Question NW2812 to the Minister of Tourism
02 October 2023 - NW2812
De Freitas, Mr MS to ask the Minister of Tourism
(1) With reference to tourism projects (a) in the past three financial years and (b) since 1 April 2023, which specified projects were initiated respectively, and in each case, (i) on what date was each project initiated and (ii) which of the projects were completed and not completed; (2) what are the (a) actual completion dates for each completed project in each case and (b) deadlines by which the incomplete projects were to be concluded in each case; (3) what were the (a) dates on which it was decided that each project was incomplete in each case and (b) reasons for each project not being completed by the set deadline in each case; (4) what total (a) budget was allocated to each incomplete project in each case and (b) amounts were spent on each incomplete project in each case?
Reply:
1 (a) See table below
1 (b) No projects were initiated since 1 April 2023. The projects initiated since 2020/21 financial year are listed in the table below.
2 (a) and (b) - See table below
3 (a) and (b) - See table below
4 (a) and (b) - See table below
Please note
Practical completion – It is a stage of completion as certified by the Professional Service Provider where the work has been completed and is free of patent defects other than minor defects identified in the list for completion. The facility can be used for the intended purpose.
Works completed – Completion of works as per the scope of works and contract and the employer is entitled to possession of the works and site.
Projects |
(1)(i) On what date was each project initiated |
(1)(ii) Which of the projects were completed and not completed |
(2)(a) What are the actual completion dates for each completed project in each case |
(2)(b) What are the deadlines by which the incomplete projects were to be concluded in each case |
(3)(a) What were the dates on which it was decided that each project was incomplete in each case |
(3)(b) What were the reasons for each project not being completed by the set deadline in each case |
(4)(a) What total budget was allocated to each incomplete project in each case (4)(b) What total amounts were spent on each incomplete project in each case |
COMPLETED PROJECTS |
|||||||
Khomani San Interpretative Centre and Narrative Development |
Contract with the Implementing Agent signed in March 2020 |
Completed |
Construction started in June 2021 and was completed in March 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Nwanedi Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in January 2023 and was completed in July 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Blouberg Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in January 2023 and was completed in July 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Musina Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in January 2023 and was completed in July 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Makapans Valley WHS |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in January 2023 and was completed in July 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Modjadji Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in January 2023 and was completed in July 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Manyeleti Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in January 2023 and was completed in July 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Andover Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in January 2023 and was completed in July 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
SS Skosana Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in January 2023 and was completed in June 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Double Mouth Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in January 2023 and was completed in July 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Khayelitsha Lookout Hill |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in December 2022 and was completed in June 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
De Hoop Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in December 2022 and was completed in June 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Wolvekloof Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in December 2022 and was completed in June 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Goukamma Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in December 2022 and was completed in June 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Kogelberg Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in December 2022 and was completed in June 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Oviston Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion). PC was granted on 01.09.2023 |
Construction started in Jan 2023 and was completed in Sept 2023 |
Project completed |
