Mohlala, Ms MR to ask the Minister of Water and Sanitation

What is the status and/or condition of all the bulk water and sanitation infrastructure that his department handed over to municipalities in the Republic as at the latest date for which information is available?

Reply:

 

The Department of Water and Sanitation (DWS) is responsible for assisting the municipalities with provision of water and sanitation services to communities. In this regard, the DWS provides assistance to municipalities through conditional grants such as Regional Bulk Infrastructure Grant (RBIG) and Water Services Infrastructure Grant (WSIG) for the following:

  • Building new infrastructure
  • Refurbishment and upgrade of the existing water and sanitation infrastructure.

In accordance with the implementation protocols, the DWS is responsible for implementation of the infrastructure projects and the municipalities are responsible for Operation and Maintenance of the infrastructure. Upon completion of projects, the assets are handed over to the municipalities. Municipalities are therefore obliged to ensure that the infrastructure is operational and delivers water or sanitation services as intended.

Requesting the Honourable Member to refer to the table below for details on bulk projects implemented and completed from 2012/13 financial year to date as well as the status thereof.

Status of completed projects from 2012/13 to 2021/22 financial year

Name of the project

Name of the WSA/district municipality

Status of the project

Reasons/comments on non-functional projects

EASTERN CAPE

Mount Ayliff Bulk Water Supply

Alfred Nzo DM

Functional

None

Greater Mbizana Regional Bulk Water Supply Phase 1

Alfred Nzo DM

Functional

None

Mncwasa Bulk Water Supply

Amathole DM

Functional

None

Ibika Bilk Water Supply

Amathole DM

Not Functional

Water rationing due to drought around Butterworth and shortfall of funds to complete the project

Xonxa Bulk Water Supply Phase 1

Chris Hani DM

Functional

The contractor is busy with snags on the pumpstation

Coffee Bay Bulk Water Supply Scheme

OR Tambo DM

Functional

None

KSDPI Bulk Sanitation

OR Tambo DM

Functional

None

Steytlerville Bulk Water Supply

Dr Beyers Naude Local Municipality

Functional

Due to extreme drought. the plant is struggling to obtain water from the Poort where water abstraction is taking place.

Graaff Reinet Bulk Water Supply Phase 1

Dr Beyers Naude Local Municipality

Functional

None

Paterson BWS Phase 1 to 5A

Sundays River Valley Local Municipality

Functional

None

MPUMALANGA

Acornhoek Bulk Water Supply

Bushbuckridge LM (Ehlanzeni DM)

Functional

None

Botleng Wastewater Treatment Works

Victor Khanye LM (Nkangala DM)

Functional

None

Balfour Wastewater Treatment Works phase 2

Dipaleseng LM (Gert Sibande DM)

Functional

None

Amsterdam/Sheepmoor phase 1 & 2

Mkhodo LM (Gert Sibande DM)

Functional

None

Delmas Wastewater Treatment Works phase 1

Victor Khanye LM (Nkangala DM)

Functional

None

Lushushwane Regional Bulk Water Supply phase 1 to 4

Chief Albert Luthuli LM (Gert Sibande DM)

Functional

None

Hoxani Bulk Water Supply

City of Mbombela LM (Ehlanzeni DM)

Not functional

Waiting for the City of Mbombela to finalise the Mechanical & Electrical components that were funded through co-funding by the Municipality

Northern Nsikazi Bulk Water Supply

     

Bushbuckridge Water Services (Cunningnore) phase 1

Bushbuckridge LM (Ehlanzeni DM)

Functional

None

Empuluzi phase 3A, 4A & 8

Chief Albert Luthuli LM (Gert Sibande DM)

Functional

None

Refurb & Upgrade of Ermelo Water Treatment Works

Msukaligwa LM (Gert Sibande DM)

Functional

None

Refurbishment of Emalahleni Water Treatment Works

Emalahleni LM (Nkangala DM)

Functional

None

Balfour/Siyathemba Regional Bulk Water Supply Phase 1

Dipaleseng LM (Gert Sibande DM)

Not functional

Awaiting the completion of the Upgrading of the Balfour Water Treatment Works in Fortuna (known as the Balfour/Siyathemba phase 2)

GAUTENG

Upgrade of Hannes van Niekerk WWTW

Rand West City Local Municipality (formerly Westonaria Local Municipality)

Partially Functional

Some process units of the new module are dysfunctional due to poor maintenance, theft and vandalism.

