Questions and Replies

Filter by year

27 July 2018 - NW1429

Profile picture: Van Der Walt, Ms D

Van Der Walt, Ms D to ask the Minister of Human Settlements

1) With regard to land and housing projects undertaken in Bela-Bela, Limpopo, (a) what projects were undertaken as a result of collaboration between the Housing Development Agency and the Bela-Bela Municipality for the periods (i) 2006-2011, (ii) 2011-2016 (iii) 2016-2018 and (b) what was the amount of each agreement that was signed; 2) whether all the projects were completed; if not, (a) what are the reasons for not completing the projects and (b) what actions taken against those causing the failure to complete the specified housing projects; if so, (i) what are the full relevant details? (NW1531 E)

Reply:

(1) Land housing projects undertaken in Bela-Bela, Limpopo a) There is no collaboration agreement that was signed between the Housing Development Agency and Bela-Bela Municipality. However, as a result of relevant agreements between the Department of CoGHST A in Limpopo and HDA, the following were activities undertaken by the HOA in Bela-Bela Municipality:

(i) Period 2006 - 2011

The HDA assisted the Department in the acquisition of land (Erf. 1491 Warmbaths Ext.25). The price of the land that was paid by CoGHSTA to the land owner is R 65.4m.


(ii) Period 2011 - 2016

The HDA completed township establishment on Erf. 1491 Warmbaths Ext.25 in 2012/2013 financial year. The amount for rezoning and subdivision was R420 664. The project was completed. During 2015/16 financial year, the HDA completed installation of interim basic services on Erf.1491 Warmbaths Ext.25. This involved the following:


(a) Sewer:

• Supply and installation of 587m of Sewer pipeline, which involved construction of 9 manholes and connection to existing sewer line.

• Supply and connection of fittings to ablution facilities


(b) Water:
• Supply and installation of 50mm HDP water supply pipeline.

• Design, supply and installation of steel vertical tanks

• Supply and installation of water tanks

• Additional works, supply and installation of water taps cages

(c) Electrical:
• Supply and installation of lighting

• Supply and installation of a highlight mast.

• Additional work, supply and installation of radiant lighting at ablution facilities

(iii) No projects were undertaken during the 2016 - 2018 period.

b) The cost of the project for the period 2006 - 2011 was R2 104 822.92.

The cost of the project for the 2011 - 2016 period was R6 018 000.00. It was for the engineering designs for bulk and internal engineering services to supply Erf.1491 Warmbaths Ext.25 which was completed during the 2015/16 financial year. The project was completed.

(2) The projects were completed

a) N/A

b) N/A

(i) N/A

27 July 2018 - NW2051

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

What was the total amount spent by the Estate Agency Affairs Board for each year between 1 January 2014 and 31 December 2017 on (a) vehicle hire, (b) hotel stays, (c) conference venue hire, (d) catering, (e) furniture hire, (I) stationary, (g) I-shirts, (h) gift bags and (i) leasing of offices?

Reply:

The following is provided based on information provided by the Estate Agency Affairs Board

Cost Description

Jan 2014 – Dec14

Jan 2015 – Dec 15

Jan 2016 – Dec 16

Jan 2017 – Dec 1

Total Spent

a) Vehicle Hire

R 662,311.89 

R 1,056,831.54 

R 1,113,745.41

R 502,615.94 

 R 3,335,504.78

b) Hotel Stays

R 1,396,339.14 

R 2,559,017.68 

R 3,914,341.11 

R 1,353,506.45

R 9,223,204.38

c) Conference Venue Hire (including CPD)

R 316,996.70 

R 6,256,851.36

 R 4,064,592.10 

R 2,989,646.93

 R 13,628,087.09

d) Catering

R 408,007.70

 R 465,371.06

 R 429,801.39

R 566,204.88

  R 1,869,385.03

e) Furniture Hire

R 17,028.40

R 27,570.00

R 31,050.00

R 37,500.00

R 54,528.40

f) Stationery & Printing

R 1,175,435.08 

R 1,355,302.41

R 1,301,325.21

 R 2,353,454.68

 R 6,185,517.38

g) T-Shirts

n/a

n/a

R 32,943.28

R 37,400.00

R 37,400.00

h) Gift bags

n/a

R 35,451.00

R 52,750.00

n/a

R 88,201.00

i) Leasing of offices

n/a

n/a

R 74,660.88 

R 384,426.79 

R 459,087.67

 

R 3,976,118.91 

R 11,728,825.05

R 10,951,216.10

R 8,224,755.67 

R 34,880,015.73

 

27 July 2018 - NW1793

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

(1) (a) What was the total number of hostels in (i) the country and (ii} each province in each year since 1 January 1994; (2) Whether she will provide a list to Mr M Malatsi of all the hostels in each province owned or managed by the (a)(i} provincial government and (ii) municipality and (b) any other entity; (3} (a} which hostels have had ownership and management changed between the provincial government, municipalities and other entities after the 1994 elections, (b) on what date(s} did the change of ownership/management of the specified hostels take place and (d} what number of the specified hostels were demolished/converted?

Reply:

(1) (a} (i) The total number of hostels in the country is 166 excluding hostels in Limpopo. (Information from Limpopo is outstanding and will be submitted at a later stage)

(ii) The total number of hostels in each province since 1 January 1994 is as follows:
 

PROVINCE

NUMBER OF HOSTELS

Northern Cape

1

Eastern Cape

0

Mpumalanga

20

Gauteng

68

Kwa Zulu Natal

23

Free State

5

Western Cape

42

North West

7

Limpopo

(Information not available)

   
   


Find here: 2(a)(i)(ii) & (b) A list of all the hostels in each province owned or managed by the (a)(i) provincial government and (ii) municipality and (b) any other entity

27 July 2018 - NW1967

Profile picture: Ryder, Mr D

Ryder, Mr D to ask the Minister of Human Settlements

(a) What is the average time for construction, from foundation to key handover, of a government-subsidised house through a project led by the Government, (b) what has been the average time for construction, from foundation to key handover, of a government-subsidised house in the Savanna City housing project and (c) of the planned 18 000 houses in the Savanna City housing project, what is the total number that has been completed to date? NW2126E

Reply:

(a) The average time for construction of a government-subsidised house is 35 days.

The breakdown is as follows:

• Preparation of foundation and casting: 7 days

• Brick work: 3 days

• Roofing: 2 days

• Plumbing: 4 days

• Plastering: 3 days

• Painting: 1 day

• Glazing: 1 day

• Turnaround time for inspection by the Engineer; the Provincial Department of Human Settlements and the Municipality: 7 days

• Preparation and key handover: 7 days

(b) The average time for construction of a government-subsidised house in Savanna City has been 35 days.

(c) The total number of houses completed to date is 2 434 which comprises of 1 492 subsidised houses, 90 Financed Linked Individual Subsidy Programme (FLISP) houses and 352 bonded houses.

27 July 2018 - NW1921

Profile picture: Hlonyana, Ms NKF

Hlonyana, Ms NKF to ask the Minister for Human Settlements

1. What (a) is the total number incidents of sexual harassment that were reported to the human resources offices of (i) her department and (ii) entities reporting to her in (aa) 2016 and (bb) 2017 and (b) are the details of each incident that took place; 2. Was each incident investigated; if not, why not in each case; if so, what were the outcomes of the investigation in each case?

Reply:


3.1 What (a) is the total number incidents of sexual harassment that were reported to the human resources offices of (i) her department and (ii) entities reporting to her in (aa) 2016 and (bb) 2017

3.1.1 Two incidents of sexual harassment were reported in the Department in the period under question.

3.2 and (b) are the details of each incident that took place.

3.2.1 In the 1st incident, the complainant brought an informal complaint to the department's Employee Health and Wellness unit. The complainant reported on comments with sexual overtones received from the respondent/perpetrator that resulted in the complainant being uncomfortable. Thus this incident involved sexual harassment of a verbal nature.

3.3.2 In the 2nd incident, the complainant brought an informal complaint to the Department's Employee Health and Wellness unit. The complainant reported an incident whereby the respondent/perpetrator inappropriately physically pressed against the complainant, when the two of them were in an elevator. The complainant was upset by this incident. This incident involved sexual harassment of a physical contact nature.

3.3 Was each incident investigated; if no, why not in each case; if so, what were the outcomes of the investigation in each case?

3.3.1 Yes, the incidents were investigated.

3.3.2 The 1st incident was resolved with the perpetrator being reprimanded by his supervisor and apologizing to the complainant.

3.3.3 The 2nd incident was resolved with the perpetrator issued a warning by the relevant supervisor; an apology by the perpetrator to the complainant; and the complainant transferred to another unit, as requested.

• Sexual harassment cases are dealt with in accordance with the provisions of the departmental Management of The Sexual Harassment policy.

• The Policy was developed in order to facilitate, expedite, offer guidance and complement all other Labour relations prescripts that are meant to resolve matters related to sexual Harassment in the department.

• In addition to this, there are various interventions that the department apply for instance, awareness sessions that are frequently held in order to educate and make employees aware of lawful and prohibited behaviours at the work place especially sexual harassment.

• In essence, the department takes every opportunity and utilizes every available platform to provide information and education. For example, quarterly Human Resources Outreach Sessions; Staff meetings as well as Women Month and 16 Days of Activism Against Women and Children Abuse, are used to ensure that sexual harassment matters are given sufficient attention by all.

27 July 2018 - NW1822

Profile picture: Esau, Mr S

Esau, Mr S to ask the Minister of Human Settlements

(1) Whether (a) her spouse and I or (b) an adult family member accompanied her on any official international trip (i) in each of the past five financial years and (ii) since 1 April 2018; if not, what is the position in this regard; if so, what (aa) is the name of the person(s), (bb) was the (aaa) purpose and (bbb) destination of the trip and (cc) was the (aaa) total cost and (bbb) detailed breakdown of the costs of the accompanying person( s) to her department; (2) whether each of the specified trips were approved by the President in terms of the provisions of Section 1, Annexure A of the Ministerial Handbook; if not, why not; if so, what are the relevant details?

Reply:

(1) (a) The spouse and I or (b) an adult family member of the Minister of Human Settlements did not accompany Minister Sisulu or Minister Mfeketo on any official international trip in each of the past five financial years to date. (i) N/A, (ii) (aa) and (bb) N/A, (ii) (aaa) and (bbb) N/A, (ii) (cc) (aaa) and (bbb) N/A.

(2) N/A

27 July 2018 - NW1471

Profile picture: Stubbe, Mr DJ

Stubbe, Mr DJ to ask the Minister of Human Settlements

1. Whether, with reference to the reply of the President, Mr C M Ramaposa, to the debate on the State of the Nation Address on 22 February 2018 to implement lifestyle audits, (a) she, (b) senior management service members in her department and/or (c) any of the heads of entities reporting to her have undergone a lifestyle audit in the past three financial year; if not, have any plans been put in place to perform such audits; if so, in each case, what are the details of the (i) date of the lifestyle audit, (ii) name of the person undergoing the audit, (iii) name of the auditing firm conducting the audit and (iv) outcome of the audit; 2. Whether she will furnish Mr D J Stubbe with copies of the lifestyle audit reports?

Reply:

Entities

1. Rural Housing Loan Fund

(1)(c) The Rural Housing Loan Fund (RHLF) has not undertaken a process of lifestyle audits for Members of the Board or Senior Management. There is no plan in place to perform lifestyle audits.

(1 )(c)(i) N/A

(1)(c)(ii) N/A

(1 )(c)(iii) N/A

(1 )(c)(iv) N/A

(2) There are no reports available for submission and it should be noted that the disclosure of such reports will be done within the provisions of relevant prescripts governing such disclosure.

