Question NW2308 to the Minister of Human Settlements

Share this page:

01 July 2022 - NW2308

Profile picture: Luthuli, Mr BN

Luthuli, Mr BN to ask the Minister of Human Settlements

(1)What are the details of all the housing contractors who have entered into business with Government in the past five financial years (2) Whether any of the contractors defaulted in the completion of any projects; if not what is the position in this regard. If so, what (a) number and (b) are the recorded reasons?

Reply:

1. The implementation of housing delivery as well as appointment of contractors is the function of the provinces. The list of contractors has been requested and obtained from the provinces since they are responsible for appointment and contract management.

The details of all the housing contractors who have entered into business with Government in the past five financial years in all provinces are as follows:

A total of 2 970 contractors have entered into business with Provinces. The details of those contractors per province are attached as Annexure A.

2. (a) 95 contractors defaulted in the completion of the projects; contractors that have not defaulted have completed or are still constructing the projects that are not yet complete.

(b) Reasons for defaulting include:

  • Poor performance by the contractor;
  • Lack of bulk infrastructure;
  • Contractor Cash flow challenges;
  • Untraceable beneficiaries;
  • Legal land requirements;
  • Replacements of beneficiaries;
  • Change of local authorities;
  • Scarcity and price escalation of building material;
  • Project surrendered due to cost escalation;
  • Covid-19 challenges;
  • Unbuildable sites and missing beneficiaries;
  • Delays with beneficiary administration;
  • Social issues;
  • Change of local authorities;
  • Delays in Water Licence (WULA) approval and variation order delays.

The details of defaulting contractors per province are attached as Annexure A.

PROVINCE

(1) NUMBER OF CONTRACTORS

(2a) NUMBERS

OF DEFAULTERS

(2b) SUMMARY OF REASONS

EC

818

4

Poor performance and cash follow constrains

FS

123

0

No defaulters reported by the Province

GP

97

3

Poor performance

KZN

652

62

Poor performance; Bulk infrastructure; Cash flow; Untraceable beneficiaries; Legal land requirements; Replacements of beneficiaries; Change of local authorities; Scarcity and price escalation of building material; Project surrendered due to cost escalation; Covid-19 challenges; Unbuildable sites and missing beneficiaries; Delays with beneficiary administration; Social issues; Change of local authorities; Delays in Water Licence (WULA) approval and Variation order delays

LP

400

14

Poor performance

MP

182

5

Contractors failed to commence with the work after site hand over and poor performance

NC

66

0

No defaulters reported by the Province

NW

285

0

No defaulters reported by the Province

WC

347

7

Poor performance and cash flow challenges

TOTAL

2 970

95