ATC13108: Report of the Standing Committee on Appropriations on a follow-up oversight visit to the provinces of Limpopo and Mpumalanga for 22 to 26 July 2013, Dated 17 September 2013
Standing Committee on Auditor General
Report of the Standing Committee on
Appropriations on a follow-up oversight visit to the provinces of Limpopo and
Mpumalanga for 22 to 26 July 2013, Dated 17 September 2013
The
Standing Committee on Appropriations, having undertaken a follow-up oversight
visit to the provinces of Limpopo and Mpumalanga from the 22 to 26 July 2013,
reports as follows:
1.
Introduction
The
Standing Committee on Appropriations (the Committee) undertook a second follow-up
oversight visit to the Limpopo and Mpumalanga provinces from 22 to 26 July
2013. The aim of the visit was to follow-up on a similar visit which was
undertaken by the Committee in the years 2010 and 2011. The objective of the
oversight visit was the need to determine the extent of progress in respect of
various projects done by the Department of Water Affairs (DWA). These are the Nandoni
Water Treatment Works and Distribution Network (Thohoyandou, Limpopo), and the
Inyaka Water Treatment Works (Bushbuckridge, Mpumalanga).
The
visit had been informed by ongoing interactions between the Committee and DWA
during the in-year monitoring of its expenditure. The Committee observed that
there remain recurrent challenges in the effective expenditure of budgets
earmarked for water infrastructure projects. Furthermore, a key concern was the
efficacy of the alignment in the planning and implementation of water services infrastructure
linking the DWA, Water Boards and various stakeholders within the three spheres
of government. Therefore, the Committee took a decision to conduct a workshop
on 23 July 2013 with the relevant stakeholders, i.e. Department of Water
Affairs, Limpopo and Mpumalanga Regional Branches of the Department of Water
Affairs, Department of Cooperative Governance and Traditional Affairs, National
Treasury, South African Local Government Association, Vhembe District
Municipality, Ehlanzeni District Municipality, Water Research Commission,
Lepelle Northern Water Board, and Rand Water Board.
The objective of the workshop was for the
Committee to get a full understanding of the challenges experienced in the
delivery of water services where the two projects, i.e. Nandoni and Inyaka,
were situated. This workshop was held at the Porche-Villa Hotel in Thohoyandou,
Limpopo. The aforementioned workshop was followed by site visits as follows:
-
Vuwani to
Valdezia pipeline (24 July 2013);
-
Vuwani Reservoir
and Pump Station (24 July 2013);
-
Nandoni Water
Treatment Works (24 July 2013); and
-
Inyaka Water
Treatment Works (25 July 2013).
2.
Delegation
The
delegation was as follows: Hon E M Sogoni (Chairperson); Hon R J Mashigo; Hon
JP Gelderblom; Hon G T Snell; Hon AT Mfulo; Hon L Yengeni; Hon L Ramatlakane;
and Hon SM van Dyk. The delegation was accompanied by the following
parliamentary officials: Mr D Arends (Committee Secretary); Mr T Masoeu
(Content Advisor) Mr P Dlomo (Committee Researcher); and Ms N Chaso (Committee
Assistant); and Mr E Bacon (Personal Assistant to Hon AT Mfulo)
The
Committee met with the following stakeholders at the workshop and the various
sites during the oversight visit:
National and Regional
Departmental Officials:
Ms T Mbasa; Ms Z Y Mathe; Mr F Smith; Ms M
Maraka; Mr M Rex; Mr RL Tloubatla; Mr M Mavhungu; Mr N Oswers; Mr R Hill; Mr V
Monene; Ms C Williams; Ms L Mokhuisi; Ms P Nkgudi; Mr M Jethro; Ms N Mello; Mr
R Masibigiri; Mr M Tshilidzi; Ms N Mavuso; Ms S Moshidi; Ms R Edward; Ms MG
Nyavani; Mr P du Toit; Ms M Komape; Mr D Mabada; Mr M Nekhudzhiga; Ms MM
Ramadikela; Ms L Sefora; Mr S Thwala; Mr TS Magado;
Mr M Mulaudzi; Mr E Kubayi; Ms M Matiso; Ms C
Mashaba; Ms L Kobe; Ms P Ramunenyiwa; Mr F Guma; Mr S Ratau; Mr B Ramanyimi; Mr
D Mokome; Mr T Manyama; Ms M Musekene; Mr HA Mabuza; Ms M Matiso; Mr K Siziba;
Ms S Siwele; and Ms L Mokoena
National Treasury:
Mr M
Mulaudzi
Department of
Cooperative Governance and Traditional Affairs:
Mr G Mthethwa; Mr W
Haydenreich; Mr K Bologo (MISA); Mr P Polasek (MISA); Mr Dladla (MISA); Mr K
Katsidzira (MISA); and Mr TJ Makayela (MISA)
Limpopo Department of
Cooperative Governance, Human Settlements and Traditional Affairs:
Mr MS
Molepo
Mpumalanga Provincial
Treasury:
Mr
M Madike; and Ms L Manonyane
Mpumalanga Provincial
Department of Cooperative Governance and Traditional Affairs:
MEC SPD
Skhosana; and
Mr D Ntombela
Vhembe District
Municipality:
Cllr MR Lucy; Cllr PE Bvumbi; Cllr K Nemaranzhe; Cllr C
Nkanyami; Mr MT Makumule; Mr EF Chauke; Mr MJ Hwasie; Mr TE Masakoma; and Mr M
Muthu
Ehlazeni District
Municipality:
Cllr P Monareng; and Mr Shrinivasan
Bushbuckridge Local
Municipality:
Cllr R Khumalo (Executive Mayor); Cllr PT Selowe; Cllr M
Sesekani; Cllr D Makhubele; Cllr S Nxumalo; Mr L Mathebula; Mr E Ngomane; Mr E
Mashava; and Mr P Zingeni
Bushbuckridge Water
Board:
Mr V Gouws; Mr M Radingwana; Mr R Mnisi; Mr M Makhavhu; and Ms SR Madisha
SALGA:
Mr MV
Suzan; Ms L Siswana; and Mr L Morifi
Lepelle Northern
Water Board:
Mr N Nokepia and Mr S Mpamonyane;
Water Research
Commission:
Mr J Bhagwan and Dr S Pillay
Rand Water Board:
Mr M
Ndlela and Mr M Mdlopane
3.
