Report: Progress made in the completion of Ceres, Vanrhynsdorp & Brandvlei New-Generation Correctional Centres currently under construction in the Western Cape- dated 20 June 2012
Correctional Services
REPORT
OF THE PORTFOLIO COMMITTEE ON CORRECTIONAL SERVICES ON PROGRESS MADE IN THE
COMPLETION OF CERES, VANRHYNSDORP AND BRANDVLEI NEW-GENERATION CORRECTIONAL
CENTRES CURRENTLY UNDER CONSTRUCTION IN THE WESTERN CAPE- DATED 20 JUNE 2012
1.
INTRODUCTION
1.1.
A delegation
of the Portfolio Committee on Correctional Services (the Committee) visited the
site of the new-generation correctional centre under construction in Ceres, to
investigate the reasons for the delay in its completion, as well as the delays in
the completion of the Vanrhynsdorp and Brandvlei projects.
1.2
Overcrowding is one of the Department of Correctional Services (DCS)
major challenges: in the
1.3
The
visit comprised a briefing by the department of public works and correctional
services regional and area management, a tour of the Ceres site, interactions
with the construction company responsible for the Ceres and Vanrhynsdorp
projects, and finally a debriefing session.
1.4
A series of
questions for written response were forwarded to the DCS, the Department of
Public Works (DPW) and the construction company responsible for the Ceres and
Vanrhynsdorp projects,. The DPW and DCS written responses were discussed
during a follow-up meeting held on 22 February 2012.
1.5
None of the
three centres were completed on time. In a meeting held on 23 May 2012 the
Committee was informed that all three would be operational by the end of the
2012/13 financial year.
1.6
The
delegation paid a brief visit to remand detainees accommodated at the Ceres
centre. Though the observations made during that interaction are not recorded
here, concerns are similar to those raised elsewhere: the need to separate
those in remand for the first time, and habitual offenders; the effectiveness
of the Judicial Inspectorate for Correctional Services (JICS) indepedendent
correctional centre visitors; and the impact of delayed police investigations
and court proceedings. The Committee had in the past made numerous
recommendations in this regard and, though not repeated here, those remain
relevant.
2.
BACKGROUND
2.1
Ceres project
2.1.1
The
old Ceres Correctional Centre could accommodate 238 inmates. Once renovated,
its capacity will be doubled. The new centre will accommodated 500 inmates and will
comprise two housing units, single cells, a hospital and a kitchen. Each
housing unit will comprise four communal cells accommodating 60 inmates each.
The remaining bedspaces will be for those inmates who will be assisting with
the delivery of nutrition services and will be accommodated in cells near the
kitchen.
2.1.2
The
contract, which initially valued R 212, 5 million. was awarded in 2008, and
construction commenced on 11 July of that year. The renovations were meant to
have been completed by 10 July 2010, but, at the time of the visit,
construction was still under way.
2.1.3
,Scope
changes resulting from experience accumulated during the construction of the
Tswelopele Correctional centre, and the inclusion of a solar-heating system,
offender-management system and PMC flooring resulted in an approximately R30,4
million escalation in the cost of the project. At the time of the visit, penalties
to the amount of R3,63 million had already been charged to the contractor for
falling behind schedule.
2.1.4
The
DCS listed inclement weather, soil conditions, public holidays, construction
delays, strike action, electricity shortage and builders holidays for the 287-day
delay in the completion of the project.
2.2
Vanrhynsdorp project
2.2.1
The old Vanrhynsdorp
Correctional Centre could accommodate 327 inmates. Once completed, its capacity
too will be doubled. The new centre will accommodate 540 inmates. Upon
completion it will accommodate both male and female offenders. Male offenders
will be accommodated in two units comprising four communal cells each, while
the women will be accommodated in four communal cells. The centre will also
have a segregation unit accommodating eight inmates.. Like the Ceres centre,
the centre will have its own kitchen and hospital.
2.2.2
The contract was awarded on 12 October
2007, and initially valued R220 million. The project was meant to have been
completed by 12 October 2009.
