Question NW3623 to the Minister of Agriculture, Land Reform and Rural Development

Share this page:

20 December 2023 - NW3623

Profile picture: Masipa, Mr NP

Masipa, Mr NP to ask the Minister of Agriculture, Land Reform and Rural Development

What (a) are the full detailed arrangements and/or contracts that are in place between her department and the SA Farmers Development Association (SAFDA) and (b) is the detailed breakdown of funds received by SAFDA from the allocated budget of her department. (2) what (a) are the details of farmers who were funded and/or supported through SAFDA, (b)(i) items were received and (ii) is the price of each item and (c) is the success rate of the farmers to date. (3) what are the (a) details of farmers who were excluded from the support provided by SAFDA and (b) reasons for their exclusion?

Reply:

(1) (a) The Department of Agriculture, Land Reform and Rural Development (DALRRD) signed an overarching MoA with the National Agricultural Marketing Council (NAMC) which controls all commodity organization trusts through the Marketing of Agricultural Act No. 47 of 1996 including the introduction of levies on agricultural products. A portion of these levies is used for transformation of the sectors. The MoA allows DALRRD to enter into Service Level Agreements (SLA) which regulate this partnership.

The response is divided into three parts based on specific interventions as per agreements emanating from the main Memorandum of Agreement (MoA) concluded with the South African Farmers Development Association (SAFDA). Part 1 focuses on Land Development and Post Settlement Support, Part 2 on Fertilizer support and Part 3 on Infrastructure Development.

(b) Please refer to Annexure A.

(2) (a),(b)(i),(ii) Please refer to Annexure A.

(c) The farms are all at different levels of productivity. Infrastructure projects progress is reflected in Annexure A.

(3) (a) None.

(b) Falls away.

 

(1)(b) Breakdown of funds received by/ disbursed to SAFDA from allocated budget

(2)(a) Details of farmers funded and/or supported

(2)(b)(i)

Item received / details of support

(2)(b)(ii)

Price per item

(c) Success rate of farmers to date

Budgeted amount

Amount disbursed to SAFDA.

       

Part 1: LAND DEVELOPMENT SUPPORT PROGRAMME

KWAZULU-NATAL: FARMS UNDER SAFDA

R18 461 128.92

R18 461 128.92

Isizwe Sakwa Dludla Trust

Production inputs

R4 991 840.00

The Trust had internal conflict that delayed implementation. Following a community resolution, the Trust established a new Operational Entity for the implementation of LDS.

Current status: the new entity to sign a Financial Tripartite with the Financial Institution to enable the transfer of funds to be completed and implementation to resume.

     

Machinations

R12 907 306.50

 
     

Infrastructure

R200 000.00

 
     

Operating Capital

R0.00

 
     

SAFDA management fee (2%)

R361 982.92

 

R18 577 375.52

R18 577 375.52

Entembeni Trust, Entembeni

Production inputs

R1 529 280.00

Expenditure to date

R9 635 713.31

Implementation at 52%

     

Machinations

R15 133 833.25

 
     

Infrastructure

R1 550 000.00

 
     

Operating Capital

R0.00

 
     

SAFDA management fee(2%)

R364 262.27

 

R14 429 937.91

R14 429 937.91

Entembeni Royal Household

Production inputs

R842 400.00

Expenditure to date

R8 685 887.13

Implementation at 60%

     

Machinations

R12 754 598.30

 
     

Infrastructure

R550 000.00

 
     

Operating Capital

R0.00

 
     

SAFDA management fee (2%)

R282 939.66

 

R15 178 092.92

R15 178 092.92

Emakhasaneni Trust

Production inputs

R0.00

Expenditure to date

R9 216 378.88

Implementation at 61%

     

Mechanizations

R13 323 282.20

 
     

Infrastructure

R650 000.00

 
     

Operating Capital

R907 200.00

 
     

SAFDA management fee (2%)

R297 609.67

 
           

MPUMALANGA: FARMS UNDER SAFDA

R33 508 660.53

R33 508 660.53

Matsamo CPA

Production inputs

R5 509 769.09

90% complete

     

Mechanizations

R6 313 705.00

 
     

Infrastructure

R8 750 000.00

 
     

Operating Capital

R17 787 922.57

 
     

SAFDA management fee (2%)

R657 032.56

 

R4 839 900.00

R4 839 900.00

Rouxville

Production inputs

R00.00

25% complete

     

Mechanizations

R810 000.00

 
     

Infrastructure

R3 935 000.00

 
     

Operating Capital

R0.00

 
     

SAFDA management fee (2%)

R94 900.00

 

R14 879 839.00

R14 879 839.00

Bambanani Mlambo trust

Production inputs

R709 745.00

100% complete

     

Mechanizations

R1 464 217.25

 
     

Infrastructure

R0.00

 
     

Operating Capital

R6 322 877.00

 
     

SAFDA management fee (2%)

R291 761.65

 
 

Part 2: EDTM: FERTILIZER SUPPORT

DALRRD signed a Service Level Agreement with the SA Farmers Development Association (SAFDA) to coordinate and facilitate procurement of production inputs (fertilizers) for Small-Scale Growers (SSGs) in the Komati/Malelane Farmer Production Support Units (FPSUs) in Nkomazi Local Municipality under the Ehlanzeni District of the Mpumalanga Province:

  • SAFDA developed business plans for Mpumalanga, motivating for support to SSG’s for fertilizer support, given that fertilizer prices had trebled; and
  • Business plans were approved and SAFDA was tasked with the procurement of the fertilizer, delivery to the farmers and then invoicing DALRRD.