Terms of
reference
Section
27 (1) (b) in Chapter 2 of the Constitution of the Republic of South Africa provides
that every citizen has a right to access sufficient and clean drinkable water. The
Constitution gives national and provincial government authority to regulate
local government in terms of water services. It further gives them the
obligation to support and strengthen the capacity of local government to
provide services.
In
the 2010 State of the Nation Address (SONA), His Excellency President Zuma
stated the government shall not falter until each and every community in our
nation has clean potable water because our water supply forms a strong backbone
to all social and economic development initiatives.
The National Development Plan 2030 identifies
water as a strategic resource critical for social and economic development. Furthermore,
the National Development Plan states that water and sanitation services are a
priority for basic community services and thus their sustainable management is
critical for community health, development and economic activity.
Given
the declaration by the President of the Republic of South Africa and the
strategic importance of water provision in building sustainable communities,
the Committee sought to look into ways to enhance alignment and the utilisation
of resources in the operations of institutions in the water sector through a
workshop engagement identifying challenges and possible solutions; and to
ascertain the extent of water service provision in the communities of Limpopo
and Mpumalanga.
Table 1 below
provides the budget allocations of the Nandoni Pipeline Construction (Limpopo) and
the Inyaka Water Treatment Works (Mpumalanga) projects since 2011/12 up to
2013/14 financial years.
Table 1:
Allocations for Nandoni
Pipeline Construction and Inyaka Water Treatment Works
Programmes and Projects
R000
|
2011/12
|
2012/13
|
2013/14
|
2014/15
|
Total
|
Nandoni Pipeline
Construction
|
203,000
|
317,000
|
230,000
|
0
|
750,000
|
Inyaka Water Treatment Works
|
136,800
|
0
|
10,455
|
0
|
145,255
|
National Treasury (2011, 2013)
4.
Workshop
on Water Services Delivery
The
Committee held a workshop on 23 July 2013 with institutions in the water sector
for a comprehensive assessment of the water delivery value chain. The following
stakeholders were invited to the workshop; i.e. Department of Water Affairs,
Limpopo and Mpumalanga Regional Branches of the Department of Water Affairs,
Department of Cooperative Governance and Traditional Affairs, National
Treasury, South African Local Government Association (SALGA), Vhembe District
Municipality, Ehlanzeni District Municipality, Water Research Council (WRC),
Lepelle Northern Water Board, and Rand Water Board.
4.1.
Department
of Water Affairs Submission
The Department in its submission
outlined progress and interventions made in improving water delivery through
its Nandoni Water Bulk Distribution System and the Inyaka Water Scheme.
The Nandoni Water
Bulk Distribution System
in Thohoyandou, Limpopo commenced in 2009 and
the completion date was originally set for 2010. This water project was one of
24 water schemes in the Vhembe District Municipality. The
Nandoni Bulk Distribution System was established to secure sustainable
water supply in Vhembe Region and it covered the following supply areas
(population in brackets):
·
Kutama Sinthumule and Makhado (89 749);
·
Vondo (Thohoyandou and Vuwani) (325 577);
·
Malamulele East and West (300 644); and
·
Mhinga/Lambani (25 621).
The table below depicts the progress
of the construction of the Nandoni Bulk Water Distribution Scheme:
Table 2:
Construction stages
of components of Nandoni Pipeline
No.
|
Project name
|
Project description
|
Construction
percentage to date
|
Projected
completion date
|
1
|
NN20B
rising main
|
250
mm diameter x 10.1 km (capacity of 24 ℓ/s)
|
95
%
|
August
2013
|
2
|
NR6
rising main
|
700
mm diameter x 18.8 km (capacity of 400 ℓ/s)
|
95%
|
September
2013
|
3
|
NR6 reservoir (Vondo)
|
capacity of 16 Mℓ
|
95%
|
September 2013
|
4
|
NR5
Reservoir (Mavambe)
|
capacity
of 5 Mℓ
|
95%
|
November
2013
|
5
|
Mavambe
pump station
|
capacity
of 800 ℓ/s
|
95%
|
November
2013
|
6
|
Mavambe
to Vuwani rising main pipeline
|
800
mm diameter x 31.6 km (capacity of 800 ℓ/s)
|
70%
|
November
2013
|
7
|
NR7 Reservoir (Vuwani)
|
capacity of 5 Mℓ
|
95%
|
December 2013
|
8
|
Vuwani pump station
|
capacity of 896 ℓ/s
|
70%
|
November 2013
|
9
|
Vuwani
to Valdezia rising main pipeline
|
900
mm diameter x 30.3 km (capacity of 896 ℓ/s)
|
45%
|
December
2013
|
10
|
Valdezia
reservoir
|
capacity
of 16 Mℓ
|
80%
|
December
2013
|
DWA reported that the bulk water
distribution system would be completed by December 2013. This scheme would
supply water into the Vuwani and Valdezia reservoirs and the Vhembe District
Municipalitys schemes needed to transport the water from these reservoirs to
the communities.
DWA had a number of water intervention
programmes in the Vhembe District Municipality which include the
Accelerated Community Infrastructure Programme (ACIP), Regional Bulk
Infrastructure Programme (RBIG), Water Services Operating Subsidy (O&M and
Refurbishment), Municipal Water Infrastructure Grant (MWIG) and the Municipal
Infrastructure Grant (MIG). These interventions were earmarked to address water
services backlog of 158 427 households from a total 315 953 households in
the Vhembe District Municipality. In particular, of the 158 427 household
water services backlogs, 66 187 was due to the lack of access to water as a
result of functionality problems (i.e. refurbishment/operations and
maintenance), 45 050 required water extension to existing infrastructure,
40 942 had access to water infrastructure but no water due to source
problems whilst only 6 248 had no formal water infrastructure.
