Question NW646 to the Minister of Transport

Share this page:

17 September 2019 - NW646

Profile picture: Chetty, Mr M

Chetty, Mr M to ask the Minister of Transport

(1)(a) On what date will the tender specifications on the improvements of Cape Town International Airport Upgrades be finalised and (b)(i) what would be included in the total project scope, (ii) over what period, (iii) what are the project estimates and (iv) what are the details of the improvements; (2) what (a)(i) improvements are intended at the Tambo Springs Intermodal Terminal and (ii) bulk services for development will be needed from Ekurhuleni Metropolitan Municipality and (b)(i) what benefit will result from these improvements and (ii) at what cost?

Reply:

Airports Company South Africa SOC Limited (ACSA)

(1)

(b)Project

(iii)Estimated Value

(i)Scope of works

(ii) Period)Status

New Realigned Runway

R 3.8 bn

The construction of a new code F compliant runway with associated taxiways and ancillary systems

The tender document preparation phase was concluded and was just issued to the market.

T2 enablement works

T2 Main works

R 2.8

International Terminal expansion including check-in, baggage handling systems and arrivals carousels

The Enablement Works is currently in the procurement phase with tenders in the market

The Main Works is in the detail design phase and will be go through the procurement process during the course of next year

New Domestic Arrivals

R 688 mn

Expansion of the Domestic Arrivals Terminal

The project will be procured 2-3 months

Several other smaller projects

Multiple values

Aprons, taxiway upgrades and minor terminal expansion

The projects are in the design development phases and will go through the procurement process during the course of next year

(2) Falls away.