Upgrade of Rothdene Pump Station

Midvaal Local Municipality

Functional

None

Upgrade of Sebokeng Wastewater Treatment Works Module 6

Emfuleni Local Municipality

Functional

None

KWAZULU-NATAL

Jozini

uMkhanyakude DM

The scheme is functional. The plant is producing 20Ml/day. Bulk pipeline to Ngwavuma with 12 zonal areas completed. Zone 1 to zone 5 completed and operational with reticulation

The municipality is currently implementing zone 6 under MIG programme

Dukuduku Resettlement

uMkhanyakude DM

Functional with minor operational challenges in some areas.

Portion of the settlement with proper reticulation. UKDM has improved most of the unreliable areas through WSIG

Hlabisa

uMkhanyakude DM

The scheme is functional

There is currently not enough water coming from Mandlakazi scheme which is currently under construction. UKDM has improved most of the unreliable areas through WSIG

Emadlangeni

Amajuba DM

The scheme is functional

None

Greater Eston

uMgungundlovu DM

The scheme is functional

None

uMshwathi Phase 1-3

uMgungundlovu DM

The scheme is functional

None

Mhlabatshane

Ugu

The scheme is functional

None

Lower Tugela

iLembe

The scheme is functional

None

FREE STATE

Maluti-a-Phofung Bulk Water Supply, Phase 1: Construction of Sterkfontein WTW

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply, Phase 1: The construction of Escol Reservoir.

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply, Phase 1: Rising main to Escol Reservoir.

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply, Phase 2: Escol pipelines.

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply, Phase 2: Raw water supply system at Sterkfontein Dam.

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply, Phase 3: Makwane Scheme.

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply, Phase 3: Northern Bulk Storage Stage 1.

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply, Phase 3: Northern Bulk Storage Stage 2.

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply, Phase 3: Sealing and waterproofing of the Uniqwa Reservoirs.

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply, Phase 3: Bulk interconnection pipeline: Uniqwa Reversal.

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply, Phase 4: QwaQwa Borehole project Stage 1: Drilling and testing of 60 operational boreholes.

Maluti-a-Phofung LM

Functional

None

Maluti-a-Phofung Bulk Water Supply BWS, Phase 4: QwaQwa Borehole project Stage 2: The equipping of 5 priority boreholes.

Maluti-a-Phofung LM

Partially functional

From the five (5) priority boreholes, one (1) has been severely vandalised, and two (2) are not being operated.

Nketoana Bulk Water Supply, Phase 1: Stage 1A: Upgrading of the Reitz WTW

Nketoana LM

Partially Functional

The some components are not working fully.

Nketoana Bulk Water Supply, Phase 1: Stage 3A: Ground Water Study in Nketoana, and Development of Boreholes in Arlington, Petrus Steyn and Lindley

Nketoana LM

Functional

None

Nketoana Bulk Water Supply, Phase 1: Stage 3B: Upgrading of the Lindley WTW

Nketoana LM

Functional

None

Nketoana Bulk Water Supply, Phase 1: Stage 3C: Upgrading and refurbishment of Lindley and Arlington Water pump Stations

Nketoana LM

Functional

None

Refurbishment of Clarens Sewer Pump Station

Dihlabeng LM / Thabo – Mofutsanyana

Functional

None

Upgrading of La Provence Sewer pump station Rising Main

Dihlabeng LM / Thabo – Mofutsanyana

Functional

None

Upgrading of Bethlehem Water Treatment Works: Replacing of Asbestos Cement Pipeline from Abstraction point at Sol Plaatjies Dam to Water Treatment Works

Dihlabeng LM / Thabo – Mofutsanyana

Functional

None

Upgrading of Fouriesburg (Carolina) Pump Station

Dihlabeng LM / Thabo – Mofutsanyana

Functional

None

Refurbishment of 4 sewer pump station in Bethlehem/Bohlokong

Dihlabeng LM / Thabo – Mofutsanyana

Functional

None

Replacement of AC pipes to PVC pipes in Memel

Phumelela LM / Thabo – Mofutsanyana

Functional

None

Replacement of AC pipes to PVC pipes in Warden

Phumelela LM / Thabo – Mofutsanyana

Functional

None

Refurbishment of sewer rising main(asbestos) for Ezenzeleni Area and construction of new sewer station with outfall sewer

