Questions and Replies

Filter by year

11 December 2017 - NW2848

Profile picture: Mokgalapa, Mr S

Mokgalapa, Mr S to ask the Mr S Mokgalapa (DA) to ask Minister of International Relations and Cooperation

1)Wether her Department has decided how it will facilitate prison exchange programmes; If not, why not; if so what are the relevant details (2)Wether she will make a statement on the details of the meeting held in Gaborone, Republic of Botswana, to discuss the specified programmes?

Reply:

(1)The mandate of concluding Prisoner Transfer Agreements is vested with the Department of Correctional Services.

(2)The Department is not aware of such a meeting. The question should be directed to the Department of Correctional Services.

UNQUOTE

11 December 2017 - NW3359

Profile picture: Lees, Mr RA

Lees, Mr RA to ask the Minister of Finance

(1)What are the details of all passengers who were prevented from boarding SA Airways (SAA) flights from Munich to Johannesburg on (a) 22 July, (b) 23 July and (c) 24 July 2017; (2) whether the specified passengers received any form of compensation for being prevented from boarding the specified flights; if not, why not; if so, what amount in compensation was awarded to each passenger; (3) whether all affected passengers received the compensation immediately in Munich; if not, what are the relevant details of the payment arrangements; (4) whether all affected passengers have received compensation; if not, (a) why have compensation payments not been made to all affected passengers, (b) by which date will payments be made and (c) how will payments be made?

Reply:

1. Refer Annexure A.

2. Yes. All passengers received EUR600 in form of vouchers as per EU regulations. In addition they were accommodated in hotels and provided with meal vouchers.

3. Yes. The vouchers were handed over to the passengers in Munich.

4. Yes. All affected passengers received compensations in the form of vouchers for EUR600.

11 December 2017 - NW2828

Profile picture: America, Mr D

America, Mr D to ask the Minister of Health

(1) What is the backlog in (a) postmortem reports, (b) toxicology reports and (c) blood-alcohol test samples in laboratories administered by his department in each province (i) in the 2016-17 financial year and (ii) since 1 April 2017; (2) what are the challenges experienced by his department in eliminating the specified backlog; (3) what steps has his department taken to address the challenges experienced?

Reply:

(1) (a), (b), (c) The Department of Health has four (4) Forensic Chemistry Laboratories in the whole country and these are not necessarily distributed Provincially and hence I cannot give you any provincial figures.

(i) and (ii) Please see above

(2) The challenges in the Forensic Chemistry Laboratories relate to high volumes of samples received for blood alcohol for drunken driving which increases the workload. These high volumes in blood alcohol sample were received in the 2016/17 and the first five months of 2017/18.

(3) The Department has purchased additional equipment to deal with the blood alcohol volumes.

Secondly samples are distributed across the four (4) FCLs.

Overtime work is also implemented to assist in decreasing the backlog.

Finally, the real solution is to reduce the high incidence of drunken driving in our roads.

END.

11 December 2017 - NW3309

Profile picture: Mkhaliphi, Ms HO

Mkhaliphi, Ms HO to ask the Minister of Home Affairs

Whether the (a) chief executive officer and (b) chief financial officer of entities reporting to her are employed on a permanent basis; if not, (2) Whether the specified officers are employed on a fixed term contract; if so, (a) what are the names of each of the officers and (b) when (i) was each officer employed and (ii) will each officer’s contract end?

Reply:

Electoral Commission

CEO

(1)(a) Yes.

(2)(a) The Chief Electoral Officer is Mr Simon Phatudi Mamabolo.

(2)(b)(i) He was appointed on 1 October 2017.

(2)(b)(ii) His term ends on September 2022.

CFO

(1)(b) The Chief Financial Officer position is currently vacant.

(2)(a) Not applicable

(2)(b)(i-ii) Not applicable

Government Printing Works

CEO

(1)(a) Not applicable. The post of Chief Executive Officer of GPW is vacant and has been advertised on 16 October 2017.

(2)(a) Ms Thandi Moyo who is the General Manager: Special Projects at GPW is acting in the position until the post is filled.

(2)(i) Not applicable.

(2)(ii) Not applicable.

CFO

(1)(b) Yes.

(2)(a) The Chief Financial Officer is Ms Josephine Meyer.

(2)(b)(i) She was appointed on 1 April 2017.

(2)(b)(ii) Not applicable.

11 December 2017 - NW2849

Profile picture: Mokgalapa, Mr S

Mokgalapa, Mr S to ask the Minister of International Relations and Cooperation

(1)Wether she will provide details of a certain prisoner (name furnished) who is being held in Malaysia, and (2) At what stage are the prisoner transfer agreements?

Reply:

(1)The Department has not been authorised by the prisoner to divulge information on her case.

(2)The mandate of concluding Prisoner Transfer Agreements is vested with the Department of Correctional Services.The Department of International Relations and Cooperation is not aware of any Prisoner Transfer Agreement(and programmes) that has been concluded with any country or countries.

UNQUOTE

11 December 2017 - NW3930

Profile picture: Moteka, Mr PG

Moteka, Mr PG to ask the Minister of Health

Whether he has been informed of the arbitration hearings between employees of his department, his department’s Labour Relations Committee and a Commissioner of the Bargaining Council on 22 November 2017; if so, what was the outcome of the specified hearings?

Reply:

I am aware of the arbitration hearings between employees of the Department, the Department's Labour Relations Committee and a Commissioner of the Bargaining Council. The parties to the arbitration are still awaiting the outcome of the Comissioner.

END.

11 December 2017 - NW2573

Profile picture: Mkhaliphi, Ms HO

Mkhaliphi, Ms HO to ask the MINISTER OF INTERNATIONAL RELATIONS AND COOPERATION

When are the application dates? (a) Opening and (b) Closing for the board positions of all entities and councils reporting to her?

Reply:

(a) and (b) There are no application since the African Renaissance and International Cooperation Fund (ARF) does not have a board. However, in terms of the ARF Act 51 of 2000, Section 5. (1) it states that “the Minister must, in consultation with the Minister of Finance, establish an Advisory Committee consisting of the following members—

(a) the Director-General or the delegate of the Director-General;

(b) three officers of the Department appointed by the Minister; and

(c) two officers of the Department of Finance appointed by the Minister of Finance”.

 

UNQUOTE

11 December 2017 - NW3929

Profile picture: Ketabahle, Ms V

Ketabahle, Ms V to ask the Minister of Health

Does each province have the necessary structured plan and budget to support the roll-out of the National Health Insurance scheme?

Reply:

The NHI Bill is still to go to Parliament and be passed into a law first before budget plans per province can be entertained.

END.

11 December 2017 - NW1839

Profile picture: Carter, Ms D

Carter, Ms D to ask the Minister of Health

With reference to the reports indicating (a) a catastrophic collapse of oncology services in the state hospital system in KwaZulu-Natal, (b) that there are currently no oncologists in the employ of the state in the Durban area to service the Addington and Albert Luthuli Hospitals and (c) that there are only two remaining oncologists in the employ of the state in Pietermaritzburg, servicing Grey’s Hospital, which amount to a human rights violation, what (i) are the root causes of this unacceptable situation, (ii) steps has the KwaZulu-Natal Department of Health taken to arrest and turn this situation around and (iii) actions and interventions does his department intend to take in this regard?

Reply:

(a) The breakdown of the linear accelerator at Addington Hospital resulted from lack of maintenance following a dispute between the suppliers and the KZN Department of Health. This has resulted in the province contracting a new service provider to maintain the equipment which from all accounts they failed to do. All oncologists that worked at Addington Hospitals were transferred to work in Inkosi Albert Luthuli Hospital. This also meant that all patients that required radiation in the eThekwini district were referred to Inkosi Albert Luthuli Hospital. It appears that the perceived additional workload at Inkosi Albert Luthuli Hospital contributed to the oncologists resigning.

(b) The Department is in the process of finalising a service level agreement with the supplier of the linear accelerator that requires significant repairs.

The KZN Department of Health has issued a tender to contract private oncologists to work in the public sector. This tender closes on 14 December 2017. In addition, the Department has recently requested the National Department of Health for assistance to recruit English speaking foreign oncologists who are eligible for registration with the Health Professions Council of South Africa.

(c) The National Department of Health has:

  1. Placed an order for a new linear accelerator to replace one of those in Addington Hospital; the service provider will also address infrastructure issues related to the bunker, including air-conditioning and leaks.
  2. Concluded a benchmarking exercise to assist the KZN Department of Health to evaluate the bids received against the tender referred to above.
  3. Commenced with a search for foreign qualified oncologists as a short term measure
  4. Developed a national plan for radiation oncology that was approved by the National Health Council on 7 December 2017 – given that the need to strengthen radiation oncology services throughout the country and in anticipation of increased need for these services over the next 5-10 years.

END.

11 December 2017 - NW4013

Profile picture: Motau, Mr SC

Motau, Mr SC to ask the Minister of Environmental Affairs

(1)Which part of the Richtersveld coast line in the Northern Cape is considered to be the admiralty strip; (2) did the area of this strip change after the promulgation of the National Environmental Management: Integrated Coastal Management Act, 2008 (Act No. 24 of 2008); if so, what are the relevant details; and (3) whether the Richtersveld community owns the admiralty strip; if not, who owns the strip; if so, what are the geographical details of the admiralty strip?

Reply:

(1) The Admiralty Reserve forms part of the range of zones that describe the coast along with the seashore, coastal waters and coastal buffer zone. It is generally described as a strip of land between 150 to 200 feet (45m to 60m) wide, inland of the high water mark. The Richtersveld coastline in the Northern Cape has no admiralty strip reserved, registered or designated on an official plan deed of grant, tittle deed or other documents evidencing title or land-use right.

(2) The Richtersveld coastline in the Northern Cape has no admiralty strips reserved. The National Environmental Management: Integrated Coastal Management Act, 2008 (Act No. 24 of 2008) does not intend changing any area or status of any strip that exists as admiralty reserve. The Act has a huge influence in how properties adjacent and in proximity of the coast are managed or supposed to be managed.

(3) All admiralty reserves are state land and falls under the custodianship of the National Department of Public Works.

---ooOoo---

11 December 2017 - NW3502

Profile picture: Ryder, Mr D

Ryder, Mr D to ask the Minister of Home Affairs

Why is it not possible to gain access to her department’s offices in Vereeniging in Gauteng after 15:30 when the advertised office hours are 08:00 to 16:00 on weekdays; (2) Whether access is denied after 15:30 to ensure that staff do not remain in the offices after 16:00; if so, is this in line with departmental policy?

Reply:

1. Access to the department’s offices in Vereeniging is possible after 15:30 on weekdays until 16:00.

2. Access is not denied. However access may be controlled after 15:30 in the event where queues are long, to ensure that officials can assist the remaining clients that are inside the office until 16:00 and furthermore, to enable officials to knock off at 16:00 as per departmental policy. Employees work 8 hours per day, from 07:30 to 16:00, totalling 40 hours per week, excluding meal intervals. The needs of the Public are considered, and therefore queues are managed and clients that are in the office are served until 16:00.

11 December 2017 - NW3797

Profile picture: Hoosen, Mr MH

Hoosen, Mr MH to ask the Minister of Home Affairs

What is the current arrangement between (a) her department, (b) the National Treasury and (c) the Auditor-General in terms of resolving the (i) immigration control account and (ii) outstanding repatriation deposits?

Reply:

(a-c)(i-ii) Further to the promulgation of the Immigration Regulation during 2014, which changed the collection of repatriation deposits from travellers to RSA, the Department approached National Treasury requesting it to allow the Department to recognise all unclaimed repatriation deposits as revenue in its financial statements, to surrender all unclaimed repatriation deposits to the National Revenue Fund (NRF) and to close the Immigration Control Account.

In order to address the concerns raised by Auditor General in this regard, the Department issued a Government Gazette notifying all travellers that they will forfeit their repatriation deposits if not claimed by 31 March 2016. During the 2015/16 and 2016/17 financial years, the Department performed a reconciliation of the Immigration Control Account and paid over R441, 773 million to the NRF, R69 million to DIRCO and R8,5 million to qualifying travellers. This left the Immigration Control Account with a balance of R2,172 million as at 31 March 2017 – this amount constitutes refunds (un-cashed cheques) due to qualifying travellers.

Based on the above background that outlines the arrangement with National Treasury and the Auditor General, the Immigration Control Account is closed and all unclaimed repatriation deposits are forfeited and surrendered to the NRF.

11 December 2017 - NW3490

Profile picture: Carter, Ms D

Carter, Ms D to ask the Minister of Health

Whether his department has considered using a device researched and manufactured by a certain company (name furnished) which detects biomarkers found in human tears (details furnished); if not, why not; if so, what are the relevant details?

Reply:

No. The Department of Health is dedicated to implementing the latest available technology to diagnose breast cancers. However the technology using human tears is still being researched and is not available for clinical use.

END.

11 December 2017 - NW2960

Profile picture: Robertson, Mr K

Robertson, Mr K to ask the Minister of Health

(1)What (a) total amount of budget was allocated for the construction of the Nhlazatshe 6 CHC community clinic in the Chief Albert Luthuli Local Municipality in Mpumalanga, (b) are the full details of how the project is being funded, (c) amount of the specified budget has been spent to date and (d) is the current status of the construction of the specified clinic; (2) (a) what are the (i) names and (ii) contact details of each contractor appointed to construct the specified clinic and (b) have all contractors been paid in full in accordance with the completed phases to date; (3) by what date will the (a) construction of the clinic be completed and (b) specified clinic be fully operational?

Reply:

(1) (a) R44 million.

(b) The project is funded from a special In-kind grant.

(c) Only fencing and consulting fees have been paid up to date, to the amount of R1,493,136.00.

(d) A contractor has been appointed and has already received a letter of award.

(2) (a) (i) and (ii) Names and details of contractors:

LDM Consulting (Pty) Ltd

21 West Riding Row, Sherwood, Durban, 4091

Tel: 031 207 1340

Fax: 031 209 9441

Email: [email protected];

Mpfumelelo Business Enterprise (Pty) Ltd; and

21 Norwin Street, White River, Mpumalanga, 1200

Tel: 013 751 3381

Fax: 013 751 2498

Email: [email protected]

Central Bridge Trading 109.

48 Bester Street, Nelspruit, 1200

Tel: 013 755 1133

Fax: 086 501 2531

Email: [email protected]

(b) Yes. Currently all payments have been made to the service provider and contractor. LDM Consulting (Pty) Ltd has been appointed for the total life cycle of the project, hence the contract has not been concluded with LDM. As the Project Manager/Principal Agent, LDM was appointed to manage the construction of the Clinic. Only the fencing contract was concluded and the main contract for the construction of the Clinic will commence in January 2018 after the builders' break.

(3) (a) and (b) The construction and commissioning will be concluded within 24 months from start to finish. Site hand-over to the contractor was done in November 2017. Construction will commence in January 2018. The construction period is 18 months plus an additional 6 months for the installation of Health Technology equipment and commissioning.

END.

11 December 2017 - NW3745

Profile picture: Xalisa, Mr Z R

Xalisa, Mr Z R to ask the Minister of Environmental Affairs

(1)Whether (a) her department and/or (b) entities reporting to her procured services from a certain company (name furnished); if so, (i) what services were procured in each case and (ii) what is the total amount that was paid to the specified company in each case; (2) whether the specified company provided services related to international travel to (a) her department and/or (b) entities reporting to her; if so, (i) what is the name of each person who travelled, (ii) what was the travel route and (iii) what is the total amount that was paid for each person?

Reply:

The services that my Department and its entities procure from any service provider, be it in the sphere of travel management and or accomodation, are services that are always awarded after a fair, equitable, transparent, competitive and cost-effective bid process in line with Section 38 (1) (a) (iii) of the Public Finance Management Act. Such procurement processes are administered by the Department’s Bid Evaluation Committee in terms of the same Act.

All procurement procedures and processes are audited annually and the information pertaining to the audit opinion on these matters is reflected in the relevant annual reports which are readily available as public documents.

--ooOoo---

11 December 2017 - NW3926

Profile picture: Thembekwayo, Dr S

Thembekwayo, Dr S to ask the Minister of Health

Whether he informed the Member of the Executive Council responsible for health in Gauteng of his decision to transfer 160 employees from the payroll of the national Department of Health to that of the Gauteng provincial department in October 2016?

Reply:

I never took any decision to transfer 160 employees from the payroll of the National Department of Health to that of the Gauteng Department of Health.

END.

11 December 2017 - NW3925

Profile picture: Thembekwayo, Dr S

Thembekwayo, Dr S to ask the Minister of Health

In which sections of the National Health Insurance Project in Gauteng were some of the 160 interns employed who were transferred from the national Department of Health to the Gauteng Provincial Department of Health?