The following challenges were reported
with regards to the Nandoni pipeline project:
·
NN20B pipeline has been completed and tested,
however the reservoir which was constructed had leaks;
·
Completion of the NR6 pipeline was delayed
due to high humidity which affected lining and coating;
·
Project programme was delayed due to
persistent rainfall; and
·
Cash flow problems had been experienced by
some contractors which delayed the implementation of the projects.
The following measures were underway
in addressing the stated challenges:
·
DWA was repairing the reservoir and the
estimated completion date was 31 August 2013;
·
The contractor utilised a blowing fan method
to eradicate accumulated humidity in the pipes;
·
The contractors needed to submit revised
programmes by 26 July 2013 to the Department for review; and
·
The Implementing Agents needed to ensure the
appointed contractors have financial security.
DWA in its
presentation also outlined the progress on the Inyaka Water Treatment Works and
gave an overview of the Acornhoek, Sathale, Edinburgh, Sand River, Thulamashe,
and Hoxane water supply schemes.
The Inyaka Water Treatment Works in
Mpumalanga commenced in 2008 and the completion date as indicated in the
previous oversight visit of the Committee in 2011 was May 2013. The Inyaka Water
Treatment Works was intended to
provide a secure
source of water for domestic, municipal and industrial users in the Bushbuckridge
area. The Inyaka Water Scheme, once completed would utilize 88 existing
reservoirs and was earmarked to supply
116 villages
numbering 98 161 households. The water scheme, at the date of the visit
supplied 30 014 or 31% of the total 98 161 households.
The Inyaka Water
Treatment Works comprised of four Phases of which Phases 1 & 2 of the water
treatment plant which process 50 000 m3/day (50 ML/day) were constructed at
Maviljan in Bushbuckridge and were operational. The 3rd and 4th Phases were
intended to safeguard the domestic water supply to communities and would be
capable of providing an additional 50 000 ML/day and were in the process of
being constructed The envisaged completion dates for the 3
rd
and 4
th
phase was August 2013 after which the capacity would increase to 100 000 ML/day.
These two phases (Phase 3 & 4) were at an overall completion stage of 99
per cent at the date of the site visit and progress was as follows:
·
Raw Water Pump Line (96%);
·
Inlet Works (100%);
·
Flocculation Channels x 2
(99%);
·
Settling Tanks x 2 (99%);
·
Sand Filters x 2 (99%);
·
Clearwater Tank (100%);
·
Reservoirs 20Ml x 2 (99%);
·
Sludge Ponds x 2 (99%);
·
Extension of Administration
Building (100%); and
·
Access Road (100%).
The table below depicts the
expenditure trends of the Inyaka Water Treatment Works. These costs included
Value Added Tax.
Table 3:
Overview
of Inyaka WTW budget and expenditure
Project
Phase
|
Expenditure
|
Project
Status
|
Phase 1
|
R 93,76 m
|
Completed
|
Phase 2
|
R 120,56 m
|
Completed
|
Phase 3 & 4
|
R 482,57 m
|
Projected final amount
91%
spent
|
2008/2009
|
R 44,73 m
|
Completed
|
2009/2010
|
R 120,81 m
|
Completed
|
2010/2011
|
R 85,81 m
|
Completed
|
2011/2012
|
R 77,66 m
|
Completed
|
2012/2013
|
R 102,64 m
|
Completed
|
2013/2014
|
R 48,42 m
|
Projected
|
2014/2015
|
R 0,0 m
|
Projected
|
2015/2016
|
R 2,5 m
|
Projected (Retention)
|
Raw Water Line
|
R 31,63 m
|
70% spent
|
Mechanical & Electrical
|
R 50,09 m
|
60% spent
|
The following
challenges were reported with regards to the Inyaka Water Scheme project:
·
The household backlog and non-functional
infrastructure which stood at 69 per cent or 68 147;
·
Unauthorized connections;
·
Insufficient supply due to inadequate infrastructure
and increased demand;
·
High water losses;
·
Unreliable electricity supply; and
·
Inadequate water storage capacity.
The Committee was
informed that Phases 3 and 4 of the project had lost a total of 266 days of
work. This was attributed to 155 days lost as a result of rain since September
2008 and 111 days lost due to industrial action in 2009. It was reported that the
non-availability of material also contributed to delays.
DWA outlined its
intervention project in the Bushbuckridge Local Municipality (BLM) in
partnership with COGTA and Rand Water. The project aimed to improve the pace of
developing and constructing water reticulation systems
in the area. The project scope included the design and installation of
pipelines, yard connections, pressure valves, valve chambers and general
refurbishment. The project execution plan has been completed and a service
provider appointed.
DWA reported on a
number of challenges experienced in the roll-out of the intervention and these
included the need for coordinated Water Master Plans (WMP) at Water Service Authority
(WSA) level, lack of compliance to infrastructure funding grant criteria /
conditions, lack of co-funding by WSAs on infrastructure programs and dependency
on external technical expertise and lack of internal capacity in WSA to manage
infrastructure programs.
It was stated that some
of the measures instituted in order to address these challenges and improve
performance included the need to implement Water Related By-laws, maintain
assets registers related to water infrastructure, maintain operations and
maintenance plans, implement water conservation and water demand management,
WSAs to ensure skills transfer by external service providers, the need for benchmarking
of systems and processes across WSAs
and
to improve the Departments
monitoring and evaluation regulatory oversight on the Municipal Infrastructure
Grant (MIG).
4.2.
Ehlanzeni
District Municipality Submission
The Ehlanzeni District Municipality
(EDM) in its submission outlined various challenges affecting water service
delivery in the district and made recommendations on addressing same. Bushbuckridge
Local Municipality was the water service authority and the Bushbuckridge Water
Board was the water service provider in the Bushbuckridge Local Municipality (BLM)
and the Nsikazi area in the Mbombela Local Municipality. The EDM outlined a
number of challenges affecting water delivery which included
insufficient budget for operations and maintenance (O&M), the need
to develop underground water sources, availability of materials; poor or
outdated water master plans; lack of institutional, managerial, operations and
maintenance capacity at all levels of government; and inadequate asset
management planning.
