Question NW2981 to the Minister of Finance

Share this page:

04 October 2023 - NW2981

Profile picture: De Freitas, Mr MS

De Freitas, Mr MS to ask the Minister of Finance

(a) What tourism projects, undertaken by the Development Bank of Southern Africa, were initiated in the (i) past three financial years and (ii) current year to date, (b) on what date was each project initiated, (c) which of the specified projects were completed, (d) what was the set deadline for each project to be completed, (e) what are the actual completion dates for each completed project, (f) what are the reasons that each project was not completed by the set deadline, (g) what budget was allocated for each completed project and (h) what amount was spent in each completed project?

Reply:

The DBSA has seventy tourism-related projects, of which twenty-two have been completed, and forty-eight are in various stages of execution.

The detailed project list, which includes details (question (a)-(h)) is listed below.

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status ( c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4),Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date ( e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

1

NW

Compliance Certificates

NW Lehurutshe Bird and Trophy Hunting owned by the Bakgatla ba Lencoe Trust

2020-12-07

Construction

Construction

2024-03-22

2024-03-22

Not Applicable

R28,209,243.11

R1,176,025.47

2

KZN

Compliance Certificates

KZN Isibhubhu Project

2020-12-07

Construction

Construction

2023-09-16

2023-11-15

Slow performance of the contractor at commencement due to cash constraints and material sourcing challenges. The DBSA loan facility to the contractor has assisted in procurement of material and the performance of the contractor has improved as they are recovering to complete on time. Suspension of works due to the yearly traditional reed dance for a week was the latest stoppage. Delay also caused by client request for change in design for the maidens change rooms.

R35,470,271.15

R13,489,181.26

3

KZN

Compliance Certificates

KZN Muzi Pan Project

2020-12-07

Concurrence

Procurement - Concurrence Requested

2024-06-13

2024-06-13

Not Applicable

R21,899,635.05

R578,852.36

4

MP

Community Tourism Projects

Numbi Gate - Nkambeni Safari Lodge

2020-12-07

Construction

Construction

2024-03-26

2024-03-26

Delays in commencement of the project due to community social issues and currently a land claim.

R24,563,693.62

R2,659,306.92

5

MP

Community Tourism Projects

Numbi Gate - Mdlhuli Safari Lodge

2020-12-07

Construction

Construction

2024-03-26

2024-03-26

Delays in commencement of the works due to the delays in appointment of the CLO and labour

R33,554,531.24

R3,455,932.19

6

LP

Community Tourism Projects

Nandoni Dam

2020-12-07

Construction

Construction

2024-05-16

2024-05-16

Not Applicable

R38,982,441.65

R1,738,488.51

7

LP

Community Tourism Projects

Tshathogwe Game Farm

2020-12-07

Construction

Construction

2023-09-09

2023-11-14

Poor performance of the Contractor. Penalties to be charged in accordance with contract.

R26,741,416.87

R9,476,563.90

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status ( c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4),Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date (e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

8

LP

Community Tourism Projects

Mtititi Game Farm

2020-12-07

Construction

Construction

2023-06-10

2023-12-31

Poor performance of the Contractor. Penalties to be charged in accordance with contract.

R27,898,562.18

R14,455,737.46

2023-12-31

LP

Community Tourism Projects

Mapate Recreational Social Tourism Facility

2020-12-07

Construction

Construction

2023-06-16

2023-12-31

Suspension of works due to fatality on site, Poor performance by contractor at commencement of the constructions works.

R27,450,164.53

R9,245,260.80

2023-12-31

KZN

Local Community Museums

Product Enhancement at Anton Lembede Museum eThekwini Municipality (KZN)

2021-02-08

Construction

Construction

2024-03-02

2024-03-02

Not Applicable

R23,611,547.91

R979,096.02

11

NC

Local Community Museums

Product Enhancement at McGregor Museum (NC) WP1

2021-02-08

Evaluation

Procurement - Evaluation

2024-06-16

2024-06-16

Not Applicable

R240,750.00

 

12

NC

Local Community Museums

Product Enhancement at McGregor Museum (NC) WP2

2021-02-08

Evaluation

Procurement - Evaluation

2024-04-15

2024-04-15

Not Applicable

   

13

KZN

Local Community Museums

Product Enhancement at AmaHlubi Cultural Heritage (KZN)

2021-02-08

Concept NDT

Planning and Design

2024-03-11

2024-03-11

Not Applicable

R8,228,848.39

R979,069.02

14

NW

Local Community Museums

Product Enhancement at Sol Plaatjie Museum (NW)

2021-02-08

Construction

Construction

2024-02-01

2024-02-01

Delay in commencement of works due to an impasse on works to be implemented (new and maintenance work). Meeting between NDT, DBSA and Mahikeng Municipality to be held on 20.09.2023 to find way forward on scope.