Reply:

May the Honourable Member please clarify which interns are being referred to. Are you referring to medical interns or any other graduate who was placed in the Department of Health for internship purposes? Please specify that so that I might be able to answer you. I am otherwise unable to relate to an issue of just 160 interns.

END.

11 December 2017 - NW2163

Profile picture: Kopane, Ms SP

Kopane, Ms SP to ask the Minister of Health

(a) How many public (i) hospitals and (ii) clinics do not have running water currently and (b) will he provide Ms S P Kopane with a list of the specified hospitals and clinics?

Reply:

(a) and (b) All our health facilities do have running water supply systems.

However, sometimes there may be some interruption due to drought, maintenance work on the system or shortage from the main source of supply, for example, a dried borehole or very low dam levels. It may also happen if there are local government problems in that municipality.

In such cases arrangements are made at facility level with the relevant municipality to cart water to such a facility until the problem is solved.

Jojo water tanks are also installed in many clinics and CHCs to harvest rain water and utilise in case of emergencies.

END.

11 December 2017 - NW3706

Profile picture: Waters, Mr M

Waters, Mr M to ask the Minister of Home Affairs

Does the Independent Electoral Commission intend to purchase new (a) software and/or (b) hardware during the current financial year; if so, (i) what is the purpose of each purchase, (ii) which company has been awarded each contract, (iii) what is the total monetary value of each contract, (iv) in which country is each contractor based and (v) what is the total price of each tender that won the contract?

Reply:

(a) Yes. The present operating system is out of date and thus not subject to maintenance support and also outside Original Equipment Manufacturers (OEMs) maintenance and support. The absence of maintenance and support will negatively impact on the reliability and performance stability of operating environment and systems, and also render our network security vulnerable. The upgrade of our Operating System (OS) necessitated the upgrade of all applications systems in the environment to ensure software compatibility and integration including access to new patches, bug fixes and security enhancements.

(a)(i-v) The information on the software are tabulated in the Annexure A attached.

(b) Yes. The present ICT hardware infrastructure (i.e. servers, backup devices, switches, printers, etc.) is out of date and thus not subject to maintenance support, most of the hardware is older than 10 years and also outside Original Equipment Manufacturers (OEMs) maintenance support and availability of spare parts. The absence of maintenance, support and spare parts will negatively impact on the reliability and performance stability our ICT infrastructure and render our network security vulnerable.

(a)(i-v) The details of the hardware are tabulated in the Annexure B attached.

ANNEXURE A : SOFTWARE

 

Procurement Items

(i) what is the purpose of each purchase

(ii) which company has been awarded each contract

(iii) what is the total monetary value of each contract

(iv) in which country is each contractor based

(v) what is the total price of each tender that won the contract?

1. Enterprise Network Monitoring Solution

Upgrade enterprise network monitoring and replace current solution which is inadequate

Not determined yet, still subject to the outcome of procurement processes

Not determined yet, still subject to the outcome of procurement processes

Not established yet, still subject to the outcome of procurement processes. However, we always procure from local South African suppliers

The monetary value is not determined yet, still subject to the outcome of procurement processes

2. Network Access Management solution

Improve network security through an integrated network access control solution (NAC)

Not determined yet, still subject to the outcome of procurement processes

Not determined yet, still subject to the outcome of procurement processes

Not established yet, still subject to the outcome of procurement processes. However, we always procure from local South African suppliers

The monetary value is not determined yet, still subject to the outcome of procurement processes

3. Mobile Device Management Solution

Software solution to enable control and secure access to mobile devices and deliver services securely and

manage data on mobile devices.

Not determined yet, still subject to the outcome of procurement processes

Not determined yet, still subject to the outcome of procurement processes

Not established yet, still subject to the outcome of procurement processes. However, we always procure from local South African suppliers

The monetary value is not determined yet, still subject to the outcome of procurement processes

4. Vmware

Procure additional VMware licences to increase virtualisation capacity

Not determined yet, still subject to the outcome of procurement processes

Not determined yet, still subject to the outcome of procurement processes

Not established yet, still subject to the outcome of procurement processes. However, we always procure from local South African suppliers

The monetary value is not determined yet, still subject to the outcome of procurement processes

5. Identity Management Solution

Strengthen security and access control through a modern integrated identity management solution

Not determined yet, still subject to the outcome of procurement processes

Not determined yet, still subject to the outcome of procurement processes

Not established yet, still subject to the outcome of procurement processes. However, we always procure from local South African suppliers

The monetary value is not determined yet, still subject to the outcome of procurement processes

6. Security information and event management (SIEM)

Improve network and information security by replacing current solution which has reached end of life.

Not determined yet, still subject to the outcome of procurement processes

Not determined yet, still subject to the outcome of procurement processes

Not established yet, still subject to the outcome of procurement processes. However, we always procure from local South African suppliers

The monetary value is not determined yet, still subject to the outcome of procurement processes

ANNEXURE B: HARDWARE

 

Procurement Items

(i) what is the purpose of each purchase

(ii) which company has been awarded each contract

(iii) what is the total monetary value of each contract

(iv) in which country is each contractor based

(v) what is the total price of each tender that won the contract?

1. Servers

Replacing datacentre servers which are more than 10 years old, and out of maintenance support.

Not determined yet, still subject to the outcome of procurement processes

Not established yet, subject to market conditions, budgetary figure of

R20 660 000,00

Not established yet, still subject to the outcome of procurement processes. However, we always procure from local South African suppliers

The monetary value is not determined yet, still subject to the outcome of procurement processes

2. Provincial backup devices

Replacing backup devices at provincial offices which are too old, and out of maintenance support.

Not determined yet, still subject to the outcome of procurement processes

Not established yet, subject to market conditions, budgetary figure of

R2 800 000,00

Not established yet, still subject to the outcome of procurement processes. However, we always procure from local South African suppliers

The monetary value is not determined yet, still subject to the outcome of procurement processes

3. Wide Format Lazer printers

Replacing plotters and wide format lazer printers which are too old, and out of maintenance support.

Not determined yet, still subject to the outcome of procurement processes

Not established yet, subject to market conditions, budgetary figure of

R1 500 000,00

Not established yet, still subject to the outcome of procurement processes. However, we always procure from local South African suppliers

The monetary value is not determined yet, still subject to the outcome of procurement processes

4. Network switches

Replacing old network swithes to improve network management and security capability

Not awarded yet, but will be standardised on HP network switches.

Not established yet, subject to market conditions, budgetary figure of

R3 000 000,00

Not established yet, still subject to the outcome of procurement processes. However, we always procure from local South African suppliers

The monetary value is not determined yet, still subject to the outcome of procurement processes

11 December 2017 - NW2170

Profile picture: Dreyer, Ms AM

Dreyer, Ms AM to ask the Minister of Health

(a) Which public (i) hospitals and (ii) clinics (aa) have been damaged and (bb) had inadequate infrastructure in each of the past three financial years and (b) what are the details pertaining to this in each case?

Reply:

(a) Honourable Member, when you say public hospitals and clinics that have been damaged, what damage are you referring to? Do you mean a broken window, a burst water pipe, damage caused by earthquake? What actually do you mean? Please help me in order to be able to answer your question;

(b) Inadequate infrastructure is also relative and subjective term. May you please specify what you mean by inadequate infrastructure?

END.

11 December 2017 - NW3803

Profile picture: Maynier, Mr D

Maynier, Mr D to ask the Minister of Finance

(1)Whether the SA Revenue Service (SARS) ITA34 Notice of Assessment Income tax forms of certain persons (Mr AK Gupta and Mr RK Gupta),(a) has been released by the SARS as public information notwithstanding the provisions of section 69 (2)(d) of the Tax Administration Act, Act 28 of 2011; if so, what are the relevant details; if not; (2) Whether he has found that the Notice of the Income Tax Assessment Forms, ITA34, of the specific persons are authentic; if not, what is the position in this regard; if so, what are the relevant details in each case?

Reply:

1. The Tax Administration Act has specific secrecy requirements pertaining to the confidentiality of taxpayer information and as such SARS does not discuss or release information pertaining to the tax affairs of taxpayers unless specifically allowed for by the provisions of Chapter 6 of the Tax Administration Act. The provisions of 69(2) (d) of the Tax Administration Act speaks to allowing a senior SARS Official to disclose information which is public information. The ITA34’s of any taxpayer cannot be regarded as public information as set out in the Act.

2. Due to the provisions of Chapter 6 of the Tax Administration Act, and in specific the provisions of section 69 of that Act, SARS will not discuss the validity or not of the said documents.

11 December 2017 - NW3491

Profile picture: Carter, Ms D

Carter, Ms D to ask the Minister of Health

With reference to his reply to question 158 on 13 March 2017 wherein he stated that the internship and Community Service Programme (ICSP) online application system was introduced in 2016 for placement of 2017 medical interns and community service candidates and that during the implementation of the ICSP programme various challenges were experienced with the key process activities and the use of ICSP online, what measures have been put in place to ensure smooth and fair placements of medical interns?

Reply:

In order to improve the efficiency and effectiveness of the ICSP online system the National Department developed ICSP Guidelines which are updated yearly in order to meet the demands of applicants. The Department also developed an Improvement Plan which is meant to address identified challenges experienced during the 2016/2017 period.

Both these documents are work-in-progress and are updated annually to ensure that the system is able to cope with emanating challenges.

The Department continuously engage with stakeholders to try and trouble-shoot envisaged challenges.

The Department has also established a helpdesk that operates for 8 hours from Monday to Friday to assist with responding to enquiries from applicants and directing them appropriately. Furthermore, the Department has an email ticket system that helps to track enquiries of applicants.

END.

11 December 2017 - NW3924

Profile picture: Thembekwayo, Dr S

Thembekwayo, Dr S to ask the Minister of Health

What are the reasons that more than one-third out of about 160 interns who were transferred from the national Department of Health to the Gauteng Provincial Department of Health are not employed?

Reply:

May the Honourable Member please help clarify what interns are being referred to. Is it medical interns, or or any other graduate who was placed in the Department of Health for internship purposes?

I am unable to answer your question until this matter is clarified.

END.

11 December 2017 - NW2632

Profile picture: Kalyan, Ms SV

Kalyan, Ms SV to ask the Minister of International Relations and Cooperation

Was the flight that (a) arrived at Waterkloof Air Force Base from Harare on or about 16 August 2017 and (b) departed from Waterkloof Air Force Base to Harare on or about 20 August 2017 granted an RSA05 clearance; if so (c) who approved the clearance and (d) on what basis was the clearance done NATIONAL ASSEMBLY FOR WRITTEN REPLY QUESTION NO:2632 DATE OF QUESTION PAPER: 1 SEPTEMBER 2017 PUBLISHED IN INTERNAL QUESTION PAPER NO: 31 OF 2017 REPLY: Ms S V Kalyan (DA) asked the Minister of International Relations and Cooperation the following questions regarding the Zimbabwean aircraft that visited South Africa between 16 and 20 August 2017. Was the flight that (a) arrived at Waterkloof Air Force Base from Harare on or about 16 August 2017 and (b) departed from Waterkloof Air Force Base to Harare on or about 20 August 2017 granted an RSA05 clearance; if so (c) who approved the clearance and (d) on what basis was the clearance done? Yes Yes Department of Defence The aircraft was transporting a Head of State UNQUOTE

Reply:

  1. Yes
  2. Yes
  3. Department of Defence
  4. The aircraft was transporting a Head of State

UNQUOTE

11 December 2017 - NW3927

Profile picture: Mente-Nkuna, Ms NV

Mente-Nkuna, Ms NV to ask the Minister of Health

What are the details of the roll-out plans that his department have for the National Health Insurance in relation to (a)(i) provincial and (ii) regional hospitals and (b) clinics at municipal level?

Reply:

Detailed plans for roll-out of NHI provincially, in regional hospitals and municipal clinics will become apparent after the NHI Bill has been passed by Parliament into the NHI Act.

END.

08 December 2017 - NW3571

Profile picture: Krumbock, Mr GR

Krumbock, Mr GR to ask the Minister of Health

(a) What is the total number of supplier invoices that currently remain unpaid by (i) his department and (ii) each entity reporting to him for more than (aa) 30 days, (bb) 60 days, (cc) 90 days and (dd) 120 days and (b) what is the total amount outstanding in each case?

Reply:

(a) (i) 5 invoices remain unpaid;

     (aa) 3 invoices remain unpaid for more than 30 days;

     (bb) No invoices remain unpaid between 60 to 90 days;

     (cc) 2 invoices remain unpaid between 90 days to 120 days;

     (dd) No invoices remain unpaid for more than 120 days;

(b) R183,789.38 for more than 30 days;

R27,619.46 between 90 days to 120 days;

 

(ii) The following table reflects the details with regards to the entities:

 

Total

30 days

60 days

90 days

120 days

South African Medical Research Council (SAMRC)

Total number of supplier invoices that currently remain unpaid

99

95

4

0

0

Total amount outstanding in each case

R37,255,155.10

R37,229,425.37

R25,729,73

0

0

Office of Health Standards Compliance (OHSC)

Total number of supplier invoices that currently remain unpaid

11

2

6

3

0

Total amount outstanding in each case

R136,784.12

R124,613.01

R11,571.11

R600.00

0

Council for Medical Schemes (CMS)

Total number of supplier invoices that currently remain unpaid

12

11

1

0

0

Total amount outstanding in each case

R473,307.18

R469,772.04

R3,535.14

0

0

National Health Laboratory Service (NHLS)

Total number of supplier invoices that currently remain unpaid

384

36

111

74

163

Total amount outstanding in each case

R348,094,192.70

R6,017,985.01

R191,333,319.14

R93,676,507.35

R57,066,381.20

END.

08 December 2017 - NW2174

Profile picture: Esau, Mr S

Esau, Mr S to ask the Minister of Health

(1)(a) How many (i) qualified urologists are currently in practice in the country, (ii) are in the (aa) private and (bb) public sector in each province and (iii) are currently in training and (b) what is the guideline of the World Health Organisation pertaining to the number of urologists; (2) does the country adhere to the specified guideline; if not, why not?

Reply:

(1) (a) (i) 213

(ii) (aa) 248

      (bb) 77

(iii) 83

(b) Urologists - there are no published WHO guidelines or other benchmarks specifically for oncologists.

(2) No. There are no WHO guidelines specifically for oncologists.

END.

08 December 2017 - NW2175

Profile picture: Esau, Mr S

Esau, Mr S to ask the Minister of Health

(1)(a) How many (i) qualified radiologists are currently in practice in the country, (ii) are in the (aa) private and (bb) public sector in each province and (iii) are currently in training and (b) what is the guideline of the World Health Organisation pertaining to the number of radiologists; (2) does the country adhere to the specified guideline; if not, why not?

Reply:

(1) (a) (i) 650

(ii) (aa) 335

(bb) 130

(iii) 253

(b) Radiologists - There are no published WHO guidelines or other benchmarks specifically for radiologists.

(2) There are no WHO guidelines for specifically for radiologists.

END.

08 December 2017 - NW3574

Profile picture: Lotriet, Prof  A

Lotriet, Prof A to ask the Minister of Human Settlements

(a) What is the total number of supplier invoices that currently remain unpaid by (i) her department and (ii) each entity reporting to her for more than (aa) 30 days, (bb) 60 days, (cc) 90 days and (dd) 120 days and (b) what is the total amount outstanding in each case?

Reply:

The information requested by the Honourable Member is provided in the table below:

(i) NATIONAL DEPARTMENT OF HUMAN SETTLEMENTS:

(aa) for more than 30 days

(bb) for more than 60 days

(cc) for more than 90 days

(dd) for more than 120 days

None

None

None

None

(ii) ENTITIES:

(aa) for more than 30 days

(bb) for more than 60 days

(cc) for more than 90 days

(dd) for more than 120 days

National Urban Reconstruction and Housing Agency

13 and total  amount outstanding is

R1,573,617.68

7 and total  amount outstanding is

R26,320.12

1 and total  amount outstanding is

R33,345.00

1 and total  amount outstanding is

R91.49

National Housing Finance Corporation

R316.92

None

None

None

Social Housing Regulatory Authority

92 and total  amount outstanding is R3 179 454.82

16 and total  amount outstanding is

R946 184.22

1 and total  amount outstanding is

R77 922.95

4 and total  amount outstanding is

R83 022.03

Housing Development Agency

2 and total  amount outstanding is

R15 104,00

6 and total  amount outstanding is

R1 411 171,00

5 and total  amount outstanding is

R164 227,00

12 and total  amount outstanding is

R6 681 692,00

Rural Housing Loan Fund

None

None

None

None

Community Schemes Ombud Service

1 and total amount outstanding is

R961,879.90

None

None

2 and total amount outstanding is

R261,800.00

Estate Agency Affairs Board

13 and total amount outstanding is R242 332,46

None

1 and total amount outstanding is R11 475,00

None

National Home Builders Registration Council

20 and total amount outstanding is R2 505 610,00

2 and the total amount outstanding is R64 370,00

1 and total amount outstanding is R29 135,00

None

 

08 December 2017 - NW2176

Profile picture: Esau, Mr S

Esau, Mr S to ask the Minister of Health

(1)(a) How many (i) qualified oncologists are currently in practice in the country, (ii) are in the (aa) private and (bb) public sector in each province and (iii) are currently in training and (b) what is the guideline of the World Health Organisation pertaining to the number of oncologists; (2) does the country adhere to the specified guideline; if not, why not?