Based on the stated
challenges, the EDM made a number of recommendations which included the
prioritization of MIG funds by municipalities for bulk water supply; municipalities
to ring fence operations and maintenance funding;
councillors
to adopt the Siyabhadala Manje
campaign and encourage communities to pay for (all) services and the adoption
of a comprehensive approach to planning and co-ordination of infrastructure.
4.3.
Vhembe
District Municipality Submission
In its submission,
the Vhembe District Municipality (VDM) indicated that the district was 98.9%
rural with only 1.1% being urban and that deterioration of infrastructure was
high largely due to limited budgets and capacity. The VDM was the WSA and
provided bulk water supply. The WSA indicated that there existed good working
relations with sector partners i.e. DWA, the four local municipalities, COGTA
(Municipal Infrastructure Support Agency/MISA) and the Limpopo Department of Cooperative
Governance, Human Settlements and Traditional Affairs. The district was wholly
dependent on grant funding. In particular, the bulk distribution pipeline
network was funded through the MIG grant and the VDM stated that it had spent
100% of its MIG allocation in the past two financial years.
In its submission,
the VDM outlined a number of challenges which included delays in the completion
of Nandoni Bulk lines; the 4 schemes (i.e. Nandoni, Vondo, Xikundu and
Malamulele East) received no operation and
maintenance budget from DWA and staff allocated to the schemes were not funded
by DWA; there was a critical shortage of skilled process controllers; the DWA
staff transfer process brought in large numbers of personnel (mostly unskilled)
resulting in an unsustainable salary bill; insufficient grant funding for
operations and maintenance; and the vandalism of water equipment.
The VDM
highlighted following interventions intended to address the above reported challenges
and these include:
·
Memorandum of Understanding (MoU) signed with DWA for the
DWA Construction Division to construct the Valdezia to Mowkop pipeline;
·
The VDM was in the process of embarking on ways to
increase cost recovery as follows:
-
Billing accounts for water services were
separated
at Local Municipality and in
2012/13 financial year the District collected R20 million; and
-
Draft Revenue Enhancement strategy was in the process
of being developed.
·
MOU signed with MISA to deploy
22
Artisans (Electrical, Mechanical,
plumbing and brick layers) and
34
Process Controllers (water & waste water);
·
Pipe condition survey
in the process of being undertaken which should impact positively on revenue
collection;
·
Conversion of
Technical Services Department to Water Services Department for the said
department to
have a special focus on
water;
·
The District
installed a high lift pump of bigger pumping capacity at Albasini
water treatment works and managed to fill the
Mowkop reservoir to capacity daily; and
·
The district upgraded
a borehole in Mutoti village and constructed a rising main to existing
reservoir and the Mutoti community received water 24 hours.
The VDM made
the following recommendations to the Committee:
·
DWA should expedite completion of Nandoni bulk water
network;
·
DWA to provide O&M budget and staff to operate and
maintain Nandoni, Vondo and Xikundu schemes (schemes over R100 million);
·
Funding was required to replace the 33 km long
Albasini to Mowkop reservoir
bulk pipe
line; and
·
O&M grant from DWA to be increased in line with
scheme requirements.
4.4.
South
African Local Government Association
The South African Local Government
Association (SALGA) in its submission reported that it was working in
collaboration with the Department of Water Affairs and WSAs to ensure that
communities received essential services like water and sanitation. SALGA
indicated that a number of challenges had been experienced and these included
the finalisation of technical reports, slow spending on MIG, delays in the registration
of projects and the lengthy process of funding roll-overs.
SALGA reported that the delayed
approval of technical reports by the DWA had a negative impact on municipal
spending, especially regarding MIG. It was reported that a workshop had been held
with DWA in the 2012/13 financial year to address this matter. In addition to
the technical reports, it was stated that projects had to be registered before
commencement with the respective Provincial Departments of Cooperative
Governance and Human Settlements. The point was made that these registrations
took long in certain instances and these delays derailed the municipal planning
cycle. These challenges had a knock-on effect as they often resulted in requests
by municipalities for roll-over funds.
4.5.
Department
Cooperative Governance Municipal Infrastructure Support Agency (MISA)
The Municipal Infrastructure Support
Agency (MISA) in its submission indicated that the Vhembe District
was selected for the first phase of MISA support since it formed part
of the 23 districts prioritized by Cabinet following the July 2011 Cabinet
Lekgotla. An assessment was also done to some of the water works following the flooding
that had occurred in early 2013. The agency identified areas in plant design;
and operations and maintenance as requiring support.
One of the major
challenges identified which was within the support mandate of MISA was the absence
of technical capacity due to a lack of skilled personnel in the Vhembe District
Municipality
.
MISA has now committed to support
the district with some of the required personnel artisan plumbers, artisan electricians,
artisan bricklayers, artisan carpentry, water and waste water operators
The Vhembe district
owned 22 regional water schemes that required a considerable amount of skills
to operate and maintain for the sustainable supply of safe drinking water to
communities and the business sector. MISA reported that it had committed the
following artisans to assist the Vhembe District Municipality and they are to
commence working on 1 August 2013.
Table 4:
MISA committed
support
Trade
|
Requested number of artisans
|
Water Plant Operators
|
17
|
Waste Water Plant Operators
|
17
|
Electricians
|
5
|
Mechanical
|
7
|
Plumbers
|
7
|
Carpentry
|
2
|
Brick layers
|
1
|
Total
|
62
|
MISA indicated
that there was an agreement with the VDM that the above mentioned support staff
should be appointed by the district on a permanent basis after two years. MISA
will pay the salaries of the artisans during the first two years.
4.6.