2.2.3
Scope changes
resulting from experience accumulated during the construction of the Tswelopele
Correctional centre, the extension granted by DPW, the construction of a
see-through passage that would make the heritage building visible from the
street, and the inclusion of a solar-heating system, offender -management
system and PMC flooring resulted in an approximately R90 million escalation in
the cost of the project.
2.2.4
The
DCS listed
inclement weather, additional public and builders holidays,
unexpected land formations, late delivery of materials and additional scope
changes for the 366-day delay in the completion of the project.
2.3
Brandvlei project
2.3.1.
The old Brandvlei Correctional Centre could accommodate 654 inmates. The
new centre will have 1 000 bed spaces and will comprise four housing blocks.
Each block will comprise units accommodating 240 offenders in six 10-bed
communal cells. Each unit will have two single cells. There will also be a
segregation unit for those offenders who will need special care. In addition to
the state-of-the-art kitchen, which will provide meals to the surrounding
medium, maximum and youth centres, the centre will also have its own hospital
rendering primary health care (including dental care) as well as a dispensary. The
new centre will provide facilities for formal education and skills development.
2.3.2
At 64
degrees Celsius the Brandvlei Thermal Spring is the hottest in
2.3.3
The
contract, initially valued at R315,6 million, was awarded on 3 October 2008,
and was scheduled for completion by 2 June 2010. As projected in March 2011, the
centre was eventually completed in September that year. At the time of the
visit, however, the date for it becoming fully operational was still unknown
owing to IT installations that had not been completed.
2.3.4
At the time of completion, the cost of the
project had escalated by approximately R89,5 million. The escalation resulted
from scope changes i.e. the late addition of the laundry, a linking passage,
extension of time granted to the contractor, and the prison management system
.
2.3.5
The
DCS listed
extensions of the completion date, electricity shortages,
and builders holidays as the main reasons for the 365-day delay in the
completion of the project. Extensions granted accounted for 308 of these days.
3.
OBSERVATIONS
3.1
Reasons for the delay in completion
The reasons provided for the delays in completion were
mostly unsatisfactory. Some of them are elaborated on below.
3.1.1
The
delegation was particularly perturbed by astonishing claims that builders
holidays, which could be predicted and factored into planning, were listed
among the unforeseen causes of delay.
The DPW explained
that the contract period was calculated in working days, and included the
builders holidays. Once a contract extends over a builders holiday, that time
is added to the contract, because extensions too are calculated in working days.
3.1.2
The contractor
claimed that, because the Ceres and Vanrhynsdorp projects were basically
Extended Public Works Programme (EPWP) projects, delays were caused by the use
of about 500 inexperienced and unsophisticated labourers who, prior to their
involvement in the project, were nothing more than farm-workers. In a written
response to the Committees initial observations, the contractor added that,
whilst it supported the aims and objectives of the National Youth Service (NYS),
those it had to employ on the project in terms of its contract with the DPW, have
not always been beneficial to the project, mainly owing to lack of motivation,
absenteeism and lack of experience.
The DPW denied
most of the claims regarding the extent to which labour-related challenges had
contributed to the delays. The value of the EPWP/NYS initiative totaled only 1%
of the anticipated final cost of the Ceres and Vanrhynsdorp projects. The
contractor was not prevented from employing additional, qualified artisans
and/or labourers. The contractor had been aware at tender stage that the NYS
initiative was a mandatory component of the contract and could have made due
allowance for it.
3.1.3
The
contractors claims that the two projects were in rural farming communities
and that, therefore, the building material, skilled labour and specifically
construction capacity demanded by the extremely high specifications and
quality of workmanship required by the employer were also refuted as credible
explanations for the delays, particularly because the location of the centres
and labour requirements of the projects were known to the contractor at the
time tenders were submitted, and could therefore have been factored in.
3.1.4
The
contractors responses to concerns voiced, and the long delays associated with
both contracts awarded to the company in question, raised concerns about its
shareholding, suitability and about the reasons why it had been awarded a
second contract, when it had failed to deliver in terms of the first. According
to the DPW, the second contract was awarded only nine months after the first
project had commenced. At that time the contractor had only been approximately
five days behind schedule, and was not considered a risk. The companys
shareholding was provided to the Committee in writing.