Reply:

(1) (a) (i) 155

(ii) (aa) 163

(bb) 72

(iii) 104

(b) Oncologists - There are no published WHO guidelines or other benchmarks specifically for oncologists.

(2) There are no WHO specified guidelines specifically for oncologists.

END.

08 December 2017 - NW3715

Profile picture: Malatsi, Mr MS

Malatsi, Mr MS to ask the Minister of Human Settlements

With reference to the contract awarded by the Estate Agency Affairs Board of South Africa to a certain company (name and details furnished) (a) what is the current (i) contract value and (ii) length of the contract, (b) when was the contract awarded and (c) when is the contract due to expire?

Reply:

(a)(i & ii) The Estate Agency Affairs Board (EAAB) confirmed that it did not directly award any contract to the company referred to by the Honourable Member. Instead, the EAAB has a support service level agreement and end user licence contract with a South African company which is an authorised reseller of the company in question.

(b) Falls away.

(c) Falls away.

08 December 2017 - NW3719

Profile picture: Mashabela, Ms N

Mashabela, Ms N to ask the Minister of Health

What is the hospital bed to population ratio in (a) each province and (b) the eight biggest metropolitan municipalities?

Reply:

The following tables reflect the details in this regard

(a) Provinces

Organisation unit

Total Inpatient beds

Total population

Population to Total Inpatient bed ratio

Beds per 1000 population

Eastern Cape

13,176

7,139,336

542

1.8

Free State

4,687

2,881,998

615

1.6

Gauteng

18,103

13,773,639

761

1.3

KwaZulu-Natal

21,609

11,229,961

520

1.9

Limpopo

7,814

5,877,930

752

1.3

Mpumalanga

4,586

4,388,269

957

1.0

Northern Cape

1,646

1,200,703

729

1.4

North West

4,343

3,847,629

886

1.1

Western Cape

9,783

6,393,555

654

1.5

National

85,747

56,733,020

662

1.5

(b) The eight biggest metropolitan municipalities

Organisation unit

Total Inpatient beds

Total population Midyear 2017 DHIS

Population to Total Inpatient bed ratio

Beds per 1000 population

Buffalo City Metropolitan Municipality

2090

864,130

413

2.4

Nelson Mandela Bay Municipality

2233

1,279,035

573

1.7

Mangaung Metropolitan Municipality

2388

801,716

336

3.0

City of Ekurhuleni Metropolitan Municipality

3388

3,500,231

1033

1.0

City of Johannesburg Metropolitan Municipality

5946

5,055,664

850

1.2

City of Tshwane Metropolitan Municipality

5634

3,376,566

599

1.7

eThekwini metropolitan Municipality

7450

3,715,328

499

2.0

City of Cape Town Metropolitan Municipality

7103

4,070,914

573

1.7

END.

08 December 2017 - NW3162

Profile picture: Ketabahle, Ms V

Ketabahle, Ms V to ask the Minister of Telecommunications and Postal Services

What are the details including the ranks of service providers and /or contractors from which (a) his department and (b) the entities reporting to him procured services in the past five years 2. What (a) service was provided by each service provider and /or contactor and (b) amount was service provider and / or contractor paid 3. (a) how many of these service providers are black-owned entities, (b) what was each of the black-owned service providers awarded and; (c) how much was each black-owned service provider paid?

Reply:

I have been informed by the Department and entities as follows:

Department

The question is broad and not specific requiring detailed information over a long period of time. Various services procured by the Department range from small to big procurement of goods and services.

(1)(a) The Department of Telecommunications and Postal Services was established in May 2014. Since 2014 various services were rendered to the Department by various service providers. Therefore the answer to the question will only focus on the 2014/15, 2015/16 and 2016/17 financial years.

(2)(a) The list of service providers utilised during the abovementioned periods are too long to list.

(2)(b) The type of services that were rendered to the Department are as follows:-

Printing

Catering

Advertisements

Recruitment

Security Services

Cleaning Services

Pest Control

Hiring of a Mobile Theatre Stage

Hiring of Tents

Hiring of Furniture

Hiring of Public Address System

Hiring of Audio Visual Equipment

Hiring of Chemical Toilets

Repair and Service of Air Condition

Designing of Promotional Material

Design and Layout of Banners

Manufacturing and Installation of Blinds

Personnel Assessments

Data Capturing, Processing and Recovering

Branding and Marketing

Repair and Renovation of Building

Refuse Removal

Repair Access Control System

Competency Assessments

Furniture Removal

Transcription Services

Clothing with Logo Printing

Pluming Services

Electrician Services

Maintenance of Database

Burglar Proofing

Audit Services

Research

System Development Services

Legal Services

Advisory Consulting Services

Delivery of News Papers

Translators: Brailing Of Documents

Computer Support Services

Repair and Install CCTV System

Verification of Qualifications

Advisory Consulting Services

Video Recording

Repairing of Camera

Hiring Of Photographer

Website Development

Repair and Install Networks

Rendering of Health Care

Training

The total spent on services was R90 million for the period of 2014/15, 2015/16 and 2016/17 financial year.

 

YEAR

TOTAL SPENT ON SMMEs and BEEs

2016/17

9, million

2015/16

6, million

2014/15

14, million

(b) Entities

1. – 3, I refer the member to the Annual Reports and the Financial Statements of the entities

Approved

 

Dr Siyabonga Cwele, MP

Minister of Telecommunications and Postal Services

Date:

08 December 2017 - NW3642

Profile picture: Thembekwayo, Dr S

Thembekwayo, Dr S to ask the Minister of Health

What is the ratio of (a) nurse and (b) doctor to patient in respect of each (i) hospital and (ii) clinic in the country, based on population within the catchment area for each hospital and clinic?

Reply:

Ratios of health workers to patient was always calculated as nation per unit total population. This was deemed not useful by the World Health Organisation (WHO) because it does not talk about the spread of this Health workforce within a country.

The WHO then came with a mathematical formula called WISN (Work Indicator for Staffing Needs).

We are busy calculating these needs using this mathematical formula.

END.

08 December 2017 - NW3199

Profile picture: Thembekwayo, Dr S

Thembekwayo, Dr S to ask the Minister of Health

Whether there is a plan in place for the Alfred Nzo Hospital in the Kopanong Local Municipality in the Xariep Region, Free State province, to provide (a) maternity services, (b) oncology services, (c) neurology services, (d) eye, ear and nose care, and (e) an intensive care unit?

Reply:

There is no Alfred Nzo Hospital in the mentioned municipality and districts.

END.

08 December 2017 - NW3736

Profile picture: Ketabahle, Ms V

Ketabahle, Ms V to ask the Minister of Telecommunications and Postal Services

1. Whether (a) his department and / or (b) entities reporting to him procured services from a certain company ( name furnished); if so, (i) what services were procured in each case and (ii) what is the total amount that was paid to the specified company in each case;

Reply:

I have been informed by the Department and Entities reporting to me as follows:

1 (a) Kindly note DTPS only existed May 2014. No services were procured from Travel with Flair by the Department of Telecommunications and Postal Services

  1. Not Applicable
  2. Not Applicable

1 (b) No services by entities of DTPS that had dealings with Travel with Flair (Pty) Ltd, except USAASA and Sentech have procured services from Travel with Flair.

  1. USAASA procured travel services.
  1. USAASA paid R29, 679.00 and USAF paid R17, 106.01.

2. (b)(i)(ii)(iii) USAASA procures services from the company for international travel and the details are as follows:

Who travelled

Date

Travel Route

Invoice Amount

Agency Fee

P Radebe

17 Oct 2015

Sweden

R130 484.72

R275.00

Z Nkosi

17 Oct 2017

Sweden

R117 954.72

R275.00

SENTECH

(1)&(2) Sentech procured the following services from Travel with Flair:

Labels Sum of TWF Fee

2016 516 725

Accommodation (Acc) 234 124

Car Hire (Car) 91 522

Conference (Ccc) 31 074

Domestic Air Travel (Dom) 119 366

Insurance (Ins) 130

International Air Travel (Int) 7 985

Regional Air Tickets (Reg) 2 055

Transfers & Shuttles (Tra) 29 969

Trav Other (Sao) 280

Trav_ Accomod (Sac) 220

2017 484 090

Accommodation (Acc) 197 976

Bus & Rail Reservations (Bus) 110

Car Hire (Car) 74 501

Conference (Ccc) 58 428

Domestic Air Travel (Dom) 118 597

Insurance (Ins) 510

International Air Travel (Int) 6 215

Regional Air Tickets (Reg) 4 900

Tours (Tou) 110

Transfers & Shuttles (Tra) 22 113

Trav Other (Sao) 515

Trav_Conference (Sap) 115

2015 161 764

Accommodation (Acc) 51 790

Car Hire (Car) 22 930

Conference (Ccc) 29 207

Domestic Air Travel (Dom) 38 470

International Air Travel (Int) 4 840

Transfers & Shuttles (Tra) 14 412

Air (Ai1) 115

Grand Total 1 162 580

SENTECH

Approved/ not approved

Dr Siyabonga Cwele, MP

Minister of Telecommunications and Postal Services

Date:

08 December 2017 - NW2756

Profile picture: De Freitas, Mr MS

De Freitas, Mr MS to ask the Minister of Health

With regard to the upgrade of the South Rand Hospital in Johannesburg, Gauteng, what (a) resources has his department provided, (b) is the budget, (c) are the expenditure costs incurred, (d) additional human resources have been provided, (e) positions have been filled (f) posts remain vacant in each of the past three financial years?

Reply:

a) The NDOH has allocated Health Facility Revitalisation Grant funds for rehabilitation of Infrastructure, and for procurement of medical equipment,

b) R 3.7 million has been allocated to procure the medical equipment in 2017/18 financial year;

c) No expenditure has been incurred up to date;

d) The NDOH does not have statistics on additional human resources provided at South Rand Hospital and is awaiting information requested from the Gauteng Department of Health;

e) A total of 582 positions are filled at the South Rand Hospital;

f) A total of 70 positions remain vacant at the South Rand Hospital.

END.

08 December 2017 - NW3901

Profile picture: Kopane, Ms SP

Kopane, Ms SP to ask the Minister of Health

(1)(a) What number of forensic science laboratories are currently (i) owned and/or (ii) administered by his department in each province and (b) where is each specified laboratory located; (2) (a) what number of forensic science laboratories does his department intend to set up in each province in the (i) 2017-18, (ii) 2018-19 and (iii) 2019-20 financial years and (b)(i) where will each laboratory be set up and (ii) what are the projected costs in each case?

Reply:

(1) (a) The Department of Health owns no forensic laboratories anywhere in South Africa;

(b) Not applicable;

(2) The Department of Health is not intending to set up any forensic science laboratory in the country, because they all fall under SAPS.

END.

08 December 2017 - NW3294

Profile picture: Groenewald, Dr PJ

Groenewald, Dr PJ to ask the Minister of Health

(1)What number of the corpses in state mortuaries in each province and since the 2014-15 financial year were deaths resulting from (a) wounds caused by shootings, (b) knife wounds, (c) motor accidents, (d) motor-cycle accidents, (e) drownings, (f) fires, (g) pedestrians who were run over, (h) cyclists who were run down, (i) HIV, tuberculosis and other diseases and (j) ageing; (2) whether he will make a statement about the matter?

Reply:

The reply to questions (1) is summarized in Table 1 to 9 below:

TABLE 1: EASTERN CAPE

 

2014-15

2015-16

2016-17

(a) wounds caused by shootings

1885

820

860

(b) knife wounds

1885

1925

1971

(c) motor accidents

1537

1799

1862

(d) motor-cycle accidents

6

4

3

(e) drownings

382

379

366

(f) fires

393

376

481

(g) pedestrians who were run over

163

221

145

(h) cyclists who were run down

1

2

1

(i) HIV, tuberculosis and other diseases

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

(j) ageing

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* Forensic Pathology Services

TABLE 2: FREE STATE

 

2014-15** (2014)

2015-16** (2015)

2016-17** (2016)

(a) wounds caused by shootings

246

128

215

(b) knife wounds

476

229

508

(c) motor accidents

906

571

1025

(d) motor-cycle accidents

32

10

8

(e) drownings

154

64

112

(f) fires

169

92

143

(g) pedestrians who were run over

207

108

194

(h) cyclists who were run down

Included in 1(d) above

Included in 1(d) above

Included in 1(d) above

(i) HIV, tuberculosis and other diseases

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

(j) ageing

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* Forensic Pathology Services

** Data provided per calendar year

TABLE 3: GAUTENG

 

(a) 2014-15

(b) 2015-16

(c) 2016-17

(a) wounds caused by shootings

1608

1854

2116

(b) knife wounds

1257

1338

1438

(c) motor accidents

1707

1981

1948

(d) motor-cycle accidents

188

149

144

(e) drownings

210

249

242

(f) fires

715

702

746

(g) pedestrians who were run over

1193

1314

1413

(h) cyclists who were run down

Details not available

Details not available

Details not available

(i) HIV, tuberculosis and other diseases

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

(j) ageing

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* Forensic Pathology Services

TABLE 4: KWA-ZULU NATAL

 

2014-15

2015-16

2016-17

(a) wounds caused by shootings

1539

1735

1506

(b) knife wounds

1534

1523

1217

(c) motor accidents***

2913

2967

2576

(d) motor-cycle accidents

Details not available

Details not available

Details not available

(e) drowning**

1662

1788

1473

(f) fires

610

642

491

(g) pedestrians who were run over

Details not available

Details not available

Details not available

(h) cyclists who were run down

Details not available

Details not available

Details not available

(i) HIV, tuberculosis and other diseases

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

(j) ageing

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* Forensic Pathology Services

** Reported as asphyxia deaths, including drowning, hanging etc.

*** Transportation accidents

TABLE 5: LIMPOPO

 

(a) 2014-15

(b) 2015-16

(c) 2016-17

(a) wounds caused by shootings

221

261

245

(b) knife wounds

277

289

291

(c) motor accidents

1507

1757

1742

(d) motor-cycle accidents

1

2

7

(e) drownings

164

139

145

(f) fires

150

147

155

(g) pedestrians who were run over

Details not available

Details not available

Details not available

(h) cyclists who were run down

Details not available

Details not available

Details not available

(i) HIV, tuberculosis and other diseases

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

(j) ageing

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* Forensic Pathology Services

TABLE 6: MPUMALANGA

 

(a) 2014-15

(b) 2015-16

(c) 2016-17

(a) wounds caused by shootings

719

453

472

(b) knife wounds

165

171

161

(c) motor accidents

1150

1201

1200

(d) motor-cycle accidents

107

29

21

(e) drownings

148

144

132

(f) fires

168

169

139

(g) pedestrians who were run over

504

504

523

(h) cyclists who were run down

18

8

12

(i) HIV, tuberculosis and other diseases

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

(j) ageing

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* Forensic Pathology Services

TABLE 7: NORTHERN CAPE

 

(a) 2014-15

(b) 2015-16

(c) 2016-17

(a) wounds caused by shootings

21

23

24

(b) knife wounds

294

300

255

(c) motor accidents

333

321

297

(d) motor-cycle accidents

6

5

4

(e) drownings

95

98

108

(f) fires

63

56

54

(g) pedestrians who were run over

147

134

125

(h) cyclists who were run down

3

9

3

(i) HIV, tuberculosis and other diseases

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

(j) ageing

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* Forensic Pathology Services

TABLE 8: NORTH WEST

 

(a) 2014-15

(b) 2015-16

(c) 2016-17

(a) wounds caused by shootings

187

157

170

(b) knife wounds

298

321

453

(c) motor accidents

715

784

856

(d) motor-cycle accidents

14

23

24

(e) drownings

82

69

90

(f) fires

134

122

146

(g) pedestrians who were run over

217

181

289

(h) cyclists who were run down

2

4

20

(i) HIV, tuberculosis and other diseases

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

(j) ageing

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* Forensic Pathology Services

TABLE 9: WESTERN CAPE

 

(a) 2014-15

(b) 2015-16

(c) 2016-17

(a) wounds caused by shootings

1289

1323

1268

(b) knife wounds

1429

1508

1649

(c) motor accidents

579

701

627

(d) motor-cycle accidents

56

49

55

(e) drownings

180

202

197

(f) fires

280

330

349

(g) pedestrians who were run over

605

629

649

(h) cyclists who were run down

27

26

30

(i) HIV, tuberculosis and other diseases

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

(j) ageing

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* FPS Mortuaries only handle unnatural deaths

* Forensic Pathology Services

(2) No, there is no need to. There are many state institutions which release this data time and again, e.g quarterly police crime statistics, the Department of Transport, StatsSA and the South African Medical Research Council.