Presentation
by Lepelle Northern Water
Lepelle Northern
Water (LNW) in its presentation indicated that its primary activity was to
provide bulk water services to other water services institutions such as
municipalities and mines. LPW indicated its readiness to support water
provision in the Limpopo Province through the following measures, namely:
·
LNW stated that it is
ready to operate and maintain all the above R100 million water schemes in
Limpopo at any given period;
·
Business Plan for
funding was submitted to National Treasury through DWA to operate and maintain
all the above R100 million schemes in the Limpopo province;
·
The LNW Water Board
had a pool of 500 learnerships ranging from artisans to Process Controllers for
both Waste Water Treatment Works and Water Treatment Works; and
·
South African National Accreditation System (SANAS) Accredited laboratory
for both water & sanitation.
In terms of
its financial viability, the LNW reported as follows:
·
LNW boasted total assets of R876 million consisting of
R449 million of fixed assets and the balance being investments and working
capital;
·
The debt/equity ratio stood at 0.18 as at end of June
2012. Notwithstanding this gearing level the board continued to make surpluses
and invested these in the refurbishment and upgrading of its infrastructure;
·
The surplus generated throughout these past years was
through increases in sales and major improvements in operating efficiencies
while tariffs were kept to affordable levels; and
·
LNW has built a solid financial base and will continue
this trend all things being equal.
LNW in its
submission requested that Cabinet finalise the decision on the transfer of the
over R100 million water distribution schemes to it and that it be appointed in
the interim to run these schemes so as to prevent further dilapidation of the
schemes.
4.7.
Water
Research Commission
The Water Research Commission (WRC) in
its submission emphasised the importance of selecting appropriate and sustainable
water technologies and highlighted trends in the financial viability of Water
Service Authorities in executing their mandate. The WRC indicated that while
WSAs were under pressure to comply with strict and very high standards and
regulations, the overall water sector needed to acknowledge the limited
resources available in the WSA delivery environment and thus foster an
environment where it was possible to attain effluent quality and management;
and sustainability.
A study on
the appropriateness of the choice of wastewater technologies implemented by
Water Service Authorities in 18 treatment plants was conducted across the
country. In the report of the said study which was published in December 2012, the
WRC found that that the m
ore complex and
potentially costly level of technology enjoyed higher preference compared to
the low/medium levels of technology, there was insufficient attention to long
term cost and capacity to operate and maintain high level technologies (i.e. lack
of skills, cost of expansion, repairs and capital cost of new systems) and the
existing trend to upgrade to a higher technology level rather than resolve the
process limitations and optimise existing systems.
Findings from the study also indicated that technology options and
license applications in the water sector were strongly driven by consultants. In
the case of lower capacity municipalities, project decisions were driven from
consultants, often without investigating alternative options or sustainability
of recommended technology and consultants often recommended technologies which
they were familiar with and not necessarily those most suitable to the specific
municipality.
With regards to financial viability, the WRC outlined key trends in cost
recovery and tariffs in the water sector. Water Boards purchase bulk water from
DWA and set bulk water tariffs in areas where they provide bulk water services.
The WRC found that bulk water tariffs have increased steadily over the years
and varied widely due to the availability of water, distance distribution, raw
water quality and costs. WRC reported that a possible future consideration may
be the initiation of reforms aimed at price regulation. Furthermore, if
inefficiencies were detected by WSA in bulk water provision they should not
pass on this cost to consumers.
Mhlathuze Water was found to be the cheapest whilst Sedibeng Water was
the most expensive and others such as Rand Water, Lepelle Northern Water, Bloem
Water, and Amatola Water were also high. Local municipalities facing high bulk
water tariffs charged consumers high retail tariffs. The Local Government
Equitable Share (LGES) funding in combination with collected water revenues was
not adequate to cover bulk water expenses in some municipalities such as BLM
and Mafikeng. Cost recovery was critical for sustainability though the main challenges
reported by the WRC were the setting of tariffs below cost and the limited
collection of tariffs in rural areas.
4.8.
Deliberations on the Workshop
The Committee
welcomed inputs from all stakeholders and emphasized the need for frank and
critical assessment of areas requiring improvement by all stakeholders in their
specific roles in the water delivery value chain. The Committee viewed it
necessary for all stakeholders to clearly identify challenges so that it may be
able to intervene and unblock bottlenecks impeding the delivery of water
services to communities. In particular, the Committee noted the revision of
targets from earlier presentations made by the Department to the Committee and
was concerned at the attainability of the current stated targets.
A key consideration
by the Committee was possible cost overruns that may emanate from delays in the
completion of projects. The Committee stated that in the past, significant
funds had to be made available due to projects not meeting contracted projects
schedules. Furthermore, the Committee cited examples of past performance where
spending patterns showed that budgets had been spent but less than 10% of the pre-determined
objectives were attained. The Committee pointed out that problems of cash flows
from contractors need not impact on the Departments projects as payments were
only for work completed. The Department responded that there will not be
additional funding required for the current projects for which completion dates
have been revised and that it was in the process of putting measures in place
to ensure that expenditure was aligned with the attainment of pre-determined
objectives.
The Committee noted
that in a number of projects due for completion, the progress-to-date was indicated
as being at an advanced stage with over 90% completed. In particular, the
Committee raised concerns on whether the completion target date of December
2013 was realistic. The Department indicated that projects at an advanced stage
(i.e. over 90%) were normally only awaiting the quality assurance process to be
finalized.
The
Committee made reference to the reported court case between the Department of
Water Affairs and a service provider regarding the production of the Nandoni
pipeline and clarity was sought on the progress of same. The Department
responded that the litigation matter was at the High Court.
The Committee was
concerned with the performance of the internal construction unit of the
department and its working relationship with the Department. In particular, one
contract,
W0497
WTE
, had three contractors (including the internal
construction unit) and the Committee sought clarity on the process of issuing
tenders to internal and external service providers and the allocation of responsibilities
within the said contract. A key concern was that the internal construction unit
was outsourcing work that it was meant to complete. The Department indicated
that at present, budgets were allocated to project managers in the internal
construction unit and Service Level Agreements (SLAs) were in the process of
being developed between the Department and the internal construction unit.
