over to the competition winner despite that the house was long completed.

Metro FM has received a demand from Legal Wise representing the competition winner claiming a handover of the house to the winner.

c) Save for the demand from Legal wise, no court pleadings have been served on the SABC yet. We are still in the process of engaging with MSP to try and resolve the matter amicably by handing over the house to the competition winner.

23 April 2018 - NW1010

Profile picture: Nolutshungu, Ms N

Nolutshungu, Ms N to ask the Minister of Basic Education

What amount in funding is required (a) to train teachers to fill existing vacancies and (b) for future needs of new schools to be built?

Reply:

a) Budgeting for provisioning of educators is done in terms of the normal government budgeting processes. On an annual basis, each Member of the Executive Council (MEC) for Education declares a basket of posts his/her respective Provincial Education Department, based on the available budget. Such posts are then distributed to schools using the post provisioning model. Therefore, vacancies that exist at any point are part of the declared post establishment and are funded and there is no additional amount of funding required to fill existing vacancies.

b) Requirements for funding for infrastructure is based on the Regulations Relating to Minimum Norms and Standards for Public School Infrastructure. As at the publication of the Norms and Standards, a shortfall of R 182 billion was estimated to address new schools and new spaces to be provided to bring all schools to optimum functionality. This includes provision of new education and curricular spaces, education support areas as well as administrative spaces. The sector is planning to conduct a condition assessment of all schools to determine the current backlog and calculate the resultant funding required.

 

QUESTION: NA 1010- I

COMPILER:

MS S GEYER (3740)

CD/TE

DATE:

MR ER MAFOKO

EXT: X 4317

DATE:

DR G WHITTLE

A/DDG: SECTOR INFRASTRUCTURE MANAGEMENT

DATE:

MS P TYOBEKA

ACTING DIRECTOR–GENERAL

DATE:

QUESTION NA 1010- I APPROVED/ NOT APPROVED/ AMENDED

MR ME SURTY, MP

DEPUTY MINISTER

DATE:

QUESTION: NA 1010- I APPROVED/ NOT APPROVED/ AMENDED

MRS AM MOTSHEKGA, MP

MINISTER

DATE:

23 April 2018 - NW968

Profile picture: Cardo, Dr MJ

Cardo, Dr MJ to ask the Minister of Economic Development

(1)(a) What number of (i) case backlogs does the Competition Commission have and (ii) days has each case been backlogged for, (b) what was the average time line, in days, from receiving a complaint to resolving a case in (i) 2015, (ii) 2016 and (iii) 2017 and (c) how does the commission monitor the (i) settlement agreements reached and (ii) progress on each agreement; (2) have any cases been referred to the National Prosecuting Authority for prosecution; if so, what are the details of the cases

Reply:

1. (a) What number of (i) case backlogs does the Competition Commission have and (ii) days has each case been backlogged for, (b) what was the average time line, in days, from receiving a complaint to resolving a case in (i) 2015, (ii) 2016 and (iii) 2017 and (c) how does the commission monitor the (i) settlement agreements reached and (ii) progress on each agreement

The Competition Commission advises that it has a total of 64 cases on backlog in cartel matters, with the periods of backlog differing by case, with the complexity of cases largely driving the period of the backlog.

The following table provides information on the average time taken for different cartel investigations as well as enforcement/other abuse of dominance and restrictive practices, for the past three years:

Category

Average no. of days to complete all cases

 

2015/16

2016/17

2017/18

Cartels

1044 days

684 days

1061 days

Enforcement Other- abuse of dominance, restrictive practices

396 days

329 days

254 days

All settlement agreements concluded between the Competition Commission (“the Commission”) and respondent firms are presented to the Competition Tribunal (“Tribunal”) for confirmation as consent orders of the Tribunal in terms of section 49D of the Competition Act 89 of 1998, as amended (“the Act”). Once so confirmed by the Tribunal, a consent order may in terms of section 64 of the Act, be served, executed and enforced as if it were an order of the High Court.

Where a settlement agreement contains an on-going commitment or undertaking by a respondent firm to pay penalties or to perform remedial action, performance is monitored by the legal and economic teams of the Commission.

(2) Have any cases been referred to the National Prosecuting Authority for prosecution; if so, what are the details of the cases?

The Commission has referred certain cases to the relevant criminal investigation agency for criminal investigation. The Commissioner advises that further details of the cases cannot be disclosed at this stage because they are subject to ongoing criminal investigation.

-END-

23 April 2018 - NW567

Profile picture: Mokoena, Mr L

Mokoena, Mr L to ask the Minister of Health

(a) What is the (i) name, (ii) location and (iii) patient capacity of each clinic that does not have administrative support and (b) what is the reason for this in each case?

Reply:

(a) All clinics have administrative support.

(b) Not applicable.

END.

23 April 2018 - NW972

Profile picture: Mbabama, Ms TM

Mbabama, Ms TM to ask the Minister of Arts and Culture

How much land does (a) his department and/or the entity reporting to him (i) own, (ii) have exclusive rights to and / or (iii) lease from the State to (aa) use and / or (bb) occupy? NW1065E

Reply:

(a) (i) the department does not own land

(ii) South African resources agency has ownership of the land listed below:

ITEM

NO.