END.

08 December 2017 - NW3341

Profile picture: Thembekwayo, Dr S

Thembekwayo, Dr S to ask the Minister of Health

What number of nurses were employed at Tshilidzini Hospital in (a) 1996, (b) 2000, (c) 2005 and (d) 2010?

Reply:

The following table reflects the details in this regard.

NUMBER OF NURSES EMPLOYED AT TSHILIDZINI HOSPITAL

1996

2000

2005

2010

Information unobtainable

Information unobtainable

509

568

END.

08 December 2017 - NW3495

Profile picture: Mackenzie, Mr C

Mackenzie, Mr C to ask the Minister of Telecommunications and Postal Services

Whether the SA Post Office introduced a clearance fee for parcels and / or packages received from other countries; if so, what are the relevant (a) charges for each country and (b) details of the conditions attached to the collection and / or delivery of the parcels and / or packages?

Reply:

I have been informed by SAPO as follows:

The South African Post Office did not introduce a clearance fee for parcels and /or packages received from other countries. These handling fees were already applicable.

(a)(b) Not applicable to SAPO

 

Approved/ not approved

Dr Siyabonga Cwele, MP

Minister of Telecommunications and Postal Services

Date:

08 December 2017 - NW3507

Profile picture: Robertson, Mr K

Robertson, Mr K to ask the Minister of Rural Development and Land Reform

(1)What number of employees of (i) his department, (ii) each provincial Department of Rural Development and Land Reform and (iii) each entity reporting to him are currently on suspension, (b) what are the reasons for the suspensions in each case, (c) what amount has been paid to each suspended employee for the period of suspension and (d) for what length of time has each specified employee been on suspension; (2) What number of employment contracts of employees of (a) his department, (b) each provincial Department of Rural Development and Land Reform and (c) each entity reporting to him were terminated due to them being found guilty of corruption since 1 April 2014? NW3934E

Reply:

1. (a) (i),(ii) National and Provincial Offices of Department of Rural Development and Land Reform : 12

(iii) Ingonyama Trust Board (ITB): 6

Land Claims Commission (LCC): 2

Deeds: 2

(b),(c),(d) Refer to the table below for details regarding the reasons, the amounts paid, and the length of time of suspension for the employees of the Department, provinces and entities reporting to the Minister of Rural Development and Land Reform. One employee at the ITB was employed on a fixed-term contract which expired before disciplinary action could be taken.

2. (a),(b) None.

(c) LCC: 1

Number

Department, Province & Entity 1(i), (ii) &(iii)

Reasons for the Suspension 1(b)

Salaries paid to Suspended employees 1(c)

Duration of Suspension 1(d)

NATIONAL OFFICE

 

National Office

Possible interference with the investigation and witnesses

R581 315.06

5 Months

 

National Office

Possible interference with the investigation and witnesses

R526 716.96

5 Months

 

National Office

Possible interference with the investigation and witnesses

R568 925.78

4 Months

 

National Office

Possible interference with the investigation and witnesses

R1 251 186.00

  1. Months

WESTERN CAPE

5.

Western Cape

Possible interference with the investigations and witnesses

R165 250

2 Months

EASTERN CAPE

6.

Eastern Cape

Possible interference with the investigations and witnesses

R72 075.25

1 Month

7.

Eastern Cape

Possible interference with the investigations and witnesses

R68 926.50

1 Month

8.

Eastern Cape

Possible interference with the investigations and witnesses

R551 358.78

14 Months

9.

Eastern Cape

Possible interference with the investigation and witnesses

R846 217.61

13 Months

10.

Eastern Cape

Possible interference with the investigation and witnesses

R1 144 449.59

13 Months

LIMPOPO

11.

Limpopo

Possible interference with the investigations and witnesses

R17 271.00

2 Months

12.

Limpopo

Possible interference with the investigations and witnesses

R25 436.75

2 Months

DEEDS PTA (GP)

13.

Deeds

Possible interference with the investigation and witnesses

R415 791.28

4 Months

14

Deeds

Possible interference with the investigation and witnesses

R303 355.32

4 Months

RLCC(GP)

15.

RLCC

Possible interference with the investigation and witnesses

R169 053.00

4 Months

LCC(KZN)

16.

Kwazulu Natal

Possible interference with the investigations and witnesses

R87 415.30

3 Months

TABLE 2: INGONYAMA TRUST BOARD

17.

KZN

Pending disciplinary hearing relating to irregularities in discharge of duties

R 493 920.06

14 Months

18.

KZN

Pending disciplinary hearing relating to irregularities in discharge of duties

R 724 984.75

14 Months

19.

KZN

Pending disciplinary hearing relating to irregularities in discharge of duties

R493 920.06

14 Months

20.

KZN

Pending disciplinary hearing relating to irregularities in discharge of duties

R274 489.11

14 Months

21.

KZN

Pending disciplinary hearing relating to irregularities in discharge of duties

R398 135.52

14 Months

22.

KZN

Pending disciplinary hearing relating to irregularities in discharge of duties

R398 135.52

14 Months

07 December 2017 - NW2847

Profile picture: Kalyan, Ms SV

Kalyan, Ms SV to ask the MINISTER OF INTERNATIONAL RELATIONS AND COOPERATION

(1) Is Dr Riek Machar being hosted as a guest of the State; if so, (a) for what period will the specified person be hosted as a guest of the State and (b) what are the conditions, if any, of his stay; (2) Is the specified person’s communication with any (a) of his former advisors and/or (b) leaders of other international bodies is being monitored; if not, what is the position in this regard; if so, what are the relevant details in each case; (3) whether the specified person is perceived as a threat to the national security of the specified person’s home country; if so, what are the relevant details? NW3154E

Reply:

1. Yes, Dr Riek Machar is hosted as a guest of the State.

a) At this stage the duration of Dr Riek Machar’s stay in South Africa is not known. Dr Machar came to South Africa on humanitarian grounds following consultations with the Government of the Republic of South Sudan and the Inter-Governmental Authority on Development (IGAD).

b) The conditions of Dr Machar’s stay in South Africa are that he may not engage in any activity that would contribute to the escalation of conflict in South Sudan.

2. Dr Machar’s communication is not monitored.

3. It has to be noted that there is conflict in South Sudan between government forces and the opposition armed rebel factions, including the armed rebel group led by Dr Machar. The African Union and the region through IGAD, are assisting the Republic of South Sudan to resolve the conflict.

UNQUOTE

07 December 2017 - NW3815

Profile picture: De Freitas, Mr MS

De Freitas, Mr MS to ask the Minister of Transport

With regard to the increased vehicle licensing transaction fees, (a) how were these increases calculated, (b) what are the details (i) of parties who made submissions and (ii) of the content of the submissions received, (c) which stakeholders were consulted and (d) what public participation and/or public consultation processes were undertaken?

Reply:

(a) The increases of the transaction fees were based on the initial amount of R30 as determined by the Ministers of Transport and Finance, with the agreement that there will be an annual increase of R6.

(b) (i) In terms of the RTMC Act it is not required that the transaction fees be published for public comments, therefore the increase was not published for comments.

(ii) Not applicable, see (b)(i) above

(c) Not applicable, see (b)(i) above

(d) Not applicable, see (b)(i) above

07 December 2017 - NW3544

Profile picture: Figlan, Mr AM

Figlan, Mr AM to ask the Minister of Transport

With regard to the issuing of tenders by his department and the entities reporting to him in the past three financial years, (a) which tenders were issued without following normal tender processes, (b) what were the reasons for the deviation in each case, (c) what was the monetary value of each tender, (d) how were the tenders issued and (e) who authorised the issuing of each tender?

Reply:

Department and entities (Refer to the Annexures) of Parliamentary Question 3544

  1. CBRT
  2. RAF
  3. RTIA
  4. RTMC
  5. SANRAL
  6. ACSA
  7. ATNS
  8. SACCA
  9. SAMSA
  10. PRSA
  11. RSR
  12. PRASA

PROJECT DESCRIPTION

REASON FOR DEVIATION

CONTRACT AMOUNT

TYPE OF BID

AUTHORISING AUTHORITY

(a)

(b)

(c)

(d)

(e)

Establishment of the Single Source Transport Economic Regulator through Developing Policy, Legislation and Implementation Plan

During the Policy development, additional stakeholder engagement was required and work-shopping of various amendments

1 500 240.00

Natural Continuation

Accounting Officer

Cooperative Model for Public Transport

During the Project critical items that were not part of the TOR were identified as crucial to the success of the project, which amended the scope

1 129 536.20

Natural Continuation

Accounting Officer

RE-APPOINTMENT: Review Road based subsidized transport service

To complete the initial Project. Contract period lapsed before completion and as a result of unforeseen outside factors, at no additional cost

691 347.30

Re-Appointment

Accounting Officer

RE-APPOINTMENT :Support to Regulating Committee on Fees and Charges by ACSA and ATNS - Cost Extension

To complete the initial Project. Contract period lapsed before completion and as a result of unforeseen outside factors at, no additional cost

402 101.00

Re-Appointment

Accounting Officer

RE-APPOINTMENT :Support to Regulating Committee on Fees and Charges by ACSA and ATNS - Cost Extension

2nd re-appointment was to assist the Regulating Committee with an ongoing Court Case relating to the Fees

916 106.00

Re-Appointment

National Treasury

Forensic Analysis of Putco Sandfontein Contract

Urgent request to intervene as an emergency due to threats of violence. National Treasury notified during entire process

2 259 266.08

Closed Bid

Accounting Officer

NATURAL CONTINUATION: Forensic Analysis of Putco Sandfontein Contract

For the project to be completed successfully a census had to be conducted, which was not part of initial scope

2 338 960.80

Natural Continuation

Accounting Officer

RE-APPOINTMENT: NATMAP 2050 Review and Update

To complete the initial Project. Contract period lapsed before completion and as a result of unforeseen outside factors, at no additional cost

680 000.00

Re-Appointment

Accounting Officer

CLOSED BID: Finalize the Draft White Paper on NCAP

Open tender process was followed with no bids received that were responsive. Request to approach experts in the specific field on closed bid was approved for second attempt. Successful

983 424.00

Closed Bid

Accounting Officer

Determining the criteria for certifying Auditors and training requirements.

SAATCO is the sole provider of this service

731 300.00

Single Source

Bid Adjudication Committee

EXPANSION: Review of the National Safety Regulator Act

Additional Provincial Consultation and the development of a Money Bill had to be added to initial scope to finalise project successfully

798 000.00

Expansion

National Treasury

Develop a National Railway Safety Strategy

Open tender process was followed with no bids received that were responsive. Request to approach 5 experts in the specific field on closed bid was approved for second attempt. Successful

2 730 120.00

Closed Bid

Accounting Officer

Develop a Salvage Strategy

A quotation process was followed. No bids were received. Approval to restart as closed bid by approaching experts in the field, was approved.

782 952.00

Closed Bid

Accounting Officer

Road Tariff determination framework

A quotation process was followed. All qualifying bids received were over the threshold value of R500 000. Approval to restart as closed bid by approaching all 14 suppliers who attended the first briefing session, was approved.

639 526.00

Closed Bid

Accounting Officer

PARTICIPATION: Participate in SANRAL tender for Media buying for 6 months

Request to participate in SANRAL tender for only 6 months approved while DOT finalised own tender process

N/A

Participation

Accounting Officer

PARTICIPATION: Participate in SANRAL tender for Events Management and related Services for 6 months

Request to participate in SANRAL tender for only 6 months approved while DOT finalised own tender process

N/A

Participation

Accounting Officer

Cross-Border Road Transport Agency

Cross-Border Road Transport Agency (C-BRTA) tenders issued in the past three financial years:

YEAR

  1. Tenders issued without normal tender process

(b) Reasons for deviation

( c) Monetary Value

(d) How were the tenders issued

(e) Who authorised the issuing of the tender

2014/15

None

N/A

N/A

N/A

N/A

2015/16

Appointment of a transactional advisor to provide transactional advisory services on the development New Permit System

The initial cost estimation was below R500 000 and a Request for Proposal was issued to eight service providers. Only one bidder responded with three different options and the option that met the Agency’s specifications was above R500 000.

R651 715.20

Tender was issued through a ‘Request for Proposals’

Chief Executive Officer

2016/17

Appointment of a service provider to provide multi-functional printers on a rental basis for a period of twenty months

The printers were originally procured through a normal tender process. This appointment was to continue using the current printers for an additional 20 months based on the following reasons:

  1. The printers in use still had the capacity to service the needs of the Agency and the rentals were maintained as per the original contract as opposed to new machines at high prices. The printers would have been returned to the service provider while they could still service the needs of the Agency.
  1. There was also a pending move of the Agency’s law enforcement unit to the RTMC and getting into a three year contract for new printing machines would have led to fruitless expenditure.
  1. The contract for office accommodation was ending later in the financial year and a determination was still to be made of the new office location and layout. As such the number of printers required could not be ascertained.

R617 6516.00

Through continuation of the current service provider

Chief Executive Officer

 

Extension Office Accommodation lease of a period of 36 months

The following are the reasons for deviations:

  1. The Agency was faced with a financial instability arising from the court outcome to refund operators. The market research was conducted and demonstrated that it is more cost effective to remain in the current premises. The current rental is as per the original contract while other services provider quotations were way above the current rentals.

R25 241 519.16

Through continuation of the current service provider and after market research confirmed cost effectiveness

National Treasury approved deviation as recommended by Procurement Committee of the Board.

