With regard to water-related grants such as the Regional Bulk Water Infrastructure Grant and Water Service Infrastructure Grant making a huge positive impact in society through the rolling out of water infrastructure projects, (a) how many projects are to be completed by the end of the current financial year and (b) what total number of households across the Republic would have access to water and sanitation upon completion of these projects?

Reply:

The table below summarises the number of projects planned to be completed in the current financial year 2024/25 and the households to benefit from these projects:

Grant Funding

Number of projects to be completed (2024/25 FY)

Number of households targeted to benefit from completed projects

Water Services Infrastructure Grant

103

309 000

Regional Bulk Infrastructure Grant

32

467 000

---00O00---