ATC130520: Second Report of the Standing Committee on Public Accounts on its Oversight visits to the Provincial Departments of Education and Health in the Provinces of the Eastern Cape, Northern Cape and Gauteng from 15-18 October 2012, dated 24 April 2013

Public Accounts (SCOPA)

SECOND REPORT OF THE STANDING COMMITTEE ON PUBLIC ACCOUNTS ON ITS OVERSIGHT VISITS TO THE PROVINCIAL DEPARTMENTS OF EDUCATION AND HEALTH IN THE PROVINCES OF THE EASTERN CAPE, NORTHERN CAPE AND GAUTENG FROM 15-18 OCTOBER 2012, DATED 24 APRIL 2013

SECOND REPORT OF THE STANDING COMMITTEE ON PUBLIC ACCOUNTS ON ITS OVERSIGHT VISITS TO THE PROVINCIAL DEPARTMENTS OF EDUCATION AND HEALTH IN THE PROVINCES OF THE EASTERN CAPE, NORTHERN CAPE AND GAUTENG FROM 15-18 OCTOBER 2012, DATED 24 APRIL 2013

INTRODUCTION

On the 15-18 October 2012 a delegation of the Standing Committee on Public Accounts (the Committee) undertook oversight visits to the provinces of the Eastern Cape ( Komani Hospital , Special Youth Care Centre), the Northern Cape ( New Mental Health Facility) and Gauteng ( Zola Hospital ). The main objective of the visits was to conduct oversight on the infrastructure projects of the said departments, as per report by the Auditor-General in the 2009/10 performance audit of the infrastructure delivery process at the provincial departments of education and health.

The Committee hereby reports its findings and recommendations to the House as required by Rule 137 of the Rules of the National Assembly.

1. DELEGATION

Below is the delegation that represented the Committee on this visit:

Members of the Committee : Mr NT Godi , MP (APC); Mr A R Ainslie, MP (ANC); Mr SG Thobejane , MP (ANC); Ms G Saal , MP (ANC); Ms S Mangena , MP (ANC); Ms T Chiloane , MP (ANC); Dr P Rabie, MP (DA); Dr D George, MP (DA); and Mr IS Mfundisi , MP (UCDP) .

Support Staff : Mr P Mbele , Ms NT Nkabinde and Mr S Nqwala (Committee Secretaries).

2. BACKGROUND

The Auditor-General South Africa (AGSA) conducted performance audits at the Departments of Health and Basic Education as part of a transversal performance audit on infrastructure delivery.

The transversal report was tabled in Parliament on the 6 September 2011. The province-specific reports were tabled in their respective provincial legislatures.

On 21-22 November 2011, the Committee held hearings in Parliament with the members of executive councils responsible for the two portfolios in all nine provinces. The accounting officers and implementing agents were also in attendance. The hearings dealt (in the main) with the following issues:

· The appointment of contractors;

· The reported delays in the completion of projects;

· Commissioning and utilisation; and

· Future financial projections, where applicable.

The Committee adopted the resolutions of the Auditor-General’s report on 23 May 2012. It was after this stage that a number of projects were identified for oversight visits. The Committee hereby reports on the first phase of these visits, which took place in the provinces of the Eastern Cape , Northern Cape and Gauteng .

3. OVERSIGHT VISITS: EASTERN CAPE

3.1 The Special Youth Care Centre ( Bhisho )

The tender estimate for the construction of the Special Youth Care Centre in the Eastern Cape was not properly prepared and calculated by the quantity surveyor. The estimate of R173, 8 million was 33% below the contract amount of R231 million. According to an analysis of the tender report compiled by the implementing agent, the reasons for the increase in costs include the conservative pricing estimates. Future cost increases were not considered and operational costs, such as provision of accommodation for supervision personnel and transport of materials and equipment were not taken into account.

The centre, situated in Bhisho , was built to accommodate 314 learners with special needs, especially correctional supervision. There were 3 staff members presenting educational programmes. The newly constructed reform school had been completed in June 2009 but has only been used as from January 2011. The estimated cost of the project stands at R231 million.

4.2 Findings

a) The tender for the construction of the centre, with a budget of R118 million, was advertised in two local newspapers, and not in the Tender Bulletin;

b) Only two prospective suppliers submitted bids of which one complied with the criteria and minimum requirements to be considered during the bid evaluation process;

c) The facility is not fully operational as no action plans were in place for both the staffing needs and the procurement of furniture and equipment;

d) Funds were not budgeted for the daily running of the facility;

e) There is water leakage, some of the door handles and windows were broken and there were visible cracks on the walls. Security cameras were broken;

f) The Departments of Public Works and Education did not inform Independent Development Trust to fix all the defects; and

g) There was no business plan to manage the facility.