Road Accident Fund

(a) The Road Accident Fund (RAF), in the past three financial years issued the following tenders without following normal tender processes,

(b) the reasons for the deviation in each case were,

(c) the monetary value of each tender was,

(d) the tenders were issued in the following manner,

(e) the issuing of the tender was authorised by the,

2014-2015 FY

storage facilities - M&T Development

the service provider is the only available service provider that owns storage facilities within the proximity of not more than a one kilometer radius to the RAF head office

R3,931,829.81

(fixed price)

single source

CEO

Microsoft premier support services – Microsoft

renewal of Microsoft premier support services

R 632,240.00

(fixed price)

sole source

CEO

HP data protector support- HP South Africa

renewal of HP data protector support contract - original equipment manufacturer (OEM)

R 781,514.88

(fixed price)

single source

CEO

HP hardware maintenance - HP South Africa

renewal of HP hardware maintenance contract - (OEM)

R 9,889,578.24

(fixed price)

single source

CEO

Lucidview maintenance and support - Lucidview Pty (Ltd)

renewal of licensing, maintenance and support of Lucidview solution. - (OEM)

R 1,973,588.52

(fixed price)

single source

CEO

bulk media buying- Government Communications Information Systems (GCIS)

as per the National Treasury Regulations

R 117,617,400.00

(fixed price)

National Treasury transversal contract

Board

Nashua SLA Gold Option - Nashua Communications

support and maintenance of the Openscape Voice telephone system

R 9,777,401.77

(fixed price)

single source

CEO

employee wellbeing services – ICAS

contract extension

R 700 000.00

(fixed price)

single source - extension

CEO

security services - Imvula Security

variation- additional scope to add security

original tender/contract value –

R 4, 897, 865.07

value of the extension - R 236, 034.78

(extended for five months at R90, 052.82 per month)

single source - extension

CEO

cleaning services Bontle ke Botho

variation- extension of scope as an additional cleaner was added

original tender/contract value -

R 3, 800, 422.86

value of the extension - R 282 651.60

single source - variation extension of scope

CEO

auditing services - panel

extension- while the tender process was underway to appoint a new panel

expenditure as and when required subject to annual budgeted

amount of

R 3, 740, 983.73

single source - extension

Board

2015-2016 FY

SAP mobile platform and SAP data services - SAP South Africa

supply of SAP mobile platform and SAP data services – (OEM)

R 5,600,000.00

(fixed price)

sole source

CEO

Telephony - Nashua Mobile

service provider to provide Openscape Voice telephone system

R 9,431,126.84

(fixed price)

single source

CEO

new office space (Nelspruit) - FGK Capital

acquiring of office space in Nelspruit due to limited building space available for lease, as per the RAF specifications

R 2,600,000.00

(fixed price)

single source

CEO

supply chain management turnaround strategy- Astute Advisory

as per the National Treasury Regulations

R 8,000,000.00

(fixed price)

National Treasury transversal contract

CEO

Employee Awareness Programme (EAP) - Metropolitan Wellness

as per the National Treasury Regulations

R 1,166,666.67

(fixed price)

National Treasury transversal contract

CEO

Pro-Active 24 hardware maintenance and support - HP South Africa

renewal of the Pro-active 24 hardware maintenance and support contract- (OEM)

R 9, 889, 578.24

(fixed price)

single source

CEO

premier data protector - HP South Africa

service provider to provide premier data support- (OEM)

R 390, 757.44

(fixed price)

single source

CEO

renewal of Lucidview licenses, maintenance and support – Lucidview Pty (Ltd)

renewal of Lucidview licenses, maintenance and support- (OEM)

R 1, 891, 508.52

(fixed price)

single source

CEO

APN upgrade, Spend Manager Plus and Data Messenger- Vodacom

contract scope extension

R 21, 901, 888.08

(fixed price)

single source

Board

supply chain management turnaround strategy - Astute Advisory

variation - extension of the scope of work

R 11 260. 000.00

(fixed price)

single source - variation extension of scope

Board

Menlyn parking, increase of parking space - Interpark

no alternative parking space could be sourced within the near vicinity

R 4 524. 998.72

(fixed price)

single source - variation extension of scope

CEO

banking services - Standard Bank

banking services - extension while the tender process was underway

transactional expenditure subject to annual budgeted amount of

R 1,300,000.00

single source - extension

Board

security services - Venus Securities

extension while the tender process was underway

original tender/contract value -

R 1, 130, 726.88

value of the extension - R254, 821.65

(extended for five months at R 50, 964.33 per month)

single source - extension

CEO

security services - Fidelity Security

extension while the tender process was underway

original tender/contract value -

R 3, 615, 743.98

value of the extension – R 162, 205.85

(extended for five months at R 32, 441.17 per month)

single source - extension

CEO

security services - Securitas

extension while the tender process was underway

original tender/contract value -

R 938, 448.00

value of the extension – R 153, 375.60

(extended for five months at R 30, 675.12 per month)

single source - extension

CEO

2016-2017 FY

panel of recruitment agencies

as per the National Treasury Regulation 16A.6.6

R 3,000,000.00

(fixed price)

participation agreement (South African Civil Aviation Authority)

CEO

Road Traffic Infringement Agency

(a) The RTIA has not in the past three years issued any tender without following the normal tender processes.

(b) – N/A. See answer in (a) above.

(c) – N/A. See answer in (a) above.

(d) – N/A. See answer in (a) above.

(e) – N/A. See answer in (a) above.

Road Traffic Management Corporation

(a) The RTMC has not in the past three years issued any tender without following the normal tender processes.

(b) – N/A. See answer in (a) above.

(c) – N/A. See answer in (a) above.

(d) – N/A. See answer in (a) above.

(e) – N/A. See answer in (a) above.

South African National Roads Agency Limited

  1. (b) (c) (d) and (e) Please see attached

Airports Company of South Africa (ACSA)

Please see attached 2016 and 2017 annexures, and 2015 not yet completed.

Air Traffic and Navigation Services SOC Limited (ATNS)

  • ATNS satisfy its requirements through competitive tender process unless there are justifiable reasons to the contrary. Below is a list of tender issued without following normal tender process.

a) Tender Description

b) Reasons for Deviation

c) Monetary Value

d) method of tender

e) Authorising Authority

Componentization of assets, verification and barcoding

Urgent audit request

R 4,000,000

Closed Tender

CEO

South African Civil Aviation Authority (SACAA)

Seq

Description

Supplier

(a)

Which tenders were issued without following normal tender processes

Microsoft

SAFRAM

AFGEN (Pty) Ltd

Avdex

(b)

What were the reasons for the deviation in each case

Sole Supplier

Sole Supplier

Sole Supplier

Sole Supplier

(c)

What was the monetary value of each tender

R7, 461, 805.00

R5, 532, 258.00

R1, 276.80

R114, 000.00

(d)

How were the tenders issued

Negotiations with international supplier.

Negotiations with international supplier. Annual Software technical Assistance for the Flight inspection equipment.

Negotiations with International Supplier. PAPI light calibration Instrument.

Aircraft Registry System – Contract extension for 12 months

(e)

Who authorised the issuing of each tender

DCA, SACAA Board, and National Treasury

DCA, SACAA Board, and National Treasury

DCA, SACAA Board, and National Treasury

DCA, SACAA Board, and National Treasury

South African Maritime Safety Authority ( SAMSA)

BID DESCRIPTION

REASONS FOR DEVIATION

VALUE OF THE CONTRACT

PROCESS FOLLOWED

AUTHORISED BY

Upgrade of Great Plains

Adhering to National Treasury Circular No 10 of 2016/2017 not to engaged on long term contract agreement for ICT product, software and services.

R 1 672 722.00

Current service requested to upgrade the financial system while waiting for National Treasury to finalize the tender process for an integrated financial system.

ACEO

VMWare Software

Adhering to National Treasury Circular No 10 of 2016/2017 not to engaged on long term contract agreement for ICT product, software and services.

R 2 259 238.85

A quotation process was followed. Quotes were sourced from VMWare local partners. Permission to deviate from the tender process was supported by National Treasury.

Approval granted by National Treasury

Design,implement and support the MPLS Infrastructure

Contract over 15% National Treasury threshold

R2 904 559.04 (vat excl)

SAMSA requested contract extension from National Treasury for over 15% threshold.

Approval granted by National Treasury

Security Services

Tender still pending evaluated and contract award

R 801 436.00

Current supplier requested to extend the contract on a month to month

Approved by SAMSA board

Forensic Audit

Closed Tender

R 556 981.20

The company was appointed through the Company Secretary to ensure that staff members affected by the audit do not have influence on the awarding process.

Approved by the ACEO

Ports Regulator of South Africa

  1. The Ports Regulator has not issued any tenders in the past three financial years without following the normal tender processes.
  2. N/A
  3. N/A
  4. N/A
  5. N/A

Railway Safety Regular of South Africa (RSR)

2014/15 Financial Year

No

Question a

Question b

Question c

Question d

Question e

 

Supply information security solution and system

Selected service provider- services of special nature

R800 000.00

Deviation from a normal procurement process:

The solution requested is only provided by only supplier in Southern Africa. The service provider was approached by the organization for the security solution based on the security breaches that had transpired in the year in question.

Accounting Officer

2015/16 Financial Year

No

Question a

Question b

Question c

Question d

Question e

 

Consultant to conduct a culture alignment intervention in the RSR

Selected service provider- natural continuation

R741 000.00

Deviation from a normal procurement process:

The service provider initially conducted Culture Climate Survey on the employees of the Organization via normal procurement process, therefore this deviation was on the basis of natural continuation of the project.

Accounting Officer

 

Appointment of contractors to evaluate the condition of the current signalling and equipment installed on the Gauteng Region of PRASA

Urgency- safety of Rail Passengers following the train collision due to faulty signals

R742 539.80

Deviation from a normal procurement process:

An independent signalling systems investigation in the Gauteng South region of Metrorail focusing on the safety, technical and operational readiness of the signalling installations employed in the Gauteng Region

Accounting Officer

 

Appointment of contractors to evaluate the condition of the current signalling and equipment installed on the Gauteng Region of PRASA

Urgency- safety of Rail Passengers following the train collision due to faulty signals

R536 800.00

Deviation from a normal procurement process:
An independent signalling systems investigation in the Gauteng North region of Metrorail focusing on the safety, technical and operational readiness of the signalling installations employed in the Gauteng Region

Accounting Officer

 

An independent consultant to assess and investigate the suitability of the Afro 4000 Locomotives for use in South Africa

Urgency- safety of Rail Passengers following procurement of oversized Train Locomotives by the operator

R745 000.00

Deviation from a normal procurement process- Mechanical and Rolling Stock expertise was required urgently for the Afro 4000 to conduct an independent report.

Accounting Officer

2016/17 Financial Year

No

Question a

Question b

Question c

Question d

Question e

 

Service provider to provide strategic legal advice to the RSR on legal issues raised by operators which might have an impact on the organization

Selected service provider- expertise and experience

R2 000 000.00

Deviation from a normal procurement process:

The organisation approached the service provider on the basis of similar work which had been conducted by them before and because of their Regulatory Framework expertise as well as in order not to compromise the organisation if and when other legal issues of the same nature occur from operators as they would have a view of the history.

Accounting Officer

Passenger Rail Agency of South Africa (PRASA)

  1. The tenders issued without following normal tender processes during the period 2014 – 2017 across the PRASA spectrum amount to 243. See attached Annexure A, Column “C”.
  1. The reasons for deviation for tenders issued during the period of 2014 – 2017, see attached Annexure B, Column “D”.
  1. The monetary value of tenders issued during the period of 2014 – 2017, see attached Annexure C, Column “E”.
  1. The method of how tenders were issued during the period of 2014 – 2017, see attached Annexure D, Column “F”.
  1. Tenders were authorized by officials with different levels of responsibilities. Refer to Annexure E, Column “G”.

07 December 2017 - NW3886

Profile picture: Hunsinger, Dr CH

Hunsinger, Dr CH to ask the Minister of Transport

With reference to his reply to question 3560 on 10 November 2017, what was the total cost for the imbizos held for the Moloto Rail Development Corridor Project?

Reply:

Costs involved with regards to imbizos held for the Moloto Rail Development Corridor Project were as follow:

1 October 2013: Organised by Mpumalanga Department of Public Works, Roads and Transport as Provincial October Transport Month event. No cost known

13 July 2014: Funded by PRASA, as it was specifically for providing progress on the status of the Moloto Feasibility study to the Moloto Community, organised by the Department and PRASA. The cost of the event was R528,321.60 No cost known to the Department.

12 April 2015: This was RAF intiative, as part of their RAF on the Road. The Department used the imbizo to provide feedback to the community on progress for the Moloto Rail Corridor Project as part of the Imbizo Progress week. No cost known to the Department.

15 December 2015: The event was organized as part of the Imbizo Week Programeme with the focus on the upgrades of the Moloto Road, R573. The event was funded. No cost Known to the Department.

06 May 2016: The imbizo was a Presidential Siyahlola Monitoring Visit, and was organised and funded by Presidency. No cost known to the Department.

25 April 2016: The imbizo was a SANRAL initiative. No cost known to the Department.

05 June 2016: The imbizo was a Presidency intiative. No cost known to the Department

07 December 2017 - NW3708

Profile picture: Mokgalapa, Mr S

Mokgalapa, Mr S to ask the Minister of International Relations and Cooperation

Have the recommendations of the (a) Charles Nupen report and or (b) Cheadle and Thompson report been implemented; if so, provide details; if not, why not?

Reply:

The reply to the question is as follows:

Quote:

( a) The Charles Nupen report and recommendations were implemented with the involvement of stakeholders. The Departmental Task Team under the Deparmental Bargaining Chamber endorsed the implementation thereof.

(b) The Cheadle and Thompson report and recommendations were partly implemented, whereas some of the recommedations are in the process to be finalised by Management.

Unquote:

07 December 2017 - NW3914

Profile picture: De Freitas, Mr MS

De Freitas, Mr MS to ask the Minister of Transport

With reference to his reply to question 3550 on 10 November 2017, (a) on what date was the advertisement for the positions on the board placed, (b) what was the closing date for applications, (c) what is the current status of the selection process of a full-time board and (d) by which date will the full-time board be appointed?

Reply:

a) The positions were advertised on the 5 February 2017 and 11 June 2017.

b) The closing date was 20 February 2017 and 26 June 2017, respectively.

c) On 13 September 2017 Cabinet resolved that the Transport Ministers Cabinet Memorandum No. 20 of 2017 on the appointment of the members of the Board of Control of PRASA be withdrawn and further resolved that the Minister should consider the appointment of an Interim Board of the Passenger Rail Agency of South Africa (PRASA). The process of appointing the full-time board will be kick-started in the next financial year (2018/19).

d) In the 2018/19 financial year.

07 December 2017 - NW3983

Profile picture: Figg, Mr MJ

Figg, Mr MJ to ask the Minister of Public Works

What are the full details of each of the two international trips undertaken by him recently in terms of (a) the countries visited, (b) who was included in the delegation, (c) the total cost of the trips and (d) the purpose of the trips?

Reply:

What are the full details of each of the two international trips undertaken by him recently in terms of:

(a) International trip one: details of the trip were replied to and submitted to Parliament as per PQ No. 2749. International trip two: official visit to Ethiopia.

(b) Mr Stanley Henderson, Deputy Director General: EPWP

Mr Ignatius Ariyo, Chief Director: EPWP Infrastructure Sector

Ms. Kgomotso Zantsi, Director: EPWP Evaluation and Research

Mr Percy Molefe, Chief Director: International Relations

Mr Thabo Mavimbela, Minister’s Private Assistant

Mr Neo Nage, Minister’s Protector

(c) Total costs of the trip in respect of Mr Henderson, Mr Ariyo and Ms Zantsi were fully paid by the International Labour Organisation (ILO). Total costs of the trip in respect of Minister Nhleko, Mr Molefe, Mr Mavimbela and Mr Nage amounted to R279 779

(d) Attending the 17th International Labour Organisation (ILO) Regional Seminar for Labour-based Practitioners held in Addis Ababa, Ethiopia on 13 – 17 November 2017 under the theme: “Delivering on the Sustainable Development Goals (SDGs): The Employment-Intensive Investment Approach”.

  

06 December 2017 - NW3877

Profile picture: Mathys, Ms L

Mathys, Ms L to ask the Minister of Public Works

What is the (a) name, (b) location, (c) purpose, (d) time line, (e) contractor name and (f) contract value of each public works project currently underway?

Reply:

a) , (b), (c), (d), (e) and (f):

  • The Department of Public Works has approximately 150 number of projects under PMTE Maintenance with a total value of R 5 534 797 456.00 and Professional Fees of R 918 983 587.20.
  • The Department of Public Works has approximately 142 number of projects under PMTE Capital with a total value of R 6 058 441 006.42 and Professional Fees of R 1 178 422 286.42
  • The Department of Public Works has approximately 55 number of projects under DPW Capital with a total value of R 14 145 734.36 and Professional fee of R 190 082 845.60.