2. Social Housing Regulatory Authority

(1 )(c) The Social Housing Regulatory Authority (SHRA) has not undertaken a process of lifestyle audits for Members of the Board or Senior Management. The SHRA has no plan put in place to perform lifestyle audits.

(1 )(c)(i) N/A

(1 )(c)(ii) N/A

( 1 )( c )(iii) N/A

(1 )(c)(iv) N/A

(2) There are no reports available for submission and it should be noted that the disclosure of such reports will be done within the provisions of relevant prescripts governing such disclosure.

3. National Urban Reconstruction and Housing Agency

(1 )(c) The National Urban Reconstruction and Housing Agency (NURCHA) have not undertaken lifestyle audits for Members of the Board or Senior Management. The NURCHA has no plan put in place to perform lifestyle audits.

(1 )(c)(i) N/A

(1 )(c)(ii) N/A

(1 )(c)(iii) N/A

(1 )(c)(iv) N/A

(2) There are no reports available for submission and it should be noted that the disclosure of such reports will be done within the provisions of relevant prescripts governing such disclosure.

4. Housing Development Agency

(1 )(c) The Housing Development Agency (HOA) has not undertaken lifestyle for Members of the Board or Senior Management. The HOA has no plan put in place to perform lifestyle audits.

4

(1 )(c)(i) N/A

(1 )(c)(ii) N/A

(1 )(c)(iii) N/A

(1 )(c)(iv) N/A

(2) There are no reports available for submission and it should be noted that the disclosure of such reports will have to be done within the provisions of relevant prescripts governing such disclosure.

National Home Builders Registration Council

(1 )(c) The National Housing Builders Registration Council (NHBRC) has not undertaken any lifestyle audits for managers in the past three financial years. NHBRC Management intends making a recommending to the Audit and Risk Management Committee to execute lifestyle audits as a matter of urgency. A tender process will be initiated to request bids and appoint a firm to undertake the audits and the National Department of Human Settlements will be kept abreast on the process and outcomes.

(1 )(c)(i) N/A

(1 )(c)(ii) N/A

(1 )(c)(iii) N/A

(1 )(c)(iv) N/A

(2) Once the lifestyle audit of senior management is completed, the management will provide the results to the Audit and Risk Management Committee (ARMCO) and thereafter through the Council then to the Department if so required.

5. National Housing Finance Corporation

1)(c) The National Housing Finance Corporation (NHFC) does not conduct lifestyle audits. The Human Resource Policies provide guidelines on Business Conduct and matters related to conflict of interest. As a rule employees are not allowed to do business with the entity and its clients.

Where policy is breached the Disciplinary Code of the organisation is invoked.

(1 )(c)(i) N/A

(1 )(c)(ii) N/A

(1 )(c)(iii) N/A

(1 )(c)(iv) N/A

(2) Not available for reason stated in (1 )( c) above.


6. Estate Agency Affairs Board

(1 )(c) The Estate Agency Affairs Board (EAAB) has not undertaken lifestyle audits for Members of the Board or Senior Management. The EAAB has no plan put in place to perform lifestyle audits.

(1 )(c)(i) N/A

(1 )(c)(ii) N/A

( 1 )( c )(iii) N/A

(1 )(c)(iv) N/A

(2) There are no reports available for submission and it should be noted that the disclosure of such reports will done within the provisions of relevant prescripts governing such disclosure.

7. Community Schemes Om bud Service

(1 )(c) The Community Schemes Ombud Service (CSOS) has not undertaken lifestyle audits for Members of the Board Members or Senior Management. There is no plan put in place to perform lifestyle audits.

(1 )(c)(i) N/A

(1 )(c)(ii) N/A

(1 )(c)(iii) N/A

(1 )(c)(iv) N/A

(2) There are no reports available for submission and it is to be noted that the disclosure of such reports will have to be done consistent with the provisions of relevant prescripts governing such disclosure.

09 July 2018 - NW1870

Profile picture: Hlonyana, Ms NKF

Hlonyana, Ms NKF to ask the Minister of Human Settlements

What (a) is the total number of incidents of racism that were reported to the human resources in (i) her department and (ii) entities reporting to her in (aa) 2016 and (bb) 2017 and (b) are the details of each incident that took place; 2. was each incident investigated; if not, why in each case; if so, what were the outcomes of the investigation in each case?

Reply:

1(a) (i) The total number of incidents of racism that were reported to the human resources in (i) her department and (ii) entities reporting to her in (aa) 2016: Nil

1(a) (ii) Total number of incidents of racism that were reported to the human resources in (i) her department and (ii) entities reporting to her in (bb)

2017: Nil

1(b) Details of each incident that took place: Not applicable 

2. Not applicable.

The Department has however proactively put initiatives in place to address discriminatory practices, inclusive of racism. Including:

    • The Departmental Employment Equity Committee (DEEC), which promotes non-discrimination of any form or ground, including race; whose objectives are the identification and elimination of barriers that can have an adverse impact on designated groups.
    • The Department Policy on Management of Bullying, to enhance employee awareness on ill attitudes and behaviours in the workplace; discourage workplace harassment; procedures to report harassment cases and indicate available support structures.
    • Quarterly diversity awareness sessions to enhance employee awareness on diversity issues, as part of implementing the Affirmative Action measures as contained in the Departmental Employment Equity Plan 2015-2021.

09 July 2018 - NW2008

Profile picture: Motau, Mr SC

Motau, Mr SC to ask the Minister of Human Settlements

(1)What total amount (a) did her department spend on Breaking New Ground magazine (i) in each of the past three financial years and (ii) since 1 April 2018 and (b) was spent on the (i) compilation; (ii) publication and (iii) payment of the writing contributors: (2) What total amount (a) did her department spend on the Breaking New Ground television(i) in each of the past three financial years and (ii) since 1 April 2018 and (b) was spent on the (i) production (ii) publication and (iii) payment of the presenter of the series, Mr Eric Myeni? NW2168E

Reply:

(1) (a) Total amount the Department spent on Breaking New Ground magazine

(i) In each of the past three financial years was:

  1. 2015/2016 – R0.00
  2. 2016/2017 – R0.00
  3. 2017/2018 - R812 000.00

(ii) Since 1 April 2018 - R315 000.00

(b) Total spent on the

(i) Compilation: R0.00 – the magazine is compiled internally

(ii) Publication: R0.00 – the publication is done internally

(iii) Payment of the writing contributors: R0.00 – the Department does not pay writers or contributors

(2) (a) Total Department spent on the Breaking New Ground television

(i) In each of the past three financial years and

A. 2015/2016 – R5 000 000.00

B. 2016/2017 – R3 000 000.00

C. 2017/2018 - R2 760 000. 00

(ii) Since 1 April 2018 – R1 680 000.00

(b) Total spent on the

(i) Production – R220 000 an episode

(ii) Payment of the presenter of the series, Mr Eric Myeni? The Department is not privy to the contractual arrangements between Mr Myeni and the service provider producing BNG TV.

09 July 2018 - NW1346

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

What (a) total amounts were spent by (i) her department in each province and (ii) each provincial department of human settlements to replace asbestos roofs in government – built houses and/or buildings in each of the past five financial years and (b) is the total number of buildings of which the asbestos roofs were replaced?

Reply:

The Free State and Western Cape Provinces have incurred expenditure to replace asbestos roofs, while Gauteng and Northern Cape Provinces have incurred expenditure on the assessment of asbestos. The breakdown with regards to the above mentioned provinces is as follows:

1. Free State

a) The Province spent an amount totalling to R28 762 750 in the previous five financial years as illustrated below:

Financial Year

Total Number of Roofs replaced

Expenditure removal and disposal

Expenditure replacement

2013/14

168

R1 470 000

R4 032 000

2014/15

328

R2 846 000

R7 872 000

2015/16

76

R830 000

R1 824 000

2016/17

90

R618 250

R2 160 000

2017/18

214

R1 974 500

R5 136 000

Total

206

R7 738 750

R21 024 000

b) A total of 206 roofs were replaced.

2. Western Cape

(a) The Province spent R22 733 306 as indicated in the table below:

Financial Year

Contractor

Number of buildings

Cost

2015/16

Valostar

250

R22 733 306

b) A total of 250 units were replaced.

3. Gauteng Province

The Province reported to have spent R518 million on assessment of asbestos.

4. Northern Cape

The Province reported to have spent R72.7 million on assessment of Asbestos.

09 July 2018 - NW2022

Profile picture: Mazzone, Ms NW

Mazzone, Ms NW to ask the Minister of Human Settlements

(1) What are the details of the, (a) number of accidents that vehicles owned by her department were involved (i) in each of the past three financial years and , (ii) since 1 April 2018, (b) cost for repairs in each case and , (c) (i) number of and (ii) reasons for vehicles being written off in each case; (2) Whether all vehicles owned by her department have tracking devices installed?

Reply:

(1) The Department of Human Settlements has (a) no incidents reported for vehicles owned by the department (i) None in the past three financial years and (ii) None since 1 April 2018, (b) no cost for repairs in each case and (c) (i) N/A (ii) N/A.

(2) None of the vehicles owned by the department have tracking devices installed.

17 May 2018 - NW934

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

What number of contracts have been terminated by the (a) North West department of human settlements and (b) Free State department of human settlements during the 2017-18 financial year, including the (i) names of the companies, {ii) rand value of the contract, (iii) duration of the contract, (iv) number of houses each respective contractor was contracted to build, (v) the exact day and month when the contract was terminated, (vi) the number of houses that have been delivered by each respective contractor as at the date the contract was terminated and (vii) the exact reasons for the termination of each contract? NW1014E

Reply:

(a) The North West Department of Human Settlements has advised that no contracts were terminated during the 2017-18 financial year. (i) - (vii) Not applicable.

(b) The Free State Department of Human Settlements reported that it terminated two contracts for the 2017-18 financial year. The reasons provided for the termination by the Free State Department of Human Settlements is due to a contractual dispute. The further details as requested can be obtained from the Free State Department of Human Settlements subject to the provisions of the Promotion of Access To Information Act.

17 May 2018 - NW881

Profile picture: Chance, Mr R

Chance, Mr R to ask the Minister of Human Settlements

What (a)(i) is the purpose of the Community Schemes Ombud Service and (ii) services does it offer (b)(i) is the funding mechanism of the Ombud and (ii) was the total income and expenditure of the Ombud over the past three financial years, (c) was the performance of the Ombud over the past three financial years in terms of cases (i) heard and (ii) resolved, (d) was the original set up cost of the Ombud, (e) was its staffing structure, (f) is/are the location/s of its offices and (g) is the way in which the Ombud deliver services?

Reply:

(a) (i) What is the purpose of the Community Schemes Ombud Service?

The Community Schemes Ombud Service Act under which the Community Services Ombud Service has been established regulates the community schemes industry, to provide alternative dispute resolution mechanisms and management of all community scheme documentation.

(ii) What service does it offer?

The functions of CSOS include inter alia the following;

• Develop and provide a dispute resolution service in terms of this Act;

• Provide training for conciliators, adjudicators and other employees of the CSOS;

• Regulate, monitor and control the quality of all sectional titles scheme governance documentation and such other scheme governance documentation; as may be determined by the Minister by notice in the Gazette; and
• Take custody of, preserve and provide public access electronically or by other means to sectional title scheme governance documentation and such other scheme governance documents as may be determined by the Minister by notice in the Gazette.

In performing its functions the CSOS has an obligation to: -

• Promote good governance of community schemes;

• Provide education, information, documentation and such services as may be required to raise awareness to owners, occupiers, executive committees and other persons or entities who have rights and obligations in community schemes, as regards those rights and obligations;

(b) (i) What is the funding mechanism of the Ombud?

