Questions and Replies
24 March 2023 - NW450
Mhlongo, Mr TW to ask the Minister of Human Settlements
(a)What total number of homeowners in Orange Farm township in Johannesburg have title deeds, (b) how does her department intend to issue title deeds to such homeowners and (c) what total number of outstanding title deeds must be issued in (a)Finetown; (b)Driezik Ext.1-2, 7(a), 8,9; (c) Lakeside; (d) Migson Manor; (e) Mountain View; (f) Fine Town Majazana and (g) Thulamntwana?
Reply:
a) The Department has received the following information from the Gauteng Department of Human Settlements regarding the delivery of title deeds in Orange Farm Township.
Orange Farm
Township |
Total No. of units |
Total registered |
Total not registered |
Total issued |
Orange Farm proper |
1218 |
1182 |
36 |
1182 |
Orange Farm Ext.1 |
3214 |
3042 |
172 |
3042 |
Orange Farm Ext.2 |
2942 |
2773 |
167 |
2773 |
Orange Farm Ext.3 |
806 |
607 |
199 |
607 |
Orange Farm Ext.4 |
425 |
269 |
156 |
269 |
Orange Farm Ext.6 |
1474 |
1399 |
75 |
1399 |
Orange Farm Ext.7 |
3741 |
3638 |
103 |
3638 |
Orange Farm Ext.8 |
2104 |
1941 |
163 |
1941 |
Orange Farm Ext.9 |
958 |
678 |
280 |
517 |
b) The Department has identified the delivery of title deeds as one of its uppermost priorities- To this end, it has set aside the commensurate budget and capacity that will upscale the delivery of title deeds.
The tables below provide an account for the title deeds that are outstanding in the townships mentioned below.
Finetown
Township |
Total No. of units |
Total registered |
Total not registered |
Total issued |
Remarks |
Finetown |
2063 |
0 |
0 |
0 |
|
Finetown Ext.1 |
110 |
0 |
0 |
0 |
Drieziek
Township |
Total No. of units |
Total registered |
Total not registered |
Total issued |
Remarks |
Drieziek |
284 |
259 |
25 |
201 |
|
Drieziek Ext.1 |
1562 |
0 |
1562 |
0 |
Awaiting opening of township register |
Drieziek Ext.2 |
394 |
348 |
46 |
286 |
|
Drieziek Ext.3 |
3024 |
2783 |
241 |
2916 |
|
Drieziek Ext.4 |
1923 |
1647 |
276 |
1784 |
|
Drieziek Ext.5 |
1574 |
1345 |
226 |
1460 |
|
Drieziek Ext.6 |
209 |
0 |
209 |
0 |
|
Drieziek Ext.7 |
0 |
0 |
0 |
0 |
Done by Province |
Drieziek Ext.8 |
0 |
0 |
0 |
0 |
Done by Province |
The Department will continue with efforts to source the information required on other townships that are not accounted for.
23 March 2023 - NW556
Khumalo, Dr NV to ask the Minister of Human Settlements
What are the relevant details of department’s (a) interventions and (b) plans to ensure that a balance exists between the conflict which often arises from the social, economical and environmental needs which are a result of the spatial planning of the past regime?
Reply:
a) A Programme is instituted in terms of Section 3(4) (g) of the Housing Act, 1997 (Act 107 of 1997), (“The Housing Act”) and is referred to as the National Housing Programme: Provision of Social and Economic Facilities. This Programme promotes the provision of certain basic social/community amenities and economic facilities within existing and new housing areas as well as within informal settlement upgrading projects in order to achieve social and economic development.
In addition, the development of the new Neighbourhood Planning and Design Guide (Red Book) supports the development of sustainable human settlements by providing practical information related to the planning and design of the services and infrastructure typically provided as part of a neighbourhood development project. The Red Book covers the following Planning and Design Guidelines addressing serviced sites:
i. Neighbourhood layout and structure;
ii. Public open space;
iii. Housing and social facilities;
iv. Transportation and road pavements;
v. Water supply;
vi. Sanitation;
vii. Storm water;
viii. Solid waste management;
ix. Electrical energy; and
x. Cross-cutting issues Planning and designing safe communities’ Universal design.
Furthermore, one hundred and thirty-six (136) Priority Human Settlements and Housing Development Areas (PHSHDA’s) have been declared to address the impact of past planning practices. The PHSHDAs aim to achieve a set of uniform, equitable and integrated development objectives, and outcomes. The PHSHDAs are aligned to the National Spatial Development Framework (NSDF), the Spatial Planning and Land Use Management Act (SPLUMA) and the Integrated Urban Development Framework which guide the development of planning instruments and seek to guide the Spatial Transformation efforts of government.
b) Housing is a concurrent function between National and Provincial Departments of Human Settlements which requires that all three spheres work closely together in planning and implementation of human settlements development.
In terms of the Division of Revenue Act (DORA) funding for the implementation of National Housing Programmes is allocated to Provincial Governments by the Minister on an annual basis. The grants are transferred to provinces who are required in terms of DORA to submit grant business plans wherein Programme funding will be prioritised and reserved by provincial governments from their annual funding allocation.
Based on the municipal IDPs and provinces MYHDP Provinces determine Programme funding for the Programme: Provision of Social and Economic Facilities to ensure that a balance exists between the conflict which often arises from the social, economical and environmental needs.
23 March 2023 - NW536
Makesini, Ms M to ask the Minister of Human Settlements
(1) What steps has she taken to ensure that those who were displaced by floods in the (a) Eastern Cape and (b) Gauteng are provided with housing?
Reply:
- A Response to the 2022 & 2023 Floods in the Eastern Cape
- In the Eastern Cape Province, the April 2022 disaster affected 4799 households wherein 2959 houses were destroyed, and the remainder were partially damaged. Households affected were mainly in OR Tambo; Alfred Nzo; Joe Gqabi; Chris Hani; Amathole Districts
- Because the partially destroyed homes were made up of mud houses, they are considered as requiring a total rebuild. The HDA completed the assessment of partially damaged houses in Alfred Nzo and OR Tambo regions and the report indicates that all those houses must be replaced with a permanent solution. Those households that are destitute would in the meantime receive TRUs.
- In the 2022/23 financial year, the Eastern Cape Province was allocated an amount of R84 million to address disaster incidents in the affected municipalities. The second tranche of R42 million will be disbursed once expenditure on the first tranche reaches 80%.
- To date, 931 Temporary Residential Units (TRUs) have been completed [435 units in Alfred Nzo and 496 units in OR Tambo Districts]. The HDA has appointed contractors to erect a further 1141 TRUs in OR Tambo, Chris Hani, Amathole and Joe Gqabi District Municipalities.
- In the 2022/23 financial year, the National Department of Human Settlements also approved an application from the Alfred Nzo District Municipality for the December 2021 disaster to the value of R16 million for the construction of 258 TRUs. 50% of funds (R8,3 million) were transferred in July 2022 however, thus far, only 47 Temporary Residential Units have been constructed.
- The reported reasons for the slow progress are heavy rainfall experienced in the affected areas and inaccessibility of sites due to terrain, inability of material suppliers to keep-up with the demand for the supply of the TRU wall cladding panels.
- In February 2023 the province was affected by heavy rains again. Assessment is underway. The Department of Human Settlements is in continuous discussions with the Province through the Joint Operations Committee to ascertain the number of households that require housing assistance and submit its application for evaluation, processing and approval of funding prior to the end of this financial year, or the province could reprioritise human settlements funding to address temporary housing for the affected households. The floods affected the following municipalities: Dr AB Xuma, Sakhiziswe, Emalahleni, Intsika Yethu and Enoch Mgijima.
- The Enoch Mgijima District Municipality has established a Joint Operations Committee with sector departments and other relevant stakeholders. The affected households that were mainly from the surrounding informal settlements were relocated to mass care centres around Queenstown, with the main one being the Gali Thembani Centre. An on-site inspection of the facility was conducted. It was established that the facility is of good quality and households are accommodated in family rooms with privacy. The province reported that of the 227 households accommodated at the facility. Plans are afoot to provide the households with TRUs in a site that has been utilised for TRUs during COVID19 relocation project.
b) A response to 2022 & 2023 Floods in Gauteng
- The Gauteng floods affected 3188 households where the majority was in the City of Johannesburg. The affected households in CoJ are 3096 where 2322 houses were partially destroyed. The West Rand District has 29 houses affected, where all were partially destroyed. Sedibeng District has 63 affected houses, where 25 were partially destroyed.
- A physical assessment and verification for all partially damaged houses is being finalised by the NHBRC. An application for funding shall be submitted as soon as this process is finalised. This will focus on assisting households on the repair of houses.
22 March 2023 - NW199
De Villiers, Mr JN to ask the Minister of Human Settlements
What are the details of the (a) destination and, (b) total cost for (i) accommodation, (ii) travel and (iii)any other costs incurred for international travel of each (aa) Minister and(bb) Deputy minister of her department since 1 June 2019; (2) what is the total cost incurred for domestic air travel for each (a) Minister and (b) Deputy Minister of her department since 1 June 2019
Reply:
- The Department of Human Settlements has incurred the following expenditure:
a) destination |
(b) (i) accommodation |
(ii)Air travel |
(iii) any other(ground transport and S&T) |
|
(aa) Minister M. T Kubayi |
Switzerland |
R351 800 |
R108 999 |
R186 413 |
Poland |
R139 526 |
R139 590 |
R80 400 |
|
Switzerland |
R224 060 |
R89 963 |
R376 815 |
|
United State of America |
R108 530 |
R108 274 |
R163 250 |
|
Kenya |
R28 560 |
R74 285 |
R9 600 |
|
(bb)Deputy Minister P Tshwete |
United State of America |
R56 000 |
R166 333 |
R32 000 |
United Arab Emirates |
R10 968 |
R92 608 |
R84 734 |
2. (a) The cost for domestic air travel for the Minister
Minister M Kubayi |
R614 116 |
(b) The cost for domestic air travel for the Deputy Minister since
Deputy Minister P Tshwete |
R1 174 874 |
22 March 2023 - NW561
Semenya, Ms MR to ask the Minister of Human Settlements
Whether her department considered working with trade unions and groups representing the so-called missing middle to enable them to buy homes through the Help-Me-Buy-A-Home housing scheme that has the potential to address the housing needs as they neither qualify for both the government housing subsidy scheme nor the private sector housing loans and/or bonds; if not, why not; if so, what are the relevant detail. (2) What has been the approach of her department in disseminating information about the specified housing scheme?
Reply:
1. Yes, the National Department of Human Settlements has considered working with trade unions as it recognises the important role that is played by the trade union movement in terms of providing benefits and financial services for employees to realise their housing needs in partnership with the broadest range of organisations.
The Department through its National Implementing Agent, the NHFC, has signed a Memorandum of Understanding (MoU) with the Government Employee Housing Scheme (GEHS) located in the Department of Public Service and Administration (DPSA) and regularly engages with Organised Labour through the Public Service Co-ordinating Bargaining Council (PSCBC).
The PSCBC resolution 7 of 2015, whose founding objective of the Government Employee Housing Scheme (GEHS) is to assist employees to access affordable housing loans and finance. The resolution further requires the GEHS to facilitate and support access to housing finance, including housing subsidy instruments and other housing programmes. The GEHS serves a total of approximately 223 272 of the 1,1 million government employees who may qualify for First Home Finance (FHF) (previously named Help-Me-Buy-A-Home)
The guideline principles of the MoU are to fulfil government’s mandate of providing quality and affordable housing to low- and middle-income households. These are defined by the GEHS as those employed at levels 1-10 currently receiving a monthly housing allowance of R1456.00 and are within the FHF qualifying monthly gross income criteria of R3 501 to R22 000, which is reviewable periodically by the Department.
Furthermore, the Department through the PSCBC is advocating for measures to re-examine and recalibrate the GEHS implementation partnership arrangements for greater market participation. The benefits to the proposal will be valuable for prospective homeowners and consumers as it will: (i) enhance market competition amongst lenders; (ii) provide attractive and favourable interest rates; (iii) empower consumers to select appropriate loan instruments from diversified product offerings; (iv) enable consumers to choose repayment schedule that suits them; and (v) improve the quality of service.
With respect to other groups representing the gap housing market, one of the Department’s key priorities is to develop appropriate policy frameworks that address funding instruments, affordability issues and the leveraging of our subsidies and grants to enable sector growth and investments in the economy. We are introducing a policy-oriented Employer Assisted Housing (EAH) framework. At the heart of the EAH is the notion that employees should be able to afford to live in the communities in which they work as there are multiple spin-offs from both the demand and supply side perspectives. The implementable EAH policy advocates for a structured partnership approach between employers, governments, developers, financial institutions, and communities.
In addition to that, the NHFC has concluded a Memorandum of Association (MoA) with BASA which is aimed at stimulating the affordable housing market especially the informally employed households with irregular sources of income for housing finance.
2. The Department in partnership with NHFC and DPSA have designed a compelling marketing and communications strategy towards ensuring a broader market outreach to the GEHS-FHF target market. This is rolled out through various types of communication channels using both the print and electronic media platforms. Additionally, the GEHS-FHF advocacy and awareness campaigns are implemented through interaction with government employees, provision of brochures, use of social media pages, pre-screening assessment and providing GEHS-FHF employees with pre-approval FHF certificates.
Finally, we consider the digitization of the GEHS-FHF business as paramount thus we have introduced software solutions as part of our technological driven efforts to expand consumer access to home-financing and home-buying services. This is done by streamlining and interfacing both the front end and back-end processes at the point of origination, processing, underwriting, and loan servicing to enable smoother and faster consumer service experience.
22 March 2023 - NW546
Powell, Ms EL to ask the Minister of Human Settlements
On what basis was a certain person (details furnished) appointed in an acting position in her Private Office and (b) what are the terms under which the specified person has been appointed?
Reply:
a) The Department does not have records of Mr Maselo who is/was appointed as Parliamentary Liaison Officer in the Office of the Minister.
20 March 2023 - NW535
Makesini, Ms M to ask the Minister of Human Settlements
What is the current total number of housing backlogs in the Republic and and (b) which province has the highest number?
Reply:
a) The housing backlog numbers in the Republic are derived from Statistics South Africa (STATSSA). STATSSA General Household Survey 2020 indicated that 11.4% (1.9 million) households lived in informal dwellings and 4.3% (731 thousand) households lived in traditional dwellings.
The department has a National Housing Needs Register (NHNR) which is an application that is designed to register households/ individuals and their housing needs in South Africa. There are currently 2.3 million households/ individuals registered on the NHNR.
In terms of the NHNR, there are 2 456 773 households registered and awaiting assistance as at 02/03/2023. Below is a table with the stats per province.
