Question NW1988 to the Minister of Health

Share this page:

10 September 2021 - NW1988

Profile picture: Ismail, Ms H

Ismail, Ms H to ask the Minister of Health

(1). What (a) are the details of the progress of the (i) Sekhing, (ii) Jouberton and (iii) Mathibestad clinics that are under construction by his department in the North West, (b) is the name of the company to whom his department awarded the contract to build each clinic and (c) amount did each clinic cost his department; (2) whether the three clinics are currently in operation; if not, why not, if so, what are the relevant details; (3) what is the current breakdown of the vacancy rate of health care workers in each (a) hospital and (b) position in the North West?NW2222E

Reply:

(1)and (2)

(I) CONSTRUCTION OF A NEW JOUBERTON CHC

1.1 STATUS SUMMARY

The project status summary is highlighted in the matrix below.

Table 1.1: Project status summary: Construction of a new Jouberton CHC

No.

Item

Description

1

Contract Number

DoH/020/PS/11

2

Date of Site Handover

19 September 2016

3

Original Contractor

JV Group Five & ENM

4

Implementing Agent

NWDoH

5

Principal Agent

Tiki Architects

6

Contract Commencement Date

19 September 2016

7

Contract Duration ( Original )

410 Calendar days

8

Practical Completion (Original )

3 November 2017

9

Revised practical completion date (As per EoT 8)

21 May 2019

10

Cost of EoT

R 4 358 562,97 Excl VAT

11

Contract value before EOT 8 (with EOT 7)

R 205 320 122, 91 Excl VAT

12

Revised contract value with EOT 7 & 8 awaiting Approval by Provincial treasury

R 209 678 685,88 Excl VAT

13

Original Contract Amount

R 146 622 724,20 Excl VAT

14

Progress to Date

100 %

15

Expenditure to date

R 222 217 461.09

​1.2 PROJECT SCOPE STATEMENT

The project scope includes the following health units amongst others:

CTOP, Dental, Emergency, Maternity, Theatre, Outpatients, Crisis Control, Radiology, Sputum Booth, TB and appurtenant works.

The following service units are also included:

Guardhouse, Main Reception and Administration, Pharmacy, Service Building, Generator and Gas Control, Medical Waste and refuse Deposit, Pump Station, Carports. Staff accommodation comprising of six (6) two bedroom flats and four (4) one bedroom flats and appurtenant works also forms part of the scope of works.

​1.3 PROGRESS TO DATE

The project is at 100% completion, with final completion achieved. The clinic is currently operational.

(ii) CONSTRUCTION OF A SEKHING chc

​1.4 STATUS SUMMARY

The project status summary is highlighted in the matrix below.

Table 1.1: Project status summary: Construction of a new Sekhing CHC.

No.

Item

Description

 

Contract number

NWDOH/PS/019/11

 

Contract sum

R 84 026 731.26

 

Commencement date

4 October 2012

 

Original Contractor

ENM Trading Pty Ltd

 

Principal Agent

Phitlhelelo Properties Pty Ltd

 

Project Period

22 months

 

Practical completion date (original)

31 August 2014

 

Revised practical completion date

21 February 2019

 

Progress to date

89%

 

Revised contract amount (Incl approved V.O’s)

R 130 686 350.69

 

Expenditure to date

R 121 557 456.64

​1.5 PROJECT SCOPE STATEMENT

Community Health Centre with Administration Building, OPD, Male and Female Medical Wards, CTOP, EMRS, Crisis Control, Pharmacy, Dental Unit and Services Building. Residential Accommodation with parking Bays, Water storage tanks, Generator and Diesel Tank Rooms, Boundary Fence for both developments and parking for visitors.

​1.6 PROGRESS TO DATE

The contractor has currently abandoned the site citing financial difficulties, and further requested settlement on the project. The Department has appointed an external investigator on the project, of which the finding on the report shall provide a way forward on the project as the Department is considering termination.

iii) Information about the Mathibestad CHC is still being verified by the Province, it will be submitted as soon as it is completed.

(3) According to the North West Provincial Department of Health the current breakdown of the vacancy rate of health care workers in each hospital are as follows (a)-

HOSPITAL / HEALTH CARE WORKER CATEGORY

FILLED

VACANT

TOTAL

VACANCY RATE

Bophelong Psychiatric Hospital

220

34

254

13.4

Brits District Hospital

377

72

449

16.0

Ganyesa District Hospital

96

27

123

22.0

Gelukspan District Hospital

142

37

179

20.7

Gen De La Rey District Hospital

44

14

58

24.1

Job Shimankane Tabane Hospital

792

113

905

12.5

Joe Morelong Memorial Hospital

289

40

329

12.2

Klerksdorp Tertiary Hospital

1032

144

1176

12.2

Koster Hospital

91

11

102

10.8

Lehurutshe District Hospital

74

25

99

25.3

Mafikeng Provincial Hospital

593

56

649

8.6

Moses Kotane District Hospital

426

119

545

21.8

Nic Bodenstein District Hospital

94

23

117

19.7

Potchefstroom: Hospital Primary

457

98

555

17.7

Schweizer-Reneke Hospital

72

16

88

18.2

Taung District Hospital

330

39

369

10.6

Thusong District Hospital

136

32

168

19.0

Tshepong Primary Hospital

121

26

147

17.7

Witrand Regional Hospital

509

130

639

20.3

Zeerust District Hospital

67

17

84

20.2

Grand Total

5962

1068

7035

15.2

(b) Position in the North West

The North West Provincial Department of Health has an overall health care workers vacancy rate of 15.2%. The North West Provincial Department of Health’s budget baseline for the financial year 2020-2021 is reduced over R400 million and therefore the department is mainly filling critical replacement posts and some priority posts which were identified in the beginning of the financial year. The posts are being filled as and when the budget is available and confirmed by the Chief Financial Officer.

The Province ensure that health care service are continuously provided in the Province and not compromised through payment for overtime for additional hours worked by health care workers.

END.