PRO PERTY NAME

LACATION

PROPERTY EXTENT

PROPERTY USE/INTENDED USE

EASTERN CAPE

1

The Lookout

Kirkwood

District

3 947m2

Memorial and Grave site

2

Old Congregational

Church

Cradock

1 753m2

Church used by the local community

3

Mooimeisiesfontein

Riebeeck East

69 156 m2

Main building leased; Repurposing concepts in process of being determined for socio-economic benefit for the community

4

Old Gaol

Grahams town

3 736 m2

SAHRA office; Portion of the property vacant for leasing

5

Old Residency

King Williams Town

10746 m2

Vacant property; Best use concepts in process of being determined for State use with Dept. of Public Works

6

Concentration Camp Garden of Remembrance

Aliwal North

5 312m²

Memorial and Cemetery

FREE STATE

7

Burger Monument

Edenburg

52 589m²

Memorial

KWAZULU NATAL

8

Old Fort

Durban

20 703m²

Public Open Space

9

Blarney Cottage

Richmond

2.4571ha

Vacant; Engagements in process with the Richmond Municipality to determine best use concepts for socio-economic benefits to the community

10

Birthplace of Louis Botha

Greytown

645m²

Memorial

11

Spioenkop Battlefield

Bergville

46.7127ha

Memorial

12

Elandslaagte Memorial

Klip River District

149m²

Memorial

13

Piet Retief Grave

Ulundi

4307m²

Grave site,memorial

LIMPOPO

14

Moordfift Monument

Mokopane

132m²

Memorial

15

Old English Fort

Polokwane

18323m²

Memorial

16

Verdun Ruins

Soutpansberg

3789m²

Archeological site

17

Mapochs Caves

Roossenekal

63.1100ha

Archeological site

MPUMALANGA

18

Krugerhof

Waterval Onder

440m²

Museum

NORTH WEST

19

Old Powder Magazine

Potchefstroom

70m²

Monument

20

Old Fort & Cemetery

Potchefstroom

3 735m²

Memorial, Cemetery

21

Site of Livingstone`s House

Marico District

343m²

Ruins, natural site

NORTHERN CAPE

22

Union Masonic

Kimberely

426m²

Use of building by local church

WESTERN CAPE

23

Granite lodge

Cape Town CBD

1505m²

SAHRA Head Office

24

Wouter Wessels Vault

Green point

331m²

Vault

25

Vlakenberg Manor

Observatory

1.1456ha

Leased for portion of a hotel and restaurant

26

Van Riebeeck`s Hedge

Bishopscourt

19 151m²

Museum; Repurposing of property for conference facilities

27

Het Posthuys Museum

Muizenberg

1 977m²

Museum; Repurposing of property for conference facilities

28

Welcome Cottage

Glencairn

2 885m²

Repurposing for best use concept in process; Engagement with DPW for potential State use

29

Hugo Family Vault

Simons Town

1 042m²

Vault

30

Dal Josafat Farm

Paarl

232.5850ha

Buildings are leased; Repurposing of property for socio-economic benefit; Engagement with DPW for the best use concept; Engagement with local municipality for the best use concepts

31

Onderdal School

Paarl

8 728m²

SAHRA site office; Repurposing of property in process with DPW.

32

Kleinbosch Cemetery

Paarl

1 065m²

Cemetery

33

Groenenberg School

Wellington

8 565m²

Vacant; Repurposing concepts for community benefit in process with DPW

34

Tulbagh Erf 56

Tulbagh

4 479m²

Community Vegetable garden

35

Tulbagh Erf 255

Tulbagh

4 746m²

Open Garden for Community use

36

Struisbaai Fisherman Cottages

Struisbaai

17 043m²

Repurposing of property into holiday cottages for leasing

The head office which housed the Department and the following entities National Film and Video Foundation (NFVF); national Heritage Council (NHC) and the Pansalb are leasing their buildings from the Private persons.

All other entities occupy government properties.

23 April 2018 - NW697

Profile picture: Van Damme, Ms PT

Van Damme, Ms PT to ask the Minister of Communications

Whether BrandSA conducted any studies to determine the impact of the new visa regulations on the country’s tourism; if not, why not; if so, what are the (a) relevant details and (b) findings?

Reply:

No, (a) and (b) because Brand South Africa interfaces with and relies on research conducted by the Department of Tourism and South African Tourism.

23 April 2018 - NW98

Profile picture: Hadebe, Mr TZ

Hadebe, Mr TZ to ask the Minister of Communications

(1) With reference to the reply to question 1181 on 16 October 2017 and the annual report of the SA Broadcasting Corporation (SABC) which does not provide a detailed breakdown of the information requested, (a) which (i) officials from her department and (ii) officials and Board members from (aa) the SABC and (bb) each entity reporting to her were in Cape Town for the duration of the inquiry of the Ad Hoc Committee on SABC, (b) on which dates was each individual in Cape Town, (c) what was the cost for each specified individual to be in Cape Town, (d) what class of travel did each specified individual use to attend the SABC inquiry, (e) what accommodation costs were incurred and (f) in which hotel(s) did the specified individuals stay; (2) whether any costs will be recovered from those individuals who were in Cape Town for the duration of the SABC inquiry, but did not attend its meetings?

Reply:

DEPARTMENT OF COMMUNICATIONS (DOC)

1. 

a) (i) Mr Tshegofatso Kgarabjang.

a) 6-9 December 2016; 12-15 December 2016; and 19 January 2017.

b) The total cost incurred in attending the SABC inquiry is R27 907.10.

c) Ecomony class flight was utilised.

e) The cost incurred for accommodation is R1320 for one night on 19 January 2017.

f) Protea hotel in Seapoint.

2. Mr Kgarabjang attended all the sessions of the SABC inquiry when he was in Cape Town and as such no cost was recovered from him.

BRAND SOUTH AFRICA (BSA)

1. Not Applicable

a).Not Applicable

i) Not Applicable

ii) Not Applicable

aa) Not Applicable

bb) Not Applicable

b) Not Applicable

c) Not Applicable

d) Not Applicable

e) Not Applicable

f) Not Applicable

2. Not Applicable

FILMS AND PUBLICATIONS BOARD (FPB)

1. Not Applicable

a). Not Applicable

i) Not Applicable

ii) Not Applicable

aa) Not Applicable

bb) Not Applicable

b) Not Applicable

c) Not Applicable

d) Not Applicable

e) Not Applicable

f) Not Applicable

2. Not Applicable

MEDIA AND DIVERSITY DEVELOPMENT AGENCY (MDDA)

1. Not Applicable

a). Not Applicable

i) Not Applicable

ii) Not Applicable

aa) Not Applicable

bb) Not Applicable

b) Not Applicable

c) Not Applicable

d) Not Applicable

e) Not Applicable

f) Not Applicable

2. Not Applicable

INDEPENDENT COMMUNICATIONS AUTHORITY OF SOUTH AFRICA (ICASA)

(1) (a) (i) to (1) (a) (ii) Not applicable for ICASA

(aa) Not applicable for ICASA

(bb) ICASA was requested to present to the Ad-Hoc Committee on SABC. Councillor Batyi and Mr. Willington Ngwepe (COO) represented ICASA.

