Question NW4044 to the Minister of Public Enterprises

Share this page:

25 November 2022 - NW4044

Profile picture: Marais, Mr EJ

Marais, Mr EJ to ask the Minister of Public Enterprises

What is the total (a) percentage and (b) monetary value of capital under-expenditure by the Transnet National Port Authority in the Port of (i) Richards Bay, (ii) Durban, (iii) East London, (iv) Ngqura, (v) Port Elizabeth, (vi) Mossel Bay, (vii) Cape Town and (viii) Saldanha Bay in each of the past four financial years?

Reply:

According to the information received from Transnet

(a)– (b)

The total percentage and monetary value of capital under-expenditure by Transnet National Ports Authority in the past four (4) financial years, i.e., 2018/19 to 2021/22 has been 32%, translating into R 9 696 million under-expenditure. The proportion of the capital under-expenditure (both in monetary and percentages) per port and/or business unit is as shown in Table 1 on the following page.

Table 1: Under/ over-expenditure

 

Port/ BU

Under/ Over -expenditure
2018/19

Under/ Over -expenditure
2019/20

Under/ Over -expenditure
2020/21

Under/ Over -expenditure
2021/22

Under/ Over -expenditure
Over past 4 Years

i.

RCB

- R 219m

- R 144m

- R 278m

- R 100m

R 1,883m

   

70%

49%

93%

41%

49%

ii.

DBN

- R 305m

- R 905m

- R 317m

R 736m

- R 2,036m

   

41%

78%

70%

336%

25%

iii.

EL

- R 83m

- R 23m

- R 28m

R 56m

- R 429m

   

81%

32%

67%

525%

41%

iv.

NGQ

- R 245m

R 227m

- R 182m

- R 245m

- R 390m

   

77%

48%

41%

56%

10%

v.

PE

- R 30m

- R 31m

- R 25m

R 22m

- R 362m

   

40%

49%

45%

52%

25%

vi.

MSB

- R 27m

- R 10m

R 0m

- R 3m

- R 110m

   

86%

31%

0%

14%

57%

vii.

CPT

- R 119m

- R 26m

- R 146m

R 148m

- R 844m

   

82%

24%

63%

112%

25%

viii.

SLD

- R 243m

R 7m

- R 275m

- R 107m

- R 1,326m

   

92%

6%

80%

47%

50%

 

DRS

- R 356m

- R 340m

- R 178m

- R 369m

- R 1,578m

   
  • 88%
  • 100%
  • 99%
  • 99%
  • 50%
 

HO

- R 63m

R 149m

- R 54m

- R 119m

- R 426m

   
  • 34%

2092%

  • 52%
  • 38%
  • 20%
 

LHS

- R 40m

- R 13m

- R 21m

- R 40m

- R 312m

   
  • 76%
  • 32%
  • 71%
  • 62%
  • 51%
 

Grand Total Under-expenditure

- R 1,732m

- R 1,108m

- R 1,503m

- R 22m

- R 9,696m

   
  • 66%
  • 41%
  • 69%
  • 1%
  • 32%

NB – All negative amounts and percentages denote under-expenditure.

 