Question NW753 to the Minister of Public Enterprises
11 April 2016 - NW753
McLoughlin, Mr AR to ask the Minister of Public Enterprises
(1) With reference to the cancelled contract with Airbus in respect of eight A400M military transport aircraft, the fact that Airbus agreed to refund the sum of €835 million to the Armaments Corporation of South Africa (ARMSCOR), and that an indemnity was subsequently provided to Denel by the Government – (a) why was an indemnity provided to Denel? (b) what were Denel’s obligations to – (aa) Airbus; (bb) ARMSCOR and (cc) the Government in respect of the specified contract. (2) (a) how many more such claims are outstanding from Denel; and (b) what – (i) are the details of each one of the eleven claims made to date by Denel in terms of the indemnity; and (ii) amount was paid to Denel in respect of each claim; (3) has oversight taken place in respect of each of the eleven claims submitted by Denel; if not, why not; if so, in respect of each claim – (a) (i) when; and (ii) where did such oversight take place, (b) who conducted such oversight; and (c) has such oversight resulted in a reduction of the relevant claim. (4) what is the breakdown of the current R63,1 million claim made by Denel? NW871E
Reply:
(1) |
(a) |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(b) |
(aa) |
As a program partner on the A400M, Denel has the obligation of the design, development, manufacture, and sole supply of the WFF and TS structures. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(bb) |
Denel has no obligation to ARMSCOR. DAe is directly contracted by Airbus to deliver the WFF and TS structures to their assembly lines. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(cc) |
As contracted through the Indemnity Agreement, Denel submits a claim to the Department on an annual basis, supported by an audited financial report, fully governed risk mitigation plan and a program report. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(2) |
(a) |
From the R1.6 billion (ONE POINT SIX BILLION RANDS) indemnity cover, there is a balance of R359 million (THREE HUNDERED AND FIFTY NINE MILLION RANDS) remaining over the next 5 years.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(b) |
(i) |
To date there has been 10 (TEN) claims submitted by Denel. Details of the claims are on the table below. |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(ii) |
Amounts paid to Denel are shown on the table below. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(3) |
Yes oversight has taken place. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(a) |
(i) |
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(ii) |
The Department’s auditors physically go and verify relevant documentation and Enterprise Resource Planning (ERP) systems. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(b) |
The Department through its independent auditors. The Department conducts DAe plant visits at least twice a year to appraise itself of the A400M programme status. |
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(c) |
|
|||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
(4) |
The recent 2015 claim amounted to R33.1 million (THIRTY THREE POINT ONE MILLION RANDS). The R63.1 million (SIXTY THREE POINT ONE MILLION RANDS) was claimed and paid during 2014.
ACRONYMS:
|