Question NW570 to the Minister of Tourism

Share this page:

22 March 2024 - NW570

Profile picture: Ismail, Ms H

Ismail, Ms H to ask the Minister of Tourism

(1) Whether, with reference to the Auditor-General’s report of 2019 which highlighted that at least 14 infrastructure projects under her department had significant challenges and recommended a forensic investigation on them, she will furnish Ms H Ismail with a detailed list of these 14 infrastructure projects highlighted by the Auditor-General of South Africa; (2) (a) Who were the officials presiding over the infrastructure projects that were under her department during the 2019 period and (b) what were the (i) original project values per project and (ii) reasons for the variance between the fair value and expenditure incurred per project?

Reply:

1. Detailed list of the 14 infrastructure projects recommended for a forensic investigation as highlighted by the Auditor-General’s report of 2019

 

 Project

1

Rock Art Tourism Phase 2, Eastern cape

2

Building of a Guest House 1 & 2, Free State

3

Sentinel Peal Car Access, Free State

4

Mnisi, Limpopo

5

VhaTsonga 1 & 2, Limpopo

6

Kamiesburg, Northern Cape

7

Nyandeni, Eastern Cape

8

Mthonsi Lodge, eastern cape

9

Qatywa, Eastern cape

10

Six Day Hiking Trail, Eastern Cape

11

Muzi Pan, Kwazulu-Natal

12

Sekhukhune, Limpopo

13

Tisane, Limpopo

14

Manyane Lodge, North West

(2)(a) Who were the officials presiding over the infrastructure projects that were under her department during the 2019 period?

Ms Morongoa Ramphela - DDG

Ms Lerato Matlakala – Chief Director

Mr Jonga Kuhlane – Director

Mr Thulani Sibeko – Director

Ms Mbali Zama - Director

Mr Thulani Mhlanga – Deputy Director (Project Manager)

Ms Lufuno Netangaheni – Deputy Director (Project Manager)

Mr Mandisi Mququ – Deputy Director (Project Manager)

Mr Brandon Canham – Deputy Director (Project Manager)

Ms Sandra Mocumi – Deputy Director (Project Manager)

Mr Godukile Mbolekwa – Deputy Director (Project Manager)

Ms Nonkululeko Madela – Deputy Director (Project Manager)

(2)(b)(i) What were the original project values per project?

 

 Project

Budget

1

EC Rock Art Tourism Phase 2

R 4,750,000

2

FS Building of a Guest House 1 & 2

R 34,234,974

3

FS Sentinel Peal Car Access

R 11,432,622

4

LP Mnisi

R 10,940,000

5

LP VhaTsonga 1 & 2

R 9,185,000

6

NC Kamiesburg

R 5,100,000

7

EC Nyandeni

R 7,600,000

8

EC Mthonsi Lodge

R 28,215,000

9

EC Qatywa

R 23,750,000

10

EC Six Day Hiking Trail

R 9,405,000

11

KZN Muzi Pan

R 12,447,480

12

LP Sekhukhune

R 10,622,500

13

LP Tisane

R 18,227,174

14

NW Manyane

R 48,465,113

     

(2)(b)(ii) What were the reasons for the variance between the fair value and expenditure incurred per project?

The reasons as per the AGSA findings include:

  • Payments made to implementer for work not fully done;
  • Ineffective identification, scoping and sourcing of projects;
  • Scope of work changes not evaluated and pre-approve;
  • Reports on Work-in-Progress were not reliable; and
  • Poor quality of work.

Source file