Question NW946 to the Minister of Tourism

Share this page:

24 June 2022 - NW946

Profile picture: De Freitas, Mr MS

De Freitas, Mr MS to ask the Minister of Tourism

With reference to tourism infrastructure projects (a) in the past three financial years and (b) since 1 April 2021, (i) what total number of projects commenced, but were not completed in each specified month and/or period, (ii)(aa) what and (bb) where were the projects in each month and/or period, (iii)(aa) which projects did not have an environmental impact assessment undertaken and (bb) why not, in each case, and (iv) why were the projects not completed in each month and/or period?

Reply:

a) (1) 2018/19 Refer to Annual Performance Report 2018/19 page 46-51 https://www.tourism.gov.za/AboutNDT/Publications/Department%20of%20Tourism%20Annual%20Report%202018-2019.pdf

(2) 2019/20 Refer to Annual Performance Report 2019/20 page 47-54 https://www.tourism.gov.za/AboutNDT/Publications/Tourism%20Annual%20Report%202019-20.pdf

(3) 2020/21 refer to Annual Performance Report 2020/21 page 34-36

https://www.tourism.gov.za/AboutNDT/Publications/Tourism%20Annual%20Report%2020-21.pdf

b) Since April 2021 the following infrastructure projects are outlined in the Department’s 2021/22 Annual Performance Plan

1. Infrastructure maintenance programme implemented at 19 (nineteen) National Parks:

  1. EC Addo National Park
  2. EC Camdeboo
  3. EC Mountain Zebra
  4. WC Garden Route (Knysna, Wilderness)
  5. EC Tsitsikamma
  6. NC Karoo
  7. FS Golden Gate
  8. NW Marakele
  9. LP Mapungubwe
  10. NC Kgalagadi
  11. NC Augrabies
  12. NC Namakwa
  13. NC Richtersveld
  14. WC Agulhas
  15. WC Bontebok
  16. WC Table Mountain
  17. WC West Coast
  18. WC Tankwa-Karoo
  19. MP Kruger

2. Infrastructure maintenance programme implemented in one state owned asset in all nine Provinces.

Built Environment Professional Service Providers have been appointed and conditional assessments have been completed for sites recommended for inclusion in the provincial maintenance programme.

3. Support the Implementation of Thirty Community-based Tourism Projects:

  1. LP Matsila Lodge
  2. LP Phiphidi Waterfall
  3. LP The Oaks Lodge
  4. MP Mnisi Resort
  5. LP Ngove
  6. LP Tisane
  7. LP VhaTsonga
  8. FS QwaQwa Guest House
  9. FS Vredefort Dome
  10. FS Monotsha
  11. NW Manyane Lodge
  12. NW Lotlamoreng Dam
  13. NC Platfontein Lodge
  14. NC Kamiesburg
  15. KZN Muzi Pan
  16. EC Maluti Hiking Trail
  17. EC Mthonsi Lodge
  18. EC Qatywa Lodge
  19. EC Nyandeni Chalets
  20. EC Western Tembuland
  21. KZN Anton Lembede Museum eThekwini Municipality
  22. NC McGregor Museum
  23. KZN AmaHlubi Cultural Heritage
  24. NC & NW Sol Plaatjie Museum
  25. NW Lehurutshe Liberation Heritage Museum
  26. MP Numbi Gate
  27. LP Nandoni Dam
  28. LP Tshathogwe Game Farm
  29. LP Mtititi Game Farm
  30. LP Mapate Recreational Social Tourism Facility

(iii) (aa) and (bb) In 2021/22, built environment professionals were appointed for these projects and planning is being finalised, including the necessary planning approvals which would include EIA’s if and where applicable.

(iv) Final completions of projects can only be reported once the financial year has been concluded with an audit of all the project