KWAZULU-NATAL (KZN): SMALL SCALE GROWERS’ (SSGs) FERTILIZER SUPPORT 2023 (Summary of SSGs, HAs, Bags and value of provided fertilizer)

Budgeted amount

Amount disbursed to SAFDA.

MUNICIPAL DISTRICT

BUSINESS PLAN

No of Bags @R856

 

Price per item

Success rate to date

   

 

Area

 

Growers

     

R97 274 342

R97 274 342

Umzimkulu

1 436.65

235

7 183

R856.00 per bag

All the Growers received the fertilizer and signed for it.

   

Sezela

3 166.59

1 661

15 833

   
   

UGU

4 603.24

1 896

23 016

   
   

Umfolozi

2 478.89

1 624

12 394

   
   

UMKHANYAKUDE

2 478.89

1 624

12 394

   
   

Gledhow

2 210.40

182

11 052

   
   

Darnall

1 948.55

160

9 742

   
   

Maidstone

1 476.30

343

7 382

   
   

ILEMBE

5 635.25

685

28 176

   
   

Noodsberg

849.60

714

4 248

   
   

Eston

737.45

487

3 687

   
   

UMGUNGUNDLOVU

1 587.05

1 201

7 935

   
   

Pongola RCL

136.60

16

683

   
   

ZULULAND

136.60

16

683

   
   

Amatikulu

4 040.22

2 661

20 201

   
   

Felixton / Makhatini / Jozini

4 801.75

2 596

24 009

   
   

KING CHETSHWAYO

8 841.97

5 257

44 210

   
   

     TOTALS

23 283

10 679

116 415

   
 

MPUMALANGA : KOMATI PROJECTS

R43 million

R43 million

Project

Cession (ha)

No of growers

Cession (No of Bags)

Price per item

Success Rate

   

Spoons 8 Farmer Association

627,8

56

3139

R833.65 per bag of fertilizer throughout all the projects

All fertilisers were issued and signed for.

   

Lugedlane and Shinyokane

576

37

2880

   
   

Figtree A FA Association

447

14

2235

   
   

Figtree B Farmer Association

235

14

1175

   
   

Figtree C Farmer Association

446,4

47

2232

   
   

Figtree D Farmer Association

437,8

76

2189

   
   

Madadeni FA

327

40

1635

   
   

Magudu FA

391,2

15

1956

   
   

Mbunu B

402

52

2011

   
   

Mfumfane

634

75

3170

   
   

Ntunda A and B

33

1

42

   
   

Sibange

333

38

1665

   
   

Sikhwahlane

436

54

2180

   
   

Spoons 7 A&B

367,2

30

1836

   
   

Sibonshwa project

116

1

580

   
   

Walda

871,6

36

4358

   
   

Vuka Usebente

76

7

380

   
   

Huchinson farm Mzinti

18

1

90

   
   

Timiseleni Coop Magudu

243

15

1215

   
   

Phaphamani womens coop

23,3

2

117

   
   

JJ Maswati coop

141

40

705

   
   

Total

71 825

651

35790

   
           

MPUMALANGA: MALELANE PROJECTS

   

Projects

Cession (ha)

No of Growers

Cession

Price per item

Success rate

   

Nyubela and Sons

51

1

255

R833.65 per bag of fertilizer throughout all the projects

All fertilisers were issued and signed for.

   

Langeloop 1 (West & East)

410

40

2050

   
   

Langeloop 2

300

37

1500

   
   

Khanyangwane/ Buffelspruit

224

29

1121

   
   

Gijima Bomake Coop

135

56

677

   
   

Tikhontele Co-op

314

28

1570

   
   

Schoemansdal Trust

104

88

522

   
   

Nhlangu West

87

27

435

   
   

Nhlangu East

127,6

25

638

   
   

Ngogolo

590

39

2950

   
   

Mbongozi

135,6

18

678

   
   

Zelpy

136

22

680

   
   

Dwaleni

51

1

255

   
   

Lotswitswi

22

1

110

   
   

Middleplaas (Timiseleni n Tizameleni)

122

28

610

   
   

Rainbow

32

20

160

   
   

Rouxville farm

90

1

450

   
   

Total

2931,8

461

14659

   
               

EQUIPMENT AND MACHINERY FOR KOMATI/MALELANE FPSU

   

EQUIPMENT / MACHINERY

Specification

Usage

Quantity

Total Amount (R)

Growers that use the services of the FPSU equipment can save more than R3 500/ha on land preparation costs since private contractors have been charging more than R8 000/ha for complete land preparation while the FPSU charges between R4 500 – R5 500/ha. The current land preparation rate is more than R10 000/ha, and the FPSU currently charges R5 500/ha. Farmers that have used the growers’ machinery have saved and improved their farm profitability (though no actual impact assessment has been done at this stage). The success rate on farms will be determined after harvesting in December 2023.