Project completed |
Project was affected by hunting season. Contractor had limited access to site causing delay against the baseline PC date |
Project completed |
Cedarberg Wilderness |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in and was completed in June 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Nyandeni |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in August 2022 and was completed in Aug 2023 |
Project completed |
Project completed |
The initial phase of the project was not completed due to budget shortfall. Project is currently completed through the DBSA contract. |
Project completed |
Western Tembuland Lodge |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Works completion) |
Construction started in July 2022 and completed in June 2023 |
Project completed |
Project completed |
The initial phase of the project was not completed due to budget shortfall. Project is currently completed through the DBSA contract |
Project completed |
Maluti Hiking and Horse Trail |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Works completion) |
Construction started in July 2022 and completed in June 2023 |
Project completed |
Project completed |
The initial phase of the project was not completed due to poor workmanship. Project is currently completed through the DBSA contract. |
Project completed |
Monontsha Access Road |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in September 2022 and completed in September 2023 |
Project completed |
Project completed |
The initial phase of the project was not completed due to budget shortfall. Project is currently completed through the DBSA contract. |
Project completed |
Songimvelo Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in January 2023 and completed in September 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
Thomas Baines Nature Reserve |
Contract with the Implementing Agent signed in Nov 2020 |
Completed (Practical completion) |
Construction started in February 2023 and completed in September 2023 |
Project completed |
Project completed |
Project completed |
Project completed |
WORK IN PROGRESS PROJECTS |
|||||||
Tshahogwe Game Farm |
Contract with the Implementing Agent signed in 2020 |
Construction is about 56% towards completion. |
Construction is in progress |
2023-11-14 |
Completion date not yet due |
Completion date not yet due |
Budget R24,991,978 Exp R8,856,601 |
Mtititi Game Farm |
Contract with the Implementing Agent signed in 2020 |
Construction is about 89% towards completion. |
Construction is in progress |
2023-11-07 |
Completion date not yet due |
Completion date not yet due |
Budget R26,073,422 Exp R13,510,035 |
Mapate Recreational Social Tourism Facility |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 72% towards completion. |
Construction is in progress |
2023-10-03 |
Completion date not yet due |
Completion date not yet due |
Budget: R25,654,359 Exp: R8,640,430,66 |
LP Matsila Lodge |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 55% towards completion. |
Construction is in progress |
2024-01-05 |
Completion date not yet due |
Completion date not yet due |
Budget R40,221,328 Exp R9,289,770 |
Nandoni Dam |
Contract with the Implementing Agent signed in 2020 |
Contractor appointed. Site was handed over to the contractor on 08.09.2023. |
Construction is in progress |
2024-07-08 |
Completion date not yet due |
Completion date not yet due |
Budget R35,656,655 Exp R1,624,755 |
Numbi Gate - Mdhluli Cultural Centre |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 12% towards completion. |
Construction is in progress |
2024-03-26 |
Completion date not yet due |
Completion date not yet due |
Budget R33,009,600 Exp R2,681,202.38 |
Numbi Gate - Nkambeni Community Centre |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 8% towards completion |
Construction was halted due to land claim challenges. The Department is intervening. |
2024-03-26 |
Completion date not yet due |
Completion date not yet due |
Budget R23,724,670 Exp R2,485,333 |
Mpofu and Fordyce Nature Reserve |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 28% towards completion |
Construction is in progress |
2023-12-02 |
Completion date not yet due |
Not Applicable |
Budget R3,370,866 Exp R1,404,286 |
Baviaanskloof Nature Reserve |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 80% towards completion |
Construction is in progress |
2023-09-30 |
Completion date not yet due |
Not Applicable |
Budget R3,190,962 Exp R2,039,944 |
Cwebe and Dwesa Nature Reserves |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 20% towards completion |
Construction is in progress |
2023-12-01 |
Completion date not yet due |
Not Applicable |
Budget R4,599,194 Exp R830,624 |
Gariep Dam Resort |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 90% towards completion |
Construction is in progress |
2023-12-31 (Proposed revised Practical Completion date) |
Project is in progress |