DESCRIPTION

NO OF PROJECTS

TOTAL VALUE OF PROJECT

PROFESSIONAL FEE

PMTE Maintenance

150

R 5 534 797 456.00

R 918 983 587.20

PMTE Capital

142

R 6 058 441 006.42

R 1 178 422 286.42

DPW Capital

55

R 14 145 734.36

R 190 082 845.60

  • The location, purpose and details of the service providers are attached herewith (Annexure A)

1. PMTE CAPITAL - PROJECTS ON CONSTRUCTION PHASE

CLIENT DEPT

PROVINCE

TOWN

COMPLEX

DESCRIPTION

WCS NO

STATUS

ANTICIPATED PRACTICAL COMPLETION

CONTRACT PERIOD

CONTRACTOR CASH FLOW AMOUNT

CONSULTANT CASH FLOW AMOUNT

CONTRACTOR'S NAME

AGRICULTURE FORESTRY AND FISHERIES

MPUMALANGA

SKUKUZA

VETERINARY COMPLEX

DEPARTMENT OF AGRICULTURE FORESTRY AND FISHERIES: REFURBISHM ENT AND EXTENSIONS TO THE EXISTING VETERINARY OFFICE SKUKUZA

052069

5B

2017/05/30

12

4289223,09

1313683,00

MBANGA TRADING ENTERPRISE CC

AGRICULTURE FORESTRY AND FISHERIES

GAUTENG

PRETORIA

HARVEST HOUSE

DEPARTMENT OF AGRICULTURE FORESTRY AND FISHERIES: HARVEST HO USE; HAMILTON STREET: PRETORIA: REVAMPING OF PARKING AREA

052143

5B

2017/11/13

12

2603307,42

748873,33

REABETSWE GROUP (PTY) LTD

AGRICULTURE FORESTRY AND FISHERIES

GAUTENG

PRETORIA

SEFALA BUILDING

REPLACEMENT OF THE ROOF WATERPROOFING STRUCTURES

052387

5B

2017/08/17

8

3355085,73

928145,18

AQUAPROOF PROJECTS CC

AGRICULTURE FORESTRY AND FISHERIES

GAUTENG

PRETORIA

AGRICULTURAL : HEAD OFFICE

MAIZE BOARD BUILDING: REPAIR AND MAINTENANCE PROGRAMME

044038

5B

2013/06/29

36

14508532,30

0,00

ABE PROJECTS AND MAINTENANCE CC

ARTS AND CULTURE

FREESTATE

BLOEMFONTEIN

WAR MUSEUM OF THE BOER REPUBLICS

EXPANSION OF THE FIRE PROTECTION SYSTEM

049503

5B

2015/03/31

5

686621,51

113000,00

FIRETECH PROJECTS CAPE TOWN (PTY) LTD

ARTS AND CULTURE

WESTERN CAPE

CAPE TOWN

S A MUSEUM

CONSTRUCTION OF STORAGE STRUCTURE IN COURTYARD

042528

5B

2017/11/16

24

235870000,00

38859479,41

SUPERWAY CONSTRUCTION (PTY) LTD

ARTS AND CULTURE

EASTERN CAPE

HANKEY

 

SARAH BARTMANN CENTRE OF REMEMBRANCE

047427

5B

2018/10/22

30

181235837,63

27300020,00

LUBBE CONSTRUCTION (PTY) LTD

ARTS AND CULTURE

GAUTENG

PRETORIA

NATIONAL LIBRARY OF SOUTH AFRICA

HERITAGE - OLD BUILDING: REMEDIAL WORK

047073

5B

2017/03/29

21

96737951,83

18803091,75

LUBBE CONSTRUCTION (PTY) LTD

ARTS AND CULTURE

GAUTENG

PRETORIA

ARCHIVES BUILDING

HERITAGE - UPGRADING OF FIRE PROTECTION SYSTEM AND REFURBISH MENT OF HVA C AND RELATED INSTALLATIONS

048495

5B

2018/03/29

18

200726227,17

22266685,75

FASTMOVE ELECTRICAL CC

CORRECTIONAL SERVICES

FREESTATE

GOEDEMOED

GOEDEMOED PRISON FARM

THE UPGRADING OF THE WATER CHANNEL AND WATER LINE

022417

5B

2019/10/11

18

81211019,00

8000001,00

TOKOLOGO TECHNICAL ASSIGNMENTS

CORRECTIONAL SERVICES

FREESTATE

VILJOENSDRIF

PRISON

GROENPUNT MEDIUM PRISON: UPGRADING OF THE EXISTING KITCHEN A ND CONVERSION FROM STEAM TO ELECTRICAL

047869

5B

2017/08/14

23

35578791,02

6930517,86

REFEMO MAINTENANCE SERVICES

CORRECTIONAL SERVICES

FREESTATE

GROOTVLEI (FS)

PRISON

SEWAGE AND WATER INFRASTRUCTURE UPGRADE

047923

5B

2018/01/16

22

49552374,80

2932500,00

MLO INVESTMENTS & NEW BOSS CONSTRUCTION JOINT VENT

CORRECTIONAL SERVICES

FREESTATE

KROONSTAD

PRISON

MEDIUM A, B AND COE: REPLACEMENT OF POTATOE PEELER, MEAT SAW , 3- PLATE STOVE, TILTING PAN, CONVETION OVEN AND 2 PHUTU POTS

049701

5B

2015/11/12

6

511669,62

0,00

TSOGA O BUNE BUILDING ENTERPRISE CC

CORRECTIONAL SERVICES

FREESTATE

KROONSTAD

PRISON

IMPLEMENTATION OF EMERGENCY BACK-UP POWER SUPPLY AT KROONSTA D MEDIUM A, MEDIUM B, MEDIUM C & YOUTH CENTRE AND COLLEGE

051574

5B

2015/11/30

4

3476099,97

382700,00

BULA MAHLO TRADING AND PROJECT CC

CORRECTIONAL SERVICES

FREESTATE

WEPENER

PRISON

INSTALLATION OF BACK UP POWER GENERATOR

051586

5B

2016/10/27

6

594717,48

147156,84

BNM CIVIL CONSTRUCTION

CORRECTIONAL SERVICES

WESTERN CAPE

PAARL

DRAKENSTEIN PRISON

OUTSIDE KITCHEN: UPGRADE KITCHEN AND REFURBISH EQUIPMENT, IN CLUDING PAINTINGS & FLOORING

048170

5B

2017/12/09

8

1991312,44

381771,28

ILITHA PAINTERS AND DECORATORS CC

CORRECTIONAL SERVICES

WESTERN CAPE

PAARL

ALLANDALE PRISON

BOUNDARY FENCE PROJECT

053583

5B

2017/06/15

12

7754965,42

468112,00

GORDIAN FENCE SA (PTY) LTD

CORRECTIONAL SERVICES

KWAZULU-NATAL

ESTCOURT

PRISON

HERITAGE - REPLACEMENNT OF EXISTING CORRUGATED IRON BUILDING AND REBUILD WITH BRICK

035878

5B

2017/11/15

36

257665831,23

109967185,98

SANYATI CIVIL ENGINEERING AND CONSTRUCTION PTY LTD

CORRECTIONAL SERVICES

KWAZULU-NATAL

DURBAN

PRISON

PAROLE BOARD FACILITIES: UPGRADING AND EXPANSION OF EXISTING AND PROVISION OF NEW STRUCTURES_(NEW)

041690

5B

2017/05/12

8

3376303,50

1242582,72

MASWIDI CONSTRUCTION CC

CORRECTIONAL SERVICES

KWAZULU-NATAL

PIETERMARITZBURG

NAPIERVILLE PRISON

REPAIR AND MAINTENANCE OF INTEGRATED SECURITY SYSTEM

044016

5B

2019/02/21

36

119969533,73

0,00

JFE GROUP EMPOWERMENT (PTY) LTD

CORRECTIONAL SERVICES

KWAZULU-NATAL

KOKSTAD

PRISON

KOKSTAD MEDIUM AND MAXIMUM CORRECTIONAL CENTRES: FOLLOW ON C ONTRACT: INTEGRATED SECURITY SYSTEM

048437

5B

2019/02/21

36

135359912,29

24600507,26

JFE GROUP EMPOWERMENT (PTY) LTD

CORRECTIONAL SERVICES

EASTERN CAPE

UMZIMKULU

PRISON

SUPPLY AND INSTALLATION OF STANDBY GENERATOR AT MTUNZINI, GR EYTOWN, PORT SHEPSTONE, INGWAVUMA, UMZIMKHULU, MELMOTH, STAN GER AND WESTVILLE

049632

5B

2016/11/04

12

6509570,01

0,00

ERROL FORBAY ELECTRICAL CC

CORRECTIONAL SERVICES

KWAZULU-NATAL

LADYSMITH (KZN)

PRISON

SUPPLY AND INSTALLATION OF STANDBY GENERATOR AT DUNDEE, VRYH EID, LADYSMITH, POMEROY, NEWCASTLE, UTRECHT AND KRANSKOP

049824

5B

2017/08/04

12

6239816,47

0,00

POLO ELECTRICAL CC

CORRECTIONAL SERVICES

GAUTENG

JOHANNESBURG

PRISON

LEEUWKOP:PRISON:REPLACEMENT OF BOILERS AND MAINTENANCE OF BOILERS FOR THE PERIOD OF 24 MONTHS

047918

5B

2018/05/04

24

21796399,63

7381052,58

EXILITE 454 CC

CORRECTIONAL SERVICES

GAUTENG

DEVON

PRISON

REPLACEMENT OF ALL SECURITY / PERIMETER LIGHTING AND PUMPS A T THE PUMP STATION

048900

5B

2017/03/20

4

2551500,06

756963,00

LETLAPA BORWA CIVIL

CORRECTIONAL SERVICES

NORTHERN CAPE

KURUMAN

PRISON

REPLACEMENT OF FOUR IN ONE SLICER, KITCHEN FLOORING , FOOD P ROCESSOR AND MEAT SAW

049653

5B

2017/04/18

10

747394,20

0,00

NOMSA AND SHALILI CONSTRUCTION AND PROJECTS CC

CORRECTIONAL SERVICES

NORTHERN CAPE

UPINGTON

PRISON

INSTALLATION OF BACK UP POWER GENERATOR AT UPINGTON PRISON

051583

5B

2016/12/13

5

1058698,62

105507,00

MAMELLO TRADING 876 CC T/A KH

CORRECTIONAL SERVICES

NORTHERN CAPE

KIMBERLEY

PRISON

REPAIR AND MAINTENANCE PROJECT: FOLLOW ON CONTRACT FOR INTER GRATED SECURITY SYSTEM AT TSHWELOPELE (KIMBERLEY)CENTRE

053008

5B

2018/10/05

36

15562010,74

1099423,00

JFE GROUP EMPOWERMENT (PTY) LTD

CORRECTIONAL SERVICES

NORTH WEST

MAHIKENG

ROOIGROND PRISON

FOLLOW ON CONTRACT FOR THE REPAIR AND MAINTENANCE OF BUILDINGS, CIVIL AND WET SERVICES, FENCING, MECHANICAL AND ELECTRICAL INSTALLATIONS.

039783

5B

2008/05/05

36

17114780,22

20012274,33

JST CONSTRUCTION CC

CORRECTIONAL SERVICES

NORTH WEST

RUSTENBURG

PRISON

RUSTENBURG PRISON: REPAIR & RENOVATION AND UPGRADING OF BUIL DINGS, WET SERVICES AND CIVIL INFRASTRUCTURE.

046456

5B

2018/07/26

36

172060610,25

30816971,41

SHOMANG CONSTRUCTION CC

CORRECTIONAL SERVICES

NORTH WEST

ROOIGROND

PRISON FARM

CONSTRUCTION OF A NEW SEPTIC TANK

049499

5B

2017/04/06

6

2479597,15

630675,37

VAJ CONSTRUCTION AND TRADING JV GLOWING SUNSET TRA

CORRECTIONAL SERVICES

NORTH WEST

RUSTENBURG

PRISON

MEDIUM A: ELECTRICAL BUTCHER SCALE, POTATO PEELER X2 MINCE M ACHINE, BEND SAW

050735

5B

2017/04/29

8

1402034,66

650300,00

COMED SYSTEMS (PTY) LTD

CORRECTIONAL SERVICES

NORTH WEST

LOSPERFONTEIN

PRISON

REPLACEMENT OF TWO BOILERS

050738

5B

2017/04/29

12

21936709,18

2735031,54

SEBUSHI SOMO CONSTRUCTION AND PROJECTS

CORRECTIONAL SERVICES

MPUMALANGA

STANDERTON

PRISON

STANDERTON CORRECTIONAL CENTRE: ADAPTATION AND COMPLETE UPGRADING PHASE 2: WCS 044954

044954

5B

2018/04/29

36

380092799,30

57535227,00

CLEAR CHOICE BUILDERS (PTY) LTD

CORRECTIONAL SERVICES

MPUMALANGA

BARBERTON

PRISON

UPGRADING OF FIVE(05)CALORIFIERS

052107

5B

2016/02/14

5

2075405,31

383950,00

WOOLWICK INVESTMENTS (PTY) LTD

CORRECTIONAL SERVICES

LIMPOPO

THOHOYANDOU

PRISON

DCS:THOHOYANDOU: MATATSHE PRISON: UPRADING OF WASTEWATER TRE ATMENT PLANT AND WATER PURIFICATION PLANT

047870

5B

2018/05/30

24

38688725,03

9935002,20

TAKE NOTE TRADING 73

CORRECTIONAL SERVICES

LIMPOPO

THOHOYANDOU

PRISON

REPLACEMENT OF BOILERS

052535

5B

2018/01/04

24

24310406,54

1986893,08

MAESELA BUILDING CONSTRUCTION

CORRECTIONAL SERVICES

EASTERN CAPE

CRADOCK

PRISON

CONSTRUCTION OF NEW CLASSROOMS AT CRACOCK PRISON

052041

5B

2017/02/17

12

17796149,80

3717780,65

R O SWIKA PROJECTS CC

CORRECTIONAL SERVICES

GAUTENG

PRETORIA

PRISON

PRETORIA MANAGEMENT AREA: UPGRADING OF EXISTING 'C' MAX FACILITY INTO A HIGH SECURITY DETENTION FACILITY

046424

5B

2018/07/18

15

323314121,00

56052989,14

RAUBEX JOINT VENTURE

CORRECTIONAL SERVICES

GAUTENG

PRETORIA

PRISON

INSTALLATION OF A NEW STANDBY GENERATOR

053863

5B

2017/03/29

3

1272940,16

242000,00

DIESEL INNOVATIONS (PTY) LTD

CORRECTIONAL SERVICES

GAUTENG

SANDTON

LEEUWKOP PRISON FARM

REMAINDER CONTRACT: REPAIR AND MAINTENANCE PROGRAMME

038691

5B

2018/05/05

9

20024862,93

3696013,00

MAGODA CIVILS(PTY)LTD

CORRECTIONAL SERVICES

LIMPOPO

TZANEEN

 

REPLACEMENT OF TEMPORARY PRISON WITH A FACILITY FOR 494 INMA TES INCLUDING SECURITY FENCE AND SPORTFIELD: ADDITIONAL ACCO MODATION REQUIREMENTS

041821

5B

2017/09/27

32

234004870,15

40836033,07

MUSAN TRADING ENTERPRISE CC

DEFENCE

WESTERN CAPE

LANGEBAAN

4 SPES FORCES REGIMENT

SALAMANDER BOAT PARK: REPLACEMENT OF BREAKWATER

052017

5B

2017/05/25

7

26363919,37

1415500,00

GUERRINI MARINE CONSTRUCTION CC

DEFENCE

WESTERN CAPE

SIMONSTOWN

NAVAL BASE

EAST YARD: UPGRADING OF WATER DISTRIBUTION SYSTEM

053336

5B

2017/04/29

18

43855986,36

1975976,00

EXEO KHOKELA CIVIL ENGINEERING CONSTRUCTION

DEFENCE

KWAZULU-NATAL

DURBAN

 

ASB: SECURITY INSTALLATION: QUARTERS: MAISONETTE'S ON BLUFF & ESSENHURST ESTATE: SECURITY GATES, BURGLAR PROOFING & LIGH TING

046330

5B

2012/07/02

4

2204999,20

0,00

OMYANGO INVESTMENTS CC

DEFENCE

KWAZULU-NATAL

DURBAN

 

SA NAVY: REFURBISHMENT OF MAIN KITCHEN

052564

5B

2017/05/31

12

37408769,89

32638509,38

DURBAN MAINTENANCE AND BUILDING (PTY) LTD

DEFENCE

GAUTENG

JOHANNESBURG

 

UPGRADING OF KITCHEN EQUIPMENT,,ASB

053688

5B

2017/03/31

6

2314936,36

300000,00

M Q M E BUSINESS ENTERPRISES CC

DEFENCE

NORTHERN CAPE

KIMBERLEY

MILITARY BASE

DISKOBOLOS MILITARY SICK BAY: RESURFACING AND TARRING OF ACC ESS ROAD

052546

5B

2017/10/12

9

4183171,46

339977,43

SEGONYANA PROJECTS CC

DEFENCE

MPUMALANGA

MIDDELBURG (MPU)

4 S A I BATALION

AREA MILITARY HEALTH UNIT: UPGRADING OF BUILDINGS AND CONSTR UCTION OF NEW SICK BAY FAILITY

045457

5B

2017/11/30

24

42858730,92

7036916,92

EXILITE 454 CC

HOME AFFAIRS

KWAZULU-NATAL

HLUHLUWE

HOME AFFAIRS

CONSTRUCTION OF NEW OFFICE ACCOMMODATION

050771

5B

2017/06/09

12

36545115,67

7450000,00

MASBUILD CC

HOME AFFAIRS

NORTH WEST

MMABATHO

 

MMABATHO;VARIOUS FACILITIES: REPAIR AND UPGRADE TO ATAMELANG , MOLOPO AND MANKWE

045668

5B

2016/04/29

24

16866833,18

5448097,23

SOLIDAIRE CONSTRUCTION (PTY) LTD

HOME AFFAIRS

GAUTENG

PRETORIA

 

DEPT OF HOME AFFAIRS: MARABASTAD BUILDING: CONSTRUCTION OF W ALL AND ABLUTION BLOCK (TOILETS)

047658

5B

2014/12/08

6

8750000,00

3025677,81

LUCANGO BUSINESS AFFAIRS (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

FREESTATE

WELKOM

MAGISTRATE'S OFFICE

MAGISTRATE'S OFFICE AND FAMILY ADVOCATE ADDITIONAL ACCOMMODA TION

046406

5B

2017/06/19

18

23302664,28

4314900,00

MADIGA PROJECTS AND SECURITY

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

FREESTATE

ROUXVILLE

MAGISTRATE'S OFFICE

ADDITIONAL ACCOMMODATION

047822

5B

2017/10/20

13

8317898,30

2291230,68

RO SWIKA PROJECTS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

FREESTATE

BLOEMFONTEIN

HIGH COURT

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES

049689

5B

2017/03/15

12

1323000,00

1328836,00

NARE TRADING 503 (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

WESTERN CAPE

LADISMITH (WC)

