23 June 2021 - NW1607

Profile picture: Hicklin, Ms MB

Hicklin, Ms MB to ask the Minister of Public Works and Infrastructure

With regard to the refurbishment of the parliamentary villages which was mooted and begun with many of the brick houses being assessed first, a process which resulted in the rebuilding of a number of brick houses currently underway, and in light of the fact that many of the prefabricated houses have asbestos roofs which pose significant health concerns to residents, (a) on what date is it envisaged the refurbishments will (i) be concluded on the brick houses which were started before the start of the COVID-19 pandemic and (ii) start on the prefabricated houses in the parliamentary villages and (b) what plans are in place to fast-track the finalisation of the refurbishment programme in all three parliamentary villages?

Reply:

The Minister of Public Works and Infrastructure:

1. (a) I have been informed by the Department that:

(i) The project does not entail rebuilding but maintenance of the brick houses. The, site handover was done in September 2020 and is scheduled to be completed as follows:

  • Acacia Park - 7 February 2022
  • Laboria Park - 7 November 2022
  • Pelican Park - 7 September 2023

(ii) The demolition of the prefabricated houses and building of new units project will commence with the appointment of the contractor in October 2021, firstly the designs will be done and thereafter construction.

(b) The project will be completed within the agreed timelines.