In terms of Section 22(1) of the CSOS Act, the Community Schemes Ombud Service derives its revenue sources from:

• Money appropriated by Parliament;

• Levies collected from community schemes with the approval of the Minister;

• Fees for services rendered based on cost recovery;

• Interest derived from investments of the Service;

• Donations or contributions received by the Service with the approval of the Minister; and

• Subsidies and grants from organs of state.


(ii) What was the total income and expenditure of the Ombud over the past three financial years,

(ii) Based on information provided by the Community Schemes Ombud Service the following is the income and expenditure of the CSOS for the following periods:

Find here: Income and expenditure of the CSOS

24 April 2018 - NW322

Profile picture: Brauteseth, Mr TJ

Brauteseth, Mr TJ to ask the Minister of Human Settlements

What amount did (a) her department and (b) each entity reporting to her spend on the promotion or celebration of the Year of OR Tambo on the (i) Africa News Network 7 channel, (ii) SA Broadcasting Corporation (aa) television channels and (bb) radio stations, (iii) national commercial radio stations and (iv) community (aa) television and (bb) radio stations since 1 January 2017?

Reply:

(a)& (b)The Department of Human Settlements and its entities reporting to the Minister of Human Settlements did not spend money on the promotion or celebration of the Year of O.R. Tambo on any television channels and radio station since 1 January 2017.

23 April 2018 - NW101

Profile picture: Chetty, Mr M

Chetty, Mr M to ask the Minister of Human Settlements

How many title deeds were handed over to housing beneficiaries in each municipality in the Free State (a) in the 2016/17 financial year and (b) from 1 April 2017 up to the latest specified date for which information is available?

Reply:

(a)  + (b) The question has been referred to the Free State Province for a detailed reply. As soon as it is available, the Honourable Member will be provided with the reply.

11 April 2018 - NW716

Profile picture: Motau, Mr SC

Motau, Mr SC to ask the Minister of Human Settlements

Whether her department has a Sexual Harassment and Assault Policy in place; if not, (a) why not and (b) by what date will her Department have such a policy in place; if so (i) how are reports investigated and (ii) what are the details of the consequence management and sanctions stipulated by the policy; 2. (a) what is the total number of incidents of sexual harassment and assault that have been reported in her department (i) in each of the past three financial years and (ii) since 1 April 2017, (b) what number of cases were (i) opened and concluded, (ii) withdrawn and (iii) remain open based on the incidents and (c) what sanctions were issued for each person who was found to have been guilty.”

Reply:

1.1 The Department has a Policy and Procedure on the Prevention and Management of Sexual Harassment, approved on 7 April 2017 by the Director-General. (Annexure A)

1.2 In terms of Section 12.1.1 the policy states that “The Head of Department shall appoint the Director responsible for Labour Relations as the Department Sexual Harassment Advisor to deal with sexual harassment complaints. This shall be a permanent appointment.”

1.3 In Section 13.3 (13.3.1 to 13.3.9) of the Policy it outlines the manner on how sexual harassment should be investigated, with provisions that

1.3.1 “The Sexual Harassment Advisor serves as the first line of contact to complaints of alleged sexual harassment.

1.3.2 The role of the sexual harassment advisor is to provide a neutral, confidential and supportive environment for employees who have reported that they have been sexually harassed;

1.3.3 Explain the disciplinary procedure and time frames to complainants and respondents in both formal and informal procedures; and advise the complainant on the appropriate course of action and support available;

1.3.4 Provide guidance (if necessary) on how to complete the appropriate grievance form; and provide the respondent with a copy of this policy and any relevant document on disciplinary rules and procedures in the department;

1.3.5 Issue a written notice of the complainant to the respondent and explain the protective measures available to the complainant;

1.3.6 Investigate the complaint and bring the case to the attention of the Director-General;

1.3.7 Avoid unreasonable delays during the investigation and conclusion of any sexual harassment complaint;

1.3.8 Monitor and submit quarterly statistical reports on all cases reported, resolved and pending to the Director-General;

1.3.9 Contribute to the development, coordination, and implementation of educational programmes and awareness raising activities for prevention and management of sexual harassment in the department.”

1.4 In terms of Section 13.2.5 of the Policy it provides for ensuring that “Disciplinary measures are applied in accordance with the Disciplinary Code and Procedures (PSCBC Resolution 1 of 2003) in the Public Service, and its specified timeframes.” In addition Section 16.4.1 of the Policy provides that, “Should the respondent be found guilty of the offence, in line with Section 19.3.2, the Presiding Officer shall recommend a disciplinary sanction which may include any of the following or a combination of them: Mandatory referral for counselling and/or EHW intervention/s; Verbal warning; Written warning; Final written warning; Suspension (without pay for not more than 3 months); Demotion (as an alternative to dismissal) and Dismissal.

2(a) Two incidents of sexual harassment and assault were reported in the Department in the past three financial years:

2(b) The complaints were reported to the Employee Health and Wellness (EHW) unit although no formal grievances lodged by complainants to the Labour Relations unit, in terms of the policy.

2(c) The 1st incident was investigated with the perpetrator being reprimanded by the appointed supervisor; The 2nd incident resulted in the perpetrator being issued with a warning by his supervisor; the perpetrator apologizing to the complainant; and approval granted for the complainant to be transferred to another unit was as requested by the complainant.

11 April 2018 - NW636

Profile picture: Mashabela, Ms N

Mashabela, Ms N to ask the Minister of Human Settlements

(a)On what basis were RDP houses allocated at the Mokgoba squatter camp in Ward 29 Greater Letaba Local Municipality in Limpopo and (b) What are the (i) names, (ii) house numbers and (iii) allocation details of all recipients of RDP houses in the specified area?

Reply:

(a) Based on information provided by the Province the site to be developed was already occupied by households residing in informal dwellings. The households were approached to completed subsidy application forms. The completed subsidy applications were captured on the Housing Subsidy System (HSS) against the project. The captured subsidy applications were validated against the various datasets as prescribed in the National Housing Code. The households that passed the validation process were approved to benefit from a housing opportunity. The households that were approved on the HSS were allocated house by the municipality after the completion of the family units and houses.

(b) The Province approved 250 beneficiaries to benefit from housing opportunities in the area. Of the 250 beneficiaries who were earmarked for the housing project , an Additional 77 hostel dwellers were also assisted in the building family units for their families in the area. On completion of the construction of the houses and family units, the Municipality allocated the houses and family units. Post the allocation process it was discovered that the list used to allocate families into the project contained the details of the approved households from the Province, that were not allocated into the project.

The Province as well as the Municipality then embarked on a formalization programme in 2014 to correct the houses and family units, which were not correctly allocated. The formalization programme is currently being undertaken on a phased approach and has not been concluded to date. A current status report on the formalisation process is attached marked as Annexure A, and includes the names and house numbers of the allocated beneficiaries.

15 December 2017 - NW3521

Profile picture: Bagraim, Mr M

Bagraim, Mr M to ask the Minister of Human Settlements

(1)With reference to her reply to question 1651 on 29 August 2017, how did the Ekurhuleni Metropolitan Council spend R24,714,000 on affordable and social housing during the 2015-16 financial year and yet no units were built; (2) (a) what are the reasons that the Ekurhuleni Metropolitan Council’s ability to spend its housing budget declined from 83% in the 2014-15 financial year to 30,5% in the 2016-17 financial year and (b) what amount has been allocated to the Ekurhuleni Metropolitan Municipality for the 2017-18 financial year; (3) what are the reasons that the cost per unit dropped of each RDP house that was constructed during the 2016-17 financial year, to R66 000, whilst it cost R111 000 per unit during the 2015-16 financial year?

Reply:

(1) I have been informed by Ekurhuleni Metropolitan Municipality that the reported expenditure of R24 714 000 was for work in progress. The social housing projects are multi-year projects and the housing units are reported when the block of social housing units are complete, handed over and a completion certificate is issued. The projects have since been completed with 256 units delivered, in Germiston Fire station phase 1(144 units) and Delville (112 units) respectively, at the end of the 2016/17 financial year.

(2) (a) The contract of the appointed service providers had expired on 30 June 2016, therefore no construction could commence until new service providers were appointed. The appointment of the new service provider was finalised on 18 November 2016 and appointment letters from the Tender Office were issued on 15 December 2016. There was a period of six months where the Municipality had no service providers for the construction of houses. In addition, the late gazetting of the Human Settlements Development Grant (HSDG) funds by the Province to Ekurhuleni Metropolitan Municipality also contributed to the poor expenditure of 2016/17. The Metropolitan Municipality received this part of HDSG in March 2017.

(b) The Municipality received an Urban Settlements Development Grant (USDG) allocation of R1, 985 billion for the 2017/2018 financial year.

(3) The approved National Subsidy Quantum is R111 000. The Provincial Subsidy Quantum on the other hand is capped at R102 953.55. The unit cost did not reduce as the National Subsidy Quantum stands at R111 000. Further, the Metropolitan Municipality reported that there were certain houses under the category of work in progress, as they were at various phases of construction. In addition, there were expenses for completed houses which were not included as they were subject to internal payment approval process at the time of reporting.

15 December 2017 - NW3739

Profile picture: Mokause, Ms MO

Mokause, Ms MO to ask the Minister of Human Settlements

(1)Whether (a) her department and/or (b) entities reporting to her procured services from a certain company (name furnished); if so, (i) what services were procured in each case and (ii) what is the total amount that was paid to the specified company in each case; (2) whether the specified company provided services related to international travel to (a) her department and/or (b) entities reporting to her; if so, (i) what is the name of each person who travelled, (ii) what was the travel route and (iii) what is the total amount that was paid for each person?

Reply:

(1) (a) & (b) Yes

The Honourable Member did not specify the period for which the information is required.

(2) Furthermore, in accordance with the established practise applicable to parliamentary questions contained in the document titled, “Guide to Parliamentary Questions in the National Assembly”, I will not be able to provide names of persons as requested in the question. The document referred to prohibits Members of Parliament, including the Executive, from divulging names of persons, bodies when asking or responding to parliamentary questions. It specifically states the following:

Questions are to be framed as concisely as possible. All unnecessary adjectives, references and quotations are omitted. Names of persons, bodies and, for example, newspapers are only used in questions if the facts surrounding the case have been proven. As the mere mention of such names could be construed as publicity for or against them, it should be clear that this practice is highly undesirable. If a question will be unintelligible without mentioning such names, the Departments concerned are notified of the name (-s) and this phrase is used: ".......a certain person (name furnished)”

15 December 2017 - NW359

Profile picture: Topham , Mr B

Topham , Mr B to ask the Minister of Human Settlements

What is the (a) make, (b) model, (c) price and (d) date on which each vehicle was purchased for use by (i) her and (ii) her deputy (aa) in the (aaa) 2014-15 and (bbb) 2015-16 financial years and (bb) since 1 April 2016?

Reply:

(i) & (ii) The information requested by the Honourable Member is available in the Department’s Annual Report.

 

15 December 2017 - NW3165

Profile picture: Mokause, Ms MO

Mokause, Ms MO to ask the Minister of Human Settlements

(1)What are the details including the ranks of service providers and/or contractors from which (a) her department and (b) the entities reporting to her procured services in the past five years; (2) what (a) service was provided by each service provider and/or contractor and (b) amount was each service provider and/or contractor paid; (3) (a) how many of these service providers are black-owned entities, (b) what contract was each of the black-owned service providers awarded and (c) how much was each black-owned service provider paid?