MAGISTRATE'S OFFICE

ADDITIONAL ACCOMMODATION

032271

5B

2017/11/07

18

13084901,85

4339891,47

SIZISA UKHANYO TRADING 3 CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

WESTERN CAPE

BEAUFORT WEST

MAGISTRATE'S OFFICE

CENTRAL AIR CONDITIONING: UPGRADE AND REPLACE REDUNDANT UNITS

040220

5B

2017/03/01

12

3460920,20

1305500,00

SLYAHLANGANA CONSTRUCTION (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

WESTERN CAPE

CAPE TOWN

MAGISTRATE'S OFFICE

INSTALLATION OF AIR CONDITIONING AND UPGRADING OF BACK-UP GENERATOR

046978

5B

2015/02/11

12

17046930,21

4440400,00

SHATEL CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

WESTERN CAPE

CAPE TOWN

JUSTIA BUILDING

REFURBISHMENT OF JUSTICIA BUILDING FOR FAMILY COURT

047032

5B

2017/04/02

24

111012532,40

20733100,00

EDEL CONSTRUCTION (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

WESTERN CAPE

CAPE TOWN

HIGH COURT

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES

051605

5B

2017/05/25

9

2302857,35

461220,75

AR PROJECTS AND DEVELOPMENTS (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

WESTERN CAPE

ALBERTINIA

MAGISTRATE'S OFFICE

GROUP 1: ALBERTINIA; HEIDELBERG(WC); MOSSEL BAY: BUILDING OF FACILITIES FOR PEOPLE WITH DISABILITIES

053916

5B

2017/05/25

9

1926346,00

381139,24

VINO BUILDING CONSTRUCTIONS AND MULTI P

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

WESTERN CAPE

LAINGSBURG

MAGISTRATE'S OFFICE

GROUP 2: LAINGSBURG; PRINCE ALBERT; MURRAYSBURG: BUILDING OF FACILITIES FOR PEOPLE WITH DISABILITIES

053917

5B

2017/03/09

8

804312,01

360100,00

AFRICAN ILANGA CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

WESTERN CAPE

MOORREESBURG

MAGISTRATE'S OFFICE

GROUP 3: MOORREESBURG; TULBAGH; VAN RHYNSDORP: BUILDING OF FACILITIES FOR PEOPLE WITH DISABILITIES

053918

5B

2017/05/09

9

902073,34

316335,65

AFRICAN ILANGA CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

KWAZULU-NATAL

UMBUMBULU

MAGISTRATE'S OFFICE

ADDITIONAL ACCOMMODATION AND ALTERATIONS

034003

5B

2017/10/31

18

40064000,00

11635920,01

TAURIS GARDEN TRADING 500CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

KWAZULU-NATAL

IMPENDLE

JUSTICE COMPLEX

INSTALLATION OF PREPAID METERS

036711

5B

2017/04/25

3

53963,65

0,00

SIMPHIWE AMANDLA CONSTRUCTION PTY LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

KWAZULU-NATAL

PORT SHEPSTONE

MAGISTRATE'S OFFICE

CONSTRUCTION OF A NEW BUILDING

045757

5B

2017/02/22

24

323114263,53

56172453,89

BASIL READ (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

KWAZULU-NATAL

DURBAN

MAGISTRATE'S OFFICE

CONSTRUCTION OF ADDITIONAL ACCOMMODATION

046386

5B

2019/01/16

30

198282675,66

24950000,00

RAPID BUILDERS AND CONTRACTORS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

KWAZULU-NATAL

VULAMEHLO

MAGISTRATE'S OFFICE

REPAIRS AND RENOVATIONS TO OFFICE BUILDINGS

051045

5B

2018/05/11

24

21876478,55

3301472,04

GLOBACON (PTY) LTD T/A N E F

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

KWAZULU-NATAL

CHARLESTOWN

MAGISTRATE'S OFFICE

UPGRADING OF ELECTRICITY SUPPLY AND INSTALLATION FO METER BOX

053722

5B

2016/11/18

6

406455,60

0,00

POWERCON ELECTRICAL CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

GAUTENG

OBERHOLZER

MAGISTRATE'S OFFICE

SECURITY MEASURES UPGRADE INCLUDING MINOR NEW WORKS OF SEWERAGE PIPES.

023106

5B

2017/07/28

10

9384654,28

3108203,72

KING LAW'S ELECTRICAL CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

GAUTENG

JOHANNESBURG

HIGH COURT

ADDITIONAL ACCOMMODATION: CONVERSION TO THE 7 AND 9 TO 12 FL OORS

041546

5B

2016/11/29

30

440493492,11

69685985,56

YIKUSASA BUILDING CONTRACTORS

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

GAUTENG

VARIOUS CENTRES (GTJ)

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES:GROU P2:TEMBISA,MEADOWLANDS,KLIPTOWN

054047

5B

2016/08/15

6

1673395,62

472880,85

SMZEE PROPERTY DEVELOPMENT

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

GAUTENG

VARIOUS CENTRES (GTJ)

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES:GROU P4:KRUGERSDORP,KHUTSONG

054067

5B

2016/08/15

6

1129135,80

385014,67

SMZEE PROPERTY DEVELOPMENT

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

NORTHERN CAPE

FRASERBURG

MAGISTRATE'S OFFICE

CONSTRUCTION OF ADDITIONAL ACCOMMODATION

046253

5B

2018/07/26 

18

25509632,29

5810000,01

SHATSANE SYSTEMS SOLUTIONS PTY LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

NORTHERN CAPE

KATHU

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES

049619

5B

2014/08/08

3

50791,55

225854,60

OLORATO CATERING AND PROJECTS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

NORTHERN CAPE

VARIOUS CENTES : NORTHERN CAPE

MAGISTRATE'S OFFICE

GROUP2:CONSTRUCTIONOF FACILITIES FOR PEOPLE WITH DISABILITIE S;HANNOVER,RICHMOND,DEAAR,NOUPOORT,PRIESKA,BRITSTOWN

053909

5B

2017/05/04

10

1276203,08

706000,00

ALF AND PHILL BUILDING CONSTRUCTION CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

NORTHERN CAPE

VARIOUS CENTES : NORTHERN CAPE

MAGISTRATE'S OFFICE

GROUP3:CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITI ES:OLIFANTSHOEK,UPINGTON,GRIEKWASTAD

053910

5B

2016/11/25

10

3136140,00

810630,91

SELOANA CONTRACTORS (PTY)LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

NORTHERN CAPE

VARIOUS CENTES : NORTHERN CAPE

MAGISTRATE'S OFFICE

GROUP4:CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILIT IES:KENHARDT,SPRINGBOK,PORT NOLLOTH

053911

5B

2018/05/18

10

1477587,57

1031286,46

BANZI TRADE 26 PTY LTD T/A BOKAMOSO BRICKS

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

NORTH WEST

MAHIKENG

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES

054054

5B

2017/12/01

6

1116926,50

250000,00

SEOKE BUILDING CONSTRUCTION

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

EVANDER

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES

049866

5B

2017/02/16

6

1621970,91

538323,92

MABOSOLA CONSTRUCTION AND PROJECTS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

BALFOUR (MPUMALANGA)

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES

051615

5B

2016/05/19

4

1288949,47

314500,00

SIBONGILE THEMBISILE FLORENCE TRADING CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

BETHAL

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES

051616

5B

2016/07/29

6

2100000,00

850000,00

SILIDI PROJECTS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

VARIOUS CENTRES : MPUMALANGA

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES:GROU P1:ACORNHOEK,MHALA,WHITE RIVER,SABIE

054021

5B

2017/12/13

12

3112057,79

672381,00

TODAY'S DESTINY 47 JV SHWINGS

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

VARIOUS CENTRES : MPUMALANGA

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES:GROU P2:NSIKAZI,KANYAMAZANE,LYDENBURG

054022

5B

2017/03/13

9

2605852,00

924167,00

MOLANCO TRADING ENTERPRISE (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

VARIOUS CENTRES : MPUMALANGA

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES:GROU P3:MDUTYANA,MKOBOLA,KWAMMHLANGA

054023

5B

2017/03/27

9

1616068,50

650094,28

MUSAN TRADING ENTERPRISE CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

VARIOUS CENTRES : MPUMALANGA

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES:GROU P4:ERMELO,CAROLINA,BREYTEN

054025

5B

2017/03/13

9

1697215,80

525852,55

MOLANCO TRADING ENTERPRISE (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

VARIOUS CENTRES : MPUMALANGA

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES:GROU P5:BELFAST,SECUNDA,DAVEL

054026

5B

2017/04/12

9

1800000,00

1301483,50

MUSAN TRADING ENTERPRISE CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

VARIOUS CENTRES : MPUMALANGA

MAGISTRATE'S OFFICE

CONSTRUCTION OF GACILITIES FOR PEOPLE WITH DISABILITIES:GROU P6:VOLKSRUST,PIET RETIEF,AMSTERDAM

054027

5B

2017/07/27

9

1888413,53

445937,00

SIYEPHI TRADING PROJECTS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

PORT ELIZABETH

HIGH COURT

ADDITIONAL ACCOMMODATION REPAIR AND RENOVATIONS

045933

5B

2017/09/29

24

129823286,63

17092730,00

ALFDAV CONSTRUCTION CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

DIMBAZA

PERIODICAL COURT

CONSTRUCTION OF A NEW BUILDING

046173

5B

2018/01/10

24

89924943,24

16643229,07

TRANSTRUCT (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

VARIOUS CENTRES (EC)

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES:GROU P1:ALEXANDRIA,PORT ALFRED

053920

5B

2017/04/12

8

785573,15

0,00

CELISCAN (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

VARIOUS CENTRES (EC)

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PERSONS WITJH DISABILITIES:GR OUP2:CRADOCK,SOMERSET EAST

053921

5B

2016/06/14

6

1574928,24

0,00

S FOURIE

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

VARIOUS CENTRES (EC)

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES:GROU P4:JOUBERTINA,KIRKWOOD,PORT ELIZABETH

053923

5B

2016/07/14

9

3744103,22

0,00

MSNH MAINTENANCE

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

VARIOUS CENTRES (EC)

MAGISTRATE'S OFFICE

CONSTRUCTION OF FACILITIES FOR PEOPLE WITH DISABILITIES:GROU P5:KEISKAMMAHOEK,PEDDIE,STUTTERHEIM

053924

5B

2016/11/09

27

1076119,10

0,00

TYS DEVELOPERS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

GAUTENG

PRETORIA

PALACE OF JUSTICE

HERITAGE - MODIFICATION, UPGRADING AND AUDIT OF SECURITY SYS TEMS IN HIGH COURT AND PALACE OF JUSTICE.

042109

5B

2016/06/02

18

25744559,66

7330998,76

GEORGE THOMAS T/A TRICOR SALES & SERVICE

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

GAUTENG

MAMELODI

MAGISTRATE'S OFFICE

CONSTRUCTION OF A NEW BUILDING

044028

5B

2018/05/25

30

112147259,68

36023566,56

FIKILE CONSTRUCTION (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

GAUTENG

PRETORIA

MAGISTRATE'S OFFICE

REFURBISHMENT OF ABLUTION FACILITY FOR PERSON WITH DISABILIT Y

054388

5B

2016/01/31

3

65221,80

0,00

L AND M TUMO TRADERS CONSTRUCTION AND PROJECTS

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

BITYI

PERIODICAL COURT

CONSTRUCTION OF A NEW BUILDING

044390

5B

2018/01/10

20

62566269,50

10042756,76

DEWING CONSTRUCTION (PTY) LTD

RURAL DEVELOPMENT AND LAND REFORM

KWAZULU-NATAL

LADYSMITH (KZN)

 

NO 49 BEACON STREET: UPGRADING OF ACCOMMODATION

052548

5B

2016/08/22

6

6973536,00

0,00

KHONZI TRADING AND PROJECTS CC

SA POLICE SERVICE

FREESTATE

GARIEP DAM

POLICE STATION

INSTALLATION OF GENERATOR SETS AT NO N DEVOLVED POLICE STATIONS

054500

5B

2017/03/14

6

1356408,08

79480,80

BNM CIVIL CONSTRUCTION CC

SA POLICE SERVICE

WESTERN CAPE

CAPE TOWN

STORES DEPOT

EPPING STORES DEPOT: REPAIR ROOFS AND ASSOCIATED INFRASTRUCT URE

044673

5B

2017/04/12

18

95749155,11

9618300,00

GVK-SIYA ZAMA BUILDING CONTRACTORS (PTY) LTD

SA POLICE SERVICE

WESTERN CAPE

FAURE

SHOOTING RANGE

SAPS COMLEX: UPGRADING OF CIVIL ENGINEER INFRASTRUCTURE

048854

5B

2017/04/19

8

16735332,12

3641015,00

UMZALI CIVILS PTY LTD

SA POLICE SERVICE

WESTERN CAPE

CAPE TOWN

POLICE STATION

INSTALLATION OF GENERATOR SETS AT NON DEVOLVED FACILITIES IN THE WESTERN CAPE REGION

053467

5B

2018/09/13

30

11508990,65

1163800,00

LITE-LINE ELECTRICAL CC

SA POLICE SERVICE

KWAZULU-NATAL

DONNYBROOK

PROJECT VYFSTER

REPAIR AND RENOVATION: CONSTRUCTION OF ADDITIONAL ACCOMMODAT ION.

011014

5B

2017/03/23

6

81583095,40

21848000,00

RAMBROS CONSTRUCTION CC

SA POLICE SERVICE

KWAZULU-NATAL

MELMOTH

PROJECT VYFSTER

REPAIR AND RENOVATION: UPGRADING AND CONSTRUCTION OF ADD ACC

013016

5B

2017/07/11

30

93362031,57

16247324,70

PAN AFRICAN DEVELOPMENT (PTY)

SA POLICE SERVICE

KWAZULU-NATAL

SAWOTI

PROJECT VYFSTER

COURT: LIVING QUARTERS: CELLS: NEWLY BUILD, REPAIR AND RENOV ATE AND CONVERSION OF FACILITIES.

013020

5B

2016/11/01

24

70503212,29

18378189,25

TOKOLOGO TECHNICAL ASSIGNMENTS

SA POLICE SERVICE

KWAZULU-NATAL

COLENSO

S A POLICE COMPLEX

REPAIRS &RENOVATIONS TO STATION. UPGRADING OF EXISTING CELLS . DEMOLISH OLD STRUCTURES. CONSTRUCTION OF ADD ACC.

