Question NW144 to the Minister of Water and Sanitation

Share this page:

14 March 2024 - NW144

Profile picture: Moore, Mr S J

Moore, Mr S J to ask the Minister of Water and Sanitation

Whether he will furnish Mr S J Moore with a detailed list of ongoing (a) Regional Bulk Infrastructure and (b) Water Services Infrastructure Grants projects which have (i) exceeded original budget expectations and (ii) gone beyond the estimated construction time since 1 April 2023; if not, why not; if so, what are the relevant details?

Reply:

The purpose of the Regional Bulk Infrastructure Grant (RBIG), to develop new, refurbish, upgrade and replace ageing bulk water and sanitation infrastructure of regional significance that connects water resources to infrastructure serving extensive areas across municipal boundaries or large regional bulk infrastructure serving numerous communities over a large area within a municipality. The Water Services Infrastructure Grant (WSIG) facilitates the planning and implementation of various water and sanitation projects to accelerate backlog reduction and enhance the sustainability of services, especially in rural municipalities.

Although comprehensive planning is done by the Department of Water and Sanitation (DWS) together with municipalities prior to the implementation of RBIG and WSIG funded projects, a myriad of challenges arise during implementation which result in unavoidable delays such as:

  • Inability of municipalities to contribute their share of funding for water and sanitation projects that should be co-funded by the DWS RBIG Grant and the municipalities’ own funding
  • Supply Chain Management challenges in municipalities often result in delays in procurement of required professional services and commencement of projects
  • Poor performance of contractors, couples with inadequate project management capacity in municipalities often leads to lengthy litigation processes which also bring projects to a halt
  • Projects are often brought to halt by communities with demands for employment opportunities or construction mafia with demands for 30% of contracts
  • Non-payment of contractors by the municipalities or non-payment of workers by contractors
  • Inclement weather conditions also contribute to delays in ongoing projects

Details of projects gone beyond the estimated construction time since 1 April 2023 are indicated in Annexure A.

---00O00--

ANNEXURE A

Regional Bulk Infrastructure Grant

Project name

Original project cost

Revised project cost

Initial completion date

Revised completion date

Free State

Welbedacht Bulk water supply (Manguang pipeline)

R500 000 000

R583 677 787

July 2021

March 2024

Tokologo bulk water supply Phase 2 of 3

R717 535 306

R717 535 306

December 2024

March 2026

Maluti-a-Phofung BWS Scheme(Sterkfontein WTW)

R619 590 000

R619 590 000

March 2024

April 2025

Mohokare Bulk water supply (Rouxville)

R300 000 000

R320 000 000

March 2020

June 2025

Mantsopa Water and Sanitation Intervention

R17 660 652

No adjustment

June 2023

October 2024

Construction of reversal gravity pipeline in Phuthaditjhaba and Harrismith

R57 100 000

No adjustment (this should be N/A as per same categories below)

March 2023

August 2024

Metsimaholo Bulk Sewer. (Upgrading of Denneysville WWTW)

R164 499 946

R224 352 940

October 2019

March 2024

Mafube Bulk sewer phase 2 of 2 (Upgrading of Frankfort WWTW)

R141 448 501

R164 858 228

June 2023

"TBC” Contractor terminated due to poor performance

North West

Ratlou Bulk Water Supply: Phase 1a – Setlagole Water Supply

R 146 600 000

R153 000 000

April 2016

November 2024

Mahikeng Bulk Water Supply: Upgrading of the Mmabatho WTW to 30 Ml/day

R 185 500 500

(IRS - 2012)

R449 700 000

October 2018

August 2025

Upgrade and Extension of the Brits Water Treatment Plant from 60 Ml/D to 80 Ml/D: Madibeng Bulk Water Supply

R845 000 000

R800 000 000

31 Aug 2017

31 Aug 2024

Western Cape

Lamberts Bay Desalination Plant

R89 812 568

Not yet determined

Mar 2022

Not yet determined

Provision of Dry sanitation toilets

R 8 383 078

N/A

June 2021

May 2022

Northern Cape

Upgrading of Noupoort sewer netwok

R 22 398 854

N/A

October 2022

February 2023

Refurbishment of Nababep waste water treatment works (Phase1)

R 40 702 697

NA

June 2025

NA

RS028_Dawid Kruiper_Refurbishment of Kameelmond WWTW Upington

R78 225 986

R78 225 986

22 September 2022

31 May 2023

RS029_Magareng_Warrenton Water Treatment Works

R80 438 842

R122 917 873

22 April 2021

March 2025

Eastern Cape

Makana Bulk Water Supply (Phase 2)

R133 286 055

R393 090 217

March 2021 (All phases)

Phase 2, at a reduced scope - end of June 2024.

Ndlambe Bulk Water Supply

R161 000 000

R422 945 139

(Anticipated that the project cost might increase by another R50mil due to escalation.

May 2015

March 2025.

Xhora East Bulk Water Supply

R258 541 304

R 576 687 000 (including co-funding).

December 2022.