Reply:

Honourable Member, in accordance with the established practise applicable to parliamentary questions contained in the document titled, “Guide to Parliamentary Questions in the National Assembly”, I will not be able to provide names of the service providers as requested. The document referred to prohibits Members of Parliament, including the Executive, from divulging names of persons, bodies when asking or responding to parliamentary questions. It specifically states the following:

Questions are to be framed as concisely as possible. All unnecessary adjectives, references and quotations are omitted. Names of persons, bodies and, for example, newspapers are only used in questions if the facts surrounding the case have been proven. As the mere mention of such names could be construed as publicity for or against them, it should be clear that this practice is highly undesirable. If a question will be unintelligible without mentioning such names, the Departments concerned are notified of the name (-s) and this phrase is used: ".......a certain person (name furnished)”

In addition, to spend time sourcing information for the past five financial years will take time and it would not be prudent to spend resources on a project such as this one. The Honourable Member is, however, encouraged to provide me with specific areas of concern that she might have in respect of any service provider used by my Department and the entities reporting to me.

 

15 December 2017 - NW3894

Profile picture: Van Der Walt, Ms D

Van Der Walt, Ms D to ask the Minister of Human Settlements

(1)What number of housing projects were undertaken in the (a) Modimolle, (b) Mookgopong, (c) Bela-Bela, (d) Lephalale and (e) Thabazimbi Local Municipalities in Limpopo since the 2014-15 financial year; (2) whether the specified projects were completed; if not, in each case, (a) why not, (b) what was the monetary value of each project and (c) who were the contractors; (3) what are the details of the waiting list used to allocate houses from these housing projects to needy citizens; (4) did the residents receive title deeds of allocated houses?

Reply:

(1) The number of projects undertaken since the 2014/15 financial year in Limpopo in:

(a) Modimolle LM: 4 projects;

(b) Mookgopong LM: 6 projects;

(c) Bela Bela LM: 9 projects;

(d) Lephalale LM: 15 projects;

(e) Thabazimbi LM: 2 projects.

(2) (a) According to the information provided by the Provincial Department, not all projects mentioned above have been completed. Some projects are being implemented over multi-year periods.

(b) The names of incomplete projects and their monetary value are indicated in the table below:

NO.

PROJECT INFORMATION

(b) MONETARY VALUE

1.

WATERBERG/ MODIMOLLE / HOMES 2000 (78)

(Delayed due to contract not being signed by the contractor)

R6 474 000

2.

WATERBERG/BELA-BELA/ MMAMOLOKO (86 URBAN)

R7 138 000

3.

WATERBERG/BELA-BELA/ HIGH POINT (92) URBAN

R7 636 000

4.

WATERBERG/BELA-BELA/ BARORISI (92) RURAL

R7 636 000

 

(for the three projects above, site handover is in process after recently appointing contractors)

 

 

 

(c) Honourable Member, in accordance with the established practise applicable to parliamentary questions contained in the document titled, “Guide to Parliamentary Questions in the National Assembly”, I will not be able to provide names of the contractors as requested. The document referred to prohibits Members of Parliament, including the Executive, from divulging names of persons, bodies when asking or responding to parliamentary questions. It specifically states the following:

 

Questions are to be framed as concisely as possible. All unnecessary adjectives, references and quotations are omitted. Names of persons, bodies and, for example, newspapers are only used in questions if the facts surrounding the case have been proven. As the mere mention of such names could be construed as publicity for or against them, it should be clear that this practice is highly undesirable. If a question will be unintelligible without mentioning such names, the Departments concerned are notified of the name (-s) and this phrase is used: ".......a certain person (name furnished)”

(3) All the specified municipalities, except the Thabazimbi Local Municipality, use waiting lists. Thabazimbi Local Municipality is making use of the previous instrument, the Beneficiary Status Report. Beneficiaries were approved using this instrument. The Limpopo Province’s current waiting list is still a manual one, and is not yet automated as is the case with the National Housing Needs Register (NHNR). The province is in a process of uploading data the NHNR system.

(4) Yes, 3 205 beneficiaries have title deeds registered in their names for houses built in the specified (new) projects.

12 December 2017 - NW3612

Profile picture: Mokause, Ms MO

Mokause, Ms MO to ask the Minister of Human Settlements

Whether (a) her department and/or (b) any entity reporting to her own land; if so, in each case, (i) where is each plot of land located, (ii) what is the size of each specified plot and (iii) what is each plot currently being used for?

Reply:

(a) The National Department of Human Settlements does not own any land.

(b) Of the eight entities reporting to me, four do not own land and these are; Community Schemes Ombud Service, National Urban Reconstruction and Housing Agency, Rural Housing Loan Fund, Social Housing Regulatory Authority.

 

The other four entities own land as indicated below:

Estate Agency Affairs Board

  1. No 63 Weirda Road, Weirda Valley, Sandton, Johannesburg
  2. Erf 16 ( 3965 sqm) and Erf 17 (3965 sqm)
  3. Both properties are used for business use.

Housing Development Agency

The Housing Development Agency owns land acquired on behalf of Provinces and/or Municipalities for human settlements and housing development.

A.

  1. Erf 13120, Queenstown, Lukhanji Municipality, Eastern Cape
  2. 5.1900 ha
  3. Currently leased to a community church

B

  1. Ptn of 78 Farm, Hartebeestpoort No. 328 JR, City of Tshwane Municipality, Gauteng
  2. 18.748 ha
  3. Currently leased to vehicle dealerships, retail and panel beaters.

C

(i) The Farm Eloffs Park No. 772 JR, City of Tshwane Municipality, Gauteng

(ii) 19.3595 ha

(iii) Currently leased to a golf club, car dealership and offices.

D

  1. Erf 10509, Philippi - Cape Town, City of Cape Town, Western Cape
  2. 2.48 ha
  3. The land is vacant

E

  1. Erfs 17844, 17845,17847 and 18093, Knysna, Western Cape
  2. 56.344 ha
  3. The land is illegally occupied by the community

F

  1. Rem of Farm 755/2, Machiel Heyns, Western Cape
  2. 700.5669 ha
  3. The land is illegally occupied by small scale farmers.

National Home Builders Registration Council

A

  1. Erf 1086 Sunninghill
  2. 8 260 square metres
  3. The land is used to house the NHBRC Head Office and the Provincial Customer Care Offices for Gauteng Provincial Office.

B

  1. Eric Molobi Innovation Hub, Thorntree View, Soshanguve
  2. 15 000 square metres
  3. Used for an innovation testing facility, training centre and to display the different show houses for innovative Building technologies.

National Housing Finance Corporation

A

  1. President Place, Erven 300 and 585 West Germiston, Gauteng, known as President Place, situated at corner of President, Human, Clark and FH Odendaal streets.
  2. 2 170 square metres
  3. The land is owned on the basis of a body corporate investment property, acquired through step in rights per lending agreement, and comprises of affordable rental units.

B

  1. Vacant land in Ermelo, i.e.  Erf 10097 Ermelo Extension 14.
  2. 8 298 square metres
  3. NHFC took judgment against ABC Cash Plus (Pty) Ltd being the surety for the indebtedness of Realty Dynamix (Pty) Ltd to the NHFC. The NHFC had registered a surety bond over the immovable property belonging to ABC which was situated in Ermelo. A sale in execution was arranged in 2013 and NHFC successfully bid for and purchased the property with the objective of then selling it in order to recoup the losses made as a result of funding Realty Dynamix. NHFC is still in the process of disposing the property.

C

  1. Portions 1 to 14, 16 to 21 & 24 to 68 of Erf 12152 Mabopane X Township
  2. Estate comprising of 68 individual residential stands of various sizes and a roadway for access purposes.
  3. When Bella Casa was placed in liquidation the NHFC called up the mortgage bond which it had over the property, being Portions 1 to 14, 16 to 21 & 24 to 68 of Erf 12152 Mabopane X Township. In September 2016 NHFC entered into a development rights agreement with My Africa Holdings (Pty) Ltd in terms of which the flow of funds would be made by way of instalment payments. The transfer has not passed to the purchaser as transfer will be effected upon sale of the various completed units.

D

  1. Erf 2435 – Weltevreden Valley
  2. 11.8 hectares
  3. The land portion was acquired on the condition to develop the property for affordable rental housing numbering approx. 650 units.

E

  1. Erf 6111 and 8175 in Eerste Rivier
  2. 3.38 hectares
  3. Condition from Provincial Government of Western Cape (PGWC) to develop 211 Institutional Subsidy units. The PGWC have requested Cape Town Community Housing Company to transfer this portion back to them as they are no longer undertaking new developments.

F

  1. 40 residential erven in the David Kruiper Municipality
  2. Approx. 750 square meter each.
  3. The terms of acquisition is for development in accordance with affordable housing standards of David Kruiper Municipality.

12 December 2017 - NW3005

Profile picture: Kalyan, Ms SV

Kalyan, Ms SV to ask the Minister of Human Settlements

(1)What is the (a) total amount that was paid out in bonuses to employees in her department and (b) detailed breakdown of the bonus that was paid out to each employee in each salary level in the 2016-17 financial year; (2) what is the (a) total estimated amount that will be paid out in bonuses to employees in her department and (b) detailed breakdown of the bonus that will be paid out to each employee in each salary level in the 2017-18 financial year?

Reply:

(1) (a) (i) During the 2016/17 financial year, an amount of R6 498 634.43 was paid out to employees on salary levels 2-12 and those covered by the Occupational Specification Dispensation (OSD) for 2015/16 performance cycle.

(ii) In the same year, an amount of R191 682 was paid out to qualifying Directors and Chief Directors for 2013/14 performance cycle and R396 365.57 for the 2014/15 performance cycle.

(b) The figures indicated above were disbursements to level 2 - 12 for 2015/16 performance cycle and to Directors and Chief Directors for 2013/14 and 2014/15 performance cycle.

(2) (a) It is estimated that in 2017/18 an amount of R7 581 731.64 will be paid out to employees for 2016/17 performance cycle.

(b) There is no breakdown available because the performance assessment process has not been concluded.

12 December 2017 - NW3506

Profile picture: America, Mr D

America, Mr D to ask the Minister of Human Settlements

(1)(a) What is the current municipal valuation of the remainder of Roodekuil No 496 KR farm in the Bela-Bela Local Municipality in Limpopo that was recently purchased by the Housing Development Agency in Limpopo (HDAL), (b) why did the HDAL purchase the specified farm and (c) for what amount did the HDAL purchase the farm; (2) whether the HDAL considered any other properties for suitability before purchasing the farm; if not, why not; if so, (a) what are the relevant details and (b) on what basis was the farm purchased instead of other options?

Reply:

(1) (a) The Department of Human Settlements is not in a position to comment on the remainder of the farm which was not purchased by the HDA.

(b) The Housing Development Agency acquire land for development human settlements.

(c) R65 400 000.

(2) (a) Land in and around Bela-Bela Township was also considered. Acquisition of land in the area would have perpetuated old separate development policy.

(b) Its ability to achieve human settlements spatial structuring imperatives.

12 December 2017 - NW3717

Profile picture: Bara, Mr M R

Bara, Mr M R to ask the Minister of Human Settlements

With reference to the land evaluations conducted by the Housing Development Agency for/on behalf of the Limpopo Department of Cooperative Governance, Human Settlements and Traditional Affairs, what are the (a) costs of the valuations and (b) names of all (i) individual evaluators and/or (ii) companies appointed for the evaluations, in the (aa) 2013-14, (bb) 2014-15, (cc) 2015-16 and (dd) 2016-17 financial years?