Slow performance of the contractor. The project is now in penalties |
Budget R4,146,014 Exp R1,145,953 |
Phillip Saunders Resort |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 70% towards completion |
Construction is in progress |
2023-10-30 (Revised proposed Practical Completion date 2023-12-31) |
Completion date not yet due |
Additional scope of work requested by end under/client and extension of time under review to determine the completion date |
Budget R4,830,059 Exp R2,464,793 |
Maria Moroka Resort |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 70% towards completion |
Construction is in progress |
2023-09-15 (Revised proposed Practical Completion date 2023-12-31) |
Not Applicable |
Slow performance of the contractor. The project is now in penalties |
Budget R4,526,601 Exp R836,120 |
Sterkfontein Dam Nature Reserve |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 99% towards completion. |
Construction is in progress |
2023-08-14 (Revised proposed Practical Completion date 2023-09-29) |
Not Applicable |
Slow performance of the contractor. The project is now in penalties |
Budget R5,187,975 Exp R2,773,746 |
Doornkloof Nature Reserve |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 50% towards completion |
Construction is in progress |
2023-11-23 |
Completion date not yet due |
Not Applicable |
Budget R3,323,874 Exp R1,155,025 |
Rolfontein Nature Reserve |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 60% towards completion |
Construction is in progress |
2023-11-23 |
Completion date not yet due |
Not Applicable |
Budget R3,968,732 Exp R1,576,356 |
Goegap and Witsand Nature Reserve |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 59% towards completion |
Construction is in progress |
2023-11-23 |
Completion date not yet due |
Not Applicable |
Budget R7,879,259 Exp R3,187,007 |
Product Enhancement at Anton Lembede Museum Ethekwini Municipality (KZN) |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 10% towards completion |
Construction is in progress |
2024-02-28 |
Completion date not yet due |
Not Applicable |
Budget R22,066,867 Exp R915,043 |
Product Enhancement at Sol Plaatjie Museum (NW) |
Contract with the Implementing Agent signed in 2020 |
Contractor appointed. Construction in progress, about 1% towards completion |
Construction is in progress |
2023-12-29 |
Completion date not yet due |
Not Applicable |
Budget R22,066,867 Exp R915,043 |
Royal Khalanga |
Contract with the Implementing Agent signed in 2020 |
Construction in progress, about 26% towards completion |
Construction is in progress |
2024-03-25 |
Completion date not yet due |
Not Applicable |
Budget R16,610,039 Exp R2,252,210 |
Qatywa Lodge |
Project initially not completed in 2016. The project resumed in 2020 under the DBSA contract |
Construction in progress, about 45% towards completion |
Construction is in progress |
2024-03-12 |
Completion date not yet due |
The initial phase of the project was not completed due to budget shortfall. Project is currently in the process of being completed through the DBSA contract |
Initial incomplete phase Budget: R 23,750,000 Exp: R 23,288,668 Current Phase Budget: R37,059,884 Exp: R17,434,079 |
Mthonsi Lodge |
Project initially not completed in 2016. The project resumed in 2020 under the DBSA contract |
Construction is in progress, about 73% towards completion |
Construction is in progress |
2023-11-30 |
Completion date not yet due |
The initial phase of the project was not completed due to budget shortfall. Project is currently in the process of being completed through the DBSA contract |
Initial incomplete phase Budget: R 28,215,000 Exp: R 27,531,883 Current Phase Budget: R35,105,786 Exp: R19,299,000 |
QwaQwa Guest House |
Project initially not completed in 2018. The project resumed in 2020 under the DBSA contract |
Construction is in progress, about 98% towards completion. Practical completion anticipated for 30.10.2023. |
Construction is in progress |
2023-09-18 (Revised proposed Practical Completion date 2023-10-30) |
Completion date revised to Oct 2023 |
The initial phase of the project was not completed due to budget shortfall. Project is currently in the process of being completed through the DBSA contract. The design for the sewer had to be changed hence the delay in completion of the project |
Initial incomplete phase Budget: R21,875,949 Exp: R17,945,269.74 Current Phase Budget: R23,008,994 Exp: R18,960,588 |
Vredefort Dome Interpretation Centre |
Project initially not completed in 2012. The project resumed in 2020 under the DBSA contract |
Construction is in progress, about 37% towards completion. |
Construction was halted |
2023-10-17 |
Completion date not yet due |
The initial phase of the project was completed however there were structural defects due to geotechnical instability. Project is currently in the process of being completed through the DBSA contract. However, construction was stopped due to poor contractor performance. Contractor was terminated. DBSA currently looking for a replacement |