   

Tractors (4x4)

71-80 kw with CAB MFWD

Land Preparation/ General Purpose

2

R1 554 132

 
   

Tractor (4x4)

91-100 kw with CAB MFWD

Land Preparation /Fire Fighting

1

R1 387 284

 
   

Boom Sprayer

600L

Herbicide/Pesticide Application

1

R63 106

 
   

Fire Tanker

5000L, full house

Firefighting/ Herbicide

1

R252 800

 
   

Gyramower/

Slasher 1.8m

Heavy Duty

Slashing/Road Maint

1

R53 424

 
   

Mouldboard Plough

Reversible

Land Preparation

1

R111 700

 
   

Lowbed

6 Ton capacity

Transporting machinery between projects

1

R221 600

 
   

Bell Loader

120 model

Crop removal

4

R4 338 688

 
   

Ripper

Medium Duty – 5 Curved Shank

Land Preparation

1

R84 000

 
   

Ridger/

Furrow

Shear Ridger – 3 Row

Land Preparation

1

R77 000

 
   

TLB

 

Land Preparation /General Purpose

1

R1 017 600

 
   

3 row fertilizer applicator

3 row fertilizer applicator

Fertilizer application

1

R58 500

 
   

5 Ton Tipper Trailer

5 Ton Tipper Trailer

General Purpose

1

R128 000

 
   

INFRASTRUCTURE

         
   

Dragline rehabilitation

(50m draglines; tripods; sprinkler heads; nozzles; stoppers; piplets)

Irrigation overhauling (procurement and supply)

300

R1 500 000

 
   

Drip system materials

(filters; valves; rolls; gromets; L-couples; reducers; straight couplings; End stoppers; Submain line)

Irrigation overhauling (procurement, supply and installation)

100

R2 500 000

 
   

Dam/River Pumps

8x10/75kw motors; 8x soft starters)

Replacement and installation

400

R1 000 000

 
   

TOTAL

     

R14 347 834

 
 

Part 3: RURAL DEVELOPMENT: INFRASTRUCTURE

KWAZULU NATAL

R37 455 014

R37 455 014

Amatikulu

Macekane FPSU: Macekane has 2 600 small-scale sugar cane growers, planting approximately 5372 hectares.

R37 455 014

Progress made to date is 30-50%

R37 455 014

R37 455 014

Felixton

Amatikulu FPSU: Amatikulu has 4 025 sugar cane small-scale growers, planting approximately 5 862 hectares.

R37 455 014

Progress made to date is 30-50%

R37 455 014

R37 455 014

Gledhow

Darnall

Maidstone

Qwabe FPSU: Qwabe has 547 sugar cane small-scale growers, planting approximately 3 958 hectares.

R37 455 014

Progress made to date is 30-50%

R37 455 014

R37 455 014

Makhathini/ Jozini

Jozini FPSU: Jozini has 1240 sugar cane small-scale growers, planting approximately 2278 hectares.

R37 455 014

Progress made to date is 30-50%

R37 455 014

R37 455 014

Umzimkulu

Sezela

Sezela FPSU: Sezela has 1156 sugar cane small-scale growers, planting approximately 4283 hectares.

R37 455 014

Progress made to date is 10%

R37 455 014

R37 455 014

Noodsberg

Eston

Noordsburg FPSU: Noordsburg has 2321 sugar cane small-scale growers, planting approximately 1467 hectares.

R37 455 014

Progress made to date is 30-50%

MPUMALANGA

R44 844 404.66

R29 299 331.13

Komati:

    • Spoons 7 & 8 Farmer Association
    • Lugedlane and Shinyokane
    • Figtree A, B, C & D Association
    • Madadeni FA
    • Magudu FA
    • Mbunu B
    • Mfumfane
    • Ntunda A and B
    • Sibange
    • Sikhwahlane
    • Sibonshwa
    • Walda
    • Magudu

Farms Irrigation infrastructure development and upgrades for 2 200ha

R29 299 331.13

Progress is at 32% (700ha) to date.

 

R15 545 073.53

Malelane:

    • Langeloop 1 & 2
    • Schoemansdal Trust
    • Nhlangu West
    • Nhlangu East
    • Ngogolo
    • Middleplaas (Timiseleni n Tizameleni)

Schoemansdal

Refurbishment of 22 farms’ production inputs storage facilities and offices

Farms soil and water conservation structures development

Development of Malelane/Nkomati Sugarcane FPSU that will provide support to production farms in the form of a mechanisation centre and fuel depot.

R15 545 073.53

Progress made to date is 80%.