Furthermore, the Department indicated that in the past it had been unable to
impose penalties for non-compliance to project timeframes by the internal construction
unit but assured the Committee that this would no longer be the case in the
next financial year.
The Committee pointed
out the need for enhanced integration in the planning and implementation of
water projects. The Committee highlighted that one of its major concern was the
end result following the completion of pipelines. A central point of emphasis
was that the completion of pipelines by the Department of Water Affairs should
overlap with the completion of reticulations systems by the local authorities
thus ensuring simultaneous access to water by communities. The Committee indicated
that there were a number of grants supporting water provision infrastructure
(Regional Bulk Infrastructure, Municipal Infrastructure Grant, Municipal Water Infrastructure
Grant (MIG), etc whose funding frameworks stipulated conditions for alignment
and integration and yet alignment remains a recurring challenge.
MISA indicated that
one of the ways that may enhance the level of alignment in the delivery of water
services was the increased participation of all stakeholders in the Integrated
Development Plan Process (IDP). Furthermore, MISA reported that there were MIG
forums which sought to integrate the work of all stakeholders in the rollout of
basic services infrastructure.
The Committee noted
that the issue of illegal connections to water sources by farmers in the Vhembe
region had been raised as a significant drain of the already limited water
resources in the area. The Committee was concerned at the level of
transformation of the agricultural sector and their involvement in appreciating
the scarcity of water resources in the area. The VDM indicated that transformation
in the agricultural sector in the region was less than 5% and that they are
currently engaging local farmers with regards to illegal connection.
The Committee noted
that in many instances the Department cited the lack of capacity of local
government to implement water projects as a major challenge. The Committee
emphasized that the Constitution provided that national government and
provincial government should support municipalities in executing their
mandates. In addition, the Committee was concerned at the capacity and readiness
of Water Boards to deliver water services and support local government
institutions. Therefore, the Department should not seek to deliver only on bulk
water infrastructure without due regard to the final reticulation systems that
are required to provide water to communities. The Committee stated that the
Department should exercise leadership in the water sector and also seek
solutions together in partnership with other stakeholders such as COGTA.
The Department
indicated that whilst there were challenges of project management capacity at
local government level, similarly there was limited project management capacity
internally within the Department. In many instances, large projects amounting
to billions of rands were managed by only one official. The Department
indicated that while many Water Boards do have capacity there was work underway
in the realignment of all Water Boards to respond more swiftly to the demand
for water.
The Committee noted
the research findings showing the prevalence of consultant-driven use of high
technology intensive approaches to the roll-out of water infrastructure in
especially rural municipalities with low revenue bases. The Committee pointed
out to the Department the need for a comprehensive skills development plan that
would ensure that following the completion of all water infrastructure projects
in the Limpopo and Mpumalanga provinces, there will be a skills base to draw on
for long term operations and maintenance.
The Committee welcomed the study
findings of the WRC and sought clarity on whether the Commissions research
papers were factored into the planning processes of the Department of Water
Affairs.
The Committee viewed the
findings on the sustainability of newly built water infrastructure and
disparities in the water tariff charges as critical considerations in the
medium term planning framework of the DWA. The Department reported that the
information produced by the WRC has not yet been filtered into its planning
processes but that it was in the process of establishing an implementation
forum to ensure to that its findings filtered down to implementing officials.
The Committee expressed concern at the fact that the Department commissioned
the WRC to conduct studies, yet it had no mechanisms in place to ensure that
the findings and recommendations of such studies were thoroughly considered in
water sector planning and project implementation.
5.
Projects
Visits
5.1.
Nandoni
Bulk Water Distribution Network (Valdezia Pipeline)
On 24 July 2013, the Committee
undertook a site inspection of the Valdezia pipeline and reservoir. The Valdezia
pipeline and reservoir was scheduled for completion in December 2013 and was
earmarked to supply water to the Valdezia village, the Mowkop
Reservoir
and Waterval/Elim area. The Committee
emphasised the need for the Department to set targets that were realistic and
to furnish the Committee with reports on any possible challenges that may impede
on the successful attainment of targets. The Committee viewed the submission of
timeous information to itself as critical in allowing the Committee to
intervene and mobilise support where necessary.
The Department listed the following as
some of the challenges that may impact on the attainment of the December 2013
deadline:
·
Negotiations were ongoing with private landowners for
access to land which was situated along the route of the Valdezia pipeline. The
Department indicated that funds were in place for the purchase of the private
land, a legal opinion report has been drafted on the land matter and it
envisaged
finalisation
of the land matter
within 2 months;
·
The performance of contractors was not satisfactory.
The Department indicated that there were recurring challenges in joint ventures
between established contractors and emerging and smaller contractors;
·
There were shortages in the number of specialist
welders for the pipeline construction. The Department indicated that the steel
pipes were different from PVC pipes and that contractors
specialising
in the steel pipe installation were few and thus
various sites where steel pipe installation was in progress had to share the
same contractors; and
·
Rain and other natural disasters may impact on the set
completion date of the project.
The Committee was of the view that the
Department may not be able to respond to these challenges speedily in order to
ensure that completion date targets were reached. In particular, the Committee
enquired about the existence of a Project Gantt Chart which would illustrate
the amount and types of resources which would be required for the project to
meet targeted completion dates. The Committee pointed out that the Gantt chart
will assist the Department in planning properly around any potential challenges
to the successful completion of the project.
The Committee viewed the lack of a
readily available Gantt chart on the revised completion dates for the project
as indicative of poor planning by the Department.
The Department responded that the Gantt Chart
would be revised and undertook to furnish same to the Committee. The Committee
viewed the lack of specialist welders for the construction of the pipeline as a
significant challenge. The Committee pointed out that there was a need for
short-term and long-term skills plan by the Department to address the challenge
of specialist skills.
