Question NW1508 to the Minister of Public Works and Infrastructure

Share this page:

18 July 2023 - NW1508

Profile picture: Graham-Maré, Ms SJ

Graham-Maré, Ms SJ to ask the Minister of Public Works and Infrastructure

What progress has been made to date with implementing the necessary repairs to the roof of the Potchefstroom Magistrate’s Court that partially collapsed in September 2022? NW1751E

Reply:

The Department received the Engineers report for the reconstruction of the collapsed roof. The new construction of the roof was not on the initial scope of work for the Repairs and Renovations project that is currently underway in Potchefstroom Magistrate’s Court.

The Department invited quotations from roof specialists for the construction of the roof and the variation order application was submitted to the Variation Order (V.O.) Committee for consideration and upon approval of the V.O, the remedial work will start to reconstruct the roof.

 

 

NATIONAL ASSEMBLY: QUESTION NO. 1508 (Written Reply) Ms S J Graham (DA) asked the Minister of Public Works and Infrastructure:

The draft reply to Parliamentary Question No. 1508 (Written Reply) is submitted for your consideration.

The input has been provided by the Construction Project Management Branch.

I hereby attest that the information provided in response to NA PQ 1508 is true and correct, to the best of my knowledge.

________________________

MR. R MATLALA

REGIONAL MANAGER: MMABATHO REGIONAL OFFICE

DATE:

I hereby attest that the information provided in response to NA PQ 1508 is true and correct, to the best of my knowledge.

________________________

MR. C LOMBAARD

DEPUTY DIRECTOR GENERAL: FACILITIES MANAGEMENT

DATE:

Draft reply supported / not supported/ comments

________________________

MS. N MAKHUBELE

ACTING-DIRECTOR GENERAL

DATE:

NATIONAL ASSEMBLY: QUESTION NO. 1508 (Written Reply) Ms S J Graham (DA) asked the Minister of Public Works and Infrastructure:

Draft reply supported / not supported/ comments

_____________________

MS. B SWARTS, MP

DEPUTY MINISTER OF PUBLIC WORKS AND INFRASTRUCTURE

DATE:

Draft reply approved / not approved/ comments

__________________________

MR. S ZIKALALA, MP

MINISTER OF PUBLIC WORKS AND INFRASTRUCTURE

DATE:

Pub works-4 copy

MINISTRY

PUBLIC WORKS AND INFRASTRUCTURE

REPUBLIC OF SOUTH AFRICA

Department of Public Works l Central Government Offices l 256 Madiba Street l Pretoria l Contact: +27 (0)12 406 1627 l Fax: +27 (0)12 323 7573

Private Bag X9155 l CAPE TOWN, 8001 l RSA 4th Floor Parliament Building l 120 Plein Street l CAPE TOWN l Tel: +27 21 402 2219 Fax: +27 21 462 4592

www.publicworks.gov.za

NATIONAL ASSEMBLY

WRITTEN REPLY

QUESTION NUMBER: 1508 [NW1751E]

INTERNAL QUESTION PAPER NO.: 15 of 2023

DATE OF PUBLICATION: 05 MAY 2023

DATE OF REPLY: MAY 2023

1508. Ms S J Graham (DA) asked the Minister of Public Works and Infrastructure:

What progress has been made to date with implementing the necessary repairs to the roof of the Potchefstroom Magistrate’s Court that partially collapsed in September 2022? NW1751E

REPLY:

The Minister of Public Works and Infrastructure

The Department received the Engineers report for the reconstruction of the collapsed roof. The new construction of the roof was not on the initial scope of work for the Repairs and Renovations project that is currently underway in Potchefstroom Magistrate’s Court.

The Department invited quotations from roof specialists for the construction of the roof and the variation order application was submitted to the V.O. committee for consideration and upon approval of the V.O, the remedial work will start to reconstruct the roof.

__________________________

MR. S ZIKALALA, MP

MINISTER OF PUBLIC WORKS AND INFRASTRUCTURE

DATE:

Source file