(b) 7 December 2016

(c) Total amount incurred was R15, 228 for flights only.

(d) Economy Class.

(e) No accommodation costs were incurred.

(f) No accommodation costs were incurred.

(2) Not applicable, both officials attended the Meeting.

SOUTH AFRICAN BROADCASTING CORPORATION (SABC)

1. (ii) Refer to the attached table below.

2. No, as all employees listed below travelled on official SABC business, namely the Adhoc Inquiry held to establish the fitness of the SABC Board to hold office.

____________________

Mr Thabiso Thiti

Acting Director-General

Date:

Approved/ Not approved

_______________________________

Ms Nomvula Mokonyane

Minister

Date:

Name

Departure date

Return Date

Duration

Flight Name'

Amount

Hotel

Amount

Car rental

Amount

Total

George Hlaudi Motsoeneng

2016-12-06

2016-12-09

3

SAA/BA

9 322,07

Hilton Hotel

10 706,14

 

-

20 028,21

James Rogers Aguma

2016-12-06

2016-12-09

3

SAA/BA

9 322,07

Hilton Hotel

4 276,32

Avis Car Rental

2 588,50

16 186,89

James Rogers Aguma

2016-12-14

2016-12-15

1

SAA/BA

6 394,67

African Pride Crystal Towers

7 785,72

Avis Car Rental

1 062,88

15 243,27

Audrey Maleshane Raphela

2016-12-12

2016-12-14

2

Kulula Airways

5 692,74

African Pride Crystal Towers

4 275,79

 

-

9 968,53

Bessie Lillian Tugwana

2016-12-01

2016-12-03

2

British Airways

7 543,97

African Pride 15 on Orange

3 989,64

Avis Car Rental

1 943,97

13 477,58

Bessie Lillian Tugwana

2016-12-12

2016-12-14

2

British Airways

7 503,62

African Pride Crystal Towers

2 858,85

Europ car Rental

4 034,93

14 397,40

Ayanda Mkhize

2016-12-12

2016-12-15

3

South African Airways

4 005,72

African Pride Crystal Towers

3 740,79

Avis Car Rental

2 201,51

9 948,02

Jacob Johannes Potgieter

2016-12-07

2016-12-09

2

South African Airways

4 005,72

 

-

 

-

4 005,72

Jacob Johannes Potgieter

2016-12-13

2016-12-15

2

British Airways

4 963,62

African Pride Crystal Towers

1 246,93

Avis Car Rental

3 266,85

9 477,40

Mohlolo Lephaka

2016-12-05

2016-12-09

4

British Airways

7 543,97

African Pride Crystal Towers/Premier Hotel

12 862,28

Avis Car Rental

3 893,49

24 299,74

Nomsa Penlope Mhlanga

2016-12-06

2016-12-09

 

South African Airways

5 302,04

African Pride Crystal Towers

3 842,10

   

9 144,14

Nomsa Penlope Mhlanga

2016-12-12

2016-12-15

 

South African Airways

5 285,72

African Pride Crystal Towers

3 740,79

   

9 026,51

Keobokile Edwin Mosweu

2016-12-06

2016-12-07

1

South African Airways

5 285,72

Hilton Hotel

3 684,21

Avis Car Rental

897,66

9 867,59

Keobokile Edwin Mosweu

2016-12-13

2016-12-15

2

SAA/BA

6 233,62

African Pride Crystal Towers

2 493,86

 

-

8 727,48

Alwyn Burger Kloppers

2016-12-12

2016-12-14

2

South African Airways

4 515,72

African Pride Crystal Towers

2 493,86

Avis Car Rental

818,00

7 827,58

Zakir Allie Rawoot

2016-12-06

2016-12-09

3

SAA/BA

6 428,00

African Pride Crystal Towers

14 194,75

Avis Car Rental

4 270,99

24 893,74

Zakir Allie Rawoot

2016-12-11

2016-12-15

4

SAA/BA

9 047,53

African Pride Crystal Towers

4 987,72

Avis Car Rental

2 159,89

16 195,14

Theresa Geldenhuys

2016-11-27

2016-12-02

 

British Airways

7 563,26

African Pride 15 on Orange

15 144,78

Avis Car Rental

5 227,67

27 935,71

Theresa Geldenhuys

2016-12-01

2016-12-12

 

British Airways

7 543,96

African Pride Crystal Towers/15 on Orange

53 334,76

Avis Car Rental

14 774,28

75 653,00

David Sizwe Vilakazi

2016-11-27

2016-12-02

6

British Airways

7 543,96

African Pride 15 on Orange

9 404,61

Avis Car Rental

3 546,18

20 494,75

David Sizwe Vilakazi

2016-12-12

2016-12-15

3

South African Airways

5 285,72

African Pride Crystal Towers

3 740,79

Europ car Rental

3 252,17

12 278,68

David Sizwe Vilakazi

2016-12-06

2016-12-09

3

South African Airways

9 053,85

African Pride Crystal Towers

3 740,79

Avis Car Rental

2 617,27

15 411,91

David Sizwe Vilakazi

2017-02-16

2017-02-16

0

South African Airways

6 350,81

 

-

Avis Car Rental

1 042,51

7 393,32

Sello Emanuel Xama

2016-12-06

2016-12-08

2

South African Airways

4 332,04

African Pride Crystal Towers

3 712,20

   

8 044,24

Lindiwe Vuyelwa Bayi

2016-11-27

2016-12-02

5

British Airways

7 563,26

African Pride 15 on Orange

9 649,15

   

17 212,41

Lindiwe Vuyelwa Bayi

2016-12-05

2016-12-09

4

British Airways

10 199,98

African Pride Crystal Towers

4 125,79

BROAD HORIZON TOURS & TRANSPORT

1 200,00

15 525,77

Lindiwe Vuyelwa Bayi

2016-12-12

2016-12-15

3

British Airways

7 503,62

African Pride Crystal Towers

11 227,79

 