Phumelela LM / Thabo – Mofutsanyana

Functional

None

Refurbishment of the WTW in Vrede & Memel Water Treatment Works

Phumelela LM / Thabo – Mofutsanyana

Functional

None

Replacement of AC water pipes to PVC in Vrede – Phase 1

Phumelela LM / Thabo – Mofutsanyana

Functional

None

Phumelela BWS: Construction of the Ezenzeleni 3ML reservoir and appurtenant works

Phumelela LM / Thabo – Mofutsanyana

Functional

None

Phumelela BWS: Construction of the Ezenzeleni raw water pump station and pipelines

Phumelela LM / Thabo – Mofutsanyana

Non-functional

The pump station was vandalized and some equipment at the pump station were stolen. Currently under Construction funded under RBIG 5B COVID19 project to render it operational.

Phumelela BWS: Construction of the Ezenzeleni Water Treatment Works and construction of the civil structure and associated works

Phumelela LM / Thabo – Mofutsanyana

Non-functional

The water treatment works depended on raw water pumped from the vandalized pump station within the same scheme, making it non-functional. However, currently under construction to render it operational funded under RBIG 5B. COVID19 project.

The Upgrading of the 1,5km clear water raising main line from the WTP to Marquard Reservoir

Setsoto LM / Thabo – Mofutsanyana

Functional

None

Setsoto BWS Phase 1: Sand River Abstraction, Borehole refurbishment, Construction of the pipeline from Caledon to Meulspruit – Clocolan and Marquard

Setsoto LM / Thabo – Mofutsanyana

Functional

None

Setsoto BWS Phase 2: Construction 630mm raw water pipeline from Meulspruit to Ficksburg Water Treatment Water

Abstraction of raw water from the Caledon Riverbed

Setsoto LM / Thabo – Mofutsanyana

Functional

None

Ngwathe Bulk Sewer (Vredefort)

Ngwathe LM – Fezile Dabi DM

Non-functional

The plant is not functional due to lack of operation and maintenance.

Moqhaka Bulk Sewer

Moqhaka LM – Fezile Dabi DM

Not functional

The plant is not functional due to lack of operation and maintenance. Currently the DWS, Provincial office and Municipality are implementing a project to refurbish the plant.

Ngwathe Bulk Water Supply – Construction of concrete reservoir at Edenville

Ngwathe LM – Fezile Dabi DM

Functional

None

Ngwathe Bulk Water Supply – Construction of pump house and equipping of boreholes in Edenville

Ngwathe LM – Fezile Dabi DM

Partly functional

Not all boreholes are operational due to vandalism

Mafube Bulk Sewer Phase 1 of 2 - Construction of Namahadi Pump Station

Construction of Geelhout (Britz) Pump Station

Refurbishment of Seagull Street Pump Station and Associated Works

Mafube LM – Fezile Dabi DM

Functional

None

Moqhaka Bulk Water Supply - To construct a 9.5 km pipeline with a booster pump station

Moqhaka LM in the Fezile Dabi DM

Functional

None

Bulk water pipeline to hospital

Mantsopa LM

Functional

None

Tweespruit Bulk water Supply - Supply and Equipping of 6 Boreholes

Mantsopa LM

Functional

None

Tweespruit Bulk water Supply - Supply and Equipping of Two Boreholes within 10km Radius10km Radius Phase 2A (Exploration)

Mantsopa LM

Functional

None

Tweespruit Bulk water Supply - Supply and Equipping of Two Boreholes within 10km Radius – Phase 2B

Mantsopa LM

Functional

None

Equipping Of Boreholes and Upgrading

Of Pump Station in Excelsior

Mantsopa LM

Functional

None

Excelsior: Design and Construction Monitoring Water Tower, Raw Bulk Pipeline and Pumpstation- Phase 2

Mantsopa LM

Functional

None

Masilonyana Bulk water Supply Phase 1 of 2

Lejweleputswa DM/ Masilonyana LM

Functional

The project is functional but being a raw water pipeline, some repairs has been highly necessary to undertake through a WC/WDM project, considering water leakages in the line and mechanical / electrical issues in the high lift pump stations associated to this pipeline

Tokologo Bulk Water Supply Phase 1 of 3

Lejweleputswa DM/Tokologo LM

Functional

The project is functional, but Municipality is facing operational issues with lack of spares in the installed raw water pumps in the abstraction point.