Province |
NHNR Households not yet assisted |
Eastern Cape |
604 594 |
Free State |
265 110 |
Gauteng |
1 030 099 |
KwaZulu Natal |
34 603 |
Limpopo |
86 814 |
Mpumalanga |
254 027 |
Northern Cape |
119 401 |
North West |
62 125 |
Total |
|
b) The province with the highest number is Gauteng with 1 030 099 households registered and awaiting assistance. Below is a table with the breakdown of numbers for Gauteng Province per municipality.
NHNR Households not yet assisted |
|
Gauteng |
1 0303 099 |
City of Johannesburg |
400 361 |
City of Tshwane |
182 711 |
City of Ekurhuleni |
280 584 |
Emfuleni Local Municipality |
63 759 |
Lesedi Local Municipality |
13 830 |
Merafong Local Municipality |
12 829 |
Midvaal Local Municipality |
9 281 |
Mogale Local Municipality |
39 173 |
Randfontein Local Municipality |
16 201 |
Westonaria Local Municipality |
11 370 |
20 March 2023 - NW468
De Villiers, Mr JN to ask the Minister of Human Settlements
What (a) is the salary of each (i) chief executive officer and (ii) top executive position in each state-owned entity reporting to her and (b) total amount does each get paid to attend a meeting?
Reply:
The details of the Executive and Senior management team of each of the entities is disclosed in the respective annual reports. The final printed annual report is tabled in Parliament by 30 September yearly. The Honourable member is requested to obtain from the officially published audited 2021/22 reports. The 2022/23 annual reports are noted yet audited or published.
13 March 2023 - NW274
Mphithi, Mr L to ask the Minister of Human Settlements
(1) What was the total rental value for the Crystal Valley Shelter that was used as temporary accommodation for the victims of the KwaZulu-Natal floods; (2) Whether there was a tender process in relation to the shelter; if not, why not; if so, can the summary of the process be made available to Mr L Mphithi?
Reply:
- The province has reported that an amount of R 18 million was allocated towards rental accommodation at Crystal Valley situated at O’ Flarty Road, Durban.
- The province has further reported that the acquisition process entailed the emergency procurement process, whereby lease agreement was entered between the Housing Development Agency (HDA) and the property owner.
24 February 2023 - NW134
Singh, Mr N to ask the Minister of Human Settlements
In light of the fact that electric geysers are usually the highest electricity consuming appliances in homes accounting for about 30% to 40% of electricity used, what are the full details of the (a) roll-out of solar geysers to date, (b) feedback on their effectiveness and (c) plans and timeframes of the roll-out of solar geysers going forward?
Reply:
The Department of Human Settlements received the Parliamentary question, reviewed it against its mandate and has determined that the best respondent is the Department of Minerals and Energy
20 February 2023 - NW89
De Villiers, Mr JN to ask the Minister of Human Settlements
What are the details of the (a) make, (b) model, (c) Year of manufacture, (d) cost and (e) purchase date of all the official vehicles purchased for (i) her, (ii) former Minister and (iii) the Deputy Minister and the (iv) former Deputy Minister of her department since 1 June 2019?
Reply:
1. The Department of Human Settlements purchased only one (1) vehicle since 1 June 2019: The details are as follows
(a) Make (AUDI)
(b) Model (Q5 40 TDI )
(c)Year of manufacture is 2022
(d) Cost (R 795 280.97) and
(e) Purchase date for;
(i) Minister, None
(ii) the former Minister, None
(iii) the Deputy Minister, 27 July 2022
(iv) former Deputy Minister, None
12 December 2022 - NW3910
Langa, Mr TM to ask the Minister of Human Settlements
In light of the fire that broke out in Ward 25 Pantas in the eThekwini Metropolitan Municipality, what number of houses will her department build for the members of the community who have now been rendered homeless?
Reply:
In light of the fire that occurred on the 31st of October 2022, destroying 28 informal structures in Pantas Hill Informal Settlement, the eThekwini Municipality intervened urgently and supplied building materials for the households to rebuild their informal structures.
As a long-term solution for permanent housing for the residents of Pantas, the eThekwini Municipality appointed professionals to undertake relevant feasibility studies on the possible upgrade of the existing portion of land. However, the result of the feasibility study revealed that the existing portion was not feasible for development.
The Municipality is currently in the process of identifying alternative suitable land close to the existing informal settlement, for the construction of new houses. The number of houses will be determined upon completion of the planning and design processes.
12 December 2022 - NW4432
Motsepe, Ms CCS to ask the Minister of Human Settlements
On what date is it envisaged that adequate housing will be provided for residents of the Mzamo informal settlement in the Eastern Cape and (b) What are the further relevant details in this regard?
Reply:
My Department in conjunction with the Eastern Cape Provincial Department of Human Settlements are not able to establish where the Mzamo informal settlement is hence I am not able to adequately respond to the Question. I therefore wish to request the Honourable Member to provide further details such as the municipal area or town where the Mzamo informal settlement is situated as this information will allow me to provide an adequate Reply to the Honourable Member’s Question.
12 December 2022 - NW3930
Mohlala, Ms MR to ask the Minister of Human Settlements
What number of houses have been built by her department since July 2022, (b) where have the houses been built and (c) who is the service provider to whom her department awarded the contract to build the specified houses?
Reply:
a) The Department has built 11 971 units from July 2022 to November 2022
Province |
Total Units (Jul - Oct 2022) |
Eastern Cape |
1 479 |
Free State |
149 |
Gauteng |
1 671 |
KwaZulu-Natal |
3 908 |
Limpopo |
1 029 |
Mpumalanga |
455 |
Northern Cape |
77 |
North West |
1 257 |
Western Cape |
1 946 |
|
11 971 |
b) The houses have been built in the following areas:
Province |
District Municipality |
Local Municipality |
Town |
Units Built (Jul - Oct 2022) |
EASTERN CAPE |
Alfred Nzo DM |
Mbizana LM |
Amabhanoyi |
20 |
|
|
|
Xholobeni |
25 |
|
|
Ntabankulu LM |
Ntabankulu |
78 |
|
|
Umzimvubu LM |
Dundi |
37 |
|
|
|
Lubhacweni |
31 |
|
|
|
Nkungwini |
19 |
|
Amathole DM |
Amahlathi LM |
Stutterheim |
1 |
|
|
Great Kei LM |
Komga |
8 |
|
|
Raymond Mhlaba LM |
Cwaru |
58 |
|
Buffalo City Metro |
Buffalo City Metro |
Buffalo Flats Area P |
2 |
|
|
|
East London |
119 |
|
|
|
King William's Town |
16 |
|
|
|
Madantsane |
4 |
|
|
|
Newlands |
12 |
|
|
|
Potsdam East |
23 |
|
Chris Hani DM |
Emalahleni LM (EC) |
Indwe |
15 |
|
|
Engcobo LM |
Ngcobo |
90 |
|
|
Enoch Mgijima LM |
Queenstown |
21 |
|
|
Intsika Yethu LM |
Cofimvaba |
32 |
|
|
Sakhisizwe LM |
Cala |
218 |
|
Chris Hani DM |
Intsika Yethu LM |
Kwahala |
20 |
|
Joe Gqabi DM |
Elundini LM |
Maclear |
14 |
|
|
|
Mount Fletcher |
1 |
|
|
Senqu LM |
Sterkspruit (Transkei) |
7 |
|
|
Walter Sisulu LM |
Steynsburg |
15 |
|
Nelson Mandela Bay Metro |
Nelson Mandela Bay Metro |
Port Elizabeth |
155 |
|
|
|
Uitenhage |
5 |
|
O.R.Tambo DM |
Ingquza Hill LM |
Flagstaff |
59 |
|
|
King Sabata Dalindyebo LM |
Libode |
10 |
|
|
|
Lusikisiki |
1 |
|
|
|
Mthatha |
60 |
|
|
Mhlontlo LM |
Qumbu |
29 |
|
|
|
Tsolo |
19 |
|
|
Nyandeni LM |
Libode |
60 |
|
|
|
Ngqeleni |
47 |
|
|
Port St Johns LM |
Port St Johns |
115 |
|
Sarah Baartman DM |
Dr Beyers Naudé LM |
Graaff-Reinet |
8 |
|
|
Ndlambe LM |
Alexandria |
8 |
|
|
|
Kenton-On-Sea |
17 |
FREE STATE |
Fezile Dabi DM |
Moqhaka LM |
Kroonstad |
2 |
|
|
Ngwathe LM |
Koppies |
2 |
|
Lejweleputswa DM |
Matjhabeng LM |
Welkom |
1 |
|
Mangaung Metro |
Mangaung Metro |
Botshabelo |
21 |
|
|
|
Kwakwatsi |
13 |
|
|
|
Mangaung Ext 20 |
4 |
|
|
|
Mangaung Ext 35 |
80 |
|
|
|
Rheederpark |
9 |
|
|
|
Sasolburg |
2 |
|
Xhariep DM |
Kopanong LM |
Bethulie |
1 |
|
|
|
Fauresmith |
6 |
|
|
|
Maphodi |
2 |
|
|
Mohokare LM |
Jagersfontein |
1 |
|
|
|
Smithfield |
5 |
GAUTENG |
City of Ekurhuleni Metro |
City of Ekurhuleni Metro |
Etwatwa Ext 37 |
59 |
|
|
|
Nigel |
80 |
|
|
|
Palm Ridge |
19 |
|
|
|
Palm Ridge Ext 10 & 12 |
6 |
|
|
|
Palm Ridge Ext 18 & 19 |
87 |
|
|
|
Tsakane 22 |
1 |
|
City of Johannesburg Metro |
City of Johannesburg Metro |
Goudrand |
226 |
|
|
|
Jabulani |
104 |
|
City of Tshwane Metro |
City of Tshwane Metro |
Hammanskraal |
186 |
|
|
|
Sokhulumi |
3 |
|
|
|
Soshanguve |
14 |
|
Sedibeng DM |
Emfuleni LM |
Meyerton |
50 |
|
|
|
Sebokeng |
70 |
|
|
Lesedi LM |
Heidelberg |
84 |
|
|
|
Impumelelo |
394 |
|
|
Midvaal LM |
Savanah City |
13 |
|
West Rand DM |
Merafong City LM |
Khutsong |
252 |
|
|
Mogale City LM |
Munsieville |
23 |
KWAZULU-NATAL |
Amajuba DM |
Dannhauser LM |
Buhlebomzinyathi |
61 |
|
|
Newcastle LM |
Charlestown |
16 |
|
|
|
Madadeni |
25 |
|
eThekwini Metro |
eThekwini Metro |
Durban |
170 |
|
|
|
Emalangeni |
3 |
|
|
|
Embo |
1 |
|
|
|
Etafuleni |
28 |
|
|
|
Ethekwini |
108 |
|
|
|
Kanku Road |
98 |
|
|
|
Kennedy Road |
34 |
|
|
|
Mhlangeni |
10 |
|
|
|
Mqhawe |
195 |
|
|
|
Nazareth |
1 |
|
|
|
Ngcolosi |
41 |
|
|
|
Ngonyanweni (1) |
82 |
|
|
|
Nsukazi |
14 |
|
|
|
Ntshaseni |
41 |
|
|
|
Ntuzuma |
23 |
|
|
|
Phumelelani |
9 |
|
|
|
Sobonakona (1) |
185 |
|
|
|
Tshelimnyama |
41 |
|
|
|
Umbumbulu (1) |
1 |
|
|
|
Vumengazi |
29 |
|
Harry Gwala DM |
Ubuhlebezwe LM |
Hlokozi |
18 |
|
|
|
Mfulonubi Informal |
54 |
|
|
|
Sangcwaba |
100 |
|
|
|
Ubuhlebethu |
7 |
|
|
|
Ufafa |
73 |
|
|
uMzimkhulu LM |
Dumisa |
14 |
|
Ilembe DM |
E'ndondakusuka LM |
Macambini Ext.2 |
271 |
|
|
|
Mnqobokazi |
110 |
|
|
KwaDukuza LM |
Kwadukuza/Stanger |
17 |
|
|
|
Ntshawini |
37 |
|
|
|
Sakhamkhanya |
1 |
|
|
Mandeni LM |
Isithebe |
62 |
|
|
Maphumulo LM |
Maqumbi |
44 |
|
|
Ndwedwe LM |
Ndwedwe |
85 |
|
|
|
Nonoti |
111 |
|
|
|
Qwabe |
11 |
|
King Cetshwayo DM |
Nkandla LM |
Mangidini |
61 |
|
|
|
Ngono |
83 |
|
|
uMfolozi LM |
Hlanzeni |
32 |
|
|
uMlalazi LM |
Mathonsini |
11 |
|
Ugu DM |
Ray Nkonyeni LM |
Amhlongwa |
2 |
|
|
|
Kwamavundla |
3 |
|
|
|
Masinenge |
116 |
|
|
|
Oshabeni |
41 |
|
|
|
Shangase |
159 |
|
|
Umdoni LM |
Amahlongwa |
53 |
|
|
|
Amandawe |
36 |
|
|
Umuziwabantu LM |
Kwamboto |
67 |
|
|
|
Mazakhele |
62 |
|
|
Umzumbe LM |
Shangase |
26 |
|
Umgungundlovu DM |
Mkhambathini LM |
Kwagcina |
5 |
|
|
The Msunduzi LM |
Azalea |
34 |
|
|
|
Edendale S |
19 |
|
|
uMshwathi LM |
Trustfeed |
49 |
|
Umkhanyakude DM |
Big 5 Hlabisa LM |
Makhasa |
2 |
|
|
Jozini LM |
Jozini |
75 |
|
|
Mtubatuba LM |
Nkondosi |
19 |
|
|
uMhlabuyalingana LM |
Kwambila |
20 |
|
Umzinyathi DM |
Endumeni LM |
Dlamini |
2 |
|
|
|
Manyongazane |
4 |
|
|
Msinga LM |
Msinga |
107 |
|
|
Nquthu LM |
Mbokodwe |
31 |
|
|
|
Nquthu |
1 |
|
|
Umvoti LM |
Greytown |
8 |
|
|
|
Mabomvini |
6 |
|
|
|
Nhlosweni |
23 |
|
|
|
Umvoti Nu |
1 |
|
Uthukela DM |
Indaka LM |
Fitty Park |
6 |
|
|
Inkosi Langalibalele LM |
Mimosadale |
134 |
|
|
|
Mnyangweni |
4 |
|
|
|
Shayamoya (1) |
16 |
|
|
Okhahlamba LM |
Amazizi |
73 |
|
|
|
Emmaus |
81 |
|
|
|
Moyeni |
13 |
|
Zululand DM |
Abaqulusi LM |
Emadresini |
4 |
|
|
|
Nhlangwini |
18 |
|
|
eDumbe LM |
Opuzane |
10 |
|
|
Nongoma LM |
Nkalakuthaba |
24 |
|
|
|
Ogedleni |
3 |
|
|
Ulundi LM |
Phenyane |
27 |
|
|
uPhongolo LM |
Kwalubisi |
43 |
|
|
|
Mdiyane |
44 |
|
|
|
Nyawoshane |
19 |
LIMPOPO |
Capricorn DM |
Blouberg LM |
Mashalane |
36 |
|
|
Lepelle-Nkumpi LM |
Blydrift |
8 |
|
|
|
Ga-Mampa |
37 |
|
|
|
Mahlatjane |
1 |
|
|
|
Moletlane |
4 |
|
|
Polokwane LM |
Makgaung |
23 |
|
|
|
Makoshala |
42 |
|
|
|
Polokwane Ext 133 |
58 |
|
|
|
Polokwane Ext 134 |
17 |
|
|
|
Polokwane Ext 78 |
21 |
|
|
|
Sefene |