-

18 731,41

Mbulaheni Obert Maguvhe

2016-12-04

2016-12-09

5

British Airways

5 758,88

African Pride Crystal Towers

10 500,48

 

-

16 259,36

Mbulaheni Obert Maguvhe

2016-12-11

2016-12-14

3

South African Airways

5 275,72

African Pride 15 on Orange

6 600,00

 

-

11 875,72

Andre Webber

2016-12-06

2016-12-09

3

South African Airways

5 302,04

The residence Imvusa Park

6 578,95

 

-

11 880,99

Andre Webber

2016-12-13

2016-12-15

2

British Airways

4 963,62

African Pride Crystal Towers

1 246,93

 

-

6 210,55

Mosimanegape Daniel Mongale

2016-12-11

2016-12-15

2

South African Airways

4 515,72

African Pride Crystal Towers

4 321,28

 

-

8 837,00

Florence Nomathemba Buhlalu

2016-12-04

2016-12-09

5

South African Airways

5 758,88

African Pride Crystal Towers

9 378,74

Avis Car Rental

5 043,00

20 180,62

Florence Nomathemba Buhlalu

2016-12-11

2016-12-15

4

South African Airways

5 275,72

African Pride 15 on Orange

5 989,49

First Car Rental

2 202,97

13 468,18

Mbulaheni Obert Maguvhe - Lucky Thekiso

2016-12-11

2016-12-15

4

British Airways

7 503,62

African Pride Crystal Towers

6 564,03

First Car Rental

1 381,31

15 448,96

Mbulaheni Obert Maguvhe - Lucky Thekiso

2016-12-05

2016-12-09

4

British Airways

7 543,97

African Pride Crystal Towers - reflected on Theresa Geldenhuys

Avis Car Rental

3 344,29

10 888,26

Mbulaheni Obert Maguvhe - Lucky Thekiso

2016-11-27

2016-12-03

6

South African Airways

6 447,30

African Pride 15 on Orange

19 386,00

Avis Car Rental

2 249,53

28 082,83

Mbulaheni Obert Maguvhe - Sikhumbuzo Nhantsi

2016-12-05

2016-12-09

4

British Airways

7 543,97

African Pride Crystal Towers - reflected on Theresa Geldenhuys

-

7 543,97

Mbulaheni Obert Maguvhe - Sikhumbuzo Nhantsi

2016-12-11

2016-12-15

4

SAA/BA

6 394,67

African Pride Crystal Towers

5 307,89

 

-

11 702,56

Mbulaheni Obert Maguvhe - Kgomotso Mathipa

2016-12-05

2016-12-09

4

SAA/BA

6 428,00

African Pride Crystal Towers - reflected on Theresa Geldenhuys

-

6 428,00

Mbulaheni Obert Maguvhe - Kgomotso Mathipa

2016-12-12

2016-12-15

3

SAA/BA

7 396,25

African Pride Crystal Towers

4 689,04

 

-

12 085,29

Mbulaheni Obert Maguvhe - Jimmy Hlongwane

2016-11-27

2016-12-03

6

British Airways

10 238,58

African Pride 15 on Orange

19 513,00

 

-

29 751,58

Mbulaheni Obert Maguvhe - Jimmy Hlongwane

2016-12-05

2016-12-09

5

British Airways

7 543,97

African Pride Crystal Towers - reflected on Theresa Geldenhuys

-

7 543,97

Mbulaheni Obert Maguvhe - Matthwes Mathipa

2016-11-27

2016-12-02

5

British Airways

10 219,28

African Pride 15 on Orange

15 659,00

 

-

25 878,28

Totals

       

295 447,17

 

316 995,24

 

73 019,85

685 462,26

                     

23 April 2018 - NW89

Profile picture: Motau, Mr SC

Motau, Mr SC to ask the Minister of Communications

(1) (a) Why was the Northern Cape chosen for the Digital Terrestrial Television (DTT) migration roll-out and (b) what is the progress in this regard;(2) what are the major challenges that her department faces with regard to the DDT roll-out in the (a) country and (b) Northern Cape; (3) what number of set-top boxes (a) have been installed and (b) must still be installed in each province; (4) how far is her department behind schedule with the DTT migration roll-out; (5) how does the Government intend to support content development for the digital space created by digital migration and the roll-out of DTT?

Reply:

1. (a) The Northern Cape hosts part of the international Square Kilometre Array (SKA), which is an international radio telescope project undertaken in collaboration with other countries including the UK and Australia. Analogue television transmissions produce high levels of interference and as such they have to be switched off and replaced with digital television transmissions via satellite.

(b) To date, all qualifying households in the core towns within a Square Kilometre Array (SKA) have been connected to the digital platform. Subsequent to the installations of devices to all households’ in the core towns of the SKA; including Carnarvon, Vanwyksvlei, Brandvlei, Williston and Vorsburg; analogue transmission services have since been switched off. However, analogue transmission services could not be switched in other areas of the SKA due to households that do not qualify for government subsidised decoders.

2. (a) The major challenges relates to the lack of resources mainly funding.

(b) Majority of the areas in the Northern Cape are covered by Satellite network and currently, there is no stock to distribute to the qualifying registered households.

3.  A table below present the statistics as at 31 March 2018.

PROVINCES

ESTIMATED

INDIGENTS HOUSEHOLDS

(a)

TOTAL INSTALLATIONS

(b)

BALANCE

Northern Cape

111,559

41,687

69,872

Free State

341,306

104,051

237,255

Limpopo

562,980

24,686

538,294

Mpumalanga

455,867

40,292

415,575

KwaZulu Natal

860,786

40,399

820,387

Eastern Cape

538,633

10,946

527,687

North West

382,692

37,319

345,373

Western Cape

508,888

0

508,888

Gauteng

1,237,289

0

1,237,289

TOTALS

5,000,000

299,380

4,700,620

4. The department has not met the target in terms of

(a) the migration of five million qualifying households to receive government subsidised decoders;

(b) the migration of the majority of unsubscribed citizen who rely on the retail market to acquire migration devices

5. The Department is a policy maker and does not implement programmes on the ground. The department will ensure collaboration with relevant stakeholders such as the SABC and the industry to advocate for content development to feed the channels to be made available by digital migration. In 2018/19 the Department will develop a South African Audio-Visual content strategy to support the digital migration.