Reply:

Honourable Member, in accordance with the established practise applicable to parliamentary questions contained in the document titled, “Guide to Parliamentary Questions in the National Assembly”, I will not be able to provide names of the companies that conducted valuations as requested. The document referred to prohibits Members of Parliament, including the Executive, from divulging names of persons, bodies when asking or responding to parliamentary questions. It specifically states the following:

 

Questions are to be framed as concisely as possible. All unnecessary adjectives, references and quotations are omitted. Names of persons, bodies and, for example, newspapers are only used in questions if the facts surrounding the case have been proven. As the mere mention of such names could be construed as publicity for or against them, it should be clear that this practice is highly undesirable. If a question will be unintelligible without mentioning such names, the Departments concerned are notified of the name (-s) and this phrase is used: ".......a certain person (name furnished)”

Further, the Housing Development Agency (HDA) is a national public development agency that promotes sustainable communities by making well-located and appropriately-planned land and buildings available for the development of human settlements. As its primary activities, the HDA assembles state, private and communal land and buildings and releases it for human settlement development. It also provides land and housing delivery support services to organs of state at local, provincial and national level.

I have been informed that all land valuations undertaken by the HDA in Limpopo were undertaken at the request of the Provincial Department of COGSTA and the information is provided in the table below:

Number of valuations undertaken by HDA for Limpopo Coghta and Municipalities

Financial years

Municipality

Number of properties valued

Number of valuations

(a) Amount

(aa) 2013/14

None

0

0

 

(bb) 2014/15

Greater Tzaneen Municipality

4

6

R 25 000

       

R 23 165

       

R 27 500

       

R 7 600

       

R 8 395

       

R 16 905

 

Greater Tubatse

3

6

R 27 300

       

R 22 500

       

R 24 000

 

Modimolle

1

3

The three service providers appointed to conduct land valuations in the Modimolle municipal district were contracted to do valuations in other areas and therefore did not separate the amounts for the work undertaken.

         

(cc) 2015/16

Elias Motsoaledi

1

3

R 19 150

       

R 9 745

       

R 24 000

(dd) 2016/17

Ephraim Mogale

1

3

R 7 600

       

R 11 145

       

R 6 874

 

Elias Motsoaledi

1

3

R 12 850

       

R 11 145

 
       

R 8 718

 

12 December 2017 - NW3722

Profile picture: Bara, Mr M R

Bara, Mr M R to ask the Minister of Human Settlements

With reference to the land evaluations conducted by the Housing Development Agency for/on behalf of each of the respective municipalities in Limpopo, what are the (a) costs of the valuations and (b) names of all (i) individual evaluators and/or (ii) companies appointed for the evaluations, for the (aa) 2013-14, (bb) 2014-15, (cc) 2015-16 and (dd) 2016-17 financial years?

Reply:

Honourable Member, in accordance with the established practise applicable to parliamentary questions contained in the document titled, “Guide to Parliamentary Questions in the National Assembly”, I will not be able to provide names of the companies that conducted valuations as requested. The document referred to prohibits Members of Parliament, including the Executive, from divulging names of persons, bodies when asking or responding to parliamentary questions. It specifically states the following:

 

Questions are to be framed as concisely as possible. All unnecessary adjectives, references and quotations are omitted. Names of persons, bodies and, for example, newspapers are only used in questions if the facts surrounding the case have been proven. As the mere mention of such names could be construed as publicity for or against them, it should be clear that this practice is highly undesirable. If a question will be unintelligible without mentioning such names, the Departments concerned are notified of the name (-s) and this phrase is used: ".......a certain person (name furnished)”

Further, the Housing Development Agency (HDA) is a national public development agency that promotes sustainable communities by making well-located and appropriately-planned land and buildings available for the development of human settlements. As its primary activities, the HDA assembles state, private and communal land and buildings and releases it for human settlement development. It also provides land and housing delivery support services to organs of state at local, provincial and national level.

I have been informed that all land valuations undertaken by the HDA in Limpopo were undertaken at the request of the Provincial Department of COGSTA and the information is provided in the table below:

Number of valuations undertaken by HDA for Limpopo Coghta and Municipalities

Financial years

Municipality

Number of properties valued

Number of valuations

(a) Amount

(aa) 2013/14

None

0

0

 

(bb) 2014/15

Greater Tzaneen Municipality

4

6

R 25 000

       

R 23 165

       

R 27 500

       

R 7 600

       

R 8 395

       

R 16 905

 

Greater Tubatse

3

6

R 27 300

       

R 22 500

       

R 24 000

 

Modimolle

1

3

The three service providers appointed to conduct land valuations in the Modimolle municipal district were contracted to do valuations in other areas and therefore did not separate the amounts for the work undertaken.

         

(cc) 2015/16

Elias Motsoaledi

1

3

R 19 150

       

R 9 745

       

R 24 000

(dd) 2016/17

Ephraim Mogale

1

3

R 7 600

       

R 11 145

       

R 6 874

 

Elias Motsoaledi

1

3

R 12 850

       

R 11 145

 
       

R 8 718

 

08 December 2017 - NW3715

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

With reference to the contract awarded by the Estate Agency Affairs Board of South Africa to a certain company (name and details furnished) (a) what is the current (i) contract value and (ii) length of the contract, (b) when was the contract awarded and (c) when is the contract due to expire?

Reply:

(a)(i & ii) The Estate Agency Affairs Board (EAAB) confirmed that it did not directly award any contract to the company referred to by the Honourable Member. Instead, the EAAB has a support service level agreement and end user licence contract with a South African company which is an authorised reseller of the company in question.

(b) Falls away.

(c) Falls away.

08 December 2017 - NW3574

Profile picture: Lotriet, Prof  A

Lotriet, Prof A to ask the Minister of Human Settlements

(a) What is the total number of supplier invoices that currently remain unpaid by (i) her department and (ii) each entity reporting to her for more than (aa) 30 days, (bb) 60 days, (cc) 90 days and (dd) 120 days and (b) what is the total amount outstanding in each case?

Reply:

The information requested by the Honourable Member is provided in the table below:

(i) NATIONAL DEPARTMENT OF HUMAN SETTLEMENTS:

(aa) for more than 30 days

(bb) for more than 60 days

(cc) for more than 90 days

(dd) for more than 120 days

None

None

None

None

(ii) ENTITIES:

(aa) for more than 30 days

(bb) for more than 60 days

(cc) for more than 90 days

(dd) for more than 120 days

National Urban Reconstruction and Housing Agency

13 and total  amount outstanding is

R1,573,617.68

7 and total  amount outstanding is

R26,320.12

1 and total  amount outstanding is

R33,345.00

1 and total  amount outstanding is

R91.49

National Housing Finance Corporation

R316.92

None

None

None

Social Housing Regulatory Authority

92 and total  amount outstanding is R3 179 454.82

16 and total  amount outstanding is

R946 184.22

1 and total  amount outstanding is

R77 922.95

4 and total  amount outstanding is

R83 022.03

Housing Development Agency

2 and total  amount outstanding is

R15 104,00

6 and total  amount outstanding is

R1 411 171,00

5 and total  amount outstanding is

R164 227,00

12 and total  amount outstanding is

R6 681 692,00

Rural Housing Loan Fund

None

None

None

None

Community Schemes Ombud Service

1 and total amount outstanding is

R961,879.90

None

None

2 and total amount outstanding is

R261,800.00

Estate Agency Affairs Board

13 and total amount outstanding is R242 332,46

None

1 and total amount outstanding is R11 475,00

None

National Home Builders Registration Council

20 and total amount outstanding is R2 505 610,00

2 and the total amount outstanding is R64 370,00

1 and total amount outstanding is R29 135,00

None

 

04 December 2017 - NW3443

Profile picture: Mokause, Ms MO

Mokause, Ms MO to ask the Minister of Human Settlements

(1)How many officials and/or employees in her department were granted permission to have businesses and/or do business dealings in the past three financial years; (2) are any of the officials and/or employees that have permission to have businesses and/or do business dealings doing business with the Government; if so, (a) what was the purpose of each business transaction, (b) when did each business transaction occur and (c) what was the value of each business transaction?

Reply:

(1) Three officials were granted permission to have businesses in the past three financial years.

(2) All three requests for approval were not for business with the state or its organs.

I wish to point out to the Honourable Member that employees are prohibited from doing business with the state or its organs. Incidentally, it was during my tenure as Minister of Public Service and Administration that the Public Administration Management Act of 2013 which introduced the prohibition was drafted, processed through Cabinet and Parliament and was enacted by the President in 2013.

Honourable Member, the prohibition referred to above is currently enforceable through section 13 (c) of the Public Service Regulations. The said section stipulates that an employee shall not conduct business with any organ of state or be a director of a public or private company conducting business with an organ of state, unless such an employee is in an official capacity a director of a company listed in schedule 2 and 3 of the Public Finance Management Act”.

BACKGROUND INFORMATION:

In terms of the Public Service Regulations 13 (c), “An employee shall not conduct business with any organ of state or be a director of a public or private company conducting business with an organ of state, unless such an employee is in an official capacity a director of a company listed in schedule 2 and 3 of the Public Finance Management Act”;

Further, in terms of the Public Service Regulations 24, “An application by an employee to perform remunerative work outside his or her department shall be in accordance with the process determined by the Minister and in the form issued by the Minister.”

Accordingly, a Directive on Conducting Business with an Organ of State was issued in January 2017 by the Minister for Public Service and Administration.

 

04 December 2017 - NW3713

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

With regard to the car accident that involved her official vehicle in the 2016-17 financial year, (a) on what date did the accident occur, (b) where did it happen, (c) what was the extent of the damage to the vehicle, (d) who was driving the vehicle at the time of the accident (e) what official business were they engaged in when the accident occurred and (f) what is the current state of the vehicle?

Reply:

My official car was not involved in an accident in the 2016/17 financial year.

(a) to (f) Fall away.

 

04 December 2017 - NW3397

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

Why was a new ministerial vehicle bought for her in the 2016-17 financial year?

Reply:

There was no new vehicle purchased for the Minister or the Deputy Minister in the 2016/17 financial year.

 

01 December 2017 - NW2819

Profile picture: Steyn, Ms A

Steyn, Ms A to ask the Minister of Human Settlements

(1)(a) What is the total number of houses that has been built by the Walter Sisulu Local Municipality, previously known as Gariep and Maletswai Municipalities, (i) in each of the past ten financial years and (ii) since 1 April 2017, (b) what amount did each house cost and (c) what are the names of each contractor appointed for each project; (2) (a) what is the total amount of money that was allocated to the specified municipality’s human settlements department in each of the specified financial years and period and (b) of the specified allocation, what is the total amount that was not spent in each case; (3) (a) what amount was spent during each of the specified financial years on rebuilding or repairs of the houses, (b) how many houses were affected, (c) in which town and community is each house situated and (d) who were the contractors in each case?

Reply:

(1) (a) The information provided to me in response to the Honourable Members’ question is indicated in the table below:

(i) Houses built in the Walter Sisulu Local Municipality in the past ten years:

FINANCIAL YEAR

HOUSES BUILT IN GARIEP LM

HOUSES BUILT IN MALETSWAI LM

TOTAL HOUSES BUILT (WSLM)

2007/08

-

854

854

2008/09

-

227

227

2009/10

243

362

605

2010/11

295

18

313

2011/12

43

33

76

2012/13

127

68

195

2013/14

285

59

344

2014/15

45

14

59

2015/16

160

175

335

2016/17

88

43

131

(ii) Houses built since April 2017 (01 April 2017 to 31 July 2017)

FINANCIAL YEAR

HOUSES BUILT IN GARIEP LM

HOUSES BUILT IN MALETSWAI LM

TOTAL HOUSES BUILT (WSLM)

2017/18

-

86

86

Each of the houses built during the period of ten years cost between R54 650 and R110 947, informed by the approved national subsidy quantum to be used in the relevant project implementation period.