27 |
|
|
|
Setateng |
22 |
|
|
|
Thakgalang |
6 |
|
Greater Sekhukhune DM |
Elias Motsoaledi LM |
Bapeding |
44 |
|
|
|
Doroom |
6 |
|
|
Ephraim Mogale LM |
Kromdraai |
20 |
|
|
|
Marble Hall |
2 |
|
|
|
Matla-A-Ramoshebo |
34 |
|
|
|
Regae |
18 |
|
|
Fetakgomo-Greater Tubatse LM |
Apel |
33 |
|
|
|
Burgersfort |
24 |
|
|
|
Haenertsburg |
3 |
|
|
|
Mapareng |
31 |
|
|
|
Nchabeleng |
25 |
|
|
|
Phiring |
34 |
|
|
|
Steelpoort |
2 |
|
|
Fetakgomo-Tubatse LM |
Mahlokwane |
12 |
|
|
|
Modimole |
29 |
|
|
Makhuduthamaga LM |
Jane Furse |
1 |
|
|
|
Mashegwane-Tswaledi |
5 |
|
|
|
Phatantshwane |
23 |
|
|
|
Pitsaneng |
15 |
|
Mopani DM |
Ba-Phalaborwa LM |
Mapikiri |
26 |
|
|
Greater Letaba LM |
Mohokone |
10 |
|
|
Greater Tzaneen LM |
Lwandlamuni |
10 |
|
|
|
Sape |
6 |
|
Vhembe DM |
Collins Chabane LM |
Bevhula |
31 |
|
|
|
Nwamatatani |
6 |
|
|
|
Ribungwani |
15 |
|
|
Makhado LM |
Elim |
19 |
|
|
Musina LM |
Mutale A |
31 |
|
|
|
Rangani |
11 |
|
|
Thulamela LM |
Gogogo |
71 |
|
|
|
Muledzhi |
9 |
|
|
|
Tshanzhe |
16 |
|
|
|
Tshivhilidulu |
2 |
|
Waterberg DM |
Bela-Bela LM |
Bela Bela Ext 25 |
22 |
|
|
Lephalale LM |
Tshikota |
11 |
|
|
Mogalakwena LM |
Galelia |
50 |
|
|
|
Preezberg |
3 |
|
|
|
Rapadi |
6 |
|
|
|
Rooibokfontein |
11 |
MPUMALANGA |
Ehlanzeni DM |
Bushbuckridge LM |
Alexandria |
5 |
|
|
|
Clare "A" |
8 |
|
|
|
Mandela Village |
1 |
|
|
|
Marcia |
8 |
|
|
|
Mkhuhlu-F |
2 |
|
|
|
Thabakgolo Trust |
2 |
|
|
City of Mbombela LM |
Emjindini Ext 19 |
3 |
|
|
|
Kabokweni |
2 |
|
|
|
Karino |
4 |
|
|
|
Matsulu |
13 |
|
|
|
Msogwaba |
6 |
|
|
|
Umjindi Trust |
15 |
|
|
Mbombela LM |
Karino |
5 |
|
|
Thaba Chweu LM |
Lydenburg |
4 |
|
Ehlanzeni DM |
Bushbuckridge LM |
Bushbuckridge |
7 |
|
Gert Sibande DM |
Chief Albert Luthuli LM |
Elukwatini |
2 |
|
|
Dipaleseng LM |
Balfour |
100 |
|
|
Govan Mbeki LM |
Bethal |
5 |
|
|
Mkhondo LM |
Mkhondo |
101 |
|
|
|
Piet Retief |
25 |
|
|
Msukaligwa LM |
Breyten |
37 |
|
|
|
Ermelo |
1 |
|
Nkangala DM |
Dr JS Moroka LM |
Siyabuswa |
6 |
|
|
Emakhazeni LM |
Belfast |
13 |
|
|
|
Waterval Boven |
4 |
|
|
Emalahleni LM (MP) |
Emalahleni |
1 |
|
|
|
Witbank |
14 |
|
|
Steve Tshwete LM |
Middelburg - Mp |
59 |
|
|
Thembisile Hani LM |
Kwamhlanga |
1 |
|
|
Victor Khanye LM |
Delmas |
1 |
NORTHERN CAPE |
Frances Baard DM |
Dikgatlong LM |
Barkly West |
10 |
|
|
Sol Plaatje LM |
Kimberley |
18 |
|
John Taolo Gaetsewe DM |
Ga-Segonyana LM |
Kuruman |
14 |
|
|
Joe Morolong LM |
Mothibistad |
10 |
|
Pixley ka Seme DM |
Siyathemba LM |
Prieska |
24 |
|
|
Umsobomvu LM |
Colesberg |
1 |
NORTHWEST |
Bojanala DM |
Kgetlengrivier LM |
Derby |
3 |
|
|
Madibeng LM |
Brits |
41 |
|
|
Moretele LM |
Moretele |
151 |
|
|
Moses Kotane LM |
Mogwase |
215 |
|
|
Rustenburg LM |
Rustenburg |
208 |
|
Dr Kenneth Kaunda DM |
City of Matlosana LM |
Klerksdorp |
33 |
|
|
|
Orkney |
21 |
|
|
JB Marks LM |
Ventersdorp |
19 |
|
|
Maquassi Hills LM |
Leeudoringstad |
30 |
|
|
|
Wolmaransstad |
77 |
|
Dr Ruth Segomotsi Mompati DM |
Lekwa-Teemane LM |
Bloemhof |
7 |
|
|
Naledi LM |
Vryburg |
119 |
|
Ngaka Modiri Molema DM |
Ditsobotla LM |
Lichtenburg |
65 |
|
|
Mahikeng LM |
Mafikeng |
20 |
|
|
|
Mahikeng |
72 |
|
|
Ratlou LM |
Kraaipan |
5 |
|
|
Tswaing LM |
Delareyville |
171 |
WESTERN CAPE |
Cape Winelands DM |
Breede Valley LM |
Worcester |
129 |
|
|
Langeberg LM |
Robertson |
112 |
|
|
Stellenbosch LM |
Stellenbosch |
98 |
|
City of Cape Town Metro |
City of Cape Town Metro |
Blue Downs |
58 |
|
|
|
Cape Town |
920 |
|
Garden Route DM (old Eden) |
Bitou LM |
Plettenberg Bay |
66 |
|
|
George LM |
Kleinkratz |
2 |
|
|
|
Syfertontein |
3 |
|
|
Knysna LM |
Knysna |
15 |
|
|
Mossel Bay LM |
Mossel Bay |
10 |
|
|
Oudtshoorn LM |
Oudtshoorn |
84 |
|
Overberg DM |
Overstrand LM |
Gans Bay |
92 |
|
West Coast DM |
Cederberg LM |
Citrusdal |
14 |
|
|
Matzikama LM |
Vredendal North |
162 |
|
|
Swartland LM |
Malmesbury |
181 |
TOTAL |
11 971 |
c) The National Department does not award contracts to builders, Provinces award contracts to build houses. The service providers that were awarded contracts to build the houses are listed below:
No. |
Province |
Company Type |
Company Name |
Eastern Cape |
Contractor/Builder |
Amabhele T/A Petatron Cc Trading |
|
Eastern Cape |
Contractor/Builder |
Bendolite Trading Pty Ltd |
|
Eastern Cape |
Contractor/Builder |
Charlene Bodenstein Services (Pty) Ltd |
|
Eastern Cape |
Contractor/Builder |
Chiware Civil Engineering Constr |
|
Eastern Cape |
Contractor/Builder |
Dignify Construction |
|
Eastern Cape |
Contractor/Builder |
Express Builders Cc |
|
Eastern Cape |
Contractor/Builder |
Ezuluweni Construction |
|
Eastern Cape |
Contractor/Builder |
Gaza Construction |
|
Eastern Cape |
Contractor/Builder |
Gc Housing Cc |
|
Eastern Cape |
Contractor/Builder |
Hydraform Sa (Pty) Ltd |
|
Eastern Cape |
Contractor/Builder |
Ikubantu Trading Enterprise Cc |
|
Eastern Cape |
Contractor/Builder |
Jade Africa Developments Pty |
|
Eastern Cape |
Contractor/Builder |
Kantey & Templer Consulting Engineers |
|
Eastern Cape |
Contractor/Builder |
Kentha Construction |
|
Eastern Cape |
Contractor/Builder |
Kontinental Amigen Consortium |
|
Eastern Cape |
Contractor/Builder |
L & R Welding And Tool Supplies ( Pty) Ltd |
|
Eastern Cape |
Contractor/Builder |
M Mashibe General Trade Cc |
|
Eastern Cape |
Contractor/Builder |
Mageba Projects Cc |
|
Eastern Cape |
Contractor/Builder |
Mahiri Construction Jv |
|
Eastern Cape |
Contractor/Builder |
Masakhane Project Managers & Qs |
|
Eastern Cape |
Contractor/Builder |
Milwa Construction |
|
Eastern Cape |
Contractor/Builder |
Mosegedi And Associates |
|
Eastern Cape |
Contractor/Builder |
Mwendane Skills Providers |
|
Eastern Cape |
Contractor/Builder |
Ngangalala Trading Cc |
|
Eastern Cape |
Contractor/Builder |
Quantum Leap Investments 656 (Pty) Ltd |
|
Eastern Cape |
Contractor/Builder |
Real Deal Investors (Pty )Ltd |
|
Eastern Cape |
Contractor/Builder |
Sakhirhi Trading Cc Jv Prhurraz Building Civil |
|
Eastern Cape |
Contractor/Builder |
Simply Do Construction (Pty) L T D |
|
Eastern Cape |
Contractor/Builder |
Snethemba Tshiya Infrastructure Jv |
|
Eastern Cape |
Contractor/Builder |
Stedone Developments |
|
Eastern Cape |
Contractor/Builder |
Summerlane Trading 288cc T/A African Isolations |
|
Eastern Cape |
Contractor/Builder |
Thamandla Cifu & Associates |
|
Eastern Cape |
Contractor/Builder |
Ultramatix Forty Nine Cc |
|
Eastern Cape |
Developer |
Buffalo City Metro Municipality |
|
Eastern Cape |
Developer |
Housing Development Agency (Hda) |
|
Eastern Cape |
Developer |
Ndlambe Municipality |
|
Eastern Cape |
Developer |
Nelson Mandela Metropolitan Municipality |
|
Eastern Cape |
Developer |
O.R.Tambo District Municipality |
|
Free State |
Contractor/Builder |
3sixty Precast Concrete |
|
Free State |
Contractor/Builder |
Distinctive Choice 712 Cc |
|
Free State |
Contractor/Builder |
G2g Construction |
|
Free State |
Contractor/Builder |
Iceburg |
|
Free State |
Contractor/Builder |
Jsebaka Madikane Trading |
|
Free State |
Contractor/Builder |
Kaykaysim Projects |
|
Free State |
Contractor/Builder |
Lechesa Manaba Consulting And Projects |
|
Free State |
Contractor/Builder |
Malapi Investment |
|
Free State |
Contractor/Builder |
Mulaudzi's Development Projects |
|
Free State |
Contractor/Builder |
Phethisang Merero General Trading |
|
Free State |
Contractor/Builder |
Reananetse Trading |
|
Free State |
Contractor/Builder |
Shirona |
|
Free State |
Contractor/Builder |
Superb Home & Kitchen Manufacturers |
|
Free State |
Contractor/Builder |
Switch Up Investment |
|
Free State |
Contractor/Builder |
Tshwara Thebe Construction Cc |
|
Free State |
Contractor/Builder |
Tswakeletsa |
|
Free State |
Contractor/Builder |
Zimvo Trading Cc |
|
Gauteng |
Contractor/Builder |
Makole Property Development |
|
Gauteng |
Contractor/Builder |
Ntshiza Technical Services |
|
Gauteng |
Developer |
Blue Print Housing (Pty) Ltd |
|
Gauteng |
Developer |
Inkanyeli Development |
|
Gauteng |
Developer |
Motheo Group |
|
Gauteng |
Developer |
Nep Consulting Engineers |
|
Gauteng |
Developer |
South African Women In Construction |
|
Gauteng |
Developer |
Xanado Trade Ltd Mwalimu Holdings |
|
KwaZulu-Natal |
Contractor/Builder |
Brocon/Miands Joint Venture |
|
KwaZulu-Natal |
Contractor/Builder |
Busizwe Trade & Supplies |
|
KwaZulu-Natal |
Contractor/Builder |
Fezeka Business Services Cc |
|
KwaZulu-Natal |
Contractor/Builder |
Isiboniso Projects Management |
|
KwaZulu-Natal |
Contractor/Builder |
Khazimula Investment Cc |
|
KwaZulu-Natal |
Contractor/Builder |
Mabune Consulting |
|
KwaZulu-Natal |
Contractor/Builder |
Motheo Construction Group (Pty) Ltd |
|
KwaZulu-Natal |
Contractor/Builder |
Stedone Developments (Pty) Ltd |
|
KwaZulu-Natal |
Developer |
Alfred Duma Local Municipality |
|
KwaZulu-Natal |
Developer |
Basfour 170 Cc T/A Fairfield Developments |
|
KwaZulu-Natal |
Developer |
Dannhauser Municipality |
|
KwaZulu-Natal |
Developer |
Ethekwini Municipailty |
|
KwaZulu-Natal |
Developer |
Habitat For Humanity-South Africa |
|
KwaZulu-Natal |
Developer |
Inkosi Langalibalele Local Municipality |
|
KwaZulu-Natal |
Developer |
Kantey & Templer Pty Ltd |
|
KwaZulu-Natal |
Developer |
Kwadukuza Municipality |
|
KwaZulu-Natal |
Developer |
Msunduzi Housing Association |
|
KwaZulu-Natal |
Developer |
Msunduzi Municipality |
|
KwaZulu-Natal |
Developer |
Newcastle Municipality |
|
KwaZulu-Natal |
Developer |
Ntuzuma H Block 1 And 6 Housing Project |
|
KwaZulu-Natal |
Developer |
Ntuzuma Unit H Block 2 Trust |
|
KwaZulu-Natal |
Developer |
Ray Nkonyeni Municipality |
|
KwaZulu-Natal |
Developer |
Stedone Developments (Pty) Ltd |
|
KwaZulu-Natal |
Developer |
Ubuhlebezwe Municipality |
|
KwaZulu-Natal |
Developer |
Umdoni Municipality |
|
KwaZulu-Natal |
Developer |
Umlalazi Municipality |
|
KwaZulu-Natal |
Developer |
Umpheme Development (Pty) Ltd |
|
KwaZulu-Natal |
Developer |
Umzumbe Municipality |
|
KwaZulu-Natal |
Developer |
Uphongolo Municipality |
|
Limpopo |
Contractor/Builder |
Sello Ramothwakla |
|
Limpopo |
Developer |
Aventino Group |
|
Limpopo |
Developer |
Carorox (Pty) Ltd |
|
Limpopo |
Developer |
Ditlou Suppliers & Services Cc |
|
Limpopo |
Developer |
Dot Africa |
|
Limpopo |
Developer |
Estacol |
|
Limpopo |
Developer |
Firm |
|
Limpopo |
Developer |
Gpmvr |
|
Limpopo |
Developer |
Khanaba Business Enterprise Cc |
|
Limpopo |
Developer |
Koketji |
|
Limpopo |
Developer |
Kwenabel Trading |
|
Limpopo |
Developer |
Letsimane Trading & Projects 85 Cc |
|
Limpopo |
Developer |
Linspire 139 Cc |
|
Limpopo |
Developer |
Lupikopi |
|
Limpopo |
Developer |
Malatsane Business Enterprise (Pty) Ltd |
|
Limpopo |
Developer |
Mamondo Development & Construction Cc |
|
Limpopo |
Developer |
Mangatlu Trading Enterprise |
|
Limpopo |
Developer |
Mavestra Construction |
|
Limpopo |
Developer |
Mdb Projects (Pty) Ltd |
|
Limpopo |
Developer |
Mmamoloko Trading Enterprise Cc |
|
Limpopo |
Developer |
Mmanyana-Anna Trading Enterprise Cc |
|
Limpopo |
Developer |
Monala G/T |
|
Limpopo |
Developer |
Mothikeni |
|
Limpopo |
Developer |
Mzerewa Group (Pty) Ltd |
|
Limpopo |
Developer |
Nax Most Construction |
|
Limpopo |
Developer |
Ngwacon Developers |
|
Limpopo |
Developer |
Nhlohlorhi Tilo Trading Cc T/A Telegenix 655 |
|
Limpopo |
Developer |
Prudev Trading |
|
Limpopo |
Developer |
Ramkol Construction & Projects Cc |
|
Limpopo |
Developer |
Rheiland Investment |
|
Limpopo |
Developer |
Rurafo Trading Ent |
|
Limpopo |
Developer |
Smtm Construction Cc |
|
Limpopo |
Developer |
Thaba And Sons |
|
Limpopo |
Developer |
Thale Civils |
|
Limpopo |
Developer |
Thalema |
|
Limpopo |
Developer |
Truminded Entrprises |
|
Limpopo |
Developer |
Veeking |
|
Limpopo |
Developer |
Zerbacraft Pty |
|
Mpumalanga |
Contractor/Builder |
Amaphikankani Co-Operative Pty |
|
Mpumalanga |
Contractor/Builder |