3.1.5
The Committee
was amazed that the DCS, despite having claimed that the Tswelopele Correctional
Centre, which itself had been subject to many expensive delays, would serve as
the blueprint for future new-generation correctional centres, had apparently
abandoned this blueprint in the case of the three correctional centres.
The DPW denied that the blueprint had been completely abandoned and
explained that the Ceres and Vanrhynsdorp projects had started 12 months before
the Kimberley project was completed, and that, although the generic plan was
used in the planning of the two Western Cape facilities, changes came about as
a result of knowledge and experience acquired during the Tswelopele
construction.
3.1.6
The
contractor responsible for the Ceres and Vanrhynsdorp projects, in a written
submission to the Committee, bore some responsibility for the delays, but
claimed that the professional team had some responsibility too. They claimed
that, as a broad-based black economic empowerment enterprise (BBBEE), they had
not been treated fairly but had been isolated at every opportunity by the
professional team, and that the latters failure to acknowledge their own
role in the delays had severely prejudiced the contractors rights and the due
fulfillment of the contract. These claims were not made during the visit, but
were submitted in writing after, and the DCS and DPW have therefore not had an opportunity
to respond.
3.2
Reasons for
escalations
3.2.1
The DPW
acknowledged that it faced professional capacity challenges which impacted on
how it managed its projects. That notwithstanding, the DPW explained that, once
a project has been initiated and changes of scope resulting in escalations are
requested by the client department, that department is made aware of the cost
implications and has to give the go-ahead to continue with the changes in
scope. Feasibility studies were done for each of the three projects. All
variation orders were discussed with the DCS. The DPW confirmed that
escalation clauses were contained in all contracts exceeding six months,
and therefore such clauses were included in all three contracts. The Contract
Price Adjustment Provisions (CPAP) allow for contracts to be adjusted in
accordance with the Joint Building Contracts Committees (JBCC) 2000 Principal
Building Agreement Edition 4.1 (March 2005).
3.2.2
The Committee
noted that letters were sent to contractors that were underperforming, and
thought this intervention meaningless as it did not force contractors to adhere
to their contractual obligations. It was suggested that contractors who
habitually underperformed should be blacklisted. The DPW explained that only
National Treasury could blacklist companies.
According to
the JBCC and General Conditions of Contract for Construction Works (GCC),
should a contractor underperform or fail to perform and complete the project on
time without justification, that contractor should first be placed on terms in
line with conditions of contract i.e. the JBCC or GCC. In cases where contracts
had to be reviewed for the above-mentioned reasons, the chief financial officer
(CFO) or supply chain manager (SCM) was obligated to supply National Treasury
with their details.
3.2.3
It was noted
that additional excavations, which had resulted in additional costs, had to be
done owing to trial holes that misrepresented the soil condition.
Ground conditions recorded during the investigation phase of a
construction project were the basis and gave direction to the design of, for
example, foundations, floors and walls.
According to
submissions made by the DPW and DCS, additional excavations had to be performed
because trial holes dug during the investigation phase of the three projects
had misrepresented the soil conditions. At Ceres different ground conditions
were discovered after construction had commenced, at Brandvlei unexpected
underground structures required changes, and at Vanrhynsdorp underground
structures were encountered, which the DPW claimed could not have been detected
during planning. The Committee questioned the legitimacy of these explanations,
and thought the additional excavations were the result of poor planning on the
part of the contractors, and poor monitoring by the DPW.
3.2.4
Scope changes
to the Vanrhynsdorp and Ceres contracts had resulted in escalations of about
R40 million. The DCS ascribed the scope changes to lessons learnt during the
Tswelopele project, the inclusion of solar-heating systems as per the DPW
requirement, and increased electricity tariffs. The DPW indicated that the
DCS had provided it with a generic layout of what their requirements
were for the new-generation facilities. This layout could not be implemented
exactly in any of the three projects, but had to be adapted to accommodate
conditions specific to each of the sites. As shortcomings were identified,
changes recommended were approved by the DCS. All of the scope changes were
DCS-approved.
