Question NW1448 to the Minister of Public Works and Infrastructure

Share this page:

18 August 2020 - NW1448

Profile picture: Graham-Maré, Ms SJ

Graham-Maré, Ms SJ to ask the Minister of Public Works and Infrastructure

(a) What was the percentage of budget and actual amount of money budgeted for maintenance of infrastructure owned by her department in the 2017-18, 2018-19 and 2019-20 financial years and since 1 April 2020, (b) what percentage and actual amount of the budgeted amounts were spent in the 2017-18, 2018-19 and 2019-20 financial years, (c) what were the reasons why the budget was either over- or underspent in each case and (d) which votes and/or line items were either increased and/or reduced as a result?

Reply:

The Minister of Public Works and Infrastructure:

(a) The Department of Public Works and Infrastructure (DPWI) percentage of budget and actual amount of money budgeted for maintenance of infrastructure in the 2017-18, 2018-19 and 2019-20 financial years and since 1 April 2020 is outlined in table 1 below:

Table 1: Infrastructure maintenance budget

 

Line Item

 

2017/18

2018/19

2019/20

April to June 2020

 

Budget

% of total Budget

 

Budget

% of total Budget

 

Budget

% of total Budget

 

Budget

% of total Budget

 

 

R'000

 

R'000

 

R'000

 

R'000

 

Scheduled and Unscheduled Maintenance

1 367 580

9%

1 570 448

10%

1 781 095

10%

1 437 861

7%

Repair

943 594

6%

1 087 519

7%

1 339 429

7%

1 451 024

7%

Refurbishment

1 034 464

7%

1 020 776

6%

1 233 776

7%

1 319 637

7%

Total

3 345 639

23%

3 678 743

22%

4 354 300

24%

4 208 522

22%

(b) The percentage and actual amount of the budgeted amounts were spent in the 2017-18, 2018-19 and 2019-20 financial years are listed in Table 2 below

Table 2: Infrastructure maintenance expenditure

Line Item

 

2017/18

2018/19

2019/20

April to June 2020

 

Exp

% Exp

 

Exp

% Exp

 

Exp

% Exp

 

Exp

% Exp

 

 

R'000

 

R'000

 

R'000

 

R'000 

 

Scheduled and Unscheduled Maintenance

1 316 633

96%

1 548 982

99%

1 781 095

100%

239 574

17%

Repair

952 025

101%

943 976

87%

1 057 534

79%

57 650

4%

Refurbishment

1 033 399

100%

926 515

91%

976 779

79%

57 650

4%

Total

3 302 057

99%

3 419 472

93%

3 815 408

88%

354 874

8%

(c) The scheduled and unscheduled maintenance budget for 2017/2018 was underspent by 4% and for 2018/19 the underspent was 1%, due to the portion of unscheduled maintenance, which cannot be predicted with certainty owing to breakdown of assets, equipment and conditions thereof.

In the mist of delivering infrastructure projects, DPWI encountered a number of challenges which include but not limited to the following:

  • Incapacity of some emerging contractors implementing our projects is adversely affecting timeous delivery of projects.
  • Clients requests for additional work and community protests and demands to be considered by service providers has financial implication on the preliminaries and generals costs of the projects;
  • Limited professional services positions for Sketch Plan approvals, which adds to delays for approval of sketch plans;
  • Extended tender adjudication and award dates;
  • Community protests and work stoppages;
  • Incapacity of some emerging contractors implementing DPWI projects is adversely affecting timeous delivery of projects.

(d) No Votes and/or line items were increased and/or reduced as a result of the under-expenditure.