Question NW3248 to the Minister of Justice and Correctional Services
03 November 2017 - NW3248
Selfe, Mr J to ask the Minister of Justice and Correctional Services
(a) What amount has his department spent on the (i) building of new correctional service facilities and (ii) upgrading of existing correctional service facilities in each of the past five financial years and (b) in each case, what are the relevant details of the (i) facility concerned, (ii) work done and (iii) date of completion?
Reply:
(a)(i) New facilities
Name of facility |
2012/2013 |
2013/14 |
2014/15 |
2015/16 |
2016/17 |
Vanrhysdorp |
18 906 244 |
23 380 231 |
4 382 735 |
11 842 331 |
7 207 392 |
Ceres |
39 100 354 |
11 465 436 |
2 391 946 |
7 735 778 |
- |
Matatiele |
23 065 960 |
19 278 972 |
28 538 134 |
6 642 672 |
1 590 883 |
Tzaneen |
63 836 704 |
10 632 841 |
12 594 728 |
251 266 |
1 257 334 |
Total |
144 909 262 |
64 757 480 |
47 907 728 |
26 472 047 |
10 055 5609 |
(a) (ii) Upgrade of existing facilities
Name of facility |
2012/2013 |
2013/14 |
2014/15 |
2015/16 |
2016/17 |
Pretoria C-Max |
35 016 585 |
52 410 938 |
18 550 642 |
- |
33 728 102 |
Estcourt |
16 578 791 |
43 707 716 |
41 045 027 |
72 790 162 |
102 972 817 |
Standerton |
710 957 |
42 412 324 |
115 510 008 |
162 106 331 |
70 406 036 |
Total |
52 306 333 |
138 530 978 |
175 105 677 |
234 896 493 |
207 106 955 |
(b)(i)(ii)(iii)
(b) (i) Facility concerned |
(b) (ii) Work done |
(b) (iii) Date of Completion |
Vanrhynsdorp |
New buildings: Gatehouse, Pre-processing Block, Administration Block, Admission Block, Central Visitation Block, Medical Services Block, Education Block, Vocational Training Block, 2 x Inmate Housing Blocks, Chefs Block, Food Services Block, Segregation Block, Assessment Block, Laundry Block, Electrical Services Block, Case Management Block, Asset Maintenance Block, Logistics Block and Garages for State Vehicles |
The work was completed on 01 September 2016 |
Pretoria C-Max |
'Complete upgrade of facilities including Hvac (ventilation) upgrade, 12 additional beds. Contractor on new contract paid from DPW suspense account, DCS pays only Consultant. |
To be completed on 23 November 2018 |
Ceres, Warmbokkeveld |
New buildings: Gatehouse, Pre-processing Block, Administration Block, Admission Block, Central Visitation Block, Medical Services Block, Education Block, Vocational Training Block, 2 x Inmate Housing Blocks, Chefs Block, Food Services Block, Segregation Block, Assessment Block, Laundry Block, Electrical Services Block, Case Management Block, Asset Maintenance Block, Logistics Block and Garages for state vehicles |
The work was completed on 01 March 2015 |
Matatiele |
New buildings: Gatehouse, Pre-processing Block, Administration Block, Admission Block, Central Visitation Block, Medical Services Block, Education Block, Vocational Training Block, 2 x Inmate Housing Blocks, Chefs Block, Food Services Block, Segregation Block, Assessment Block, Laundry Block, Electrical Services Block, Case Management Block, Asset Maintenance Block, Logistics Block and Garages for State Vehicles |
The work was completed on 01 January 2016 |
Tzaneen |
New buildings: Gatehouse, Pre-processing Block, Administration Block, Admission Block, Central Visitation Block, Medical Services Block, Education Block, Vocational Training Block, 2 x Inmate Housing Blocks, Chefs Block, Food Services Block, Segregation Block, Assessment Block, Laundry Block, Electrical Services Block, Case Management Block, Asset Maintenance Block, Logistics Block, Garages for State Vehicles, Sports field and Security Fence. Contractor on new contract paid from DPW suspense account, DCS pays only Consultant. |
To be completed on 31 May 2018 |
Estcourt |
Restored Heritage House and Storeroom and 'New buildings (comprised of Pre-processing Block, Administration Block, Admission Block, Central Visitation Block, Medical Services Block, Education Block, Vocational Training Block, 2 x Inmate Housing Blocks, Chefs Block, Food Services Block, Segregation Block, Assessment Block, Laundry Block, Electrical Services Block, Case Management Block, Asset Maintenance Block, Logistics Block, Garages for State Vehicles, Sports field and Security Fence. |
To be completed on 28 February 2018 |
Standerton |
Upgrading of existing Medium A and Medium B Prisons and New buildings (comprised of Gatehouse, Pre-processing Block, Administration Block, Admission Block, Central Visitation Block, Medical Services Block, Education Block, Vocational Training Block, 1 x Inmate Housing Block, Chefs Block, Food Services Block, Segregation Block, Assessment Block, Laundry Block, Electrical Services Block, Case Management Block, Asset Maintenance Block, Logistics Block, Garages for State Vehicles, Agricultural Store, Bus Stop, Sports fields and Security Fence) |
To be completed on 26 April 2016 |