R8,228,848.31

R832,007.41

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status ( c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4), Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date ( e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

15

NW

Local Community Museums

Product Enhancement at Lehurutshe Liberation Heritage Museum

2021-02-08

Concept NDT

Planning and Design

2024-02-27

2024-02-27

Not Applicable

R15,384,460.00

R832,007.41

16

NC

lndi-Atlantic Route (Coastal and Marine Tourism initiatives)

Tourism development at Orange River Mouth (NC) as part of the Indi-Atlantic Route

2021-02-08

Design Development

Planning and Design

N/A

N/A

Project works to be completed till Design Stage. Further stages will await NDT instruction to Proceed.

R76,121,200.33

R949,421.57

17

EC

lndi-Atlantic Route

Tourism Development at Hole in the Wall (EC) as part of the Indi-Atlantic Route

2021-02-08

Design Development

Planning and Design

N/A

N/A

Project works to be completed till Design Stage. Further stages will await NDT instruction to Proceed.

R56,103,208.95

R1,760,791.87

18

KZN

lndi-Atlantic Route

Tourism development at Harold Johnson Nature Reserve as part of the Indi-Atlantic Route

2021-02-08

Design Development

Planning and Design

N/A

N/A

Project works to be completed till Design Stage. Further stages will await NDT instruction to Proceed.

R48,708,342.83

R1,443,770.69

19

GP

Maintenance & Beautification

Suikerbosrand Nature Reserve, Gauteng

2020-12-07

Evaluation

Procurement - Evaluation

2024-03-20

2024-03-20

Not Applicable

R8,733,665.78

R257,326.41

20

KZN

Maintenance & Beautification

J L Dube Precinct, KZN

2020-12-07

Design Development

Planning and Design

2023-11-27

2023-11-27

Not Applicable

R4,277,257.82

R37,527.79

21

FS

Maintenance & Beautification of Provincial State-Owned Attractions.

Gariep Dam Resort, Free State

2020-12-07

Construction

Construction

2023-09-14

2023-12-31

The contractor is behind schedule. Penalties to be charged in accordance with contract.

R4,999,748.71

R2,182,007.88

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status ( c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4),Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date (e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

22

FS

Maintenance & Beautification of Provincial State-Owned Attractions.

Maria Moroka Resort in Thaba Nchu, Free State

2020-12-07

Construction

Construction

2023-09-15

2023-12-31

The contractor is behind schedule. Penalties to be charged in accordance with contract.

R4,999,748.71

R894,648.15

23

FS

Maintenance & Beautification of Provincial State-Owned Attractions.

Phillip Saunders Resort in Bloemfontein, Free State

2020-12-07

Construction

Construction

2023-08-15

2023-12-31

Additional scope of work requested by the end user Client and extension of time under review to determine the completion date.

R4,999,748.71

R2,637,239.48

24

FS

Maintenance & Beautification of Provincial State-Owned Attractions.

Sterkfontein Dam Nature Reserve, Free State

2020-12-07

Construction

Construction

2023-08-14

2023-12-31

The contractor is behind schedule. Penalty to be charged in accordance with contract.

R4,999,748.71

R2,967,908.65

25

MP

Maintenance & Beautification of Provincial State-Owned Attractions.

Manyeleti Nature Reserve, Mpumalanga

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

2023-06-08

Not Applicable

R3,736,433.94

R2,922,378.71

26

MP

Maintenance & Beautification of Provincial State-Owned Attractions.

Andover Nature Reserve, Mpumalanga

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

2023-06-08

Not Applicable

R3,736,433.94

R3,476,227.74

27

MP

Maintenance & Beautification of Provincial State-Owned Attractions.

Songimvelo Nature Reserve, Mpumalanga

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

2023-06-08

Not Applicable

R3,736,433.94

R3,801,835.77

28

MP

Maintenance & Beautification of Provincial State-Owned Attractions.

SS Skosana Nature Reserve, Mpumalanga

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

2023-06-08

Not Applicable

R3,736,433.94

R3,089,137.42

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status (c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4),Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date (e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

22

FS

Maintenance & Beautification of Provincial State-Owned Attractions.