(2) (a) (b) The funding allocated, spent and not spent per applicable financial year:

FINANCIAL YEAR

(a) Amount

allocated

Amount spent

(b) Unspent Funds

2010/11

 

77 297

 

2011/12

60 514

9 192

51 322

2012/13

59 855

28 833

31 022

2013/14

57 953

29 597

28 356

2014/15

22 075

31753

-9 678

2015/16

30 616

35 857

-5 241

2016/17

31 025

45 870

-14 845

2017/18

45 122

23 162

21 960

(c) In accordance with the established practise applicable to parliamentary questions and guidelines contained in the document titled, “Guide to Parliamentary Questions in the National Assembly”, I will not provide names of each contractor appointed for each project. The document referred to specifically states the following:

 

Questions are to be framed as concisely as possible. All unnecessary adjectives, references and quotations are omitted. Names of persons, bodies and, for example, newspapers are only used in questions if the facts surrounding the case have been proven. As the mere mention of such names could be construed as publicity for or against them, it should be clear that this practice is highly undesirable. If a question will be unintelligible without mentioning such names, the Departments concerned are notified of the name (-s) and this phrase is used: ".......a certain person (name furnished)”.

(3) (a)(b) & (c) The table below refers to the number of houses that required rebuilding or residual repairs, the amount spent on the repairs and the communities in which the houses are located and the contractors who undertook the repairs.

Houses that required rebuilding and the amount spent on rebuilding houses in Burgersdorp.

Financial Year

Amount Spent(a)

How many houses were affected(b)

In which town or community(c)

Contractors(d)

2014/15

1 523 781

1 000

Burgersdorp

NHBRC,

Provincial and Municipal

2015/16

79 250

1000

Burgersdorp

NHBRC,

Provincial and Municipal

2016/17

5 035 525

1000

Burgersdorp

NHBRC,

Provincial and Municipal

2017/18

6 482 983

1000

Burgersdorp

NHBRC,

Provincial and Municipal

Houses that required rebuilding and the amount spent on rebuilding houses in Steynsburg:

Financial Year

Amount Spent(a)

How many houses were affected(b)

In which town or community(c)

Contractors(d)

2014/15

13 016 837

600

Steynsburg

In terms of applicable policy the information should be requested from the Municipality and/or Province

2015/16

7 205 121

600

Steynsburg

 

2016/17

219 600

600

Steynsburg

 

2017/18

43 050

600

Steynsburg

 

Houses that required rebuilding and the amount spent on rebuilding houses in Venterstad:

Financial Year

Amount Spent(a)

How many houses were affected(b)

In which town or community(c)

Contractors( d)

2014/15

2 849 242

500

Venterstad

NHBRC,

Provincial and Municipal

2015/16

193 649

500

Venterstad

NHBRC,

Provincial and Municipal

2016/17

6 784 177

500

Venterstad

NHBRC,

Provincial and Municipal

2017/18

7 740 133

500

Venterstad

NHBRC,

Provincial and Municipal

Houses that required rebuilding and the amount spent on rebuilding houses in James Town:

Financial Year

Amount Spent(a)

How many houses were affected(b)

In which town or community(c)

Contractors(d)

2011/12

3 985 512

244

James town

In terms of applicable policy the information should be requested from the Municipality and/or Province

2012/13

7 076 612

244

James town

 

2013/14

4 825 948

244

James town

 

2014/15

2 007 720

244

James town

 

2015/16

5 874 028

244

James town

 

2016/17

-

244

James town

 

2017/18

-

244

James town

 

01 December 2017 - NW3716

Profile picture: Bara, Mr M R

Bara, Mr M R to ask the Minister of Human Settlements

What number of land valuations were commissioned by the National Housing Development Agency for or on behalf of (a) the Limpopo Department of Cooperative Governance, Human Settlements and Traditional Affairs and/or (b) each of the respective municipalities in Limpopo in the (i) 2013-14, (ii) 2014-15, (iii) 2015-16 and (iv) 2016-17 financial years?

Reply:

The information requested by the Honourable Member is provided in the table below:

Question Number

Municipality/ Department

Number of land parcels Valued

Number of Valuations

(a)

None

0

0

(b)(i) 2013-14

None

0

0

(b)(ii) 2014-15

Greater Tzaneen Municipality

4

6

 

Greater Tubatse

3

6

 

Modimolle

1

3

 

Thabazimbi

2

6

(b)(iii) 2015-16

Elias Motsoaledi

1

3

(b)(iv) 2016-17

Ephraim Mogale

1

3

 

Elias Motsoaledi

1

3

Total

 

13

30

01 December 2017 - NW3484

Profile picture: Matiase, Mr NS

Matiase, Mr NS to ask the Minister of Human Settlements

With reference to her reply to question 2919 on 17 October 2017, (a) how can the topography not be adequate when there are RDP houses in the area and across the country that are constructed on similar topography and (b) what are the exact details of the location of the site that was suggested (i) for a Mr Sipho Mnguni and (ii) to the four families currently residing on the same site?

Reply:

(a) The Ethekwini Metropolitan Municipality had indicated that the topography of the site on which the property is located is not conducive for the construction of a home within the required standards due to the steepness of the site and limited developable space. Proceeding with the construction of a house will require extensive excavation, levelling and filling to create sufficient space. Furthermore, retaining walls will have to be built on the front and back of the house, to retain the steep banks in order to prevent the house from being damaged during the rainy seasons. The other attendant matter which required attention was the relocation of other families residing in the informal structures on the site to another area before the site could be developed.

In the reply, I have included photographs to illustrate the challenging topography which led to the delay in resolving the matter.

The photograph below indicates the site boundary which extends from the edge of the footpath to where the lower informal structures are located on the site. The limited developable space of the site can be observed (it is where officials are standing), as well as the informal structure on the level portion of site. Note must be taken of the location and proximity of the existing dwellings, to the footpath with running water.

C:\Users\Sandile.Zondi\AppData\Local\Microsoft\Windows\Temporary Internet Files\Content.Word\20171011_143058_resized.jpg

The photograph below illustrates the steepness of the bank and thus the need for the construction of retaining walls.

C:\Users\Sandile.Zondi\AppData\Local\Microsoft\Windows\Temporary Internet Files\Content.Outlook\G4XKPJHO\20171011_143450_resized.jpg

The eThekwini Municipality has now confirmed that after a long protracted consultation, a decision has been taken a decision to build houses for the five families living in the area and a process of identifying alternative accommodation has already commenced. However, it has also been brought to my attention that the said person is not prepared to relocate to a temporary residential area (TRA) to allow for the required planning and construction work to commence.

(b) The property details are as follows:

Site No: Erf 1210, Section F, Umlazi

Coordinates: 30°53'38.175"E 29°56'28.788"S.

Extent: 278m²

27 October 2017 - NW2919

Profile picture: Ndlozi, Dr MQ

Ndlozi, Dr MQ to ask the Minister of Human Settlements

With reference to her reply to question 2468 on 5 September 2017, why has Mr Sipho Mnguni (details furnished) not been allocated an RDP house and why was one not built for him?

Reply:

As the Honourable Member is aware, housing is a concurrent function and the Housing Act of 1997 clearly stipulates the mandates of the national, provincial and local spheres of government in respect of housing delivery. In addition, the National Housing Code 2009 requires municipalities to include a Housing Chapter in their Integrated Development Plans. The case that the Honourable Member is inquiring about resides within the local sphere, at the eThekwini Metropolitan Municipality to be specific.

The eThekwini Metropolitan Municipality has advised that it has not been able to construct a house for the person referred to by the Honourable Member due to the following reasons:

  • The site on which he resides is situated on unfavourable topography (steep terrain) and
  • There are four other families residing informally on the same site.

The eThekwini Municipality also advised that the person referred to by the Honourable Member is not prepared to relocate to an alternative site, as was suggested by the Municipality. This means that a retaining wall will have to be constructed when the construction of the house commences.

My Department has also been informed by the eThekwini Municipality, that it was in the process of identifying alternative land for the four families who are at present informally residing on the same site, and the target date for the completion of the process of relocation (once the site has been identified) is June 2018.

11 September 2017 - NW2033

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

(a) How many (i) black-, (ii) white- and (iii) female-owned contractors initiated legal action against each provincial department of human settlements for non-payment of work within the prescribed 30 days period in the 2016-17 financial year, (b) what was the value of each payment, (c) what are the full details of the work to be conducted in each case and (d) what is the current status of each contract?

Reply:

Of the nine Provincial Departments of Human Settlements, only the Eastern Cape and the Gauteng province confirmed that there were contractors who initiated legal action for non-payment within the prescribed 30 days. All other provinces indicated “none” to the question posed by the Honourable member.

The Honourable Member should take note that I cannot provide much detail pertaining to these matters for the following reasons:

  1. Some of the matters are before courts the and therefore sub judice.
  2. The document titled “Guide to Parliamentary Questions in the National Assembly” prohibits Members of Parliament, including the Executive, from providing names when responding to parliamentary questions. The document referred to states that:

Questions are to be framed as concisely as possible. All unnecessary adjectives, references and quotations are omitted. Names of persons, bodies and, for example, newspapers are only used in questions if the facts surrounding the case have been proven. As the mere mention of such names could be construed as publicity for or against them, it should be clear that this practice is highly undesirable. If a question will be unintelligible without mentioning such names, the Departments concerned are notified of the name (-s) and this phrase is used: ".......a certain person (name furnished)”

In the tables below, please find information provided by the Eastern Cape and the Gauteng Province:

Eastern Cape

(a) The number of contractors who initiated legal action:

(d) current status of each contract (paid or not paid)

(i) Black

(ii) White

(iii) Female-owned contractors

 

The cases were mostly with subcontractors that have no direct contract with the Department of Human Settlements and therefore we do not have detailed information on them, including their BBEE Codes

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Matter finalized .Department ordered to pay the claim with interest and costs. The department settled the amount.

 

Department settled the amount as per court order. Contract ended 18 May 2017 and extension of time requested

 

Parties are exchanging pleadings.

Contract ended 23 March 2013

 

Matter pending before court. Parties are exchanging pleadings.

 

Matter pending before court. Parties are exchanging pleadings.

 

Matter still pending at court.

Contract extended up to 31st March 2018

 

Matter still pending at court.

The Extended contract ended 11 February 2016

Gauteng Province

(a) How many contractors initiated legal action:

(d) current status of each contract (paid or not paid)

(i) Black

(ii) White

(iii) Female-owned contractors

 

Black

 

Male

The matter is pending before a court of law

Black

 

Male

The matter is pending before a court of law

Black

 

Male

The matter is pending before a court of law

 

White

Female

The matter is pending before a court of law

Black

 

Male

The Department has received a letter from the company concerned informing the Department that it is withdrawing the case against the Department. We have requested it to request his attorneys to file a formal withdrawal notice in court. We will close the file once a formal withdrawal has been served to the Department

Black

 

Female

State Attorney was instructed to enter an appearance to defend as there is no contractual relationship between the Plaintiff and the Department.

Black

 

Male

The matter is pending before a court of law

 

White

Male

The matter is pending before a court of law

 

The Department has settled the outstanding amount and the Plaintiff has been requested to formally file a withdrawal Notice in court.

 

White

Male

The dispute related to the amount of claim for damages as a result of terminating the contract and interest for late payment of the capital amount.

The Department has since effected payment to settle the claim.

11 September 2017 - NW1881

Profile picture: Mokause, Ms MO

Mokause, Ms MO to ask the Minister of Human Settlements

Whether (a) her department and (b) each entity reporting to her appointed transaction advisors for tenders in the period 1 January 2012 to 31 December 2016; if so, (i) who were the transaction advisors that were appointed for the tenders, (ii) for which tenders were they appointed, (iii) what was the pricing for the tenders in question and (iv) what amount were the transaction advisors paid?

Reply:

(a) No Transaction Advisors were appointed by the National Department of Human Settlements for tenders between 1 January 2012 and 31 December 2016.