 

23 April 2018 - NW694

Profile picture: Van Dyk, Ms V

Van Dyk, Ms V to ask the Minister of Communications

(1) (a) What portion of Brand SA’s budget for the 2017-18 financial year was used for offices abroad and (b) what was the cost of running offices in each country (i) in each of the past three financial years and (ii) since 1 April 2017; (2) whether Brand SA will increase its budget for the 2018-19 financial year; if not, what is the position in this regard; if so, what are the relevant details; (3) what are the details of the top 10 countries targeted by Brand SA?

Reply:

1. (a) R21,375,360 14% of R154,910,000

(b) (i) China

2014/2015 = R2,761808

2015/2016 = R5,281,620

2016/2017 = R2, 846, 987

United States

2014/2015 = R2, 933,350

2015/2016 = R4, 072,220

2016/2017 = R4, 561,451

United Kingdom

2014/2015 = R5, 991,782

2015/2016 = R5, 365,610

2016/2017 = R2, 843,252

(ii) China (since 1 April 2017) = R3, 112,108

United States (since 1 April 2017) = R6, 892,777

United Kingdom (since 1 April 2017) = R5, 493,852

2. Yes, by 6%.

3. Not Applicable

23 April 2018 - NW698

Profile picture: Van Damme, Ms PT

Van Damme, Ms PT to ask the Minister of Communications

What are the relevant details of the campaigns that BrandSA will run in the first two quarters of the 2018-19 financial year, (b) where will the campaigns be run, (c) what number of persons will be reached and (d) what is the estimated budget in each case?

Reply:

(a)

(b)

(c)

(d)

(i) Play Your Part programme: programme designed to promote active citizenship amongst South African’s

a) Partnership with Sunday Times Generation Next which includes a conference and a media programme

b) Play Your Part programme through activations, radio, online TV

  1. National (Conference to be hosted in Gauteng)
  1. 12 million
  1. R3 390 000

(ii) Constitutional awareness: designed to promote Constitutional awareness as part of Outcome 14 requirements.

a) National Marketing campaign developed and executed on various media platforms (TV, radio and digital platforms)

b) On the ground stakeholder engagements in Western Cape, Eastern Cape, Limpopo, Gauteng and KwaZulu-Natal)

  1. National
  1. 8 million
  1. R4 690 000

(iii) Promotion of the Nation Brand on domestic and international platforms: promotion of the country and its positive attributes.

a) Marketing campaign promoting the Nation Brand targeting traffic at Airports pre and during the BRICS Summit.

b) Marketing campaign promoting the Nation Brand at Airports Telecommunication Union (ITU) Conference

c) Media partnership support

  1. Gauteng, KwaZulu-Natal and National (Media)
  1. Estimated reach 15 million

(iii)R 2 500 000

(iv) Domestic and international Research Analysis: analysis on performance of the Nation Brand produced and communicated online and through various PR driven media platforms

a) SA Inc project consultation on investor experience and Perceptions with business from the EU region.

b) Research engagement with BRICS

c) Pan-African Nation Brand University Dialogue.

  1. Domestic and international
  1. Estimated

5 000 000

iv) R3 500 000

(v) Stakeholder Programmes in collaboration with business, govt & civil society

  • Nelson Mandela Centenary
  • Investment Promotion Roundtables
  • Road Safety Campaign
  • Campus Dialogues
  • Schools Outreach
  • Thought Leadership Engagements
  1. National

Estimated Reach 5 000 000

  1. R6 500 000

(vi) International Reputation Management Campaign to promote country reputation

  1. China, US, UK, Germany, Russia
  1. Not applicable
  1. R4 400 000

vii) International Stakeholder relations engagements and Global South Africans Programme (South Africans in the diaspora)

  1. China, US, UK, Germany, Ghana
  1. Not applicable
  1. R3 300 000

viii) International & Domestic Media: CNN, BBC, CNBC Africa, EURONEWS, Local Radio, TV, Print and Online to support projects

North America, Europe, Asia, Africa, Middle East,

South Africa

  1. Estimated reach 2 000 000 000
  1. R15 000 000

23 April 2018 - NW403

Profile picture: Nolutshungu, Ms N

Nolutshungu, Ms N to ask the Minister of Health

(a) What number of doctors are currently suspended in (i) total and (ii) each province and (b) in each case, what is the (i) doctor’s place of employment, (ii) reason for the suspension and (iii) timeline of the suspension?

Reply:

(a) (i) Seven (7) doctors are suspended, as per table below.

PROVINCE

NUMBER

Eastern Cape

1

Free State

0

Gauteng

2

KwaZulu Natal

3

Limpopo

0

Mpumalanga

1

North West

0

Northern Cape

0

Western Cape

0

(b) The table below reflects the details in this regard

PROVINCE

(i) Place of Employment

(ii) Reason for suspension

(iii) Timelines

Eastern Cape

Livingstone Hospital

Sexual harassment

10/01/2018

Free State

N/A

N/A

N/A

Gauteng

Weskopies Mental Hospital

Sexual harassment

09/02/2018

 

Yusuf Dadoo

Sexual harassment

21/02/2018

KwaZulu Natal

Ngwelesana Hospital

Endangering life of patient and poor administration

12/10/2017

 

Prince Mshiyeni Hospital

Insubordination

12/02/2018

 

Prince Mshiyeni Hospital

Insubordination

12/02/2018

Limpopo

N/A

N/A

N/A

Mpumalanga

Witbank Hospital

Sexual harassment

15/01/2018

North West

N/A

N/A

N/A

Northern Cape

N/A

N/A

N/A

Western Cape

N/A

N/A

N/A

TOTAL

7

   

END.