Maria Moroka Resort in Thaba Nchu, Free State

2020-12-07

Construction

Construction

2023-09-15

2023-12-31

The contractor is behind schedule. Penalties to be charged in accordance with contract.

R4,999,748.71

R894,648.15

23

FS

Maintenance & Beautification of Provincial State-Owned Attractions.

Phillip Saunders Resort in Bloemfontein, Free State

2020-12-07

Construction

Construction

2023-08-15

2023-12-31

Additional scope of work requested by the end user Client and extension of time under review to determine the completion date.

R4,999,748.71

R2,637,239.48

24

FS

Maintenance & Beautification of Provincial State-Owned Attractions.

Sterkfontein Dam Nature Reserve, Free State

2020-12-07

Construction

Construction

2023-08-14

2023-12-31

The contractor is behind schedule. Penalty to be charged in accordance with contract.

R4,999,748.71

R2,967,908.65

25

MP

Maintenance & Beautification of Provincial State-Owned Attractions.

Manyeleti Nature Reserve, Mpumalanga

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

2023-06-08

Not Applicable

R3,736,433.94

R2,922,378.71

26

MP

Maintenance & Beautification of Provincial State-Owned Attractions.

Andover Nature Reserve, Mpumalanga

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

2023-06-08

Not Applicable

R3,736,433.94

R3,476,227.74

27

MP

Maintenance & Beautification of Provincial State-Owned Attractions.

Songimvelo Nature Reserve, Mpumalanga

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

2023-06-08

Not Applicable

R3,736,433.94

R3,801,835.77

28

MP

Maintenance & Beautification of Provincial State-Owned Attractions.

SS Skosana Nature Reserve, Mpumalanga

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

2023-06-08

Not Applicable

R3,736,433.94

R3,089,137.42

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status ( c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4),Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date ( e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

29

EC

Maintenance & Beautification of Provincial State-Owned Attractions.

Thomas Baines Nature Reserve, Eastern Cape

2020-12-07

Construction

Practical Completion Achieved

2023-08-08

2023-09-14

Certain areas on site were put on hold due to environmental concerns which did not form part of the scope. Practical completion has been achieved.

R4,285,162.35

R3,415,779.54

30

EC

Maintenance & Beautification of Provincial State-Owned Attractions.

Hluleka Nature Reserve, Eastern Cape

2020-12-07

Concept To be Approved

Planning and Design

2023-12-27

2024/25FY

Not Applicable

R4,185,939.39

R83,973.60

31

EC

Maintenance & Beautification of Provincial State-Owned Attractions.

Double Mouth Nature Reserve, Eastern Cape

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-06

N/A

Not Applicable

R3,528,146.03

R2,859,541.75

32

EC

Maintenance & Beautification of Provincial State-Owned Attractions.

Oviston Nature Reserve, Eastern Cape

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-25

2023-09-01

Project was affected by the hunting season as the contractor had limited access to site, hence the delay in completion against the baseline PC date. The project has achieved practical completion.

R3,504,584.39

R2,622,218.39

33

EC

Maintenance & Beautification of Provincial State-Owned Attractions.

Baviaanskloof Nature Reserve, Eastern Cape

2020-12-07

Construction

Construction

2023-07-25

2023-10-31

Change in the design of the kitchen building and location allocated by the end user.

R3,528,146.03

R2,182,741.34

34

EC

Maintenance & Beautification of Provincial State-Owned Attractions.

Cwebe and Dwesa, Eastern Cape

2020-12-07

Construction

Construction

2023-12-01

2023-12-01

Delays in granting contractor access to all facilities on site due to a movie recording or filming.

R4,263,982.64

R888,768.16

35

EC

Maintenance & Beautification of Provincial State-Owned Attractions.

Mpofu and Fordyce Nature Reserve, Eastern Cape

2020-12-07

Construction

Construction

2023-12-02

2023-12-02

Delay on works as some facilities had to be put on hold to accommodate the hunting season which generates revenue for the reserve.

R4,263,982.64

R1,502,586.19

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status ( c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4),Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date ( e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

36

NC

Maintenance & Beautification of Provincial State-Owned Attractions.

Doornkloof Nature Reserve, Northern Cape

2020-12-07

Construction

Construction

2023-11-23

2023-11-23

Not Applicable

R5,254,310.06

R1,235,877.71

37

NC

Maintenance & Beautification of Provincial State-Owned Attractions.