Balethavha Business Enterprise |
|
Mpumalanga |
Contractor/Builder |
Crane Fly Trading Cc |
|
Mpumalanga |
Contractor/Builder |
Deepspace Construction |
|
Mpumalanga |
Contractor/Builder |
Delu Trading Cc |
|
Mpumalanga |
Contractor/Builder |
Elsina Construction And Projects |
|
Mpumalanga |
Contractor/Builder |
Gumza Technologies |
|
Mpumalanga |
Contractor/Builder |
Inga Asavela Investment |
|
Mpumalanga |
Contractor/Builder |
Kd Madonsela Trading & Projects |
|
Mpumalanga |
Contractor/Builder |
Maphoyisa Construction |
|
Mpumalanga |
Contractor/Builder |
Maroala Enterprise |
|
Mpumalanga |
Contractor/Builder |
Matjoba Maria Trading |
|
Mpumalanga |
Contractor/Builder |
Mazocha Business Enterprise |
|
Mpumalanga |
Contractor/Builder |
Mbhene Trading |
|
Mpumalanga |
Contractor/Builder |
Mnomo Maintenance And Costruction |
|
Mpumalanga |
Contractor/Builder |
Mthwakazi Africa Investment |
|
Mpumalanga |
Contractor/Builder |
Mtjopi Trading |
|
Mpumalanga |
Contractor/Builder |
Na075 Trading |
|
Mpumalanga |
Contractor/Builder |
Rospa Trading 49 Cc |
|
Mpumalanga |
Contractor/Builder |
Sakhile And Sikhulile Trading Pty |
|
Mpumalanga |
Contractor/Builder |
Sizampilo Projects Cc |
|
Mpumalanga |
Contractor/Builder |
Sukuyimani Construction |
|
Mpumalanga |
Contractor/Builder |
Superose Pty Ltd |
|
Mpumalanga |
Contractor/Builder |
Tssn Carriers |
|
Mpumalanga |
Contractor/Builder |
Ucebisile Umnotho (Pty) Ltd |
|
Mpumalanga |
Developer |
Basadi Civil Construction |
|
Mpumalanga |
Developer |
Infratech Projects |
|
Mpumalanga |
Developer |
Prince Of Tides |
|
Mpumalanga |
Developer |
Sizampilo Projects |
|
Mpumalanga |
Developer |
Tiger Business Enterprise |
|
Mpumalanga |
Developer |
Xjr Construction Cc |
|
Northern Cape |
Contractor/Builder |
Gap Infrastructure Corporation (Gic) |
|
Northern Cape |
Contractor/Builder |
Modiles Logistics |
|
Northern Cape |
Contractor/Builder |
Neoking Trading Cc |
|
Northern Cape |
Contractor/Builder |
V3 Consulting Engineers |
|
Northern Cape |
Developer |
Moke Construction And Projects |
|
Northern Cape |
Developer |
Settley Trading (Pty) Ltd |
|
Northern Cape |
Supplier |
Biz Afrika985 (Pty)Ltd |
|
North West |
Developer |
Agisanang Velakude Jv |
|
North West |
Developer |
Andisa Consulting |
|
North West |
Developer |
Baipati Civil And Electrical Contractor |
|
North West |
Developer |
Ch Enterprises |
|
North West |
Developer |
Dick'n Roll Construction |
|
North West |
Developer |
Drop Dot |
|
North West |
Developer |
Ezekiel Moeti Construction |
|
North West |
Developer |
Leano 87 Solutions |
|
North West |
Developer |
Leretletse-Lesedi |
|
North West |
Developer |
Leungo Construction |
|
North West |
Developer |
M P Construction |
|
North West |
Developer |
Malapane Property Service & Development |
|
North West |
Developer |
Marabe Projects (Pty) Ltd |
|
North West |
Developer |
Masikhule Project Consultants |
|
North West |
Developer |
Mercycon Construction And Projects |
|
North West |
Developer |
Metroprojects Development |
|
North West |
Developer |
Mhlava Civil Construction |
|
North West |
Developer |
Nxm Construction |
|
North West |
Developer |
Pace Setters Construction & Supply Of Goods |
|
North West |
Developer |
Rauco Trading Enterprise Cc |
|
North West |
Developer |
Renanao Construction (Pty) Ltd |
|
North West |
Developer |
Renekhumo Developers (Pty)Ltd |
|
North West |
Developer |
Ryxor |
|
North West |
Developer |
Sdn Civils (Pty) Ltd |
|
North West |
Developer |
Sechoaro Supply And Delivery Cc |
|
North West |
Developer |
Sekoko Sam Matubetube T/A Vision Construction |
|
North West |
Developer |
Sun Success Construction And Projects Cc |
|
North West |
Developer |
Tigane Developers And Property Administrators Cc |
|
North West |
Developer |
World Focus 2346 |
|
Western Cape |
Developer |
Cederberg Municipality |
|
Western Cape |
Developer |
City Of Cape Town |
|
Western Cape |
Developer |
Langeberg Municipality |
|
Western Cape |
Developer |
Matzikama Municipality |
|
Western Cape |
Developer |
Oudtshoorn Municipality |
|
Western Cape |
Developer |
Stellenbosch Municipality |
|
Western Cape |
Developer |
Swartland Municipality |
|
Western Cape |
Developer |
Swellendam Mun |
|
Western Cape |
Developer |
Western Cape Dept Of Human Settlements |
12 December 2022 - NW4557
Tambo, Mr S to ask the Minister of Higher Education, Science and Innovation
Whether the constant imposition of administrators at institutions of higher learning that are plagued by governance issues has assisted in the governance and operational functions of the affected institutions; if not, what is the position in this regard; if so, in what areas of governance has the improvement occurred?
Reply:
The Higher Education Act makes provision for the Minister to appoint a person as Administrator, if any of the following circumstances occur:
a) An audit of the financial records of a public higher education institution or the report by an independent assessor or any other report or information reveals financial or other maladministration of a serious nature or serious undermining of the effective functioning of the public higher education institution.
b) If the Minister has reasonable grounds to believe that the council of the public higher education institution concerned has failed to comply with the directive within the stated period, or the steps taken fail to remedy the deficiency within a reasonable period.
c) the council of the public higher education institution requests such appointment; or
d) if the council of the public higher education institution is deemed to have resigned (i.e., 75 per cent or more of the members of the council of a public higher education institution resign at a meeting of council.
Three institutions were placed under administration since 2019, namely UFH, VUT and MUT. This is out of 26 public higher education institutions.
UFH: Several governance challenges arose at UFH. Additional details can be found in the report of the Independent Assessor (gazette 42902, dated 13 December 2019). The University Council also found itself in a dilemma as it was unable to reach the required quorum at most of its meetings, which rendered the Council unable to make critical decisions. As a result, the University management was hampered by the inability of Council to meet and discharge its responsibilities.
The problems in the university and within Council continued through until April 2019 when the Minister intervened by appointing an Administrator to take over the functions of the Council. The Administration period came to an end in November 2020, and stability is evident in the Council.
VUT: Within a decade of VUT being placed under administration, from June 2018 the Minister received correspondence from stakeholders and people from within the University community making allegations and counter-allegations of maladministration, governance, and management challenges. The correspondences revealed challenges relating to governance, management, financial management, the conflicts exacerbated by the existence of factions within Council and management. The circumstances led to the resignation of several members of Council during April 2019, which rendered Council unable to reach the required quorum at most of its meetings and ultimately prevented it and management from discharging their responsibilities.
The subsequent resignation of Council in August 2019 necessitated an intervention at the level of an administrator. Since the departure of the Administrator in August 2021, VUT has started addressing some historical governance problems. The Department continues to engage with the University about its governance and post-administration work.
MUT: MUT has a long history of governance challenges. Recurring themes across the various assessors’ findings include governance and management problems characterized by conflict and role confusion; human resources capacity issues; a weak policy environment; a weakly formulated academic project; and an institutional identity and culture that is not consistent with the understanding of what a university should be.
The various independent assessor reports provided recommendations which should have been implemented to enable the University to recover from its problems. On one occasion, the University was placed under administration. Yet, despite this intervention, its problems persisted. The 2018 Report recommended an administration, however after careful consideration of various factors and engagement with the Council, the Minister decided not to appoint an Administrator but rather to issue a directive.
Following the suspension of the VC in April 2020 and the subsequent events, the appointment of yet another Independent Assessor became necessary. Although the Independent Assessor report did not recommend the dissolution of the Council; the Minister considered the Report of the Independent Assessor, the response of the Council, other developments, the advice of the Council on Higher Education; the history of the University; and other recent developments at the University.
The Administrator's quarterly reports assist the Minister to obtain better insight into the problems which are identified, and how they can be resolved. The above examples show that the appointment of administrators follow serious considerations of what best serves the interest of the academic enterprise. The circumstances in the various institutions necessitated that the mandate of the administrator includes specific tasks to ensure that specific governance-related challenges are addressed.
25 November 2022 - NW4112
Mohlala, Ms MR to ask the MINISTER OF HUMAN SETTLEMENTS
Whether her department conducted any investigation into illegal occupation of low-cost housing by government officials in the Free State; if not, why not; if so, what are the full, relevant details of the progress report of the investigation?
Reply:
The Free State Provincial Department of Human Settlements has advised that its Security Management and Anti-Corruption (SMAC) unit conducted an investigation into illegally occupied low-cost housing in the following areas of Welkom, Warden, Sasolburg, Clarens, Schoonplaatz, Harrismith, and Mangaung Hillsideview. The Provincial Department states that the investigation was in response to the public outcry about the illegally occupied houses in the province, and that the aim was to determine the extent of illegal occupation of low-cost housing in the province.
The Provincial Department further indicates that the investigation though not necessarily targeting government officials, revealed that government officials were occupying some of the low-cost houses. In total 326 houses were found to be illegally occupied and 15 of those were occupied by government officials. For the benefit of the Member, detailed findings of the investigation to date is attached (Annexure as provided by the Free State Provincial Department of Human Settlements) however the investigations are still ongoing in order to establish the full extent of the illegal occupation of low-cost housing in the province.
25 November 2022 - NW4432
Motsepe, Ms CCS to ask the Minister of Human Settlements
On what date is it envisaged that adequate housing will be provided for residents of the Mzamo informal settlement in the Eastern Cape and (b) What are the further relevant details in this regard?
Reply:
My Department in conjunction with the Eastern Cape Provincial Department of Human Settlements are not able to establish where the Mzamo informal settlement is hence I am not able to adequately respond to the Question. I therefore wish to request the Honourable Member to provide further details such as the municipal area or town where the Mzamo informal settlement is situated as this information will allow me to provide an adequate Reply to the Honourable Member’s Question.