The Committee sought clarity on the
target date for access to water by the surrounding villages once the pipeline
and reservoir have been completed. The Department reported that a MOU has been
signed between the Department and the VDM in order for the former to assist with
the water reticulation systems subsequent to the finalisation of the bulk water
infrastructure (i.e. bulk pipeline and reservoir). The VDM reported that it had
placed reticulation systems in neighbouring villages but had insufficient
funding for the bulk pipe from Valdezia to Mowkop and needed an additional R400
million for the construction of the Mowkop pipeline.
The Committee commended all stakeholders
for the undertaking to deliver in an integrated manner water services to the
communities in the Vhembe District Municipality. The Committee further
requested a costed works programme for the construction of the pipeline from the
Valdezia reservoir to all envisaged beneficiaries.
5.2.
Inyaka
Water Treatment Works
On 25 July 2013, the
Committee undertook a site inspection of the Inyaka Water Treatment Works. On
site, there was a joint presentation led by the Mpumalanga Provincial
Department of Cooperative Governance and Traditional Affairs (MCoGTA). The MCoGTA
indicated that the presentation was a joint effort between provincial
government, the DWA, the Bushbuckridge Local Municipality and the Rand Water
Board. In its submission, the MCoGTA indicated that tap water provision in the
Mpumalanga province has increased from 58.2% in 1996 to 71.7% in 2011 while tap
water access in the Ehlanzeni District Municipality had increased from 48.3% in
1996 to 57.8% in 2011.
Some of
general challenges reported by MCoGTA in its submission on general water access
in the province and the EDM included the
inconsistent water
supply (e.g. rationing and no supply for many days), high water losses and
illegal connections, limited supply of electricity, ageing infrastructure, inadequate
bulk water infrastructure (storage), poor cost recovery due to an inadequate
billing system and insufficient technical capacity. Storage was highlighted as
a key challenge as many reservoirs in the area were originally designed with
the intention for use for farming irrigation and thus unsuitable for
facilitating regular access to water for household use by communities.
With regard to the
Acornhoek Bulk Pipeline, the pipeline project had commenced in August 2011 and was
originally scheduled for completion for August 2012. The revised completion
date for the pipeline project was 31 July 2013. It was reported that the
original contract budget was R130.2 million but due to the delays in completion,
the budget this year has increased to R155.3 million. The reported number of
jobs created was 92 and all were young people with 30% being women. It was
reported that a number of challenges were experienced during the construction
of the Acornhoek Bulk Pipeline and these included delays in the delivery of
pipes to site, 180 days delay due to rain, community unrest, unexpected deep
excavation to remove the Glass-Reinforced Polyester (GRP) pipes, leaking
flanges found on existing air valve chambers, leaking flanges at existing scour
valve chambers and continual vandalism.
The MCoGTA indicated
that Bushbuckridge Municipality had been placed under administration in terms
of section 139(1) (b) of the Constitution of the Republic of South Africa. As
such the powers of the Executive Mayor and Municipal Manager of the municipality
had been assigned to an administrator. It was further reported that a MOU had
been signed between the Minister of Water and Environmental Affairs and the
Premier of the Mpumalanga Province with a view to accelerating water
implementation in the province. It was reported that the Rand Water Board has
been appointed to implement the intervention at the Bushbuckridge, Msukaligwa
and Emalahleni Local Municipalities. In addition to this, the Mpumalanga
Economic Growth Agency (MEGA) had been assigned to support eight municipalities
in the province for the implementation of bulk water and sanitation
infrastructure. The point was made that 70 per cent of the provinces CAPEX had
been allocated towards the delivery of water and sanitation services.
In the joint submission,
the MCoGTA indicated that one of the key objectives of the intervention between
the Department of Water Affairs, Department of Cooperative Governance and Rand
Water was to improve the delivery of water services in the municipality by
developing and constructing water reticulation systems and to connect municipal
customers to the water supply. The number of villages to be reticulated between
May 2013 and February 2014 as per the project scope were 40. The project scope
included the design and installation of water reticulation pipelines with
associated pipe fittings; yard connections; pressure reducing valves; gate
valves; valve chambers; customer meters; and refurbishment of selected bulk
infrastructure. It was reported that the service provider implementing the
project had been appointed in June 2013 and that the project execution plan had
been completed.
The Committee
commended the Mpumalanga Province, DWA, MCoGTA, district and local
municipalities and all stakeholders involved in the project for their
integrated approach towards the delivery of water services to communities in
the Ehlanzeni District Municipality and the Bushbuckridge Local Municipality in
particular. The Committee emphasised that the DWA needed to play a leading role
in the water sector and in the fostering of partnerships to ensure accelerated
water delivery.
The Committee expressed
concern at the challenges affecting cost recovery and enquired whether there
were mechanisms in place to ensure that the matter is addressed. In addition to
this, clarity was sought on whether Eskom has provided assurance that there
would be a steady supply of electricity in the region so as to ensure that the
project on supplying water to communities succeeds. The MCoGTA responded that
it had developed a comprehensive revenue enhancement strategy to address the
loss of income and stated that there were ongoing discussions with Eskom
regarding the supply of electricity. The Committee noted the indication by
MCoGTA that the current debt owed by BLM to Bushbuckridge Water Board was R300
million and indicated that in its previous oversight visit to the Inyaka Dam in
2011 the debt amounted to R190 million.
In respect of the
projected completion date for the Inyaka Water Treatment Works, clarity was
sought on whether any expected delays, for instance, as a result of rain have
been factored in and whether there were measures in place to ensure that these
delays do not impact significantly on the completion dates. The Committee was
concerned at the attainability of the reported completion date of August 2013
for the Phases 3 and 4 of the Inyaka Water Treatment Works. The Committee
sought clarity on the alignment of expenditure as opposed to actual work
completed on site (i.e.99% construction versus 91% of budget spent). The DWA
indicated that the mechanical and electrical works were complete on Phase 3 and
4 and only the environmental inspection process was outstanding. Furthermore,
the outstanding payment amount for the Phase 3 and 4 included the processing of
payment certificates and a final insurance amount which will only be paid to
the contractor once the construction is operational and no defects detected.