Initial incomplete phase Budget: R 3,009,453 Exp: R 2,927,652 Current phase Budget: R26,320,876 Exp: R6,695,541 |
Isibhubhu |
Project initially not completed in 2011. The project resumed in 2020 under the DBSA contract |
Construction in progress, about 80% towards completion |
Construction is in progress |
2023-09-16 (Revised proposed Practical Completion date 2023-11-15) |
Completion date revised to Nov 2023 |
The initial phase of the project was completed however not maintained over time. Project is currently in the process of being completed through the DBSA contract. Project experienced slow performance of contractor at commencement of project due to cash constrains and material sourcing challenges. DBSA loan facility assisted in the procurement of material and contractor performance improved. Suspension of work due to annual reed dance also delayed progress |
Initial incomplete phase Budget: R 15,000,000 Exp: R 14,889,708 Current Phase Budget: R33,149,775 Exp: R12,606,711 |
The Oaks |
Project initially not completed in 2019. The project resumed in 2020 under the DBSA contract |
Construction in progress, about 36% towards completion |
Construction is in progress |
2024-02-07 |
Completion date not yet due |
The initial phase of the project was not completed due to budget shortfall. Project is currently in the process of being completed through the DBSA contract |
Initial incomplete phase Budget: R 26,550,216 Exp: R 25,483,869 Current phase Budget R28,542,771 Exp R6,151,499 |
Ngove |
Project initially not completed in 2016. The project resumed in 2020 under the DBSA contract |
Construction in progress, about 20% towards completion |
Construction is in progress |
2024-02-06 |
Completion date not yet due |
The initial phase of the project was not completed due to budget shortfall. Project is currently in the process of being completed through the DBSA contract |
Initial incomplete phase Budget: R 20,133,951 Exp: R 19,993,013 Current Phase Budget: R 33,167,262 Exp: R1,824,192 |
Tisane |
Project initially not completed in 2015. The project resumed in 2020 under the DBSA contract |
Construction in progress, about 53% towards completion |
Construction is in progress |
2024-01-05 |
Completion date not yet due |
The initial phase of the project was not completed due to budget shortfall. Project is currently in the process of being completed through the DBSA contract |
Initial incomplete phase Budget: R 18,810,000 Exp: R 18,299,799 Current Phase Budget: R30,374,169 Exp: R9,320,845 |
Lehurutshe Bird and Trophy Hunting |
Project initially not completed in 2009. The project resumed in 2020 under the DBSA contract |
Contractor procurement finalised and contractor appointed. Construction will commence in Oct 2023 |
Contractor procurement was finalised |
2024-03-26 |
Completion date not yet due |
The initial phase of the project was not completed due to budget shortfall. Project is currently in the process of being completed through the DBSA contract |
Initial incomplete phase Budget: R 2,827,500 Exp: R 2,809,808 Current Phase Budget: R22,917,686 Exp: R1,099,089 |
Phiphidi Waterfall |
Project initially not completed in 2019. The project resumed in 2020 under the DBSA contract |
Contractor appointed. Site was handed over to the contractor on 08.09.2023. |
Contractor procurement was finalised |
2024-07-16 |
Completion date not yet due |
The initial phase of the project was not completed due contractual disputes with the Implementing Agent. Project is currently in the process of being completed through the DBSA contract |
Initial incomplete phase Budget: R 29,477,099 Exp: R 23,264,771.67 Current Phase Budget: R23,350,230 Exp: R1,176,489 |
Muzi Pan |
Project initially not completed in 2015. The project resumed in 2020 under the DBSA contract |
Contractor procurement finalised. DBSA currently preparing contract documents. Construction will commence in Oct 2023. |
Contractor procurement was finalised |
Completion date will be determined once the contract is signed |
Completion date is yet to be determined |
The initial phase of the project was not completed due to budget shortfall. Project is currently in the process of being completed through the DBSA contract |
Initial incomplete phase Budget: R 12,447,480 Exp: R 11,887,690 Current Phase Budget: R18,376,724 Exp: R540,983 |
Manyane Lodge |
Project initially not completed in 2016. The project resumed in 2020 under the DBSA contract |
Contractor procurement phase. Tender evaluation has been completed |
Contractor procurement is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
The initial phase of the project not completed due to budget shortfall. Project is currently in the process of being completed through the DBSA contract |
Initial incomplete phase Budget: R 48,465,113 Exp: R 47,884,114 Current Phase Budget will be disclosed after contractor is appointed |