25 November 2022 - NW4231
Buthelezi, Ms SA to ask the Minister of Human Settlements
Whether she will furnish Ms. SA Buthelezi with the details of how her department has addressed the project management shortfalls which resulted in the (a) delays and (b) lack of compliance in the construction of Temporary Relief Units (TRUs) in KwaZulu- Natal; if not why not; if so, what are the relevant details of (i) any measures that have been taken to increase project management capacity and (ii) the revised plan of her department to monitor the construction of TRUs to ensure quality completion of the promised units?
Reply:
a) Several initiatives have been adopted by the KwaZulu-Natal Department of Human Settlements to address delays resulting in project management shortfalls. Firstly, additional service providers have been appointed to expedite the construction of Temporary Residential Units (TRUs).
Secondly, built environment professionals have been appointed to expenditure any land planning development required including Town and Regional Planners, Urban Planners, Civil Engineers, Quantity Surveyors, Environment Management Specialists, and Build Control Inspectors.
Thirdly, during the early stages of implementing recovery efforts, a need to appoint social facilitators was identified and this has since been addressed. Lastly, the Housing Development Agency (HDA) an entity of the National Department of Human Settlements has been appointed by the Province as a Project Manager. Therefore, any initial project management shortfalls have been adequately addressed and continue to be attended to as they arise.
b) The monitoring of the quality of TRUs occurs at various levels and by various spheres and entities of government. As a result, all TRUs constructed are in compliance with the norms and standards contained in the National Housing Code of 2009 and are subjected to quality control inspections by the Provincial quality assurors prior to payment of any service providers. In addition, both the National and the Provincial Departments conduct verification of the TRUs in order to ensure adherence to policy and construction standards. Furthermore, the Office of the Auditor-General as well as the Department of Planning, Monitoring and Evaluation conduct physical verification and quality assessment on samples of TRUs that have been constructed.
25 November 2022 - NW3765
Ceza, Mr K to ask the Minister of Human Settlements
What support mechanism has her department provided people left homeless after the floods particularly with regards to the total number of houses that need to be built in the aftermath of the KwaZulu - Natal flood disaster.
Reply:
In response to the question raised, The KwaZulu -Natal Province accessed funds of R342 million from the Provincial Emergency Housing Grant to assist 4983 households and as of 17 October 2022 a total of 1 442 temporary residential units have been erected in various municipalities. The balance of the households will be assisted through other interventions. Hence the Kwa-Zulu-Natal Province has also through this Department and with the approval of the National Treasury sought consent to utilise the funding to accommodate the balance of the affected households in Transitional Emergency accommodation whilst a permanent solution is being addressed simultaneously.
14 November 2022 - NW3376
Mokgotho, Ms SM to ask the MINISTER OF HUMAN SETTLEMENTS
What steps has she and/or her department taken to curb the wasteful expenditure caused by contractors who have not completed their contracts in the North West?
Reply:
The North West Provincial Department of Human Settlements has indicated that there has been no wasteful expenditure incurred due to contractors failing to complete their contracts. It has been reported that contractors had been paid on the basis of progress related to milestones completed, inspected and approved by the National Home Builders Registration Council (NHBRC) and the Department.
14 November 2022 - NW3671
Mokgotho, Ms SM to ask the Minister of Human Settlements
On what date is it envisaged that the Reutlwile Informal Settlements at Zinniaville in Rustenberg, which was developed in 2015, will be formalised according to the request of the community?
Reply:
At present, the municipality has indicated that it is not in a position to pronounce on the timeframe for the formalisation of Reutlwile Informal Settlement at Zinniaville in Rustenberg as there are a number of informal settlements in the process of being formalised, including budgetary constraints as well as the existing court order on Reutlwile Informal Settlement.
11 November 2022 - NW2845
Buthelezi, Ms SA to ask the Ms. S.A Buthelezi (IFP) to ask the Minister of Human Settlements
Whether the natural disasters that have occurred recently have set her department back financially and in terms of plans that her department had at the start of the year, if not, what is the position in this regard; if so, what total (a) amount has her department spent overall in the attempt to provide victims of the disasters with adequate housing and (b) number of housing units will be established and distributed in each province?
Reply:
a) All provinces are allocated the Provincial Emergency Housing Grant in anticipation of natural disasters. When the disasters happened there was a necessity to respond timeously to bring immediate relief to the victims. However, the application process that needs to be followed to access the emergency grant is not flexible enough to allow for a speedy response. In response, the National Department agreed to an early transfer, within the DORA framework, to KZN provincial department, R733 086 000 (HSDG) and R189 217 000 (ISUPG), in April, to respond to the disasters whilst waiting for the emergency funds. Due to delays caused by issues such as land availability, intimidation of provincial personnel and other administrative delays the money from the two grants was not utilised until the emergency funds were made available. An amount of R342m was approved for KwaZulu-Natal and R103m for the Eastern Cape from the Provincial Emergency Housing Grant to provide Temporary Residential Units. In addition, about R54m from Human Settlements Development Grant was approved for North West to also provide emergency housing. Consequently, the department was not set back financially and the plans were not affected.
b) The target is to build 4 983 emergency dwellings in KwaZulu-Natal, 2959 for Eastern Cape and 250 for North West communities. The distribution of emergency housing assistance in KwaZulu-Natal and Eastern Cape provinces is as follows;
EASTERN CAPE |
|
REGION |
NO OF UNITS COMPLETED |
OR TAMBO DISTRICT |
442 |
ALFRED NZO |
395 |
CHRIS HANI |
5 |
JOE GQABI |
0 |
AMATHOLE DISTRICT |
0 |
TOTAL |
835 |
KWAZULU-NATAL |
|
REGION |
NO OF UNITS COMPLETED |
eThekwini |
231 |
Harry Gwala |
150 |
iLembe (First Allocation) |
400 |
iLembe (First Allocation) |
74 |
King Cetshwayo (First Allocation) |
40 |
King Cetshwayo (Second Allocation) |
95 |
uGu |
111 |
uMgungundlovu |
113 |
uMkhanyekude |
40 |
Amajuba |
87 |
uMzinyathi |
70 |
uThekela |
70 |
Zululand |
40 |
TOTAL |
1 521 |
08 November 2022 - NW3251
Mokgotho, Ms SM to ask the MINISTER OF HUMAN SETTLEMENTS
Which steps of intervention have been taken in ensuring that houses and toilets built for residents of Ba-Phalaborwa Local Municipality also accommodate persons living with disabilities?
Reply:
The Limpopo Provincial Department of Human Settlements has committed itself to ensuring that houses and toilets that are constructed do accommodate specifications for persons living with disabilities throughout the Province. It has indicated that in terms of the National Building Regulations, the departmental house layout includes the house plan for persons with disabilities as guided by the applicable SANS 10400 Part S providing specifications for both houses and toilet facilities.
Furthermore, the Limpopo Provincial Department of Human Settlements has also undertaken to ensure that the above specifications are adhered to and that both houses and toilet facilities built for residents in the Ba-Phalaborwa Local Municipality do accommodate persons living with disabilities.
08 November 2022 - NW3064
Msane, Ms TP to ask the Minister of Human Settlements
(a) What is a total number of service providers that have been blacklisted for shoddy workmanship on Reconstruction and Development Programme houses in the past 10 years, (b) who are the directors of the companies that have been blacklisted and (c) what vetting process are in place to assess service providers who want to engage in work with the Government?
Reply:
The National Department is currently in the process of profiling service providers that have been blacklisted by the National Treasury and contractors who may be involved in illegal activities or defaulted in contracts in the conducting of business with all spheres of government.
a) There are no contractors that have been requested by the National Department of Human Settlements to be blacklisted.
b) Not applicable based on (a) above.
c) The process of vetting of service providers in the Department and Provincial Departments of Human Settlements must include the following aspects;
- Ensure all contractors are registered in the Central Supplier Database
- Ensure all contractors are tax compliant
- Ensure that contractors have a valid CIDB status
- Ensure that contractors have disclosed all interests in line with appropriate SBD forms
- Ensure that contractors are not previously blacklisted from doing business with the state
- Submission of relevant BBB-EE score cards to ensure calculation of points as per the relevant supply chain management prescripts
- In the case of construction of a house, the service provider has a National Home Builders Regulatory Council (NHBRC) certificate as proof of enrolment before any commencement of construction.
- All applicable and relevant processes and procedures as per SCM prescripts are followed, adhered and complied with.
08 November 2022 - NW3695
Mogale, Mr T to ask the Minister of Human Settlements
What total number of social housing schemes are currently(a) under her department,(b) being planned and/or (c) under construction? (NW 4524E)
Reply:
a) There is a total of 194 completed and tenanted social housing projects representing a portfolio of 42 797 units as at end March 2022
b) The pipeline of new social housing projects planned and not yet approved include seventy-eight (78) projects with the potential for delivery of 46 646 social housing units.
c) Fifty-three (53) social housing projects with 25 891 social housing units have been approved and are at different stages of construction.
08 November 2022 - NW3696
Mogale, Mr T to ask the Minister of Human Settlements
What total (a) amount of the budget was allocated for the residential relief programme for tenants affected by COVID-19 lockdowns and (b) number of tenants (i) benefitted from the relief programme nationally and (ii) from Thembelihle in Tshwane were beneficiaries of the programme; (2) whether she has been informed of the hostile relationship between the managing agency and the tenants in Thembelihle; if not, what is the position in this regard; if so, what steps have been taken to resolve issues raised by the tenants in relation to excessive billing by the private metering companies?
Reply:
1. (a) A total of R300 million was allocated for the rent relief programme for tenants affected by the impact of the National State of Disaster on COVID-19.
(b) Based on information received from the Social Housing Regulatory Authority (SHRA), two hundred and one (201) households have benefitted nationally from the programme. In addition, post-March 2022 applications have been reassessed based on further revisions to the policy in February 2022, based on representations to the Minister. Thus, an additional two hundred and eight (208) households have been approved to benefit from the programme, subject to the approval of the retention of the surplus by the National Treasury.
(2) A Memorandum was submitted in June 2020 to Yeast City Housing which developed and managed the Thembelihle Village Social Rental Project and these required several interventions, which are in various stages of agreement and resolution. This included cancelling the contract Sand’s several interventions were actioned. This included cancelling the contract of a utility billing service provider, procuring the prepaid metering systems, installation of biometric access systems, and instituting legal process cases for non-payers and instigators of violence in the Thembelihle Village Social Rental Housing project.
Additional Information on the Thebelihle Village and Landlord Dispute
The current hostility is caused by some tenants who do want to comply with the provisions of their lease agreements signed with the Social Housing Institution, namely Yeast City Housing, when they rented the units at Thembelihle Village in the City of Tshwane between 2018 and 2020 the billing of utilities was outsourced. Yeast City Housing did not have the resources and capabilities to undertake the billing function. The rates charged aligned with the charges by the City of Tshwane to its residential customers (although this was challenged).
From October to December 2020 some tenants boycotted the project and destroyed equipment, intimidated staff, and tampered with the meters. The service provider was forced to resign, and some tenants were found by the Court to have caused the violence and tampered with the meters and given five (5) year suspended prison sentences.
Yeast City Housing staff now undertake meter readings, and the calculations of the amount payable is outsourced and currently, tenants appear to be satisfied as the billing is done in accordance with the rates per unit prescribed by the Municipality (City of Tshwane). However, as at 31 March 2022 the tenants owe Yeast City Housing R17 million (rental arrears) and also did not pay for utilities, which results in the City of Tshwane being owed R9, 9 million. The City disconnected water and electricity due to non-payment of the arrears and tenants again became agitated damaging the company’s property and intimidating the staff.
Tenants requested prepaid electricity meters (at a cost of approximately R5 million) and Yeast City Housing agreed to this. However, the equipment is held by the supplier, which is the City of Tshwane and cannot be installed before payment of 60% of outstanding arrears of 9, 9 million (which is approximately 5, 5 million) of the municipal arrears and payment arrangements for the remainder.
This was communicated to the tenants on 31 March 2022, but tenants remain unwilling to pay and legal action has been initiated against the tenants who refuse to pay their rentals and the outstanding utilities. The Local Ward Councillor, Cllr. Conride Ngoveni, is fully aware of the situation and was also involved in the negotiations for the tenants to pay their arrears.
17 October 2022 - NW2581
Powell, Ms EL to ask the Minister of Human Settlements
(1) What was the total amount that was allocated for the (a) Urban Settlement Development Grant, (b) Human Settlements Grant, (c) Development Grant, (d) Emergency Housing Programme Grant and (e) Informal Settlement Upgrading Programme Grant in KwaZulu-Natal in the (i) 2021-22 and (ii) 2022-23 financial years (2) what amounts have been transferred against the specified amounts of the grants as at the latest specified date for which information is available; (3) what are the relevant details of all approved reprioritisation from existing and future budget allocations from the grants for the specific purposes of flood relief in KwaZulu-Natal? NW3096E
Reply:
1). The allocations of Human Settlements Grants in the KwaZulu-Natal Province:
(i) 2021/22 Financial Year
Provincial Allocations- KwaZulu-Natal Province
Name of Grant |
Allocations (R’000) |
Human Settlements Development Grant |
2 455 021 |
Informal Settlement Upgrading Programme Grant |
714 375 |
Provincial Emergency Housing Grant |
- |
Municipal Allocations-eThekwini Metropolitan Municipality
Name of Grant |
Allocations (R’000) |
Urban Settlements Development Grant |
1 288 158 |
Informal Settlement Upgrading Programme Grant |
686 369 |
(ii) 2022/23 Financial Year
Provincial Allocations- KwaZulu-Natal Province
Name of Grant |
Allocations (R’000) |
Human Settlements Development Grant |
2 935 224 |
Informal Settlement Upgrading Programme Grant in KwaZulu-Natal |
756 868 |
Provincial Emergency Housing Grant |
- |
Municipal Allocations- eThekwini Metropolitan Municipality
Name of Grant |
Allocations (R’000) |
Urban Settlements Development Grant |
1 279 036 |
Informal Settlements Upgrading Partnership Grant |
727 265 |
2). Transferred Amounts
(i) 2021/22 Financial Year
Provincial Grant Transfers
Name of Grant |
Allocations (R’000) |
Transferred (R’000) |
Human Settlements Development Grant |
2 455 021 |
2 455 021 |
Informal Settlements Upgrading Partnership Grant |
714 375 |
714 375 |
Provincial Emergency Housing Grant |
- |
- |
Municipal Grant Transfers- eThekwini Metropolitan Municipality
Name of Grant |
Allocations (R’000) |
Transferred Funds (R’000) |
Urban Settlements Development Grant |
1 288 158 |
1 288 158 |
Informal Settlements Upgrading Partnership Grant |
686 369 |
686 369 |
Municipal Emergency Housing Grant |
- |
- |
(ii) 2022/23 Financial Year
Provincial Grant Transfers as at 31 August 2022
Name of Grant |
Allocations R’000) |
Transferred Funds (R’000) |
Human Settlements Development Grant |
2 935 224 |
1 472 072 |
Informal Settlements Upgrading Partnership Grant |
756 868 |
415 937 |
Provincial Emergency Housing Grant |
325 764 |
140 003 |
Municipal Grant Transfers as at 31 August 2022
Name of Grant |
Allocations (R’000) |
Transferred (R’000) |
Urban Settlements Development Grant |
1 279 036 |
447 663 |
Informal Settlements Upgrading Partnership Grant |
727 269 |
363 633 |
Municipal Emergency Housing Grant |
- |
- |
3). Relevant details of all approved reprioritization from existing and future budget allocations from the grants for the specific purposes of flood relief in KwaZulu-Natal:
(i) KwaZulu-Natal Province
a) Human Settlements Development Grant
The natural disasters that occurred recently implied that the National Department had to approve the entire annual allocation of Provincial Emergency Housing Grant (PEHG) amounting to R326 million to assist the reported disaster of KwaZulu-Natal Province and therefore had no funds afterwards to assist any other Province with similar funding needs.