23 April 2018 - NW262

Profile picture: Paulsen, Mr N M

Paulsen, Mr N M to ask the Minister of Agriculture, Forestry and FisheriesQUESTION

Number of farms is a certain company (name furnished) leasing in villages in and around Keiskammahoek, particularly in Lower and Upper Zingcuka, Lenye, Zanyokhwe and Mkhubiso; (2) Is the nature of support that they are receiving from his department and (c) are the reasons for supporting the specified company at the expense of broad-based agricultural production in Keiskammahoek?

Reply:

1. Rance Timber is not leasing land from communities or state land.

2. Neither the Department of Agriculture, Forestry and Fisheries nor the Eastern Cape Department of Rural Development and Agrarian Reform is supporting the said companies of Rance Timber. The only support that was given was in 2013 to producers and they were supported with production inputs.

23 April 2018 - NW346

Profile picture: Van Der Walt, Ms D

Van Der Walt, Ms D to ask the Minister of Basic Education

(a) What is the total amount that was (i) budgeted for and (ii) spent on her private office (aa) in each of the past three financial years and (bb) since 1 April 2017 and (b) what was the (i) remuneration, (ii) salary level, (iii) job title, (iv) qualification and (v) job description of each employee appointed in her private office in each of the specified periods?

Reply:

(a)

(aa) Financial year

(a)(ii) Budget

(a)(ii) Expenditure

2014/15

R 16 032 000

R 15 928 000

2015/16

R 15 214 000

R 15 203 000

2016/17

R 19 030 000

R 18 120 000

(bb) since 1 April 2017

R 14 068 000

R 14 247 000

     

2014/15

SURNAME

INITIALS

(b)(i)

(b)(ii)

(b)(iii)

(b)(iv)

(b)(v)

   

REMUNERATION

SALARY

LEVEL

JOB TITLE

QUALIFICATION

JOB

Motshekga

AM

R 2 211 937.00

16

Minister

Master’s Degree in Education

Minister

Sehlabelo

SP

R 988 152.00

14

Chief Director

Bachelor of Education Degree

Chief Of Staff of the Ministry

Khala

R

R 856 554.00

13

Director: Office Of The Minister

Bachelor of Arts Degree

Administrative Secretary

Mncube

W

R 819 126.00

13

Director: Office Of The Minister

B-Tech: Journalism

Media Liaison Officer

Mabua

RS

R 669 534.00

12

Deputy Director: Office Of The Minister

Senior Certificate

Private Secretary/Appointments Secretary

Van den Heefer

RPZ

R 856 554.00

13

Director: Office Of The Minister

BA Honours Degree

Parliamentary Officer

Skwatsha

JN

R 203 589.00

7

Principal Ministerial Typist

Senior Certificate

Secretary Receptionist

Mphigalale

P

R 157 701.00

6

Senior Secretary Grade III

Senior Certificate

Secretary Receptionist

Masote

O

R 123 738.00

5

Senior Messenger

National Diploma: Information Technology

Aid or Driver/Messenger

2015/16

SURNAME

INITIALS

(b)(i)

(b)(ii)

(b)(iii)

(b)(iv)

(b)(v)

   

REMUNERATION

SALARY

LEVEL

JOB TITLE

QUALIFICATION

JOB

Motshekga

AM

R 2 309 262.00

16

Minister

Master’s Degree in Education

Minister

Sehlabelo

SP

R 1 042 500.00

14

Chief Director

Bachelor of Education Degree

Chief Of Staff of the Ministry

Khala

R

R 903 663.00

13

Director: Office Of The Minister

Bachelor of Arts Degree

Administrative Secretary

Mncube

W

R 864 177.00

13

Director: Office Of The Minister

B-Tech: Journalism

Media Liaison Officer

Mabua

RS

R 727 149.00

12

Deputy Director: Office Of The Minister

Senior Certificate

Private Secretary/Appointments Secretary

Van den Heefer

RPZ

R 917 220.00

13

Director: Office Of The Minister

BA Honours Degree

Parliamentary Officer

Skwatsha

JN

R 221 106.00

7

Principal Ministerial Typist

Senior Certificate

Secretary Receptionist

Mphigalale

P

R 171 273.00

6

Senior Secretary Grade III

Senior Certificate

Secretary Receptionist

Masote

O

R 132 399.00

5

Senior Messenger

National Diploma: Information Technology

Aid or Driver/Messenger

2016/17

SURNAME

INITIALS

(b)(i)

(b)(ii)

(b)(iii)

(b)(iv)

(b)(v)

   

REMUNERATION

SALARY

LEVEL

JOB TITLE

QUALIFICATION

JOB

Motshekga

AM

R 2 309 262.00

16

Minister

Master’s Degree in Education

Minister

Sehlabelo

SP

R 1 084 599.00

14

Chief Director

Bachelor Of Education

Chief Of Staff of the Ministry

Khala

R

R 855 516.00

12

Deputy Director: Office Of The Minister

Bachelor of Arts Degree

Administrative Secretary

Mncube

W

R 898 743.00

13

Director: Office Of The Minister

B-Tech: Journalism

Media Liaison Officer

Mabua

RS

R 794 145.00

12

Deputy Director: Office Of The Minister

Senior Certificate

Private Secretary/Appointments Secretary

Van den Heefer

RPZ

R 855 516.00

12

Deputy Director: Office Of The Minister

BA Honours Degree

Parliamentary Officer

Skwatsha

JN

R 241 476.00

7

Principal Ministerial Typist

Senior Certificate

Secretary Receptionist

Mphigalale

P

R 187 059.00

6

Senior Secretary Grade III

Senior Certificate

Secretary Receptionist

Masote

O

R 144 591.00

5

Senior Messenger

National Diploma: Information Technology

Aid or Driver/Messenger

2017/18

SURNAME

INITIALS

(b)(i)

(b)(ii)

(b)(iii)

(b)(iv)

(b)(v)

   