3.3
Role of the Accounting Officer in
ensuring compliance with contracts
3.3.1
The Committee
was unconvinced that the DPW and DCS accounting officers had done enough to
ensure that the contractors adhered to the terms of their contracts. The
delays, and associated cost escalations, might have been avoided had greater
caution been exercised during the tender process, and greater control and
management of the project once contracts were awarded.
3.4
Electricity supply
3.4.1
The DPW
indicated that the three facilities had been
constructed
within the confines of existing correctional facilities and therefore had power
connections to the supplier grid.
Eskom could meet
the Brandvlei centres maximum power requirements, but additional supply would
have to be applied for.
Although an application to increase the
power supply had been submitted, the
project also
provides for energy-saving measures such as the use of hot spring water and the
use of only one kitchen for cooking. The power to the Vanrhynsdorp site had
been increased to the maximum that the local municipality could provide.
Shedding devices have been installed to control peak consumption. The Ceres
facility was connected to the supply-authority grid and therefore power is
available. Each centre will have generators for use in the event of a power
failure.
3.5
Projects contribution to job creation
3.5.1
At the time
of the visit, the Ceres, Vanrhynsdorp and Brandvlei correctional centres
reported 125, 135 and 200 vacancies respectively. According to the regional
management, the excess vacancies had been created with the understanding that students
would fill them once their learnerships had been completed in March and October
2012. As these could only be filled once the centres became operational, the
delegation voiced its dissatisfaction that the delays in construction had
resulted in a lack of meaningful job creation in the region.
3.6
Training and Development
3.6.1
The
DPW explained that the EPWP/NYS initiative was a Government training initiative
aimed at contributing to the artisan skills development programme and targets
youth interested in careers in the built environment. While it had not formed
part of the requirements of the initial Brandvlei contract, it was part of the
Ceres and Vanrhynsdorp project documentation. Between 2007 and 2008, 104, 124
and 65 learners had received training as part of the Ceres, Vanrhynsdorp and
Brandvlei projects respectively.
4.
RECOMMENDATIONS
The Committee requests that the
Minister of Correctional Services (the Minister) ensures that the following
recommendations are considered, and where possible, implemented. The Minister
should further ensure that responses on their feasibility and/or implementation
progress reports are submitted within one month of the adoption of this report
.
4.1
The DCS and DPW should provide clarity on
how the delays could be justified /rationalised, particularly in relation to
accounting officers obligations in terms of sections 38 and 39 of the Public
Finance Management Act (PFMA), and the relevant National Treasury regulations.
4.2
The DCS should provide clarity on what
the monies earmarked for the funded posts which had not been filled owing to
the delays in the completion of the three projects had been spent on and/or
would be spent on pending the coming into operation of the centres.
4.3
Despite the
DCS continued complaints of the DPWs failure to deliver services as per its
mandate, the Committee has had no indication of the DCS commitment to ensuring
that the DPW delivers, or that the working relationship is improved. At the
time of the compilation of this report, the long outstanding DPW-DCS
service-level agreement (
4.4
The long
delays in the above-mentioned projects, and the various claims made by the
contractor, raised serious concerns about the integrity of the tender process,
and, in particular, the composition of bid-adjudication committees.
The DCS and DPW should ensure strict
compliance with the relevant PFMA and National Treasury requirements. Every
effort should be made to ensure that the integrity of the tender process is
maintained. In addition, bid-adjudication committees should comprise
individuals who are suitably experienced and qualified, and therefore able to
identify unrealistic proposals, which, as in the case of the above-mentioned
projects, inevitably lead to costly delays.
4.5
The Committee fully supports broad-based
black economic empowerment (BBBEE) initiatives, but Government departments, in
this case the DCS and DPW, should ensure that contracts are awarded to
candidates that are able to provide quality services, on time and at reasonable
prices. In addition those that are awarded contracts should have an
understanding of Government priorities such as skills development and job
creation. Contractors awarded Government projects should not use their
obligations in this regard as an excuse for poor delivery. Action should be
taken against those who repeatedly fail to deliver in terms of their
contractual obligations.
5.
ACKNOWLEDGEMENT
The Committee expresses its appreciation to the
regional and area management of the the three centres, the DPW officials, the
contractors, as well as the local authorities who had participated in the visit
and the subsequent discussions.
Report
to be considered.
Documents
No related documents