In the case of KwaZulu-Natal Province, an amount of R515 million (HSDG-R326 million and ISUPG – R189 million) was reprioritised by the Province to address the disaster and after the PEHG was approved, the Province decided to utilise the R326 million from PEHG and reverse the same amount which was reprioritised to address the disaster back to the HSDG.This implied that the Province still has the full annual allocation of HSDG of R2.9 billion to address human settlements needs for the 2022/23 financial year.
b) Informal Settlements Upgrading Partnership Grant
The Province had reprioritised R189 million from ISUPG and that amount remains to cater for the widely reported and declared disaster. The annual allocation of the grant amounts to R727 million for this current financial year.
(ii) eThekwini Metropolitan Municipality
Municipal Reprioritised Funds from the Urban Settlements Development Grant (USDG) and Informal Settlements Development Grant (ISUPG) for Municipalities are for the 2022/23 financial year as detailed below:
a) Urban Settlements Development Grant (USDG)-R340.3 million
- Sundry replacements (Blocksum) and replacement of network to ensure security of supply to existing customers - R14.4 million;
- Repair of damaged road surface, sidewalks, manhole, storm recovery, bridges, catch pit, embankments Damaged gabion, road reinstatement and storm water repairs in various areas – R218.4 million;
- Marrianhill Storm Water Protection and Environments Protection, replacement of Leachate Treatment Plants, Sundry Replacements (Blocksum) Lovu Landfill cell PH and Infrastructure, Bisassar Road Landfill – R72.3 million; and
- Tongaat Water Treatment Works Remedial to storm damage – R35.2 million.
b) Informal Settlements Upgrading Partnership Grant – R124.4 million
- Purchase of land in Quarry Road West and Ezingwenyeni Informal Settlements – R8 million; and
- Three projects for refurbishment or rehabilitate the infrastructure damaged by storm in various informal settlements namely, Dassenhook Informal Settlement, Salvia Place Informal Settlement, Quarry Road Informal Settlement, Umlazi Z and Q Informal Settlement and Mayville Informal Settlement – R116.4 million.
17 October 2022 - NW2582
Powell, Ms EL to ask the Minister of Human Settlements
(1) What are the details of (a) any additional funding and/or (b) reprioritisation from her department that will be transferred to either the KwaZulu-Natal Provincial administration or the City of eThekwini for flood relief purposes over and above the different types of Human Settlements grants;
Reply:
a). Additional Funding
There is no additional funding for either the Province or the Metro of Human settlements grants provided in the current financial year.
b). Reprioritization
An amount of R340.3 million was reprioritised under Urban Settlement Development Grant (USDG) and R124.4 million under Informal Settlements Upgrading Partnership Grant (ISUPG). These reprioritised funds, as part of the 2022/23 annual allocations, have already been transferred to eThekwini Metropolitan Municipality for the reprioritization for the flooding disaster relief purposes. It should be noted that the above-stated funds are not additional funds but are part of the allocated 2022/23 financial year.
(2) What are the details of the impact of the above-mentioned local, provincial or national reprioritisation of any Human Settlements grants on the provision of housing and basic services in the (a) 2021-22 and (b) 2022-23 financial years? NW3097E
a) 2021-22 financial year
There were no declared disasters that necessitated the reprioritisation measure during the 2021/22 financial year. The Provinces and Metropolitan Municipalities were able to continue with the normal operational tasks as expected of them without any impact on the annual budgets allocated to the Province.
b) 2022-23 financial year
(i) KwaZulu-Natal Provincial Department of Human Settlements
The natural disasters that occurred recently implied that the National Department had to approve the entire annual allocation of Provincial Emergency Housing Grant (PEHG) amounting to R326 million to assist the reported disaster of KwaZulu-Natal Province and therefore had no funds afterwards to assist any other Province with similar funding needs.
In the case of KwaZulu-Natal Province, an amount of R515 million (HSDG-R326 million and ISUPG – R189 million) was reprioritised by the Province to address the disaster and after the PEHG was approved, the Province decided to utilise the R326 million from PEHG and reverse the same amount which was reprioritised to address the disaster back to the HSDG. This implied that the Province still has the full annual allocation of HSDG of R2.9 billion to address human settlements needs for the 2022/23 financial year
(ii) eThekwini Metropolitan Municipality
The Metro reprioritised funds allocated under Urban Settlements Development Grant amounting to R340.3 million to cater for the following projects:
- Sundry replacements (Blocksum) and replacement of network to ensure security of supply to existing customers - R14.4 million;
- Repair of damaged road surface, sidewalks, manhole, storm recovery, bridges, catch pit, embankments Damaged gabion, road reinstatement and stormwater repairs in various areas – R218.4 million;
- Marrianhill stormwater Protection and Environments Protection, replacement of Leachate Treatment Plants, Sundry Replacements (Blocksum) Lovu Landfill cell PH and Infrastructure, Bisassar Road Landfill – R72.3 million; and
- Tongaat Water Treatment Works Remedial to storm damage – R35.2 million
Under the Informal Settlement Upgrading Partnership Grant, the Metro reprioritised an amount of R124.4 million to cater for:
- Purchase of land in Quarry Road West and Ezingwenyeni Informal Settlements – R8 million; and
- Three projects for refurbishment or rehabilitation of the infrastructure damaged by the storm in various informal settlements namely, Dassenhook Informal Settlement, Salvia Place Informal Settlement, Quarry Road Informal Settlement, Umlazi Z and Q Informal Settlement and Mayville Informal Settlement – R116.4 million.
14 October 2022 - NW3373
Mohlala, Ms MR to ask the Minister of Human Settlements
(1) (a) Who was the service provider for the 50 housing shack structures in Burgersfort in the Sekhukhune region project which was ultimately cancelled, (b) what total amount did the Government pay before the specified project was halted and (c) who approved the deal to build shoddy houses in Burgersfort: (2) Whether any consequences management measures were applied to any of the officials involved; if not, why not; if so, what are the relevant details?
Reply:
(1)(a) The Limpopo Provincial Department of Cooperative Governance, Human Settlements and Traditional Affairs has indicated that Aventino Group had been appointed as the service provider for the project.
(b) The Limpopo Provincial Department also advised that no payment was made on the Burgersfort project that was halted.
(c) It further advised that the Housing Development Agency had been appointed as the implementing agent for the project, and therefore it was responsible for the appointment of the service provider.
(2) The Limpopo Provincial Department has advised that as part of consequence management three officials that were involved in the contract were placed on precautionary leave and subjected to a disciplinary process.
14 October 2022 - NW3387
Khawula, Ms MS to ask the Minister of Human Settlements
Whether she has considered reviewing the size of the houses built under the Breaking New Ground; if not, why not; if so what are the relevant details.
Reply:
The Department has done a number of reviews and evaluations together with the Department of Planning, Monitoring and Evaluation (DPME) and has increased the size of the gross floor area for constructing subsidised houses.
The minimum and maximum size of the subsidised houses to be provided to beneficiaries of the Housing Subsidy Scheme are as follows:
- 24 – 30 square metres of gross floor area for temporary residential units.
- 30 square metres of gross floor area for social housing units
- 40 square metres of gross floor area for persons without any disabilities.
- 45 square metres of gross floor area for a person with disabilities using a wheelchair and
- 45 square metres of gross floor area for the higher density designs in a form of different layouts such as a double storey semi-detached units; or three-storey walk-up units
- 50m2 square metres house is provided for qualifying military veterans in line with the Regulations published by the Department of Military Veterans.
The subsidised houses have to be built in line with South African National Building Regulations Standards ( SANS) and the National Home Building Regulations Council has to ensure that these standards are met.
Effecting changes in the gross floor area (size) of the house to be constructed brings more cost over and above the changes that are brought by inflation. As it stands, the current subsidy amount available for financing a 40 square metre house is R141 294. In the case of subsidised houses for Disabled Persons and Military Veterans the subsidy amount increases to R209 072 and R240 608 respectively.
In light of the fact that the budget allocated to the Department becomes less every year and that any increases in the size of subsidised housing will result in a substantial increase in cost, it would not be advisable to implement such an increase as it would result in a decrease in the delivery of housing units.
14 October 2022 - NW3066
Msane, Ms TP to ask the Minister of Human Settlements
a) What is the status of her department’s Alexandra Human Settlements Progress Report on the title deeds and / or transfer of restorable properties and (b) by what date will her department finalise the specified report.
Reply:
(a+ b) The National Department has referred the matter to the Gauteng province and will provide a detailed and final reply as soon as the information is obtained.
14 October 2022 - NW3065
Tafeni, Ms N to ask the Minister of Human Settlements
What total (a) number of low cost houses has she had to demolish and rebuilt as a result of poor workmanship and (b) amount has been spent on this? NW 3705 E
Reply:
Three, Gauteng, Kwa Zulu Natal and Northern Cape responded to Parliamentary Question 3065 as follows:
1. Gauteng
- The Gauteng Department of Human Settlements does not have houses to be demolished because of poor workmanship. The construction of houses/units are done in stages, e.g., foundation, wall plate, roof, and completions. These stages are also used as payment milestones for each stage completed and compliant. If non-compliance or incompleteness is observed during inspection, no approval is granted until the snags are fixed.
- No additional amount is spent because houses are still under construction and would be fixed before approval is granted to the next milestone.
2. Kwa Zulu Natal
a) The Department enrols all new developments with NHBRC, which acts as a quality assurer and keeps a register of contractors. When poor workmanship is identified, it is reffered to the contractor to repair at own cost.
The Department has embarked on a programme to repair units with structural damages that were constructed in the earlier years of the housing development programme. The units were constructed prior to the enrolment with NHBRC. 10 368 units have been rectified under this programme.
b) The amount spent for the rectification of 10 368 units was R976 521 000.
3. Northern Cape
- There has not been any houses demolished and repaired in the Northern Cape.
- No expended has been incurred in the Province for repairs.
14 October 2022 - NW2915
Buthelezi, Ms SA to ask the Minister of Human Settlements
In view of the fact that the Social Housing Regulatory Authority (SHRA) is mandated to invest in, regulate and transform the social housing sector, and that the authority has also been increasing its capacity to deal with non- compliance, what (a) are the details of the (i) interventions that have been implemented to increase the capacity of the SHRA in order to deal with non-compliance and (ii) cases of non-compliance that SHRA has managed and (b) total amount that has been lost through non-compliance cases thus far?
Reply:
(a)(i) To strengthen the SHRA’s regulatory role and to build a sector that is capable of delivery and management of social housing at the level of scale and form required, the Compliance, Accreditation and Regulation (CAR) Operational Framework was reviewed. Implementation is underway, with the SHRA aiming to increase its internal capacity and reduce the past reliance on consultants. Organisational capacitation of key personnel including resources to provide more in-depth compliance monitoring and a Regulations Manager and to increase in-house capacity when dealing with issues of regulatory enforcement and non-compliance, in line with section 12 provisions contained within the Social Housing Act 16 of 2008 are being implemented.
(a)(ii) Cases of non-compliances which have escalated for enforcement relates to the following institutions:
- Free State Social Housing Company: Placed Under Administration.
- Troyeville Housing Cooperative: Placed under Administration.
- Communicare: Allegations of maladministration have been made against the institution, and the finalisation of a forensic investigation is imminent.
- Housing Association East London (Belgravia): Failure to meet compliance conditions has resulted in a downgrading of accreditation status. There are suspected grounds of maladministration, and a forensic audit has been approved.
- Urban Scape Rentals: Failure to meet compliance conditions has resulted in a downgrading of accreditation status. There are suspected grounds of maladministration, and a forensic audit has been approved.
(b) Irregular expenditure incurred in the past five years pertain to investing in projects that fell outside a restructuring zone, which has since been declared and regularised. The remaining irregular expenditure relates to a single grant recipient (TBGI) amounting to R26.7 million which is being dealt with by implementing the court judgement to recover the funds – a loss cannot be established at this stage.
There have been no funds lost through non-compliance, as most non-compliance has been limited to the submission of documents. Three institutions are about to be taken through regulatory enforcement and forensic investigations are to be conducted. These are Housing Authority of East London (HAEL), Urban Scape and Communicare. The extent of maladministration and if funds have been lost, can only be ascertained when these investigations are concluded.
14 October 2022 - NW2846
Buthelezi, Ms SA to ask the Minister of Human Settlements
1) Whether, with reference to the perceived ambivalence of the Government towards Informal Settlements and poor development of implementation and capacity mechanisms, there has been any proactive programmes her Department initiated to tackle this, if not, why not, if so, what are the relevant details thereof; 2) Whether she has found that the specified programmes have been successful in dealing with the deficiencies that surround the construction of viable housing; if not, why not, if so, what are the relevant details?
Reply:
(1) The Informal Settlements Upgrading Programme was instituted in terms of section 3(4) (g) of the Housing Act, 1997 (Act No. 107 of 1997), (The Housing Act) and is reffered to as the National Housing Programme: Upgrading of Informal Settlements. The programme seeks to facilitate the structured in situ upgrading of informal settlements as opposed to relocation to achieve, tenure security, health & security and empowerment etc.
In 2019/2020, the National Department of Human Settlements in consultation with the National Treasury introduced the Informal Settlements Upgrading Partnership Grant (ISUPG), this was an attempt by the Department to ensure that there is a focus on the upgrading of informal settlements projects within the sector. The main objective of the Grant was to strengthen the policy in relation to the Informal Settlements Upgrading Programme, for both provinces and metropolitan municipalities. The Grant seeks to ensure the provision of basic services such as water, electricity, roads, stormwater, refuse removal and sanitation services to households.