May 2024

Ngqamakhwe Regional Bulk Water Supply

R724 million

R646 000 000

September 2023

September 2025

Sundays River Valley BWS (Paterson Project)

R73 300 000

R101 792 000

March 2016

Phase 6 - 31 March 2024

Overall – 31 March 2025

Xonxa Bulk Water Supply

R 413 017 890

R 657 663 506

August 2023

February 2025

Cluster 9 BWS project at Chris Hani DM

R254 695 667

R485 700 000

November 2022

February 2024

Cluster 4 BWS

R427 099 000

R 849 474 094

May 2020

February 2024

Cluster 6 BWS

R323 952 670

R474 323 951

May 2023

January 2025

Mpumalanga

Driekoppies Phase 1a

R424 000

No adjustments

December 2023

June 2024

Sibange Phase 2

R186 600

No adjustments

September 2022

February 2024

Water Services Infrastructure Grant

Municipality

Project

Original Budget

Revised Budget

Planned Completion date

Actual completion date

Free State

Masilonyana

Theunissen WC/WDM

R18 800 000

R 20 403 462

June 2021

March 2024

Tokologo

Dealesville Emergency Water Supply: Phase 3

R15 921 972

NA

June 2020

June 2024

Tswelopele

Bultfontein: Refurbishment of sewer pump station

R11 552 960

NA

April 2023

March 2024

Dihlabeng LM

Upgrading of Clarens Water Treatment Works From 1 Ml to 4Ml/day

R49 989 987

R59 314 755

February 2024

June 2024

Mantsopa LM

Ladybrand: Construction of 6ML Reservoir & Pipeline

R16 837 385

R16 837 385

December 2023

June 2024

Mantsopa LM

Ladybrand: Construction of 3Ml Reservoir (Phase 2)

R 13 459 632

R 13 459 632

December 2023

June 2024

Mantsopa LM

Ladybrand: Re-Construction of Sewer Outfall Line

R2 500 000

R2 500 000

December 2023

June 2024

Mantsopa LM

Hobhouse: Refurbishment of a Weir

R 2 053 181

R 2 053 181

December 2023

June 2024

Setsoto LM

Upgrading of the Van Soelen Outfall Sewer in Ficksburg

R39 994 762

R39 994 762

November 2023

June 2024

Phumelela LM

upgrading of Outfall sewer line and revamping of pump station station #3 and WWTW in Warden/Ezenzeleni

R22 001 373

R22 001 373

September 2023

June 2024

Nketoana LM

20,34km Pipeline (250mm dia) from Lindley to Arlington

R75 400 794

R75 400 794

June 2024

June 2025

Kopanong LM

Bulk Water Supply in Trompsburg

R19 000 000

R 22 000 000

June 2021

TBC

Kopanong LM

Water Supply Reddersburg

R 13 534 058

No adjustment

May 2017

TBC

Kopanong LM

Water Supply Bethulie

R 6 500 000

No adjustment

June 2021

TBC

Kopanong LM

Upgrading of Philippolis WWTW

R 12 000 000

R 38 994 885

June 2021

TBC

Mohokare LM

Rouxville Abstraction Works

R39 412 741

No adjustment

July 2022

TBC

Mafube LM

Namahadi 12Ml Reservoir

R36 904 336

No adjustment

November 2022

May 2024

Majuba LM

Mafube WC/WDM (Pre-paid Water Meters

R15 000 000

No adjustment

August 2023

March 2024

Metsimaholo LM

Oranjeville WWTW Upgrade

R61 938 621

No adjustment

July 2022

TBC

Ngwathe LM

Refurbishment of pipelines from Parys WTW to Reservoirs 3 & 4

R24 691 873

No adjustment

July 2022

January 2024

Ngwathe LM

Construction of sewer line in Heilbron / Phiritona

R8 604 802

TBC

Contractor terminated due to poor performance

December 2022

TBC

Ngwathe LM must procure new contractor

Ngwathe LM

Heilbron – Elevated water tower and 3km water pipeline

R18 720 677

No adjustment

April 2023

March 2024

Moqhaka LM

Kroonstad – 11th Avenue water pipeline and Bloemhoek Dam sluice gate

R24 189 695

R25 022 859

August 2023

June 2024

Northern Cape

ZF Mgcawu

Kakamas: Water treatment works

R 11 370 115

N/A

March 2023

N/A due to fact that IA’s allocation was converted from schedule 5b to 6b

Frances Baard

Construction of Carters Ridge Pump station (Phase1)

R 32 832 662

N/A

November 2018

June 2021

Frances Baard

Construction of Carters Ridge Pump station (Phase 2)

R 25 966 926

N/A

June 2021

July 2023

Frances Baard

Provision of dry sanitation toilets

R 8 383 078

N/A

June 2021

May 2022

Eastern Cape

Blue Crane Route Local Municipality

Refurbishment of Cookhouse Water Treatment Works

R18 799 060

N/A

November 2023

September 2024

Chris Hani DM

Chris Hani DM Cluster 7 Water Supply Scheme: Ngxogi Emadizeni Mantlaneni Xuka Entabeni Emantlwaneni Cefane Emafusini Mhlontlo KwaMhlontlo and Dwaleni/Matyeni Water Backlog Project

R2 000 000

N/A

July 2023

June 2024

Mpumalanga

Thaba Chweu LM

Refurbishment of the Lydenburg Waste Water Treatment Works

R114 777 382

N/A

June 2025

NA