REMUNERATION

SALARY

LEVEL

JOB TITLE

QUALIFICATION

JOB

Motshekga

AM

R 2 401 633.00

16

Minister

Master’s Degree in Education

Minister

Sehlabelo

SP

R 1 161 423.00

14

Chief Director

Bachelor Of Education

Chief Of Staff of the Ministry

Khala

R

R 917 970.00

12

Deputy Director: Office Of The Minister

Bachelor of Arts Degree

Administrative Secretary

Mncube

W

R 962 409.00

13

Director: Office Of The Minister

B-Tech: Journalism

Media Liaison Officer

Mabua

RS

R 864 903.00

12

Deputy Director: Office Of The Minister

Senior Certificate

Private Secretary/Appointments Secretary

Nkonyeni

NP

R 1 116 918.00

13

Director: Office Of The Minister

Post Graduate Diploma in Management

Parliamentary Officer

Skwatsha

JN

R 262 992.00

7

Principal Ministerial Typist

Senior Certificate

Secretary Receptionist

Mphigalale

P

R 203 721.00

6

Senior Secretary Grade III

Senior Certificate

Secretary Receptionist

Masote

O

R 157 491.00

5

Senior Messenger

National Diploma: Information Technology

Aid or Driver/Messenger

23 April 2018 - NW951

Profile picture: Purdon, Mr RK

Purdon, Mr RK to ask the Minister of Environmental Affairs

Whether, with reference to the restaurant and visitors complex that burnt down in November 2016 in the Tsitsikamma National Park, Storms River, any steps have been taken to rebuild the facility; if not, why not; if so, (a) what steps and (b) what are the timelines?

Reply:

a) The planning for the Tsitsikamma restaurant precinct development has been completed following the fire in November 2016 and is ready to be subjected to a tender process. After the restaurant was destroyed by the fire, SANParks decided to upgrade the entire restaurant precinct to include all infrastructure.

The project scope includes the following:

  • Restaurant that accommodates 250 seats
  • Curio shop with offices and stores
  • Information centre as first point of arrival for visitors
  • Multi use Boat house
  • General Amenities for visitors that includes play areas, picnic areas as well as beach showers and dressing areas
  • Bulk Services (Electricity, water and sewer)

b) It is envisaged that the tender and contracting process will take six months from May 2018 to October 2018. Construction is scheduled to commence in January 2019 after the peak tourism season. The estimated construction period is 18 months due to the difficult site and visitor management requirements, with estimated completion in September 2020.

The clients are being serviced from provided marquee since 10th December 2016

---ooOoo---

23 April 2018 - NW347

Profile picture: James, Ms LV

James, Ms LV to ask the Minister of Communications

(a) What is the total amount that was (i) budgeted for and (ii) spent on her private office (aa) in each of the past three financial years and (bb) since 1 April 2017 and (b) what was the (i) remuneration, (ii) salary level, (iii) job title, (iv) qualification and (v) job description of each employee appointed in her private office in each of the specified periods?

Reply:

a) (i) The private office does not have a separate budget from that of the Ministry.

(ii)The budget and the expenditure of the private office is included in the budget of the Ministry which is reflected in the Annual Reports of the 2014/15, 2015/16 and the 2016/17 financial years.

b) The remuneration of employees in the private office is included in the compensation of all employees in the department as reflected in the relevant annual reports.

The salary levels and job descriptions are in line with the guidelines provided by the Handbook for Members of the Executive as well as the Public Service Regulations.

23 April 2018 - NW531

Profile picture: De Freitas, Mr MS

De Freitas, Mr MS to ask the Minister of Transport

With regard to the Gillooly’s interchange in Gauteng and the applications for billboards erected on the SA National Roads Agency SOC Ltd properties such as bridges, (a) what is the total number of (i) applications that have been supported in each month, (ii) objections that have been lodged with the Ekurhuleni Metropolitan Municipality and (b) what were the reasons for (i) supporting and (ii) objecting the applications (aa) in the (aaa) 2014-15, (bbb) 2015-16 and (ccc) 2016-17 financial years and (bb) since 1 April 2017?

Reply:

Despite the presence of various billboards on bridges owned by SANRAL in Ekurhuleni Metropolitan Municipality, none of these where applied for with SANRAL nor approved by SANRAL. These billboards are illegal and should be removed, but SANRAL is prevented in doing so by the dispute resolution mechanisms provided for in Intergovernmental Relations Framework Act with Ekurhuleni Metropolitan Municipality (they illegally approved these billboards) and litigation relating to similar billboards with one of the transgressors. Please see detailed answers to questions below.

a) (i)

(aaa) 2014-2015 = No applications received by SANRAL, so none supported by SANRAL.

(bbb) 2015-2016 = No applications received by SANRAL, so none supported by SANRAL.

(ccc) 2016-2017 = No applications received by SANRAL, so none supported by SANRAL.

(bb) since 1 April 2017 = No applications received by SANRAL, so none supported by SANRAL.

(a) (ii)

(aaa) 2014-2015 = 2 objections lodged by SANRAL

(bbb) 2015-2016 = 13 objections lodged by SANRAL

(ccc) 2016-2017 = 22 objections lodged by SANRAL

(bb) since 1 April 2017 = 12 objections lodged by SANRAL

(b) (i)

(aaa) 2014-2015 = No applications received by SANRAL, so none supported by SANRAL.

(bbb) 2015-2016 = No applications received by SANRAL, so none supported by SANRAL.

(ccc) 2016-2017 = No applications received by SANRAL, so none supported by SANRAL.

(bb) since 1 April 2017 = No applications received by SANRAL, so none supported by SANRAL.

(b) (ii)

(aaa) 2014-2015 = Do not comply to section 48 and 50 of the SA National Roads Agency Limited and National Roads Act, 1998 (Act no. 7)

(bbb) 2015-2016 = Do not comply to section 48 and 50 of the SA National Roads Agency Limited and National Roads Act, 1998 (Act no. 7)

(ccc) 2016-2017 = Do not comply to section 48 and 50 of the SA National Roads Agency Limited and National Roads Act, 1998 (Act no. 7)

(bb) since 1 April 2017 = Do not comply to section 48 and 50 of the SA National Roads Agency Limited and National Roads Act, 1998 (Act no. 7)

23 April 2018 - NW1023

Profile picture: Sonti, Ms NP

Sonti, Ms NP to ask the Minister of Basic Education

What (a) number of (i) high schools and (ii) primary schools in each province do not offer healthcare services and (b) is the (i) location and (ii) name of each specified school?