(b) Of the eight entities reporting to me, six entities indicated that they did not appoint Transaction Advisors for tenders in the period 1 January 2012 to 31 December 2016. The Housing Development Agency and the National Home Builders Registration Council advised that they did appoint Transaction Advisors as per the Honourable Member’s question. However, in accordance with the established practise applicable to parliamentary questions and guidelines contained in the document titled, “Guide to Parliamentary Questions in the National Assembly”, I will not provide names of the Transaction Advisors that the two entities appointed. The document referred to specifically states the following:

Questions are to be framed as concisely as possible. All unnecessary adjectives, references and quotations are omitted. Names of persons, bodies and, for example, newspapers are only used in questions if the facts surrounding the case have been proven. As the mere mention of such names could be construed as publicity for or against them, it should be clear that this practice is highly undesirable. If a question will be unintelligible without mentioning such names, the Departments concerned are notified of the name (-s) and this phrase is used: ".......a certain person (name furnished)”

The Housing Development Agency appointed two Transactions Advisors for tenders in the period 01 January 2012 to 31 December 2016.

(ii) (a) For the release of two inner city buildings for Human Settlements.

(b) For the Assessment of the Private Sector Human Settlements Projects.

(iii) (a) R478 122.00.

(b) R5 900 000.00.

(iv) The amounts were included as total values in (iii) above as the contracts were for the procurements of transaction advisors to assist with transaction advice on both the release of inner city buildings and assessment of Private Sector Human Settlements Projects.

The National Home Builders Registration Council has appointed three Transactions Advisors for tenders in the period 01 January 2012 to 31 December 2016.

(ii) (a) For the implementation of the SAP tender.

(b) For the leasing of two (02) mobile offices tender.

(c) For the provision of Human capital services tender.

(iii) (a) SAP tender was awarded at R73 754 352.00.

(b) Mobile offices tender was awarded at R11 080 800.00.

(c) Provision of human capital tender was awarded at R5 397 444.00.

(iv) (a) R134 250.00.

(b) R299 179.06.

(c) R22 550.00

11 September 2017 - NW2646

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

(1)Whether the National Home Builders Registration Council (NHBRC) consulted her about its Board's (a) intention and (b) ultimate decision to suspend its official (name and details furnished); if not, in each case, what is the position in this regard; if so, what was the outcome of the consultation(s); (2) did she approve NHBRC board's decision to appoint a certain person (name furnished) in the position of the specified official; if not, why not; if so, what were her reasons?

Reply:

(1) (a) & (b) No. The Council of the NHBRC took a decision to place the official referred to in the question on precautionary suspension pending the outcome of an investigation.

(2) Honourable Member, the Council has advised me that it has never taken a decision to appoint the gentlemen referred to in the question in any position.

05 September 2017 - NW2574

Profile picture: Mokause, Ms MO

Mokause, Ms MO to ask the Minister of Human Settlements

When are the application dates (a) opening and (b) closing for the board positions of all entities and councils reporting to her?

Reply:

I responded to a similar question from the Honourable Member on 30 June 2017 and indicated the terms of the Boards and Councils reporting to me. Please find enclosed a copy of the reply for ease of reference.

Currently, there are no new advertisements out for filling of any positions in Boards and Councils in my portfolio.

05 September 2017 - NW2468

Profile picture: Ndlozi, Dr MQ

Ndlozi, Dr MQ to ask the Minister of Human Settlements

Why was an RDP house not built for a certain person (name and details) living in Umlazi, South of Durban was after his shack was demolished, while houses were built on the sites next to the site that was allocated to him?

Reply:

Honourable Member, the Department could not find any information using the ID number provided and efforts to gain more information from your office failed.

I am therefore requesting that you provide me with further details so that we can make the necessary intervention and assist to resolve the matter.

Further, cases such as these should concern all of us as public representatives and our first instinct should be to assist. I hope the Honourable Member has, beyond asking the question, provided some assistance and advice on what the person referred to should do while this matter is being investigated.

29 August 2017 - NW1651

Profile picture: Waters, Mr M

Waters, Mr M to ask the Minister of Human Settlements (transferred from the Minister of Cooperative Governance and Traditional Affairs)

(1)What is the total number of houses that the Ekurhuleni Metropolitan Municipality built in the (a) 2014-15, (b) 2015-16 and (c) 2016-17 financial years; (2) (a) what is the total amount of money that was allocated to the specified municipality’s human settlements department and (b) of the specified allocation, what is the total amount that was not spent in each of the specified financial years?

Reply:

The information availed to me by the Ekurhuleni Metropolitan Municipality is provided in the tables below:

Fully Subsidised Individual Units Constructed

Financial Year

1) Number Of Houses Built

2(a) Allocation To The Human Settlements Department

Expenditure

2(b) Amount Not Spent

 

R’ 000

2014-15

1(a) 303

42 751

35 604

7 147

2015-16

1(b) 368

106 765

40 984

65 782

2016-17

1(c) 305

65 782

20 107

45 674

Affordable and Social Housing Rental Units Constructed

Financial Year

1) Number Of Houses Built

2 (a) Allocation To The Human Settlements Department

Expenditure

2 (b) Amount Not Spent

 

R’ 000

2014-15

1(a) Nil

-

-

-

2015-16

1(b) Nil

29 079

24 714

4 365

2016-17

1(c) 256

23 158

23 158

-

29 August 2017 - NW2070

Profile picture: Mokause, Ms MO

Mokause, Ms MO to ask the Minister of Human Settlements

Whether (a) her department and/or (b) any entities reporting to her are funding, including by way of discretionary funding, any institution of research and development (i) domestically and/or (ii) internationally; if so, (aa)(aaa) what are the names of the specified institutions and (bbb) what are their functions, (bb) from what date has her department or any entity reporting to her been funding them and (cc) what amount has her department contributed towards such funding?

Reply:

(a)(aa) In its endeavour to ensure the professionalization of the human settlements sector, the National Department of Human Settlements has partnered with the Nelson Mandela Metropolitan University (NMMU) and Mangosuthu University of Technology (MUT), to enhance the capacity of the sector to deliver sustainable human settlements. The department funded the establishment of the Chair for Education in Human Settlements Development Management at the Nelson Mandela Metropolitan University (NMMU) and the Chair for Research in Human Settlements at the Mangosuthu University of Technology (MUT)

The aforementioned Chairs established in the two universities are responsible for the following functions, amongst others:

  • Conducting of research in human settlements to inform policy and programmes development, as well as informing relevant solutions to deal with the housing challenge;
  • Development and teaching of human settlements qualifications to enhance the availability of requisite skills in the human settlements sector.
  • Providing a consultation service and advice to the Department in support of its capacity building and professionalization endeavours;
  • Providing training in the form of Short Learning Programmes, workshops and seminars, ensuring transfer of skills to public officials;
  • Conducting skills audits and analyses that align with the human settlements education and capacity development strategy of the Department; and
  • Providing solutions to problems faced by the government, CBOs, communities, and NGOs relating to human settlements.

Further, the National Department of Human Settlements has in February 2015 appointed the Council for Scientific and Industrial Research (CSIR) to revise and update the Guidelines for Human Settlements Planning and Design, commonly referred to as the Red Book. The guidelines review project is implemented over three years and is scheduled for completion by the end of the 2017/18 financial year.

The review was necessitated by substantial shifts in policy, priorities, values and the understanding of human settlements that have occurred globally as well as in South Africa in the 15 years since publication of the previous version of guidelines.

The purpose of the guidelines is to specify the Built Environment performance qualities that should be sought in South African settlements, and to provide practical guidance to users on how these qualities can be practically implemented to create sustainable human settlements.

(bb) The amount paid to the two universities are as tabulated below:

University

Period

Funding amount

Nelson Mandela Metropolitan University (NMMU)

2013/14 To 2015/16

R11, 538, 000, 00

Mangosuthu University Of Technology (MUT)

2016/17

R3, 500, 000, 00

Total Amount Paid To Universities

R15, 038, 000, 00

The total amount contracted for the revision of the guidelines, is R19 932 574.00 (Vat included) and is paid in tranches in line with quarterly deliverables. To date R10 702 775.74 has been transferred to the CSIR for work completed.

(b) Entities reporting to the Minister

Of the eight entities reporting to me, it is only the National Housing Finance Corporation that is funding an institution.

(bb) The details of the funding arrangements are provided below:

Domestically / Internationally

Name Of The Institution

Function

Date

Amount

(i) Domestically

Centre for Affordable Housing Finance in Africa (CAHF)

Strategic partnership with research specialist in the field of affordable housing to capacitate and strengthen research capability.

2014 - 2017

R3 424 243

(ii) Internationally

None

None

None

None

29 August 2017 - NW2034

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

(a)What total expenditure did each provincial department of human settlements incur on legal fees over (i) contractual disputes with contractors and (ii) labour disputes with departmental officials in the 2016-17 financial year and (b) what are the (i) full details and (ii) final outcomes in each case?

Reply:

The information provided by the provinces in response to the Honourable Member’s question is provided below:

Eastern Cape:

(i)Contractual Disputes With Contractors

Expenditure Incurred on Legal Fees

(i)Contractual Disputes With Contractors

Final Outcomes In Each Case

(ii) Labour Disputes With Departmental Officials In 2016/17 Financial Year

(i) Full Details

(ii) Final Outcomes In Each Case

1 105 773

The dispute was about the services rendered.

The Department settled the amount as per court order and the matter has been finalized.

value of R276159.00

Unfair Dismissal

Case was dismissed in favour of the employer

490 530

Plaintiff claimed after rendering services to the Department without a valid extension to the agreement with the Department on the Mayfield Phase 2 project.

The Department settled the amount as per court order. The contract ended 18 May 2017 and extension of time was requested

value of R33832.80

Unfair Dismissal

Case in progress

955 737

Plaintiff is suing the Department for professional services rendered on the Motherwell project. Plaintiff left site but claimed to be paid for services rendered as it is claimed that they suspended services due to the conduct of the Department and therefore be paid for the time they could have spent on the project.

The parties are exchanging pleadings. The contract ended 23 March 2013

-

-

-

2 280 301

The contractor is suing the Department for work done and completed in terms of a cession entered into with a contractor, contracted to the Department on the Lubala 94 project.

Matter pending before court.

-

-

-

400 338

The contractor is suing the Department for services rendered on the Gardening and Greening project. There is a dispute on the value of the services rendered and the contractor has failed to submit documentation proving their claim.

The matter is pending before court.

-

-

-

4 287 111

The dispute was about the installation of services in the Bethelsdorp Phase C project.

But the matter has been finalised and the department settled.

The contract extended up to 31st March 2018

-

-

-

147 247

The Department entered into an agreement with the contractor for construction services on the All Saints 700 Inkwenkwezi Project. The contractor contracted a number of subcontractors in the project without the knowledge of the Department.

The claim is a dispute for non-payment of the subcontractors.

The matter still in court.

An extended contract ended 11 February 2016

-

-

-

Free State:

(I)Contractual Disputes With Contractors

(Ii) Labour Disputes With Departmental Officials In 2016/17 Financial Year

(I) Full Details

(Ii) Final Outcomes In Each Case

Contractor vs the provincial Department of Human Settlements

 None

Dispute is as a result of a breach of contract by the Contractor that led to the Department terminating the contract for poor performance and poor workmanship.

A plea has been filled and the case is pending in court.

Contractor vs the provincial Department of Human Settlements

 

Matter is a contractual dispute over a cession agreement that the parties cancelled.

Province has filed a plea and the matter is set down for trial for the 21, 22 and 24th November 2017.

Contractor vs the provincial Department of Human Settlements

 

Dispute arose as a result of a breach of contract by the Contractor, which led to the Department terminating the contract, based on failure to perform in terms of the contract.

