Question NW2951 to the Minister of Sport, Arts and Culture
28 September 2022 - NW2951
Joseph, Mr D to ask the Minister of Sport, Arts and Culture
What are the (a) names and (b) locations and/or areas of the (i) total 64 softball clubs and (ii) four softball diamonds with a 1000-seats capacity in the (aa) Cape Town Region and (bb) Western Cape Districts. (2) What (a) is the total building cost of the 3 500 –seater softball stadium in Polokwane and (b) is the time frame of his department for the project?
Reply:
1(a)(b)(i). The document with the names and locations of softball clubs is attached.
(ii). The following are the four softball diamonds in (aa) Cape Town region and (bb) Western Cape Districts:
Softball Diamond |
Capacity |
Turf Hall Stadium Athlone |
3500 |
Lavender Hill |
500 |
Beaufort West |
500 |
Malmesbury |
1500 |
(2)(a). The total building cost of the 3 500 –seater softball stadium in Polokwane is R90,960,827.34.
(b). The projected time frame for the completion of the project is 28 February 2023.