Reply:

(a) and (b) The Intergrated School Health Programme (ISHP) is implemented by school health teams employed by the Department of Health (DoH) in provinces. The reach of the services and the package provided, is dependent on the availability and composition of these school health teams in each geographic area. The Department of Basic Education receives signed off collated data on the number of learners that have received services in the preceding quarter from the national Department of Health. The list of schools is not provided.

23 April 2018 - NW210

Profile picture: Lees, Mr RA

Lees, Mr RA to ask the Minister of Health

(1)With reference to his reply to question 1263 on 13 December 2017, has the overpayment of R 1 181 977,52 been recovered; if not, why not; if so, what are the details of (a) the repayment and (b) interest charged and paid to date; (2) whether any disciplinary action has been taken and/or criminal charges laid against any persons found to have been involved in the specified overpayment; if not, why was no disciplinary action taken and/or criminal charges laid; if so, what are the details of any disciplinary action taken and/or criminal charges laid against those responsible for the overpayment?

Reply:

(1) (a) The correct overpayment as per response 1263 of December 2017 is R1,196,482.92, not the R1,181,977.52 as stated above. Of the R1,196,482.82, an amount of R826,116.60 was for Commuted Overtime, which the previous response clarified that this was properly authorised and there is no overpayment.

The balance of R370,373.22 was for rural allowance which the official had continued earning even though he had moved to another institution. This is the amount that the employee raised as a grievance through his union that his transfer between the two institutions, included that the new salary package was to compensate the previous rural allowance. This matter as been followed up and no evidence of the agreement has been found. The employee was sent written communication to acknowledge the debt and to respond with a payment plan.

(b) As there had been a grievance that had to be attended, no interest has been charged, as the employee also needs to acknowledge the debt. Only when the debt is captured on BAS, the system will then calculate interest, and only if the debt type is interest bearing

(2) There has been no disciplinary action taken as the grievance needed to be attended to first.

The matter is now being followed up on why the rural allowance was not stopped by HR officials when the transfer was done, and then disciplinary action will be considered against HR officials on not stopping the rural allowance.

END.

23 April 2018 - NW101

Profile picture: Chetty, Mr M

Chetty, Mr M to ask the Minister of Human Settlements

How many title deeds were handed over to housing beneficiaries in each municipality in the Free State (a) in the 2016/17 financial year and (b) from 1 April 2017 up to the latest specified date for which information is available?

Reply:

(a)  + (b) The question has been referred to the Free State Province for a detailed reply. As soon as it is available, the Honourable Member will be provided with the reply.

23 April 2018 - NW238

Profile picture: Thembekwayo, Dr S

Thembekwayo, Dr S to ask the Minister of Health

What are the relevant details of the (a) name, (b) patient capacity and (c) location of each (i) hospital, (ii) clinic and (iii) other healthcare facility at (aa) national, (bb) provincial and (cc) municipal level?

Reply:

Attached is the schedule providing the details as requested.

END.

23 April 2018 - NW581

Profile picture: Nolutshungu, Ms N

Nolutshungu, Ms N to ask the Minister of Transport

By what date will his department scrap the failing e-toll system that privatises public roads and which motorists are refusing to pay?

Reply:

As things stand, there are no plans to scrap the e-toll system. However there are ongoing discussions at National and Provincial governments. Once decision has been reached and finalised it will be communicated.

23 April 2018 - NW530

Profile picture: De Freitas, Mr MS

De Freitas, Mr MS to ask the Minister of Transport

With regard to the Gillooly’s interchange in Gauteng and applications for billboard structures along roads, what is the total number of applications that (a) have been received in each month, (b)(i) were approved in each month and (ii) the reasons for approval in each case (c)(i) were rejected in each month and (ii) what are the reasons for rejection in each case (aa) in the (aaa) 2014-15, (bbb) 2015-16 and (ccc) 2016-17 financial years and (bb) since 1 April 2017?

Reply:

Despite the presence of various billboard structures at Gillooly’s Interchange, none of these where applied for with SANRAL nor approved by SANRAL. Please see detailed answers to questions below.

(aaa) 2014-2015 = No applications received by SANRAL with regard to the Gillooly’s.

(bbb) 2015-2016 = No applications received by SANRAL with regard to the Gillooly’s.

(ccc) 2016-2017 = No applications received by SANRAL with regard to the Gillooly’s.

(bb) since 1 April 2017 = No applications received by SANRAL with regard to the Gillooly’s.

(b)(i)

(aaa) 2014-2015 = No applications received, so none approved by SANRAL.

(bbb) 2015-2016 = No applications received, so none approved by SANRAL.

(ccc) 2016-2017 = No applications received, so none approved by SANRAL.

(bb) since 1 April 2017 = No applications received, so none approved by SANRAL.

(b)(ii)

(aaa) 2014-2015 = No applications received, so none approved by SANRAL.

(bbb) 2015-2016 = No applications received, so none approved by SANRAL.

(ccc) 2016-2017 = No applications received, so none approved by SANRAL.

(bb) since 1 April 2017 = No applications received, so none approved by SANRAL.

(c)(i)

(aaa) 2014-2015 = No applications received, so none rejected by SANRAL.

(bbb) 2015-2016 = No applications received, so none rejected by SANRAL.

(ccc) 2016-2017 = No applications received, so none rejected by SANRAL.

(bb) since 1 April 2017 = No applications received, so none rejected by SANRAL.

(c)(ii)

(aaa) 2014-2015 = No applications received, so none rejected by SANRAL

(bbb) 2015-2016 = No applications received, so none rejected by SANRAL

(ccc) 2016-2017 = No applications received, so none rejected by SANRAL

(bb) since 1 April 2017 = No applications received, so none rejected by SANRAL.