Case was withdrawn by the Applicant.

Total Legal Costs Paid during 2016/17 financial year is R 164 487.00.

 

 

Mpumalanga Province

Expenditure Incurred On Legal Fees

(i)Contractual Disputes with contractors

Final Outcomes In Each Case

(ii) Labour Disputes With Departmental Officials In 2016/17 Financial Year

(i)Full Details

(ii) Final Outcomes In Each Case

R926 216.47

The Attorneys were appointed to represent the Department against matters involving four contractors.

 Two matters are still being processed and the other two have been finalised

R407 586.00

 

 

 

The matter is between the Department and two employees

Both matters are still being processed

North West

(i)Contractual Disputes with contractors

(ii) Labour disputes with departmental officials in 2016/17 financial year

(i) Full details

(ii) Final outcomes in each case

N/A

The Department of Local Government and Human Settlements in North West and an employee

The case is about a nullified appointment

The matter is still before the labour court

N/A

The Department of Local Government and Human Settlements in North West and an employee

Unfair dismissal claim

The matter is still before the labour court

N/A

The Department of Local Government and Human Settlements in North West and an employee

Level of grading dispute in terms of Resolution 3 of 1999

The matter is still before the labour court

N/A

The Department of Local Government and Human Settlements in North West and an employee

Unfair dismissal claim

The matter is still before the labour court

KwaZulu-Natal

(a)(i) None

(ii)None

(b)(i)None

(ii)None

Limpopo Province

(a)(i) None

(ii)None

(b)(i)None

(ii)None

Northern Cape

(a)(i) None

(ii)None

(b)(i)None

(ii)None

Western Cape

(a)(i) None

(ii)None

(b)(i)None

(ii)None

Gauteng Province

The information is being collated and it will be provided once the process has been finalised.

20 July 2017 - NW1982

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

What is the average number of years that persons (a) under the age of 40 years and (b) over the age of 40 years have to be on the waiting list for Government-subsidised houses?

Reply:

Our policy does not prescribe a minimum waiting period as per the honourable member’s question because the allocation of a house to a qualifying beneficiary depends primarily on the completion of a housing project. However, our National Housing Needs Register indicates that the waiting period in the past fluctuated between 6 to 11 years on average. I am confident that as provinces and municipalities continue to improve the planning and packaging of projects, the waiting period will be minimised.

Further, this is one of the reasons that, during my budget vote speech on 18 May 2017, I indicated that the one-track system of building is no longer sustainable. We need to adopt a multi-pronged approach together with provinces and municipalities because time is not on our side. We are now concentrating on servicing sites and partitioning them so that people can build their own houses through a monitored PHP programme.

30 June 2017 - NW1724

Profile picture: Kalyan, Ms SV

Kalyan, Ms SV to ask the Minister of Human Settlements

Whether any staff of (a) her department and (b) each entity reporting to her were awarded any contracts or agreements to conduct business with any state entity in the (i) 2014-15, (ii) 2015-16 and (iii) 2016-17 financial years; if so, what are the (aa)(aaa) names and (bbb) professional designations of the staff members and (bb)(aaa) details of the contract(s) and/or agreement(s) awarded and (bbb) amounts in each case?

Reply:

(a) No.

(b) All eight entities reporting to me confirmed that they had not awarded any contracts or agreements to any staff members to conduct business with any state entity in the (i) 2014-15, (ii) 2015-16 and (iii) 2016-17 financial years.

30 June 2017 - NW1759

Profile picture: Matsepe, Mr CD

Matsepe, Mr CD to ask the Minister of Human Settlements

Does (a) she, (b) her Deputy Minister or (c) any of the heads of entities or bodies reporting to her make use of security services paid for by the State for (i) him/herself, (ii) his/her immediate family members or (iii) any of their staff members; in each case (aa) what are the reasons for it, (bb) from which department or entity’s budget is the security services being paid, and (cc) what are the relevant details?

Reply:

The Deputy Minster and I, including our families, do not use any security services paid for by the State. Needless to say, both of us use the VIP Protection Services provided by the Department of Police.

The entities reporting to me confirmed that none of them use and pay for security services from State funds.

 

 

30 June 2017 - NW1792

Profile picture: Mokause, Ms MO

Mokause, Ms MO to ask the Minister of Human Settlements

(1)Which entities reporting to her (a) have a board in place and (b) do not have a board in place, (i) of those that have a board, (aa) when was each individual board member appointed and (bb) when is the term for each board lapsing and (ii) how many (aa) board members are there in each board and (bb) of those board members of each entity are female; (2) with reference to entities that do not have boards in place, (a) who is responsible for appointing the board and (b) when will a board be appointed?

Reply:

The information requested by the Honourable Member is provided in the table below:

Entity

Board or Council composition

Appointment date

Expiry date

Person responsible for appointment

The Community Schemes Ombud Service (SCOS)

The Board has two (2) executive members (CEO & CFO) and seven (7) non-executive members.

There are four (4) females currently on the CSOS Board.

1 January 2016

31 December 2018

The Executive

Estate Agency Affairs Board

The Board has fifteen (15) members.

There are seven (7) females currently on the EAAB Board.

6 July 2016

5 July 2019

The Executive

The Housing Development Agency

The Board consists of two (2) executive members (CEO & CFO) and seven (7) non-executive members.

There are two (2) females currently on the Board.

4 Nov 2015

3 Nov 2018

The Executive

Human Settlements Development Bank/NHFC

There are eleven Board members

There are currently three (3) females on the Board.

24 November 2016

October 2019

The Executive

National Home Builders Registration Council

The Council consists of thirteen (13) members.

There are five (5) females currently on the Council.

1 August 2015

31 July 2018

The Executive

Social Housing Regulatory Authority

The Council consists of Twelve (12) members.

There are Five (5) females currently on the Council.

18 March 2015

17 March 2018

The Executive

 

30 June 2017 - NW1109

Profile picture: Bara, Mr M R

Bara, Mr M R to ask the Minister of Human Settlements

What (a) amount was spent by her department on e-government services in the 2016-17 financial year and (b) is the projected expenditure for the 2017-18 financial year?

Reply:

(a) The Department spent an amount of R49.3 million in the 2016-17 financial year on e- government services.

(b) The approved budget for the 2017/18 financial year is R52.7 million.

30 June 2017 - NW1314

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

(a) What number of supplier invoices of each provincial department of human settlements currently remain unpaid for more than 30 days and (b) in each case, what (i) is the name of the company and/or supplier, (ii) amounts are outstanding, (iii) is the reason for nonpayment and (iv) is the envisaged date on which the amounts will be paid?

Reply:

Honourable Member, we are grappling with the issue of the paying supplier invoices within 30 days, it is a standard item on the agenda of MinMEC. The challenges remain and they are multi-faceted. The reasons provided by provinces for the late payment vary from late submission of invoices to verification of information pertaining to those invoices. Sometimes the required details for new suppliers are not always available in the financial system to facilitate payments due to inadequate completion of registration forms by suppliers.

With respect to the provision of names of suppliers or companies, the Honourable Members is referred to the established practise applicable to parliamentary questions and guidelines contained in the document titled, “Guide to Parliamentary Questions in the National Assembly”. The document referred to prohibits Members of Parliament, including the Executive, from divulging names of persons, bodies when asking or responding to parliamentary questions. Accordingly, I will not provide names of the companies and/or suppliers whose invoices were not paid within the 30 days. The document referred to states the following:

Questions are to be framed as concisely as possible. All unnecessary adjectives, references and quotations are omitted. Names of persons, bodies and, for example, newspapers are only used in questions if the facts surrounding the case have been proven. As the mere mention of such names could be construed as publicity for or against them, it should be clear that this practice is highly undesirable. If a question will be unintelligible without mentioning such names, the Departments concerned are notified of the name (-s) and this phrase is used: ".......a certain person (name furnished)”

The information received from provinces is provided below:

Eastern Cape Province

(a) 184 invoices remain unpaid by Eastern Cape Province.

(b) (ii) The amounts outstanding are included in the table below.

(b)(i) SUPPLIER

(ii) AMOUNTS OUTSTANDING

 

R’000

TOTAL

176 564 089

(iii) The Eastern Cape Province reported the reason for the non-payment as being the shrinkage of the equitable share over commitments and top slicing at the beginning of the financial year as well as the first tranche of the grant which was not enough to pay all the contractors.

(iv) The Eastern Cape Province is attending to its cash flow problems and it is hoped that this matter will be resolved soon.

Free State

  1. 227 invoices remain unpaid by the Free State Province
  2. (ii) The amounts outstanding are included in the table below:

(b)(i) SUPPLIER

(ii) AMOUNTS OUTSTANDING

 

R’000

TOTAL

122 196 958

 

(b)(iii) The Free State Province reported the reason for non-payment as due to insufficient funds being available for fund commitments.

(b)(iv)The Free State Department of Human Settlements has commenced honouring these claims in the 2017/2018 financial year as funding is disbursed from the National Department of Human Settlements. As at 24 May 2017 an amount of R46 million was still outstanding for payment which will be settled soon.

Gauteng Province

  1. 824 invoices remain unpaid by the Free State province
  2. (ii) The amounts outstanding are included in the table below:

(b)(i) SUPPLIER

(ii) AMOUNTS OUTSTANDING

 

R’000

TOTAL

597 600 355.14

(b)(iii) The Gauteng Department advised that it could not make payments linked to the Human Settlements Development Conditional Grants (HSDG) as from 1st April 2017 until Mid-May 2017, mainly because the first payment tranche for the 2017/18 financial year was transferred in late May from National department of Human Settlements. The reason for the late transfer of the first tranche is that the business plan was not able to be approved by the National Department, due to non-compliance and the Division of Revenue Act, which prohibits the transfer of funds before approval of the business plan.

(b)(iv) The Gauteng Department of Human Settlements plans to pay the outstanding invoices within the month of June.

KwaZulu-Natal

  1. The province did not have any invoices that were unpaid for more than 30 days.

Limpopo Province

  1. 3 invoices remain unpaid by the Limpopo province
  2. (ii) The amounts outstanding are included in the table below:

(b)(i) SUPPLIER

(ii) AMOUNTS OUTSTANDING

 

R’000

TOTAL

529 631.83

(iii) Limpopo advised that one invoice was returned on the 19/04/2017 because of a negative amount on the budget line item and the other two were returned to the end-user as a result of a court order.

 
 

(b)(iv) Not specified.

 

Mpumalanga Province

  1. 7 invoices remain unpaid by the Mpumalanga province
  2. (ii) and (iii) The amounts outstanding and reasons for non-payments are included in the table below:

(b)(i) SUPPLIER

(ii) AMOUNTS OUTSTANDING

 

R’000

TOTAL

4 499 193.00

(iii) Mpumalanga reasons for non-payment within 30 days include:

  1. Delay by the contractor in registering with CSD. CSD finalized on 19/05/2017 by the contractor and the account will now be linked with Logis. A call was logged with Provincial Treasury in this regard;
  1. The Bank account details submitted to the Department did not agree with CSD.

(iv) The invoices will be paid when all outstanding issues have been resolved.

Northern Cape

  1. The province did not have any invoices that were unpaid for more than 30 days.

North West

  1. 50 invoices remain unpaid by the North west province
  2. (ii) The amounts outstanding are indicated below:

(b)(i) SUPPLIER

(ii) AMOUNTS OUTSTANDING

 

R’000

TOTAL

5 756 280.05

(b)(iii) The Province reported the reason for non-payment as being the error in capturing of invoices which reflected as unpaid instead of being updated on the system as they were paid.

Western Cape

  1. The Province did not have any invoices that were unpaid for more than 30 days.