Rolfontein Nature Reserve, Northern Cape

2020-12-07

Construction

Construction

2023-11-23

2023-11-23

Not Applicable

R5,254,310.06

R1,686,739.19

38

NC

Maintenance & Beautification of Provincial State-Owned Attractions.

Goegap and Witsand Nature Reserve, Northern Cape

2020-12-07

Construction

Construction

2023-11-23

2023-11-23

Not Applicable

R5,254,310.06

R3,410,098.70

39

LP

Maintenance & Beautification of Provincial State-Owned Attractions.

Makapans Valley WHS, Limpopo

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

N/A

Not Applicable

R3,145,623.58

R2,997,834.07

40

LP

Maintenance & Beautification of Provincial State-Owned Attractions.

Nwanedi Nature Reserve, Limpopo

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

N/A

Not Applicable

R3,145,623.58

R2,558,202.70

41

LP

Maintenance & Beautification of Provincial State-Owned Attractions.

Blouberg Nature Reserve, Limpopo

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

N/A

Not Applicable

R3,145,623.58

R2,465,052.22

42

LP

Maintenance & Beautification of Provincial State-Owned Attractions.

Musina Nature Reserve, Limpopo

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

N/A

Not Applicable

R3,145,623.58

R2,777,971.87

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status ( c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4),Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date (e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

43

LP

Maintenance & Beautification of Provincial State-Owned Attractions.

Modjadji Nature Reserve, Limpopo

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-16

N/A

Not Applicable

R3,145,623.58

R2,430,597.23

44

WC

Maintenance & Beautification of Provincial State-Owned Attractions.

Kogelberg Nature Reserve, Western Cape

2020-12-07

Practical Completion

Practical Completion Achieved

2023-06-14

N/A

Not Applicable

R3,634,316.46

R3,003,843.38

45

WC

Maintenance & Beautification of Provincial State-Owned Attractions.

Goukamma Nature Reserve, Western Cape

2020-12-07

Practical Completion

Practical Completion Achieved

2023-06-14

N/A

Not Applicable

R3,634,316.46

R2,527,332.95

46

WC

Maintenance & Beautification of Provincial State-Owned Attractions.

Lookout Hill Khayelitsha, Western Cape

2020-12-07

Practical Completion

Practical Completion Achieved

2023-06-14

N/A

Not Applicable

R3,634,316.46

R3,277,649.65

47

WC

Maintenance & Beautification of Provincial State-Owned Attractions.

De Hoop Nature Reserve, Western Cape

2020-12-07

Practical Completion

Practical Completion Achieved

2023-06-14

N/A

Not Applicable

R3,634,316.46

R2,026,649.36

48

WC

Maintenance & Beautification of Provincial State-Owned Attractions.

Wolwekloof Nature Reserve, Western Cape

2020-12-07

Practical Completion

Practical Completion Achieved

2023-06-14

N/A

Not Applicable

R3,634,316.46

R3,072,463.11

49

WC

Maintenance & Beautification of Provincial State-Owned Attractions.

Cederberg Wilderness Area, Western Cape

2020-12-07

Practical Completion

Practical Completion Achieved

2023-06-14

N/A

Not Applicable

R3,634,316.46

R1,946,132.58

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status ( c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4),Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date (e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

50

NW

Maintenance & Beautification of Provincial State-Owned Attractions.

Mafikeng Hotel School

2022-04-04

Concept NDT

Planning and Design

2024-09-12

2024/25FY

Not Applicable

   

51

NW

Maintenance & Beautification of Provincial State-Owned Attractions.

Pilanesberg Nature Reserve, North West

2022-04-04

PSP Appointment

Pre-Initiation

2024-06-11

2024/25FY

Not Applicable

   

52

NC

Construction Planning, Procurement & Implementation

NC Platfontein Lodge

2020-12-07

Concept

Planning and Design

2023-12-27

2024/25FY

Not Applicable

R36,944,350.33

R464,114.63

53

NW

Further detailed planning & construction

NW Lotlamoreng Dam

2020-12-07

Tender / Retender

Procurement - Contractor

2024-02-11

2024/25FY

Not Applicable

R21,680,806.49

R392,300.67

54

NW

Construction Planning, Procurement & Implementation

NW Manyane Lodge

2020-12-07

Evaluation

Procurement - Evaluation

2023-11-02

2024/25FY

Not Applicable

R25,788,890.01

R392,300.67

55

LP

Construction Planning, Procurement & Implementation

LP Matsila Lodge

2020-12-07

Construction

Construction

2023-12-14

2023-12-14

Contractor is running behind schedule due to cashflow constraints on purchasing the high value items. DBSA has approved a loan facility and is assisting the contractor with purchasing of the material.