4.3 Recommendations

The executive authority should ensure that:

a) There is coordination between different role players to ensure that projects are commissioned and utilised after the handover processes; and

b) Processes of communication, especially the reporting of any defects to the implementing agent are formalised.

5. Komani Hospital (Queenstown)

The facility serves the area as a special hospital for patients with mentally-related clinical needs. It was designed to cater for 440 patients, but at the time of the visit, it had 380 patients. It is serviced by a multi-disciplinary team of health professionals. The hospital has an overall vacancy rate of 52 percent. It operates on a budget of R88 million; of which 86 percent (R76 million) is spent on the compensation of staff. The facility shares the premises with offices of other departments and units; namely education, housing, environment, traffic, emergency medical services and forensic services. T his has led to administrative challenges when it comes to billing of electricity and water.

5.1 Findings

a) Although the planned completion date for the laundry section at the hospital was 17 April 2008, the section was still not completed at the time of the visit.

b) This resulted in laundry equipment, valued at R4, 9 million being stored in an unsecured uncovered area within the hospital complex (at the time of the visit, the equipment had been moved to health facilities in East London and Bhisho ).

c) Furthermore, the hospital management decided to outsource a portion of the laundry service (at an estimated cost of R76 000 a month).

d) The contract for the construction of this phase (phase 2) of the project had been awarded to Ilima Projects, who abandoned the project and were later liquidated. They had already been paid R20 million of the R110 million total cost of the project.

5.2 Recommendations

The executive authority should ensure that:

The purchasing of equipment for infrastructure is coordinated with project completion in order to ensure effective use.

6. NORTHERN CAPE

6.1 Kimberley Mental Health Facility

6.1.1 Background

a) In August 2005, the Provincial Tender Board awarded the contract to Vista Park/JOH Arch Investments, with the project set to commence in September that same year.

b) Delays in bulk earthworks meant that the construction only commenced in February 2006.

c) Further delays saw the revision of the completion date, then set at 20 March 2008. By the end of 2007, slow construction had been noted, including poor workmanship and incomplete remedial work. By the end of August 2009, the contractor was 565 days behind schedule.

d) Penalties in this regard, totalling R11.3 million were levied but never deducted from the service provider.

e) The contractor failed to submit a revised construction programme but instead submitted claims for extension of time and costs.

f) The slow delivery compounded by water penetration caused structures to deteriorate.

g) Non-payment to sub-contractors caused delays. Cash flow problems were reported as the reason at the time.

h) There was poor supervision of the workforce by the contractor.

6.1.1.2 Termination of initial contract

— Poor performance

· In February 2008, the contractor made a request for an opportunity to provide definitive plans that would see the project completed by 20 March 2008.

· By April 2008, the contractor had failed to complete the project or submit the required completion plan. They were then informed that they were in breach of contract.

· In February 2009, the contractor submitted claims for extension of delivery timeframe with costs.

· A revised programme was requested from the contractor. They set a new completion date of May 2010.

· In December 2009, the Northern Cape Department of Roads and Public Works (DRPW) terminated the contract, subject to legal processes.

— The court process and liquidation of the contractor

· Between January and October 2010, the contractor repeatedly challenged the DRPW through the courts.

· The lengthy delays, with the construction site legally under the control of the contractor, resulted in significant deterioration due to weathering, vandalism and theft.

· In October 2011 the contractor was liquidated before the courts could make the final pronouncement on the matter.

— Surety or guarantee

· Two percent (R5 million) of the contract value was provided through Investec for a period of 24 months.

· Four percent (R10.2 million) retention from contract was kept by the client after termination.

— Increase of the original contract amount

· There were significant variations in cost caused by averaging methodology used to estimate costs at the outset.

· The design work continued while construction was underway.

· R420 million was spent on the initial part of this project.

6.1.1.3 New Contractor

— Appointment

· Towards the end of 2011, Inyatsi Construction was appointed using the JBCC contract. The site hand-over took place on 21 December 2011.

· The contract value then, stood at R400.57 million for the hospital, internal roads and guardhouse, excluding professional fees.

· This was to be a 24-month project - with completion expected in January 2014.

— Scope of work and latent defects

· At the end of 2011, structural reports were commissioned to estimate remedial work and inform the bill of quantities, which was R6.78 million.

· In June 2012, sample drilled courses were conducted to determine concrete strength - only two of the three passed the tests.

In August 2012, further strength tests were conducted on some surface beds and concrete slabs - preliminary findings indicated significant variation in strength.

