Question NW3075 to the Minister in The Presidency for Electricity

Share this page:

06 October 2023 - NW3075

Profile picture: Graham, Ms SJ

Graham, Ms SJ to ask the Minister in The Presidency for Electricity

What (a) number of megawatts are being transmitted to the Republic from the Cahora Bassa power transmission system, (b) are the details of the extent of financing undertaken by the Republic to build and maintain the specified system since it was put back into operation in 1997 and (c) are the long-term plans for the system in terms of (i) life-span of the existing infrastructure, (ii) expansion of the system and (iii) on-going usage?

Reply:

(a)Eskom is contracted for 1 150 MW until 31 March 2030.

(b)The extent of infrastructure investment/financing undertaken by Eskom to build/sustain Apollo high-voltage direct-current (HVDC) is provided in Table 1 below for a period of 13 years. Ten of the listed projects have been completed (over R241 million), and eight of the projects are in the execution phase (over R951 million), with the remainder in the development phase (R321 million). The infrastructure includes HVDC key components such as transmission lines, converter transformers, and shunt capacitors, which amounts to a total of R1.5 billion. Obtaining information prior to the year 2010 will require more time, as this information has been archived.

Table 1: Details of infrastructure investment (from 2010)

PROJECT NAME

PLANT TYPE

INITIATIVE PHASE

TOTAL (rand)

Apollo Shunt Capacitor Bank Refurbishment

CAP BANKS

COMPLETED

18 693 718

Apollo CS Breaker 11 kV Replacement

BREAKERS

EXECUTION

31 116 104

Apollo CS Pietersburg Security Fence and Road

SECURITY

COMPLETED

12 342 665

Apollo Bridge 5 Converter Transformers

TRANSFORMERS

COMPLETED

11 554 690

Apollo Upgrade DC Harmonic Filters

CAP BANKS

EXECUTION

11 800 000

Apollo CS Line Voltage Divider Replacement

LINE DIVIDERS

EXECUTION

62 143 000

Apollo CS Problematic Bypass Breakers

BREAKERS

EXECUTION

219 225 000

Apollo CS HVDC Line No. 1: Tower 322

TOWER

COMPLETED

4 266 123

Apollo Songo PLC refurbishment

PLC

EXECUTION

14 200 000

Apollo Storage Plinths DC Side

NON-PLANT

CONCEPT

11 600 000

Apollo CS: HVDC Refurbishment Phase 2: Bridge 4 Transformers

TRANSFORMERS

EXECUTION

296 156 754

Apollo CS: HVDC Refurbishment Phase 2: Bridge 2 Transformers

TRANSFORMERS

EXECUTION

296 156 754

Apollo – Cahora Bassa No. 1 and 2 Quad Spacers

LINES

CONCEPT

130 000 000

Apollo CS: Deluge System Water Storage Tank

NON-PLANT

CONCEPT

17 769 000

Apollo – Cahora Bassa Lines Bird Guards

BIRD GUARDS

CONCEPT

5 400 000

NSP1 Security Build 2 – Apollo (NKP) ERA

SECURITY

EXECUTION

20 450 000

Apollo CS: Replacement of Pole 1 533 kV Reactor

REACTORS

CONCEPT

155 500 000

Apollo HVDC Lines Reinsulation Project

REINSULATION

COMPLETED

44 602 502

Apollo CS: CCTV Installations

SECURITY

COMPLETED

3 834 421

Replacement Bushings for Converter Transformers – Apollo CS

TRANSFORMERS

COMPLETED

17 193 111

Apollo CS Install Spare Transformer in Bridge 6

TRANSFORMERS

COMPLETED

10 000 000

Apollo CS Install Spare Transformer in Bridge 8

TRANSFORMERS

COMPLETED

10 000 000

Apollo 2 x Converter Transformers + Reactor (Capital Spares)

TRANSFORMERS

COMPLETED

109 145 411

   

TOTAL

1 513 149 254

The maintenance costs component, provided in Table 2 below, for a period of 14 financial years, amounted to over R165 million, which included the following:

  • Servitudes maintenance
  • Maintenance by Rotek Industries
  • Materials
  • Equipment spares
  • Production plant services
  • Facility services

The maintenance costs information can only be provided from the 2009/10 financial year, as Eskom changed to the current SAP system at that point. Obtaining information prior to that period will require more time, as this information has been archived.

Table 2: Maintenance (from the 2009/10 to the 2022/23 financial years)

(C) Are there long-term plans for the system in terms of (i) life-span of the existing infrastructure, (ii) expansion of the system and (iii) on-going usage?

(i) Details of the long-term plans for Apollo HVDC in terms of the lifespan of the existing infrastructure (refurbishment plan) are provided in Table 3 below.

Table 3: Long-term refurbishment plan

PROJECT NAME

PLANT TYPE

INITIATIVE PHASE

TOTAL (rand)

Apollo Install New Earth Electrodes

ELECTRODE

PRE-CONCEPT

14 000 000

Apollo CS: Permanent Bipole Bypass

ISOLATORS

PRE-CONCEPT

69 010 000

Apollo CS: Replace Bridge 1, 3, and 7 Transformers

TRANSFORMERS

PRE-CONCEPT

888 470 262

Apollo CS Repeater Station Pietersburg Battery System

BATTERY

PRE-CONCEPT

15 000 000

Apollo CS HVDC Line No. 1 Refurbishment

LINES

PRE-CONCEPT

230 000 000

Apollo CS HVDC Line No. 2 Refurbishment

LINES

PRE-CONCEPT

230 000 000

Apollo CS Problematic Equipment Phase 2

SUBSTATION

PRE-CONCEPT

105 600 000

Apollo CS Problematic Equipment Phase 3

SUBSTATION

PRE-CONCEPT

124 200 000

Apollo SS Auxiliary Transformer Bund Walls

NON-PLANT

PRE-CONCEPT

10 300 000

Apollo CS: HVDC System Ref. Upgrade Phase 3

SUBSTATION

PRE-CONCEPT

1 700 562 263

   

TOTAL

3 387 142 525

(ii) Currently, there is no long-term plan for expansion for the Apollo Converter Station.

(iii) Hidroeléctrica de Cahora Bassa (HCB) has indicated that it would like to start engagements in terms of the contractual extension beyond 2030. Eskom will be open to such engagements, as HCB power forms part of the baseload power supply mix.

Source file