Lotamoreng Dam |
Contract with the Implementing Agent signed in Nov 2020 |
Construction tender went out on 04.09.2023. Briefing was on 12.09.2023. Tender closes on 28.09.2023 This is a re-tender. |
Contractor procurement is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
VhaTsonga |
Project initially not completed in 2011. The project resumed in 2020 under the DBSA contract |
Contractor procurement stage |
Contractor procurement is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
The initial phase of the project was not completed due to poor workmanship. Project is currently in the process of being completed through the DBSA contract |
Budget and expenditure on the initial incomplete phase Budget: R 9,185,000 Exp: R 9,068,064 Current Phase Budget will be disclosed after contractor is appointed |
Kamiesburg |
Project initially not completed in 2011. The project resumed in 2020 under the DBSA contract |
Design Development stage |
Design development is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
The initial phase of the project was not completed due to budget shortfall. Project is currently in the process of being completed through the DBSA contract |
Budget and expenditure on the initial incomplete phase Budget: R 5,100,000 Exp: R 4,815,074 Current Phase Budget will be disclosed after contractor is appointed |
Platfontein |
Project initially completed in 2017 however with structural defects. The project resumed in 2020 under the DBSA contract |
Concept stage |
Concept development is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
The initial phase of the project was completed however there were structural defects post completion Project is currently in the process of being completed through the DBSA contract |
Budget and expenditure on the initial incomplete phase Budget: R 32,206,320 Exp: R 32,072,057 Current Phase Budget will be disclosed after contractor is appointed
|
Hluleka Nature Reserve |
Contract with the Implementing Agent signed in 2020 |
Concept stage |
Concept development is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
JL Dube Precinct |
Contract with the Implementing Agent signed in 2020 |
Design Development stage |
Design development is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
Suikerbosrand Nature Reserve |
Contract with the Implementing Agent signed in 2020 |
Contractor tender evaluation |
Contractor procurement is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
Product Enhancement at McGregor Museum (NC) |
Contract with the Implementing Agent signed in 2020 |
Contractor tender evaluation |
Contractor procurement is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
Product Enhancement at AmaHlubi Cultural Heritage (KZN) |
Contract with the Implementing Agent signed in 2020 |
Concept stage |
Concept development is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
Product Enhancement at Lehurutshe Liberation Heritage Museum (NW) |
Contract with the Implementing Agent signed in 2020 |
Concept stage |
Concept development is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed is appointed |
Tourism development at Orange River Mouth (NC) as part of the Indi-Atlantic Route |
Contract with the Implementing Agent signed in 2020 |
Design Development stage only. Will not proceed to the construction phase |
Design development is in progress |
Design planning to be completed in Oct 2023 |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
Tourism Development at Hole in the Wall (EC) as part of the Indi-Atlantic Route |
Contract with the Implementing Agent signed in 2020 |
Design Development stage only. Will not proceed to the construction phase |
Design development is in progress |
Design planning to be completed in Oct 2023 |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
Tourism development at Harold Johnson Nature Reserve (KZN) as part of the the Indi-atlantic Route |
Contract with the Implementing Agent signed in 2020 |
Design Development stage only. Will not proceed to the construction phase |
Design development is in progress |
Design planning to be completed in Oct 2023 |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
Mahikeng Hotel School |
Contract with the Implementing Agent signed in 2020 |
Concept stage |
Concept development is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
Pilanesberg Game Reserve |
Contract with the Implementing Agent signed in 2020 |
Professional Service Provider procurement |
Professional Service Provider Procurement stage |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |
SKA Visitor Interpretation Centre |
Contract with the Implementing Agent signed in 2021 |
Design development stage |
Design development is in progress |
Completion date will be determined once the contractor is appointed |
Completion date is yet to be determined |
Not Applicable |
Budget will be disclosed after contractor is appointed |