R43,036,821.09

R9,940,053.98

56

LP

Construction Planning, Procurement & Implementation

LP Phiphidi Waterfall

2020-12-07

Construction

Construction

2024-03-16

2024-03-16

Not Applicable

R24,984,745.91

R1,258,843.25

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status ( c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4),Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date (e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

57

LP

Construction Planning, Procurement & Implementation

LP Oaks

2020-12-07

Construction

Construction

2024-02-07

2024-02-07

Not Applicable

R30,540,765.25

R6,582,104.00

58

LP

Construction Planning, Procurement & Implementation

LP Ngove

2020-12-07

Construction

Construction

2024-05-19

2024-05-19

Not Applicable

R35,488,790.91

R1,951,886.39

59

LP

Construction Planning, Procurement & Implementation

LP Tisane

2020-12-07

Construction

Construction

2023-12-24

2023-12-24

The Contractor had cashflow constraints that affected purchasing of material. The DBSA has approved a loan facility and the material has already been provided to the contractor.

R32,500,362.51

R10,759,639.31

60

LP

Further detailed planning & construction

LP Vhatsonga

2020-12-07

Evaluation

Procurement - Evaluation

2024-04-11

2024/25FY

Not Applicable

R34,509,658.61

R1,164,067.68

61

FS

Construction Planning, Procurement & Implementation

FS QwaQwa Guesthouse

2020-12-07

Construction

Construction

2023-09-18

2023-10-30

The design of the sewer had to be changed by engineers.

R24,619,623.73

R20,195,710.68

62

FS

Construction Planning, Procurement & Implementation

FS Infrastructure through Monontsha

2020-12-07

Practical Completion

Practical Completion Achieved

2023-09-18

N/A

Not Applicable

R7,852,914.40

R5,605,553.72

63

FS

Construction Planning, Procurement & Implementation

FS Vredefort Dome

2020-12-07

Construction

Construction

2023-10-17

2024/25FY

Contract Terminated due to poor performance of the contractor

R28,163,338.17

R7,165,192.19

No

Province

Work Package

Project Name (a)

Date IPW signed off by NDT to DBSA (b)

Status ( c)

Current Status (Planning & Design stage 1-3, Procurement (stage 4),Construction Stage 5, Close Out (stage 6-7)

Baseline Targeted Practical Completion & Occupation Date (d)

Actual & revised Practical Completion & Occupation date (e)

Comments on Delays & targets not being met (pls be precise to the point) (f)

Total Budget (PSP, Construction, DBSA Fees) (g)

Actual Total Expenditure as at End August 2023 (h)

64

NC

Construction Planning, Procurement & Implementation

NC Kamiesberg Tourism Development

2020-12-07

Design Development

Planning and Design

2024-04-15

2024/25FY

Not Applicable

R19,816,186.00

R1,016,253.44

65

EC

Construction Planning, Procurement & Implementation

EC Maluti Hiking and Horse Trail

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-07

N/A

Not Applicable

R21,953,838.99

R21,099,619.33

66

EC

Construction Planning, Procurement & Implementation

EC Mthonsi Lodge

2020-12-07

Construction

Construction

2023-11-14

2023-11-30

Delay due to inclement weather. EOT approved

R7,563,919.96

R20,649,930.73

67

EC

Construction Planning, Procurement & Implementation

EC Qatywa Eco Tourism Development

2020-12-07

Construction

Construction

2024-01-16

2024-03-12

Delay due to inclement weather. EOT approved

R39,654,075.62

R18,654,465.84

68

EC

Construction Planning, Procurement & Implementation

EC Chalets at Nyandeni Great Place

2020-12-07

Practical Completion

Practical Completion Achieved

2023-08-15

N/A

Penalties charged to contractor for late completion

R22,996,656.27

R20,600,239.42

69

EC

Construction Planning, Procurement & Implementation

EC Western Thembuland

2020-12-07

Practical Completion

Practical Completion Achieved

2023-07-07

N/A

Not Applicable

R28,333,432.75

R26,545,363.06

70

LP

Construction Planning, Procurement & Implementation

Royal Khalanga Lodge

2021-09-13

Construction

Construction

2024-03-25

2024-03-25

Not Applicable

R17,772,742.44

R2,409,864.34

Source file