With reference to her letter of 27 August 2016, addressed to Mr KP Robertson, (a) which (i) waste water treatment plants and (ii) sewerage pipelines are due to be (aa) upgraded and/or (bb) refurbished in the Chief Albert Luthuli Local Municipality in Mpumalanga, (b) by when are the specified improvements due to begin and (c) what portion of the R25 million allocated by her department through the Municipal Infrastructure Grant will be used in each case?

Reply:

Refer to the table below:

(a)(i) Name of Waste Water treatment plant

(a)(ii) (aa) Sewerage pipelines upgrade

(a)(ii) (bb) Sewerage pipelines refurbished

(b) Due date for specified improvements to begin

(c) Allocation through MIG

Emanzana phase II Waste Water Treatment Works (WWTW)

None

None

Technical report not yet approved

Allocated with R5 million

Selobella Extension 2&3 toilet top structure

None

None

Commenced on 01/07/2015

Top structure allocated with R6 million

Carolina Phase I WWTW

None

None

Will commence on 01/10/2016

Top structure allocated with R6 million

Ekulindeni WWTW

None

None

Technical report not yet approved

Allocated with R1 million

Elukwatini WWTW

None

None

Commenced on 01/07/2016

Allocated with R7 million