Question NW93 to the Minister of Water and Sanitation

Share this page:

26 February 2024 - NW93

Profile picture: Macpherson, Mr DW

Macpherson, Mr DW to ask the Minister of Water and Sanitation

(1)What is the average amount of water that Umgeni Water has provided to the eThekwini Metropolitan Municipality over the past 12 months, (2) whether the entity has challenges in providing the required amount of water to the municipality; if not, what is the position in this regard; if so, what are the challenges?

Reply:

1.  The average amount of water provided by uMngeni-uThukela Water to the eThekwini Metropolitan Municipality is summarised in the table below:

Month

Targeted Volume in kl/day

No. of days

Monthly Target in kl

Actual Supplied Volume in kl

Monthly Variance in kl

January

1 105 000

28

30,940,000

32,126,382

1,186,382

February

1 105 000

31

34,472,000

34,255,000

-217,000

March

1 105 000

28

31,136,000

32,126,382

990,382

April

1 105 000

31

34,472,000

34,255,000

-217,000

May

1 105 000

30

33,360,000

33,150,000

-210,000

June

1 105 000

36**

40,032,000

39,780,000

-252,000

July

1 011 000#

25

25,275,000

28,225,771

2, 950, 771

August

1 011 000#

31

31,341,000

34,769,031

3,428,031

September

1 011 000#

31

31,341,000

34, 971,532

3,630,532

October

1 011 000#

30

30,330,000

33,567,957

3,237,957

November

1 011 000#

31

31,341,000

34,799,924

3,458,924

December

1 011 000#

33*

33,363,000

38,019,751

4,656,751

TOTAL

   

387,403,000

410,046,730

22,643,730

*Mid-term: meter reading done at month end

**Financial Year End: meter reading done at month end

#Targeted volume for the 2023/2024 financial year reduced in order to ensure compliance with the raw water abstraction license.

2. uMngeni-uThukela Water has been able to provide eThekwini Metropolitan Municipality with the required volume of water as stipulated in the Bulk Supply Agreement. However, there were four months wherein the actual volumes supplied were slightly below the targeted volumes.

During the year 2023, uMngeni-uThukela Water supplied eThekwini Metro with 410, 046, 730 kl which was 22, 643, 730 kl above the targeted supply volumes.

During the course of 2023, uMngeni-uThukela Water carried out planned maintenance as detailed in the table in Annexure A below:

---00O00---

ANNEXURE A

No

Details of Shutdown

Planned Date & Duration

Actual Completion Date

1.

Reservoir 3, Roof Rehabilitation.

Floor & wall lining and installation

07 August 2019 (39 Months)

10 January 2023

2.

Maphephetheni Works & Inanda Dam Pumping Main 700mm dia. Butterfly Valve Installation

08 February 2023 (12 Hours)

08 February 2023

3.

Aqueduct 1 and 2 Rehabilitation following the April 2022 floods.

28 June 2022 (12 Months)

30 June 2023

4.

Avondale Pump Station

Replacement of the Inlet Control Valve

03 March 2023

(8 Hours)

03 March 2023

5.

Hazelmere Works

Installation of the Inlet Control Valve

31 March 2023 (24 Hours)

01 April 2023

6.

Verulam Pump Repairs

05 June 2023

(24 Hours)

05 June 2023

7.

Toti System Reservoir 1 Outlet valve replacement & PDT’s

24 May 2023

(12 Hours)

24 May 2023

8.

Northdene Pump Station: Installation of 700mm diameter steel

22 May 2023

(9 Hours)

22 May 2023

9.

Nagle Dam – New Intake Repairs

21 July 2023 (12 Hours)

21 July 2023

10.

Maphephetheni – Inlet Control Valve Repair

11 July 2023 (12 Hours)

11 July 2023

11.

Maphephetheni – Aqueduct 2 Isolation for penstock installation tunnel 6 - 7

11 July 2023 (12 Hours)

11 July 2023

12.

Maphephetheni – Aqueduct 2 Isolation for penstock installation tunnel 8

21 July 2023 (12 Hours)

21 July 2023

13.

La Mercy Pump Repairs

10 August 2023 (12 Hours)

10 August 2023

14.

357 Pipeline Relocation DN1400 tie-in

20 September 2023 (63 Hours)

23 September 2023

15.

257 Pipeline Relocation: DN 1000 tie-ins at Fairview Road

28 September 2023 (60 hours)

30 September 2023

16.

Northern Aqueduct – Replacement of Air Valves

22 September 2023 (9 hours)

22 September 2023

17.

Installation of the Isolation Plate on Aqueduct 2 at the Head of Works Durban Heights WW

04 October 2023 (24 Hours)

05 October 2023

18.

Removal of an Isolation Plate on Aqueduct 2 at the Head of Works Durban Heights WW.

21 November 2023 (18 Hours)

21 November 2023

19.

Wiggins HLPS Repair of the Cooling Water Pump System.

24 October 2023 (8 hours)

24 October 2023

20.

357 Pipeline Relocation DN1400 tie-in

18 October 2023 (60 hours)

18 October 2023

21.

257 Pipeline Relocation

DN 1400 tie-in

25 October 2023 (60 hours)

27 October 2023

22.

Relocation of DN 700, 54 Pipeline and tie-in to the existing pipeline along the N3 Durban route at Ashburton Interchange for SANRAL to complete the Construction of N3 Road.

14 November 2023 (72 hours)

17 November 2023

23.

Northern Aqueduct – Replacement of Air Valves

05 October 2023 (9 hours)

05 October 2023

Source file