To support the implementation of the Grant, a total budget of R14.7 billion was reprioritised from the Human settlements Development Grant (HSDG) and Urban Settlements Development Grant (USDG) in 2020/21 and 2021/2022. The funds were set aside to support the upgrading of 231 000 households in informal settlements over the medium-term.
2. In terms of finding out whether the identified programmes have been successful in dealing with the deficiencies that surround the construction of viable housing, it must be noted that the introduction of the dedicated Informal Settlements Upgrading Partnership Grant was in 2019/2020 and actual implementation started during the 2021/22 financial year, thus it is still too early for the Department to pronounce on the success or failure of the Grant in dealing with the deficiencies that surround the construction of viable housing. However, the non-financial performance of the programme in provinces and municipalities was provided and reported that 610 informal settlements were upgraded by provinces and 674 by metropolitan municipalities during the 2021/22 financial year. Furthermore, a total of 21 075 sites were provided with basic services such as electricity, water and sanitation by provinces and a total of 3 596 sites by metropolitan municipalities in 2021/22.
14 October 2022 - NW2489
Mey, Mr P to ask the Minister of Human Settlements
(1) (a) What (i) is the total number of employees of her department who are currently working from home (ii) the number of such who employees have special permission to work from home and (iii) are the reasons for granting such special permission and (b) on what date will such workers return to their respective offices; (2) Whether she will make a statement on the matter.
Reply:
(1) (a) (i)
No employees of the department are currently working from home, this is in line with section 4 of the Department of Public Service and Administration (DPSA) Circular 38 of 2022 (29/06/2022): REPEAL OF THE REGULATIONS RELATING TO THE SURVEILLANCE AND CONTROL OF NOTIFIABLE MEDICAL CONDITIONS, which states that ‘Departments are required to ensure that all employees return to normal work conditions with no restrictions.’
(1) (a) (ii)
Not applicable.”
(1) (a) (iii)
Not applicable
1) (b)
Not applicable
(2)
A statement on the matter will not be made as employees have returned to the office at 100% capacity, in line with Circular 38 of 2022.
14 October 2022 - NW2859
Siwisa, Ms AM to ask the Minister of Human Settlements
Which intervention has her department taken to ensure that houses that were built in ward 4, Ubuntu in Victoria West in 2022, are completed and (b) what disciplinary measures have been taken against the contractor for the incomplete project?
Reply:
a ) The Northern Cape Provincial Department of Human Settlements has advised that it has directed the National Home Builders Registration Council (NHBRC) to conduct a forensic investigation in order to determine all the relevant facts and reasons for the project not being completed and the mitigation measures required. The investigation has been completed by the NHBRC and a report referred to the Petitions Committee in the province for consideration. Once the report has been considered, the provincial department will take the required measures against the said contractor as recommended by the NHBRC and the Petitions Committee.
b) No disciplinary measures have been taken by the provincial department as yet pending the outcome and recommendations of the NHBRC and the Petitions Committee.
14 October 2022 - NW3438
Mokgotho, Ms SM to ask the Minister of Human Settlements
What plan has she put in place to ensure that the housing project in ward 24 in the Elias Motsoaledi Local Municipality is completed by her department?
Reply:
The Limpopo Provincial Department of Cooperative Government, Human Settlements and Traditional Affairs (CoGHSTA) has advised that it has appointed Kgawana Construction and Enterprise CC to construct ten (10) houses in Ward 24 and that the contractor is currently on site. It has further indicated that the contractor is anticipating to complete all the houses as per Implementation Plan by the end of January 2023.
13 October 2022 - NW2914
Buthelezi, Ms SA to ask the Minister of Human Settlements
(1) With reference to the State of the Cities Report released earlier this year by the South African Cities Network, which indicates that 1 in 5 people in Johannesburg and Cape Town live in Informal settlements, and in my view of the fact that Cabinet has approved just over 14 000 hectares made up of 167 portions of land held by the Department of Public Works and Infrastructure for release for human settlements development and the portions of land will be held by the Housing Development Agency, while the programme is aimed at providing the poor and marginalised access to land in urban areas. (a) What criteria will be used to allocate land, (b) on what date is it envisaged within this current financial year that the reported 7000 hectors of land will be released and (c) what plans does the Government have in place to ensure delivery of services to those who settle on the land?
Reply:
(1)(a) The identified and targeted land parcels are required for the implementation of various key human settlements programmes which include upgrading of informal settlements, rural housing programme, social housing, integrated residential development programme, title restoration programme (tenure upgrading) and the finance-linked individual subsidy programme. The respective programmes, therefore provide for criteria for allocation of completed units with preference being given to local qualifying beneficiaries residing within the specific localities where the projects are located.
The generic qualification criteria for housing subsidy and therefore land allocation are the following:
- A lawful resident of South Africa or in possession of permanent residence status.
- Legally competent to contract.
- Not yet benefited from government housing assistance.
- Married or cohabiting.
- Single with financial dependents, must reside permanently with the applicant.
- Single persons without financial dependents – apply for purchase of a vacant serviced site or rental accommodation.
- Monthly household income (proof of income required), R0 – R3500 for a full housing subsidy, R3501 – R 22 000 for a partial subsidy known as Finance Linked Individual Subsidy Programme (FLISP).
(1)(b) The Department of Public Works and Infrastructure (DPWI) has already released 2491 hectares of land located in all nine provinces and seventeen municipalities for human settlements development purposes.
DPWI targets to conclude the release of over 7000 hectares of land for human settlements by the end of the current financial year. Additional land parcels have also in the meantime been identified by various municipalities for human settlements development including emergency housing
(1)(c) The Housing Development Agency works with the respective municipalities and the provinces to ensure joint development planning of the released land parcels. This includes coordination and monitoring of infrastructure planning and budgeting for the required services to support human settlements projects.
13 October 2022 - NW3055
Tafeni, Ms N to ask the Minister of Human Settlements
What (a) form of support will her Department provide to i) non-governmental organizations and ii) civil society organizations for the acceleration of sustainable and integrated human settlements and (b) what opportunities does her Department provide to the sector to participate in the acceleration of human settlements?
Reply:
(a) (i) The current housing and human settlements policy framework makes provision for various roles that Non-governmental Organizations (NGOs), as well as Civil Society Organizations (CSOs), can and do play within the human settlements value chain. This is evident in the role played by the sector in the implementation of the People’s Housing Process (PHP) programme. In various Provinces and Municipalities, NGOs and/or CBOs are participants in the housing delivery process either as support and/or as community resource organisations. The current grant framework for the Informal Settlements Upgrading Grant now also allows for NGOs and CBOs to form part of the implementing teams when an informal settlement is upgraded.
(ii) The NGOs and CBOs provide the necessary support to communities, provinces, and municipalities in various programmes, and this includes social facilitation. The policies allow for the conclusion of social compacts and partnership agreements to be concluded signed with the CSOs and NGOs, to allow for the sector to be part of the delivery of human settlements. Our various policy and legislative reviews also ensure that the sector is consulted and assists in the development and review of human settlements legislation and policies.
(b) The Department has constantly held consultations and engagements with the sector to ensure that they continue supporting Provinces and Municipalities in the implementation of human settlements programmes.
Based on various Memoranda of Understanding (MoU), Social Compacts and Partnership Agreements signed with the Sector in past years, a number of CSOs and NGOs continue to support provinces, municipalities and communities in the delivery of sustainable integrated human settlements.
Among the opportunities created by the Department for sector participation in the housing and human settlements delivery chain, and include:
- The sector has worked with the Department, Provinces and Municipalities to build the capacity and empowerment of communities, promote active citizenry, and provided support to these communities in Provinces/Municipalities that implement the PHP programme.
- Some of the CBO and NGO sector partners are involved in the enumeration and profiling of beneficiaries within settlements and the feedback assists Provinces in planning for the upgrading of informal settlements.
- The sector partners are also involved in re-blocking which entails that prior to a settlement being upgraded with infrastructure and services, the settlement is reordered in terms of an approved or draft layout plan. This also allows households to access emergency health services as well as collection and provision of interim municipal services.
- During the period of the recent COVID-19 pandemic, NGOs and CSOs supported the Department, Provinces, and Municipalities in the identification of informal settlements without water and sanitation and ensured that such settlements are provided with these basic services. The sector partners also supported provinces and municipalities in the distribution of Personal Protective Equipment (PPE) in informal settlements.
One of the outcomes of the 2022 Human Settlements Indaba, is that the Department will intensify and resuscitate quarterly engagement sessions with the sector to monitor and oversight various agreements and commitments made with regard to the sector involvement in the housing and human settlements delivery chain.
13 October 2022 - NW2916
Buthelezi, Ms SA to ask the Minister of Human Settlements
In view of the success of the social housing programme relies on, amongst other things, the creation of more sustainable social housing institutions and the development of mechanism for better social housing management, what (a) has her department done to (i) develop and capacitate social housing institutions and (ii) develop a mechanism for social housing management and (b) mechanism in place for the monitoring and evaluation of the social housing programme
Reply:
(a) (i) & (ii) Capitation and mechanisms are largely driven through Institutional Investment Grant (IIG) support which include training, incubation, and project packaging support summarised as follows:
Social Housing Training rolled out, nineteen (19) training sessions were conducted reaching over a thousand participants countrywide. Topics included Introduction to Social Housing, Planning and Project Packaging a Social Housing Project, Governance Training, Property Management and Social Housing Institution Accreditation Process training. To increase accessibility, reach and raise awareness the training has been converted to a series of short 5-10 minute videos available on the Social Housing Regulatory Authority (SHRA) website.
Incubation Programme – in the 2021/22 financial, year, nine (9) Social Housing Institutions (SHI) received support under this multi-year programme. Two of these we successful in registering potential Social Housing Projects in the pipeline and received further grand funding to carry out project feasibility studies on these projects. One of these SHIs has since began with construction of the project and has been provided with legal support around contracting.
Pre-Accreditation Grant support – five (5) emerging companies are supported for Accreditation.
(b) Through compliance monitoring on the performance of institutions areas of poor performance and areas of improvement are identified. Tenancy audits and building condition audits undertaken by SHRA have led to the development and implementation of remedial action plans.
Failure to adhere to the remedial actions identified would then result in enforcing powers of intervention (section 12 of the Social Housing Act 16 of 2008) permits the SHRA to undertake forensic investigations and in instances where maladministration is identified seek for a high-court application to place the institution under administration.
The Social Housing Act 16 of 2008 specifies that the delivery of sustainable Social Housing requires participation of National Government, Provincial Government, Local Authorities, and the Regulator.
As a schedule 3A public entity, the SHRA under the Human Settlements portfolio is required to comply with the legislative prescripts such as the Public Finance Management Act 1 of 1999 and the Department of Public Monitoring and Evaluation (DPME) revised framework for Strategic and Annual Performance Plans. The National Department of Human Settlements is in the process of a mid-term review of its programmes.
13 October 2022 - NW2865
Mohlala, Ms MR to ask the Minister of Human Settlements
What are the (a) full details of the progress with regard to the R255 million Free State asbestos corruption case and (b) reasons that it has taken so long to arrest the former Head of the Gauteng Department of Human Settlements, Ms. Ann Diedricks?
Reply:
a) The Free State Provincial Department of Human Settlements indicated that 13 accused have been charged by the State and are going to appear in the Bloemfontein High Court on the 23rd of September 2022. Amongst the individuals charged are the following: former HOD of the Department and three current employees namely the Chief Financial Officer, Chief Director responsible for Project Management and the Director responsible for Supply Chain Management.
b) The Gauteng Provincial Department of Human Settlements did not open a criminal case against the former Acting Head of the Gauteng Department of Human Settlements. The appropriate organ of state to respond to this Question is the Free State Directorate of Priority Crimes Investigation (DPCI) which is investigating the matter.
13 October 2022 - NW2844
Buthelezi, Ms SA to ask the Minister of Human Settlements
What total (a) number of employees of her department have been fingered as perpetrators of scams and other illegal activity, (b) the number of cases and or complaints have been brought against her department and its employees in this regard and (c) amount did it cost her department in the past five financial years?
Reply:
a) Two officials were fingered in allegations of illegal activities.
b) Two cases were referred to the Department and one criminal case was opened with the South African Police Service (SAPS) and the matter is currently in court and the other matter is still under investigation within the department; and
c) The Department lost an amount of R320,0000.00, during 2018/2019 financial period through two fraudulent payments and the other matter was reported in 2022/2023 financial period. The matter is still under investigation and the determination of financial implications will be concluded once the investigation has been completed.
03 October 2022 - NW2785
Powell, Ms EL to ask the Minister of Human Settlements
Whether she will furnish Ms E L Powell with the details of (a) all contracts awarded to training and development service providers, (b) the breakdown of costs for training and development services in the (i) 2021-22 and (ii) 2022-23 financial years, (c) the number of persons trained, (d) the NQF level of the training attained, (e) the certificates awarded and (f) the amounts spent on travel, venues and catering from the cost centre; if not, what is the position in this regard: if so, what are the relevant details?