Tswelopele Bulk water Supply Phase 1 of 2

Lejweleputswa DM/Tswelopele LM

Functional

None

Wesselsbron / Monyakeng Bulk Sewer

Lejweleputswa DM/Nala LM

Non-functional

The plant is not functional due to lack of operation and maintenance.

Jagersfontein /Fauresmith BWS Phase 1

Xhariep DM/Kopanong LM

Functional

The project is complete and functional connected to phase 2 which is at practical completion stage

WESTERN CAPE

Worcester Bulk Water

Breede Valley

Functional

None

Grabouw Wastewater Treatment Works

Theewaterskloof

Functional

None

Paarl Bulk Sewer

Drakenstein

Functional

None

Drakenstein Wastewater Treatment Works

Drakenstein

Functional

None

Swellendam Wastewater Treatment Works

Swellendam

Functional

None

Citrusdal Wastewater Treatment Works

Cederberg

Functional

None

George Bulk Water

George

Functional

None

Stellenbosch Wastewater Treatment Works

Stellenbosch

Functional

There is a challenge on the inlet works but municipality is sorting matter.

Lamberts Bay

Cederberg

Non-functional

There is a need to complete the installation of the sea outfall. The contractor has been appointed and the anticipated completion date is end of February 2022

Tulbugh BWS

Witzenberg

Functional

There is a need to complete the construction of the dam and tributaries. The contractor has been appointed and the anticipated completion date is end of June 2024

LIMPOPO

Mogalakwena Phase 1

Waterberg

Non-functional

The challenge is with the water abstraction point that has not been developed as yet

Polokwane BWS

Capricorn

Functional

None

NORTH WEST

Koster Wastewater Treatment Works

Kgetleng river

Functional

None

Tlokwe phase 1

Tlokwe

Functional

None

Pilanesburg phase 1

Moses Kotane /Rusternburg

Functional

None

Pilanesburg phase 2

Moses Kotane /Rusternburg

Functional

None

Madibeng /Britsphase 1

Madibeng

Functional

None

Maqussi hills WWTW/BWS

Maquassi

Functional

None

Moretele south phase 1

Moretele

Functional

None

Greater Mamusa phase 1

Mamusa

Functional

None

Taung Naledi phase 1 Podumong

Dr Ruth Mompati

Functional

None

NORTHERN CAPE

Colesburg Wastewater Treatment Worksulk

Umsobomvu / Pixley ka Seme

Functional

None

Hopetown Water Treatment Works

Thembelihle / Pixley ka Seme

Functional

None

Niekershoop Bulk Water Supply

Siyathemba / Pixley ka Seme

Functional

None

Kathu Wastewater Treatment Works

Gamagara / John Toalo Geatsewe

Functional

Functional, but need to be upgraded again

Colesburg Water Treatment Works

Umsobomvu / Pixley ka Seme

Functional

None

Vanderkloof Wastewater Treatment Works

Renosterberg / Pixley ka Seme

Functional

None

Norvalspont Bulk Water Supply

Umsobomvu / Pixley ka Seme

Functional

None

Noupoort Bulk Water Supply

Umsobomvu / Pixley ka Seme

Functional

None

Britstown Oxidation Ponds

Emthanjeni / Pixley ka Seme

Functional

None

Van Wyksvlei Bulk Water Supply Phase 1

Kareeberg / Pixley Ka Seme

Functional

None

Marydale Bulk Water Supply

Siyathemba / Pixley ka Seme

Functional

None

Strydenburg Bulk Water Supply

Thembelihle / Pixley ka Seme

Functional

None

Kalahari East Pipeline phase 1

Dawid Kruiper / Pixley ka Seme

Functional

None

Homevale Wastewater Treatment Works

Sol Plaatje / Frances Baard

Non-Functional

The plant is currently not fully functional due to poor Operation & Maintenance, theft, and vandalism

Ricthie Bulk Water Supply

Sol Plaatje / Frances Baard

Functional

None

Loeriesfontein Bulk Water Supply

Hantam / Namakwa

Functional

None

Brandvlei Bulk Water Supply

Hantam / Namakwa

Functional

None

Williston Bulk Water Supply

Karoo Hoogland / Namakwa

Functional

None