The MCoGTA indicated
that the Premier and MCoGTA have committed to the February 2014 completion date
for access to water by communities in the BLM. The DWA also reported that a
lack of funding could be an obstacle to the achievement of the targeted date of
February 2014 and that there was a R250 million shortfall at present although
all stakeholders are to look into their finances to cover this shortfall. The
Committee requested that the Department furnish it with a comprehensive project
implementation plan for the intervention to supply water to communities by
February 2014 in the Bushbuckridge Local Municipality.
The Committee pointed
out the need for all stakeholders to indicate clearly on any material risks
that may affect the completion of the Inyaka Water Treatment Works. The Rand
Water Board indicated that the main risks identified included water metering,
operations and maintenance in the long-term by the BLM once the intervention was
complete and the future supply of electricity. The MCoGTA highlighted financial
viability and the retaining of the financial and technical skills in the
municipality. Furthermore, expenditure on the infrastructure grant funding
allocated to the BLM needed to be improved (2012/13 Municipal Infrastructure
Grant total expenditure was only 60%).
6.
Findings
The
Standing Committee on Appropriations made the following findings:
6.1.
The revised completion dates for the Nandoni
Distribution Network and the Inyaka Water Treatment Works were December 2013
and August 2013 respectively.
6.2.
The Department of Water Affairs was still in
the process of finalising negotiations with private land owners whose land was
along the route of the Nandoni Distribution Network (Valdezia) pipeline. The
DWA indicated that the land matter in the Valdezia pipeline construction area
should be finalised with two months.
6.3.
The Committee noted the significant increase
in the personnel expenditure for operating water schemes in the Vhembe District
Municipality and the lack of skilled personnel in its water schemes.
6.4.
Half the households in the Vhembe region do
not have access to piped water and a significant portion of the backlogs in
access to water emanate from the lack of operations and maintenance of water
infrastructure.
6.5.
The Committee found the lack of an integrated
skills plan by the Department of Water Affairs as a major concern. There was no
skills plan in place to address the need for specialist welders at the Nandoni
pipeline project.
6.6.
The Department of Water Affairs and the
Mpumalanga Department of Cooperative Governance and Traditional Affairs
committed to the completion target date of February 2014 for reticulation
systems which will ensure continuous (24 hour) water access for communities in
the Bushbuckridge Local Municipality.
6.7.
The Committee welcomed the Memorandum of
Understanding on providing water services concluded between the Minister of
Water Affairs and the Premier of the Mpumalanga Province and commends the
coordination of work by the Mpumalanga Department of Cooperative Governance and
Traditional Affairs, National Department of Cooperative Governance and
Traditional Affairs and the Department of Water Affairs in rolling out water
services infrastructure in the Bushbuckridge Local Municipality.
6.8.
The existing reservoirs in the Inyaka Water
Scheme supplying the Bushbuckridge area were originally designed for farm irrigation
systems and will need to be upgraded to ensure water from the reservoirs is
suitable for household consumption and thus accessible to the surrounding
communities.
6.9.
The Committee welcomed the intervention of
Rand Water Board and Mpumalanga Economic Growth Agency in upgrading the
existing water reservoirs and water pipelines the Bushbuckridge Local
Municipality and thus accelerating the rollout of water infrastructure.
6.10.
There was a significant increase in the debt
owed by the Bushbuckridge Local Municipality (BLM) to the Bushbuckridge Water
Board which was reported as R190 million in the Committees 2011 oversight
visit and is now at R300 million.
6.11.
The Committee welcomed the work undertaken by
the Water Research Council. The Committee noted that the findings of studies
and research activities undertaken by the Water Research Commission were not
integrated in the planning activities of the Department of Water Affairs and
thus found limited expression in the implementation of water projects.
6.12.
There was a need to enhance planning for the
delivery of water services at local government level and that generally there
was a lack of Water Master Plans in Water Service Authorities.
6.13.
There were Service Level Agreements being developed
between the Department of Water Affairs and its Internal Construction Unit and
the agreements would include the imposition of penalties for poor performance.
6.14.
Poorer municipalities were likely to adopt
consultant-driven high technology water infrastructure solutions in their areas
of jurisdiction due to a lack of internal technical capacity. The adoption of
expensive technologies in municipal water systems will pose a significant
financial and skills burden on the sustainability of operations and maintenance
of these water schemes.
7.
Recommendations
The
Standing Committee on Appropriations, having taken the deliberations with the
abovementioned stakeholders into consideration, recommends as follows:
7.1.
That the Minister
of Water and Environmental Affairs should ensure the
following:
7.2.
That the Department of Water Affairs submit a
detailed progress report for the construction of the Nandoni pipeline,
inclusive of the targeted dates for the completion of the reticulation of water
from the Nandoni bulk water distribution system to communities. This report
should be inclusive of possible challenges that could delay progress.
7.3.
That the Department of Water Affairs consider
the development of a comprehensive skills plan for its entire water
infrastructure programme.
7.4.
That the Department of Water Affairs submit a
report on the litigation case on the Nandoni Distribution Network.
7.5.
The Department of Water Affairs consider
developing an operational mechanism in its planning and implementation
procedures to incorporate the outcomes of the study and research activities of
the Water Research Commission.
7.6.
That the Department of Water Affairs consider
extending partnership agreements such as the concluded Memorandums of
Understanding (MoUs) between Mpumalanga Province and the Department of Water
Affairs, to other provinces as well, so as to expedite the rollout of water
services infrastructure.
7.7.
The Department of Water Affairs consider
putting in place measures to ensure that capacity for operations and
maintenance of water infrastructure is in place following the installation and
completion of the bulk water infrastructure in the Nandoni Water Scheme (Vhembe
District Municipality) and Inyaka Water Scheme (Ehlanzeni District
Municipality).
8.
Conclusion
All
the requested reports as set out in section 5 above need to be submitted to the
National Assembly within 60 days of this report being adopted in the
House.
Report
to be considered.
Documents
No related documents