Reply:
a) Contracts awarded to training and development service providers:
The Department has not awarded any contracts to training and development service providers. When a training and development request is received, a RFQ is issued to Supply Chain Management to obtain quotations which are sourced as per National Treasury requirements for service providers through the Central Supplier Database through National Treasury.
b) The breakdown of costs for training and development services in the (i) 2021-22 and (ii) 2022-23 financial years is tabulated below:
Description |
Amount Spent |
2021-22 Financial Year |
|
Bursaries |
R1 237 000.00 |
NQF aligned Training and Development |
R346 820.49 |
Non NQF aligned Training and Development |
R567 238.51 |
Internship |
R849 781.68 |
Total spent |
R3 000 840.68 |
2022-23 Financial Year |
|
Bursaries |
R117 791.00 |
NQF aligned Training and Development |
R0.00 |
Non NQF aligned Training and Development |
R390 193.00 |
Total spent |
R507 984.00 |
c) The number of persons trained:
The number of staff members trained in the Department for:
- 2021-22 financial year amounts to 185 staff members for NQF and Non-NQF aligned training; and
- 2022-23 financial year amounts to 34 staff members trained for Non-NQF training from 01 April to 05 September 2022.
d) The NQF level of the training attained is tabulated below
NQF Training and Development Interventions for staff :2021-22 |
||
NQF Training and Development |
||
NQF Level |
Intervention |
Number of staff members |
NQF levels 1-3 |
SHE Representative training |
25 |
NQF levels 1-3 |
Fire Fighting training |
25 |
NQF levels 1-3 |
Evacuation Marshal training |
25 |
NQF levels 4-6 |
Assessor training |
1 |
NQF levels 4-6 |
Moderator training |
1 |
Qualifications |
||
NQF level 6 |
BA in Public Administration and Communication Facilitation |
1 |
NQF level 8 |
BCom Honours: Industrial & Organisational Psychology |
1 |
BCom Business Management |
1 |
|
BCom Media Studies |
1 |
|
BCom Integrated Organizational Communication |
1 |
|
B-Tech Project Management |
1 |
|
B-Tech Forensic Investigation |
1 |
|
Postgraduate Diploma Management |
2 |
|
Postgraduate Diploma in Public Administration |
1 |
|
Bachelor of Law |
1 |
|
NQF level 9 |
Master’s in Business Leadership |
1 |
Master’s in Business Administration |
2 |
|
Masters in Urban Infrastructure Design and Management |
1 |
e) The certificates awarded to staff:
Certificates awarded to staff members for 2021-22 and 2022-23 financial years are:
NQF, Non-NQF Training and Development Interventions and Qualifications obtained by staff for 2021-22 and 2022-23 financial years |
||
NQF Training and Development |
||
NQF/ Non Level |
Intervention |
Number of staff members |
Certificate as per Programme |
||
None NQF training |
Executive Education Programme |
2 |
Certificate as per Qualifications |
||
NQF level 6 |
BA in Public Administration and Communication Facilitation |
1 |
NQF level 8 |
BCom Honours: Industrial & Organisational Psychology |
1 |
BCom Business Management |
1 |
|
BCom Media Studies |
1 |
|
BCom Integrated Organizational Communication |
1 |
|
B-Tech Project Management |
1 |
|
B-Tech Forensic Investigation |
1 |
|
Postgraduate Diploma Management |
2 |
|
Postgraduate Diploma in Public Administration |
1 |
|
Bachelor of Law |
1 |
|
NQF level 9 |
Master’s in Business Leadership |
1 |
Master’s in Business Administration |
2 |
|
Masters in Urban Infrastructure Design and Management |
1 |
f) The amounts spent on travel, venues and catering from the cost centre:
The amount spent on travel, venues and catering for:
- 2021-22 financial cycle amounted to R38 400.00; and
- 2022-23 financial cycle (01 April to 05 September) amounts to R0.00.
03 October 2022 - NW3187
Malatsi, Mr MS to ask the Minister of Human Settlements
(1)On what date did she attend the last meeting of any structure outside the Government in order to receive recommendations on the deployment of personnel in her department and/or entities reporting to her; (2) whether any appointments to her department and/or entities reporting to her were discussed during her attendance at any private forum and/or external structures to the Government; if not, what is the position in this regard; if so, what (a) are the details of appointments that were discussed and recommendations received and (b) other Government matters were discussed during the last meeting of any such forum?
Reply:
I do not discuss my diary and political activities with those deemed not to be relevant on the matter. The member is requested to explain the relevance of the question to my work as a Minister.
19 September 2022 - NW2783
Powell, Ms EL to ask the Minister of Human Settlements
With regard to the Community Scheme Ombud Service (CSOS), what number (a) of the 1 191 cases that were referred for adjudication in the 2020-21 financial year were resolved, (b) were dismissed by the adjudicator and (c) of the cases that were dismissed by the adjudicator were due to technical shortcomings of the application and not due to the merit of the cases?
Reply:
a) A total of 410 disputes were referred to adjudication of which 109 adjudication orders were issued. Out of 1 191 disputes referred for conciliation, 331 were resolved. All three regions experienced a backlog during the 2020/21 financial year, with the total number of outstanding disputes estimated at 3 335. The backlog was cleared up in the 2021/22 financial year.
The table below depicts the breakdown of the adjudication and conciliation of disputes per region:
REGION |
REFERRED TO CONCILIATION |
CONCILIATED |
REFERRED TO ADJUDICATION |
ORDERS |
Gauteng |
557 |
201 |
360 |
99 |
Kwa-Zulu Natal
|
297 |
50 |
16 |
6 |
Western Cape |
337 |
80 |
34 |
4 |
TOTAL |
1191 |
331 |
410 |
109 |
b) The performance information in the 2020/2021 financial year did not have a filtering method for adjudications that were dismissed in the 2020/2021 financial year. The SharePoint system incorporated dismissals from the 2021/2022 financial year onwards. Out of the 109 adjudications, the Community Scheme Ombud Service (CSOS) is unable to determine which adjudication orders were for dismissals.
c) CSOS does not capture performance information that refers to dismissals for technical reasons. They are categorised as “Dismissals”. The CSOS Assessment and Quality Assurance processes ensures the elimination of dismissals for technicalities. Furthermore, adjudicators have the investigative powers to probe outstanding aspects of the disputes in order to proceed on the merits of the matter.
NATIONAL ASSEMBLY
QUESTION FOR WRITTEN REPLY
QUESTION NUMBER: PQ 2783 (NW3374E)
DATE OF PUBLICATION: 2 SEPTEMBER 2022
__________________________________________________________
MR J MARITZ
DIRECTOR: HUMAN SETTLEMENTS ENTITIES OVERSIGHT
DATE:
__________________________________________________________
Recommended / not recommended
MS S NGXONGO
ACTING DIRECTOR-GENERAL
DATE:
__________________________________________________________
Approved / not approved
MS MT KUBAYI, MP
MINISTER OF HUMAN SETTLEMENTS
DATE:
16 September 2022 - NW3000
Malatsi, Mr MS to ask the Minister of Human Settlements
Whether she and/or her Department submitted a policy review document and/or any other government policy document to structures outside of the Government, either to private and/or external structures or structures of any political affiliation during the past five years; if not, what is the position in this regard; if so, (a) will she furnish Mr M S Malatsi with copies of all such documents and (b) what are the reason that the Government documents were provided to each structure?
Reply:
No. The Department’s policy review and development process is informed and guided by the National Policy Development Framework, approved by Cabinet in 2020. The process sets out the following:
(a) A political manifesto of the Governing Party is a public declaration of policy and programmes aimed at improving the lives of citizens. These priorities are further processed through the government for implementation.
(b) The Manifesto of the Governing Party is processed for implementation through the Medium Term Strategic Framework (MTSF). The MTSF is the government’s strategic plan which reflects commitments made in the election manifesto of the governing party, as well as priorities of the National Development Plan (NDP).
The Framework guides the Department on policy review, policy development, policy authorisation, policy implementation and policy analysis. It sets standards and guiding principles for the entire policy making cycle and clarifies approaches to intra/inter departmental consultation and external stakeholder consultations during policy-making processes. The Framework enlightens the process through which a platform is created for an interaction between the Department and consultation with communities for participatory-based evidence.
In addition, since Housing is a concurrent function, the Department has a structured and systematic policy approval process which includes a multi-sectoral intergovernmental consultation forum in the form of the National Policy Task Team (NPTT). The NPTT comprises of Provinces, Metropolitan Municipalities, South African Local Government Association (SALGA); Human Settlements Entities, Civil Society, Chapter Nine Institutions, i.e. South African Human Rights Commission (SAHRC); Commission for Gender Equality (CGE), etc. To establish the envisaged developmental impact, rationale, associated risks, cost estimates and quality standards, the draft policy is subjected to the Socio-Economic Impact Assessment System (SEIAS) exercise at the Department of Planning, Monitoring and Evaluation (DPME).
If necessary, the draft policy will then be shared with the Chief State Law Advisor for concurrence. Thereafter it will be submitted for approval to a pertinent Ministerial Cluster, Ministers and Members of Executive Councils (MINMEC) and Technical MINMEC forums.
11 July 2022 - NW2037
Herron, Mr BN to ask the Minister of Human Settlements
With regard to her department’s policy review and proposed new Human Settlements Code, (a) on what date was the first Policy and Legal Expert Team (POLERT) successfully established and (b) what were the terms of office in the specified initiative; (2) what were the POLERT’s terms of reference; (3) what was the outcome of the POLERT’s work; (4) what was the total cost of the POLERT; (5) whether the POLERT has been terminated due to term limits; if not, what is the position in this regard; if so, (a) will there be a replacement and (b) what will the goals of that initiative be?
Reply:
1. (a) On the 27th of October 2018, the Department of Human Settlements appointed twenty-seven (27) persons as members of POLERT for a period of two (2), 13 Legal Experts, and 14 Policy Experts.
2. The terms of reference for POLERT were to assist the Department with, inter alia, the following:
a) To review the housing and human settlements macro policies such as the White Paper Housing, 1994, the Comprehensive Plan for the Development of Sustainable Human Settlements, 2004 (otherwise known as the ‘Breaking New Ground’ [BNG], including with International Treaties and Commitments such as the New Urban Agenda, and to further analyse the implications against other approved policies in the human settlements space, and to make recommendations for consideration by the Minister of Human Settlements;
b) To review the housing and human settlements legislation, and existing court judgments (jurisprudence), with a view to analysing the implications thereof and make appropriate recommendations for consideration by the Minister of Human Settlements, and
3. The outcome of the work carried out by POLERT includes, among others: The process of the incremental review of the Draft Housing and Human Settlements White Paper, 2016; Research and literature review, and the development of macro policy frameworks toward a Policy Foundation for Housing and Human Settlements White Paper, including the development of policy programmes for a new Human Settlements Code in at least four (4) critical themed areas - Integrated Planning and Residential Development, Informal Settlements Upgrading, Social Housing Interventions, and Affordable Housing.
These are underpinned by a macro policy framework on Human Settlements Land Assembly, Land Release (Site and Service) as well as the Individual Voucher Subsidy Programme, the programme for the removal of asbestos in homes, diagnostic investigation, and the empowerment of designated groups.
Over and above the initial assignment, some POLERT members were extensively utilised to formulate a Human Settlements response to the outbreak of the Covid-19 pandemic and the subsequent declaration of the State of Disaster and Lockdown for a sector that was hugely impacted upon, as part of the entire construction industry, by the pandemic.
4. The initial operational budget that was set aside for POLERT was R4 million for a period of two (2) years. An amount of R3 530 416, 40 was paid to POLERT members, with an additional amount of R187 520,00 for traveling costs. In all, a total of R3 717 936,40 was expended on POLERT.
5. Yes, POLERT has been terminated due to term limits. The initial contract period was two (2) years, after which an extension for a period of one (1) year was granted until the end of October 2021. Currently, there are no POLERT members and there are no contractual appointments under POLERT. (a) Yes, there will be a replacement and a procurement process to this effect has commenced (b) the goal will be to conclude the development of a Human Settlements Policy Foundation i.e. the White Paper on Human Settlements as well as the new Human Settlements Code.
08 July 2022 - NW2425
Mokgotho, Ms SM to ask the Minister of Human Settlements
On what date is it envisaged that her department will provide adequate housing for the community of Clarens in Thabo Mofutsanyana District Municipality in the Free State, which has been promised housing since 2007?
Reply:
Based on information provided by the Dihlabeng Local Municipality is currently finalizing various township establishment projects in Clarens, whereafter the sites will be made available to qualifying and approved households.
08 July 2022 - NW2400
Powell, Ms EL to ask the Minister of Human Settlements
(a) On what date did her department receive the application for funds from the Emergency Housing Programme Grant for flood relief in KwaZulu-Natal from the (i) KwaZulu-Natal Provincial Government and (ii) eThekwini Metropolitan Municipality and (b) what are the details of the (i) amounts disbursed and (ii) dates thereof?
Reply:
(a) The final consolidated application from both KwaZulu-Natal Department of Human Settlements and eThekwini Metropolitan municipality to access funds from the Provincial Emergency Housing Grant to provide 4983 Temporary Residential Units (TRUs) was received by the Department of Human Settlements on 5 May 2022.
(b) Due to the limited annual allocation for 2022/23 of funds in the Provincial Emergency Housing Grant (R325,8 million) and Municipal Emergency Housing Grant (R175,4 million) both the province and eThekwini Metropolitan Municipality were advised to reprioritise funding from the Human Settlements Development Grant and the Informal Settlements Upgrading Partnership Grant. Concurrently, eThekwini Metropolitan municipality was requested to reprioritise the Urban Settlements Development Grant and the Informal Settlements Upgrading Partnership Grant. These requests were meant to ensure that both the Province and eThekwini Metropolitan municipality is able to expeditiously assist floods victims whilst the application is being processed.
(i)The application was approved by this Department for the provision of 4983 Temporary Residential Units at a cost of R342 million. However, National Treasury could only approve an amount of R325,8 million which is the entire 2022/23 annual allocation of the Provincial Emergency Housing Grant. Furthermore, as the 2022 Division of Revenue Bill (DoRB) is not presently enacted, only R140.003 million could be transferred as the first tranche, in compliance with section 27 of the 2021 Division of Revenue Act. The second tranche can be made after the 2022 DoRB has been enacted.
(ii)The first tranche was disbursed to the Province on 17 June 2022.
08 July 2022 - NW1900
Powell, Ms EL to ask the Minister of Human Settlements
(a) What remedial assistance will be provided to beneficiaries of the Breaking New Ground houses that were destroyed during the KwaZulu-Natal floods and (b) on what date is it envisaged that such assistance will be provided?
Reply:
In terms of the provisions of the Constitution, policy, and legislation, the KwaZulu-Natal Department of Human Settlements (KZNDHS) is responsible for the planning and implementation of housing and human settlements programmes in the KwaZulu-Natal Province. This includes the Human Settlements Emergency Housing Programme. The Province has advised that they have commenced with the construction of Temporary Residential Units (TRUs) for households whose homes have been damaged or destroyed by the floods which occurred during the course of April 2022. The households are currently being accommodated and housed with neighbours and/or in halls and/or churches and/or tents.
The Department is planning in the immediate future to construct approximately one thousand eight hundred and ten (1810) temporary residential units. One hundred and eight (108) temporary residential units (TRUs) have been completed for families affected by floods in various District Municipalities including eThekwini Metro.
The target is to complete all the 1810 Temporary Residential Areas (TRAs) within a period of three months (May to July 2022), however, it should be noted that the set timeframes will depend on a number of operational and technical variables which include obtaining suitable land for displaced families, the necessary planning and environmental approvals, availability of materials to construct the temporary residential units (TRUs) and so on.
KwaZulu-Natal Department of Human Settlements in conjunction with eThekwini and the National Department of Human Settlements developed a long-term or permanent solution to assist flood victims. To date, a total of 199 Serviced Sites located within eThekwini Metro have been identified and a verification process, as well as site visits, have been completed. A total of 65 sites have been identified as developable and will be suitable for development as a permanent solution. The 65 sites vary in size, ranging from 300sqm-2800sqm, therefore more than one unit can be constructed. The Department also identified various land parcels to provide permanent accommodation.