Question NW583 to the Minister of Human Settlements, Water and Sanitation

Share this page:

29 May 2020 - NW583

Profile picture: Meth, Ms N

Meth, Ms N to ask the Minister of Human Settlements, Water and Sanitation

By what date will her department complete the water project in Wards (a) 17, (b) 18 and (c) 19 of Intsika Yethu Local Municipality since the Ncora dam programme was announced by the former Minister Mokonyane (details furnished)?

Reply:

The Ncora Regional Bulk Infrastructure Project, which is funded by the Department of Water and Sanitation (DWS) in terms of the Regional Bulk Infrastructure Grant (RBIG), has been completed and bulk supply lines have been installed in the Ncora zone areas that feed wards 17, 18 and 19. 

Components of the projects that are outstanding comprise of the villages’ internal reservoirs and reticulation which is funded through the Municipal Infrastructure Grant (MIG) funding from the Department of Cooperative Governance (CoGTA). Progress can be summarised as follows:

  • Ward 17: The Department has completed the bulk supply lines under Ncora Programme in Ward 17. The Chris Hani District Municipality is currently busy with connecting infrastructure through the “KwaMzola Water Supply Project" funded through MIG.
  • In Ward 18 bulk supply lines: The Ncora (Zone A) Villages Water Project is also complete. The project was completed in 2018. However, Qaqane village which was part of the scope of this project is now being implemented as part of the Kwa-Mzola and completion is projected for January 2021. The project is funded through MIG.
  • In Ward 19: The Bulk line from Ncora WTW to Ngxabangu and reticulation of surrounding villages was competed in 2013 and 2016 respectively. They were funded through RBIG and MIG. Progress on remaining villages is reflected below. Requesting the Honourable Member to refer to the table below indicating projects under each ward:

CHDM CLUSTER 4 NCORA ZONES

WARD

Village Names

Population

Completed

Duration

Comments

WARD 19

Gcina-K

935

Completed

 

Supplied from the Ncora Water Treatment Works. Rehabilitation of existing reticulation required.

 

Maqwathini-C

739

Completed

 

 
 

Mqanqeni

951

Completed

 

 
 

KwaMqanqeni

1 283

completed

 

 
 

Maqwthini-A

1 613

Completed

 

 
 

Nquqhu-B

1 954

Completed

 

 
 

Nonqonqwama

2 093

Completed

 

 
 

Ngxabangu

2 308

Completed

 

 
 

Dipini-A

1 013

Completed

 

 
 

Hoyana

1 115

Completed

 

 
 

Taiwan

181

Completed

 

 
 

eQolweni-A

452

Outstanding

32 weeks

Technical reports ready. Awaiting budget allocation. Supplied from Ncora Treatment Works.

 

Halla BB

418

Outstanding

32 weeks

 
 

Mtinwevu Mission

340

Outstanding

40Weeks

 
 

Mpunga & Nquqhu

421

Outstanding

40 Weeks

 

Sub Total

 

14 185

 

 

 

WARD18

Banti

673

Completed

 

Supplied from the Ncora Water Treatment Works. Under ConstructIon

 

Mahlungulu-C

683

Completed

 

 
 

Gongqo

1 854

Completed

 

 
 

Kwachotha

1 292

Outstanding

28 weeks

Design Ready, CHDM to finalise Budget allocation

 

Nomadambe

903

Outstanding

43 weeks

 
 

Nomadamba

1 302

Outstanding

56 weeks

 
 

lahlangobo-D

465

Outstanding

24 weeks

 
 

Longqayi

883

Outstanding

43 weeks

 
 

Lower Ncora

783

Outstanding

43 weeks

 
 

Jojweni-N

2 754

Outstanding

 

 

Sub Total

 

11 592

 

 

 

WARD 17

Melika

832

Completed

 

Supplied from the Ncora Water Treatment Works. Village Reticulation completed.

 

Luqolweni

112

Completed

 

 
 

KwaMzola

3981

Under Construction

 

80 Weeks

 

 

Immediate Future Supply from the Ncora Water Treatment Works. Village reticulation and 12km of secondary bulk line still to be implemented. CHDM busy with procurement and funding prioritisation.

 

Luqolweni-F

215

     
 

Matafeni - B

279

     
 

Pesikeni

811

Outstanding

56 weeks

 
 

Mqwazini

320

Outstanding

36 weeks

 
 

Matafeni - A

692

Outstanding Tender doc Ready

 

 
 

Mgababa- A

1495

Outstanding

26 weeks

 
 

Gesini

371

Outstanding Tender doc Ready

43 weeks

 
 

Esigangeni-A

816

outstanding

43 weeks

 
 

Bhotani-A

543

outstanding

36 weeks

 
 

Tshayelela

455

outstanding

24 weeks

 
 

Bhotani-A

543

outstanding

36 weeks

 
 

Bhotani-B

857

outstanding

43 weeks

 
 

Home

209

outstanding

24 weeks

 

Sub Total

 

12 531

 

 

 

Grand Total

 

38 308

 

 

 