— Performance of the new contractor

· The Construction Industry Development Board (CIDB) down-graded the contractor from a Grade-9 to 7GB (General Building Works) during final stages of awarding the contract.

· Advice was sought by the DRPW from the CIDB on how to proceed – the three options given are under consideration, including cancellation of the contract.

· At the time of the visit, the contractor was already falling behind the set time schedule, and the monthly expenditure was at 50% less than cash flow projections.

— Budgetary concerns

· There was no capital budget currently available for this project – the expenditure is being paid from a budget for another Hospital Revitalisation Project.

· The significant and unexpected increase in the capital cost of the electric sub-station is being reviewed.

· Additional costs for prolongation fees were yet to be quantified.

Performance of contractors

· Contractors were unable to meet the monthly agreed deliverables due to insufficient capacity in their companies.

· Their respective under-performance subsequently led to under-spending on the project.

· Poor coordination between the contractors/consultants and implementing agent led to further delays of the project.

Capacity to implement the project

· The Department of Public Works is responsible for the implementation of the programme.

· The Department of Health is only responsible for planning (development of the business case, project brief and supervision of designs), reporting and monitoring of projects.

· Due to limited capacity at the Department of Public Works, there was no proper monitoring on projects.

6.2 Follow-up hearing with the project stakeholders: 02 November 2012

Background :

The Committee had visited the site of the mental health facility in Kimberley on 17 October 2012. As per tradition with visits of this nature, the Committee sought to have a formal discussion with all the project stakeholders on the day of the visit. Due to the absence of key individuals in the life of the project and lack of information, amongst other things, the Committee resolved to convene a follow-up hearing in Parliament.

The hearing took place on 02 November 2012. It was attended by the executive authorities, former and present accounting officers, and officials representing the implementing agent.

The meeting discussed at length the issues that are reported herein, and sought to find answers as to what had gone wrong with the project. The following is a summary of the issues that were covered on the day, and they confirmed the findings of this report:

· Due process were not followed when dealing with the contractors;

· The roles that were played by different individuals (in their official capacities) and departments (including the then Tender Board) over the years;

· The escalation in costs – the project is expected to cost about R1.8 billion by the time of estimated completion (March 2014);

· Unauthorised payments over the years, with no satisfactory explanations offered;

· The multiple investigation into the project by different parties at different times, which have not yielded results;

· The subsequent appointment of another contractor – and the processes therein; and

· The capital budget for the hospital.

6.3 Recommendations

The Committee wishes to place on record its disappointment at the state of affairs surrounding this important project in the Northern Cape . The project is almost a decade overdue, and even then does not look anywhere near completion. The initial projected costs have quadrupled over the years. The Committee is concerned that this was allowed to happen, without any apparent intervention.

In light of the seriousness of the issues as reported herein, the Committee recommends that a full-scale investigation be undertaken by the appropriate investigative authority, to look into the roles of various individuals and/or entities in the management of the project.

7. GAUTENG

7.1 Zola Hospital

The project comprises of a multi storey 300 bed District Hospital with 120 step-down beds, a Gateway Clinic and Service Buildings .

7.2 Findings

Ilima Joint Venture was appointed in May 2006 as the contractor for the project. The original contract sum was for an amount of R335 million and the project was to be completed at the end of May 2008.

Three of the joint venture partners withdrew and only one contractor remained. This contractor misrepresented the validity of their tax clearance certificate and had outstanding tax returns since 2004. The contract was terminated in September 2008. They cited changes, escalating costs and constant late payments to the contractor among the many problems. The Department terminated the contract with the Ilima Joint Venture and proceeded to enter into another contract with Ilima Projects, the terms of which were inter alia that the Department would avail the services of Tau Pride and PMRG to provide capacity support to Ilima Projects to ensure delivery of the project by 2010.

The Committee observed that there had been poor planning by the departments involved, especially after the termination of the initial contract and the appointment of the second contractor.

During the Committee visit the project was incomplete and the Department anticipated the completion date as April 2013. Zola Hospital has seen an escalation of 144 per cent in initial costs, up to R480 million. The estimated cost after completion is R888 million.

7.3 Recommendations

The executive authority should ensure that:

  • The resident engineer monitors progress on all projects more frequently; and
  • The department completes projects by the completion date.

8. CONCLUSION

The Committee will continue to monitor the progress of these projects until completion of each, to ensure the effective use of public funds.

The Committee further recommends that the Executive Authority submits a progress report on the implementation of the above recommendations to the National Assembly within 60 days after the adoption of this report by the House.

Report to be considered.

Documents

No related documents