035895

5B

2017/06/30

24

67628628,52

10896688,89

SIYAXHASANA CONSTRUCTION CC

SA POLICE SERVICE

KWAZULU-NATAL

DURBAN

 

KZN: KWA-MASHU: REPAIR AND RENOVATIONS TO EXISTING POLICE ST ATION AND SINGLE QUARTERS

041851

5B

2016/06/24

36

82906835,92

29973706,61

RODPAUL CONSTRUCTION CC

SA POLICE SERVICE

KWAZULU-NATAL

NTUZUMA

POLICE STATION

CONSTRUCTION OF CCTV CONTROL ROOM

046725

5B

2017/11/10

14

16838823,68

4355889,22

UMZINGWANE CONSTRUCTION AND PROJECTS

SA POLICE SERVICE

KWAZULU-NATAL

DURBAN

POLICE STATION

INSTALLATION OF GENERATOR SET AT VARIOUS POLICE STATIONS

053376

5B

2019/07/13

36

18057083,34

0,00

POLO ELECTRICAL CC

SA POLICE SERVICE

EASTERN CAPE

MALUTI

MILITARY BASE

INSTALLATION OF TEMPORARY WATER SUPPLY BACKUP SYSTEM

054217

5B

2016/09/06

3

423808,10

380004,00

VITSHA PM CONSULTANTS CC

SA POLICE SERVICE

NORTHERN CAPE

KIMBERLEY

POLICE STATION

INSTALLATION OF GENERATOR SETS AT POLICE STATIONS : DOUGLAS, GRIEKWASTAD, HOPETOWN, JAN KEMPDORP, MODERIVIER, PAMPIERSTAD , WARRENTON AND KOOPMANSFONTEIN

053831

5B

2017/01/25

6

2478047,70

241895,28

ANIL M JESSA CC

SA POLICE SERVICE

NORTHERN CAPE

DE AAR

POLICE STATION

INSTALLATION OF GENERATOR SETS AT COLESBURG, SUNRISE, PETRUS VILLE, NONZWAKAZI, VOSBURG AND CALVINIA

053850

5B

2016/03/02

6

2441939,85

217494,90

ANIL M JESSA CC

SA POLICE SERVICE

NORTH WEST

ZEERUST

POLICE STATION

CONSTRUCTION OF ADDITIONAL ACCOMMODATION AND REPAIRS AND RENOVATIONS TO EXISTING FACILITIES

043801

5B

2017/11/02

30

80551731,70

13936667,60

K2017341003 (SOUTH AFRICA)(PTY) LTD

SA POLICE SERVICE

MPUMALANGA

NELSPRUIT

POLICE STATION

INSTALLATION OF A GENERATOR SET AT VARIOUS POLICE STATIONS

053490

5B

2017/03/30

12

4386923,60

500000,00

MAMLI PROJECTS CC

SA POLICE SERVICE

LIMPOPO

MANKWENG

POLICE STATION

PROJECTS_5 STAR, UPGRADE OF POLICE STATION AND CONSTRUCTION OF 8 ADDITIONAL OFFICES,CELLS AND LIVING QUARTERS

014335

5B

2017/03/28

24

60790429,07

7991779,71

MUMS BUSINESS ENTERPRISE CC

SA POLICE SERVICE

LIMPOPO

VUWANI

POLICE STATION

PROJECT 5 STAR, UPGRADING OF POLICE STATION AND CONSTRUCTION OF ADDITIONAL OFFICES

039789

5B

2017/04/04

18

29090508,73

9020181,33

DWELLING INNOVATIONS CC

SA POLICE SERVICE

LIMPOPO

DZANANI

POLICE STATION

UPGRADING OF POLICE STATION,REPAIR AND RENOVATION OF EXISTIN G OFFICE BLOCK & CONSTRUCTION OF ADDITIONAL ACCOMMODATION

039804

5B

2018/05/02

24

66140096,40

12168525,33

CHRYSELDA BUILDING CONSTRUCTION CC

SA POLICE SERVICE

LIMPOPO

TOLWE

S A POLICE QUARTERS

CONSTRUCTION OF NEW CSC,MARRIED & SINGLE QUARTERS,CONVERSION OF EXISTING CELL BLOCK TO GENERAL STOREAND REPAIR AND RENOV ATION TO EXISTING BUILDINGS

040352

5B

2017/11/07

24

43885004,75

6710400,56

MORETENG INVESTMENTS (PTY) LTD

SA POLICE SERVICE

LIMPOPO

HLOGOTLOU

POLICE STATION

REPAIR AND RENOVATION, UPGRADING, CONVERSION AND NEWLY BUILT FACILITIES

042527

5B

2017/03/20

30

71035179,69

12742196,00

ATILE INVESTMENT CC

SA POLICE SERVICE

EASTERN CAPE

PORT ELIZABETH

POLICE STATION

COMPLETE UPGRADING OF THE SAPS COMPLEX INCLUDING PARKING

027026

5B

2017/06/22

24

58398723,04

11706835,57

TRANSTRUCT (PTY) LTD

SA POLICE SERVICE

EASTERN CAPE

WHITTLESEA

POLICE STATION

CONSTRUCTION OF UNDERCOVER PARKING

046836

5B

2016/12/01

8

1301141,39

309700,00

NDZAMELA CONSTRUCTION

SA POLICE SERVICE

EASTERN CAPE

GRAAFF-REINET

POLICE COLLEGE

ACADEMY: COMPLETE UPGRADING OF EXISTING BOUNDARY FENCE TO COMPLEX

049997

5B

2016/03/29

8

5917246,21

1320000,00

POENIE'S BUILDERS CC

SA POLICE SERVICE

EASTERN CAPE

GONUBIE

POLICE STATION

SUPPLY, DELIVERY AND COMPLETE INSTALLATION OF GENERATOR SET

050011

5B

2017/01/03

6

665699,58

90000,00

RAM ELECTRICAL AND CIVIL CONTRACTORS (PTY) LTD

SA POLICE SERVICE

EASTERN CAPE

PORT ELIZABETH

POLICE STATION

KWA ZAKHELE: COMPLETE CONSTRUCTION OF BOUNDARY FENCE

050138

5B

2016/10/10

8

4375764,03

603000,00

BLUE DISA TRADING 754 CC

SA POLICE SERVICE

EASTERN CAPE

PORT ELIZABETH

POLICE STATION

SOUTHDENE GARAGE: COMPLETE CONSTRUCTION BOUNDARY WALL/ FENCE

050144

5B

2016/12/17

8

6950782,99

1470000,00

TWIZZA CIVLS AND BUILDING CC

SA POLICE SERVICE

EASTERN CAPE

ADDO

POLICE STATION

ADDO ACADEMY: COMPLETE CONSTRUCTION OF BOUNDARY FENCE (8KM)

050387

5B

2017/05/18

9

6067463,24

1158500,00

RC ORBAN

SA POLICE SERVICE

EASTERN CAPE

STEYTLERVILLE

POLICE STATION

ACQUISITION OF LAND: ERF 610: PROPOSED ADDITIONAL OFFICE ACC OMMODATION

050487

5B

2016/09/14

9

78935,00

0,00

DEPARTMENT OF JUSTICE (COURTS)

SA POLICE SERVICE

EASTERN CAPE

WHITTLESEA

POLICE STATION

UPGRADE OF ELECTRICITY SUPPLY

050715

5B

2016/09/05

6

492898,28

235000,00

POENIE'S BUILDERS CC

SA POLICE SERVICE

GAUTENG

PRETORIA

 

BON ACCORD: NATIONAL INTERVENTION UNIT: LAVENDER RD

030805

5B

2015/01/16

24

127428694,98

34764001,01

MOKOENA-PHUMI CONSTRUCTION AND PROJECTS CC

SA POLICE SERVICE

GAUTENG

MABOPANE

POLICE STATION

CONSTRUCTION OF POLICE STATION AND SINGLE QUARTERS

033753

5B

2017/05/10

24

31581451,41

5863142,85

ZIDLAPHI KGOMO AND ASSOCIATES CC

SA POLICE SERVICE

GAUTENG

PRETORIA

CENTRAL POLICE STATION AND SINGLE QUARTERS

SEALING OF ROOF OF RESIDENTIAL BLOCK,REPLACEMENT OF DOWN PIP ES AND UPGRADING OF WET SERVICES

039074

5B

2016/06/14

9

16725780,70

7929042,86

SPLISH SPLASH CONSTRUCTION CC

SA POLICE SERVICE

GAUTENG

PRETORIA

DOG SCHOOL

REPLACEMENT OF EXISTING SECURITY FENCE, UPGRADE OF THE FIRE BREAK ROAD AND PROVISION OF TWO ENTRANCE GATES

050128

5B

2016/01/03

18

29529302,11

5774563,80

ZIDLAPHI KGOMO AND ASSOCIATES CC

SA POLICE SERVICE

GAUTENG

CENTURION

POLICE STATION

SAPS: ERASMIA: CONNECTION OF SERVICES TO ERVEN 656 & 657

050143

5B

2016/12/09

6

17472393,17

5599284,29

ISIPHIWO TRADING CC

SA POLICE SERVICE

EASTERN CAPE

UMTATA

RADIO CONTROL CENTRE

CENTRAL POLICE STATION: CONSTRUCITON OF 10111 RADIO CONTROL CENTRE

045954

5B

2014/12/15

20

51221273,41

14973253,97

KGAFELA CONSTRUCTION CC

SA POLICE SERVICE

EASTERN CAPE

LUSIKISIKI

 

CONSTRUCTION OF NEW POLICE STATION ON PORTION 1 OF ERF 49

040174

5B

2016/12/12

18

64246718,15

17324540,40

BRIGHT HOMES CONSTRUCTION PTY LTD

  1. DPW CAPITAL - PROJECTS ON CONSTRUCTION PHASE

CLIENT DEPT

PROVINCE

TYPE

TOWN

COMPLEX

DESCRIPTION

WCS NO

STATUS

ANTICIPATED PRACTICAL COMPLETION

CONTRACT PERIOD

CONTRACTOR CASH FLOW AMOUNT

CONSULTANT CASH FLOW AMOUNT

CONTRACTOR'S NAME

PUBLIC WORKS

EASTERN CAPE

LAND PORTS OF ENTRY

MONANTSA PASS

 

MAINTENANCE AND REPAIRS OF BUILDINGS, CIVIL, MECHANICAL AND ELECTRICAL INFRASTRUCTURE AND INSTALLATIONS: 6 MONTHS INTERI M FACILITY MANAGEMENT/RAMP CONTRACT

054784

5B

2016/12/16

6

419465,13

0

LA NATURA (PTY) LTD

PUBLIC WORKS

WESTERN CAPE

DEPARTMENTAL

CAPE TOWN

SERVICE PRODUCTS

UPGRADING OF NDABENI AND EPPING SERVICE PRODUCTS

046599

5B

2017/08/14

21

46625354,54

5855249,28

PREMA RACITI CONSTRUCTION CC

PUBLIC WORKS

WESTERN CAPE

DEPARTMENTAL

CAPE TOWN

RESEARCH STATION

ANTARTICA ISLAND: SANAE IV: REFURBISHMENT OF THE EXISTING BA SE

049596

5B

2019/01/21

40

177782983,2

15912808,67

NOLITHA ELECTRICAL (PTY) LTD

PUBLIC WORKS

WESTERN CAPE

ACCESSIBILITY

KNYSNA

PRISON

INSTALLATION OF FACILITIES FOR PEOPLE WITH DISABILITIES

048761

5B

2017/05/26 

3

487974,73

0

SOUTH WEST CONTRACTORS

PUBLIC WORKS

WESTERN CAPE

ACCESSIBILITY

WORCESTER

POLICE STATION

INSTALLATION OF FACILITIES FOR PEOPLE WITH DISBILITIES

048770

5B

2013/05/21

6

667339,47

0

MAJIET BUILDERS CC

PUBLIC WORKS

WESTERN CAPE

ACCESSIBILITY

BREDASDORP

AIR FORCE BASE

INSTALLATION OF FACILITIES FOR PEOPLE WITH DISABILITIES

048771

5B

2017/04/02

6

719358,1

0

SOUTH WEST CONTRACTORS

PUBLIC WORKS

WESTERN CAPE

PRESTIGE

CAPE TOWN

PARLIAMENTARY VILLAGES

UPGRADING OF ACCESS CONTROL AT THE THREE PARLIAMENTARY VILLA GES BY MEANS OF USING AN ELECTRONIC SOFTWARE.

042638

5B

2015/10/12

8

37452925,42

8398902,4

BAMBANA MANAGEMENT SERVICES (PTY) LTD

PUBLIC WORKS

WESTERN CAPE

PRESTIGE

CAPE TOWN

PARLIAMENTARY COMPLEX

SWANS GARAGE: REDESIGN TO OPTIMALLY UTILIZE SPACE

053095

5B

2017/03/29

12

13772105,89

729791,13

NOLITHA ELECTRICAL (PTY) LTD

PUBLIC WORKS

GAUTENG

DEPARTMENTAL

JOHANNESBURG

SERVICE PRODUCTS

DEPT OF LABOUR: UPGRADE OF INFRASTRUCTURE (ROADS,PAVEMENT,ST ORM WATER,DRAINAGE SYSTEM INCLUDING BUILDINGS) AT VILLAGE MA IN & SPRINGFILEDS

046600

5B

2017/07/27

24

48796091,89

6303751,11

LANCE MANAGEMENT SERVICES CC

PUBLIC WORKS

GAUTENG

PRESTIGE

PRETORIA

RESIDENTIAL

SECURITY MEASURES AT 321 RIGEL STREET, WATERKLOOF RIDGE

048576

5B

2015/12/03

12

3000000

3000000

COEGA DEVELOPMENT CORP (PTY) LTD

PUBLIC WORKS

EASTERN CAPE

DEPARTMENTAL

PORT ELIZABETH

SERVICE PRODUCTS

DEPT OF LABOUR:PORT ELIZABETH EMPLOYMENT FACTORY: COMPLETE R EPAIRS AND RENOVATIONS

046603

5B

2015/08/19

16

33067434,65

6707215

LAWRENCE AND VICTOR CC

PUBLIC WORKS

EASTERN CAPE

DEPARTMENTAL

PORT ELIZABETH

EBEN DONGES BUILDING

ALTERATIONS AND REFURBISHMENT INCLUDING AIR CONDITIONING AND MECHANICAL INSTALLATION

049911

5B

2018/03/22

8

84611785

8990662,63

NATHAN ALEC DATNOW T/A SHAWSHANK CONSTRUCTION

PUBLIC WORKS

GAUTENG

ACCESSIBILITY

CENTURION

MILITARY BASE

INSTALLATION OF FACILITIES FOR PEOPLE WITH DISABILITIES AT LYTTELTON DOD

048739

5B

2017/10/11

6

2888473,14

0

HILLPET GENERAL DEALER CC

PUBLIC WORKS

GAUTENG

ACCESSIBILITY

HAMMANSKRAAL

 

DITHOLO MILITARY TRAINING COLLEGE:INSTALLATION OF FACILITIES FOR PEOPLE WITH DISABILITIES

048763

5B

2017/03/02

4

304881,6

0

PT LESHEGO TRADING AND PROJECTS(PTY)LTD

PUBLIC WORKS

GAUTENG

PRESTIGE

PRETORIA

BRYNTIRION

HERITAGE - CONSTRUCTION OF GATE 3 AND REFURBISHMENT OF EXIST ING GATE 4

044051

5B

2017/06/29

18

19491791,97

7628106,3

EASY SECURITY AUTO GATES AND GUARDS CC

PUBLIC WORKS

GAUTENG

PRESTIGE

PRETORIA

UNION BUILDINGS

HERITAGE - JAKARANDA PROJECT

048582

5B

2015/11/30

12

30443000

0

COEGA DEVELOPMENT CORP (PTY) LTD

PUBLIC WORKS

GAUTENG

PRESTIGE

PRETORIA

 

INSTALLATION OF SECURITY MEASURES AT 287 ALBERT STREET

052426

5B

2015/11/02

6

5577592,5

2600000

COEGA DEVELOPMENT CORP (PTY) LTD

PUBLIC WORKS

GAUTENG

PRESTIGE

PRETORIA

 

INSTALLATION OF SECURITY MEASURES AT 238 INDUS STREET

052427

5B

2015/11/02

6

3113781,49

120999

COEGA DEVELOPMENT CORP (PTY) LTD

PUBLIC WORKS

GAUTENG

DOLOMITE

PRETORIA

 

DRMS PHASE 4: EMERGENCY INVESTIGATIONS IN SUPPORT OF THE DOLOMITE RISK MANAGEMENT STRATEGY FOR THE NATIONAL DEPARTMENT OF PUBLIC WORKS

049316

5B

2016/02/27

36

13712670,12

0

KNIGHT PIESOLD (PTY) LTD

PUBLIC WORKS

GAUTENG

INNER CITY REGENERATION

PRETORIA

 

SALVOKOP: BULK SERVICES FOR STATSSA

052360

5B

2015/10/26

7

54519595,19

13701351,24

STATS SA D AND C JV

PUBLIC WORKS

GAUTENG

DEPARTMENTAL

PRETORIA

CIVITAS BUILDING

REPLACEMENT OF LIFTS

052129

5B

2016/09/20

32

55323905,49

3000000

OTIS (PROPRIETARY) LTD

PUBLIC WORKS

GAUTENG

DOLOMITE

PRETORIA

SWARTKOP AIR FORCE BASE

UPGRADING OF WET SERVICES

044991

5B

2016/02/24

24

74238616,36

5130000

BOFEPI PROJECT MANAGEMENT CC

PUBLIC WORKS

GAUTENG

DOLOMITE

CENTURION

POLICE COMPLEX

WIERDA BRIDGE, ERASMIA, IRENE COMMAND AND HOME AFFAIRS: DOLO MITE RISK MANAGEMENT: UPGRADING OF CIVIL ENGINEERING SERVICE S

045688

5B

2017/11/07

10

9584996,86

1850000

MAAUASO PROJECT CC

PUBLIC WORKS

GAUTENG

DOLOMITE

PRETORIA

 

DRMS: DOD & SAAF 68 AIR SCHOOL NORTH AND SOUTH: BULK WATER CONNECTION AND SECONDARY ENGINEERING SERVICES: REPLACEMENT AND UPGRADE

047888

5B

2017/11/08

26

87400160,45

8208000

SOUTH SOUND CIVILS/ EXEO KHOKELA CIVIL JOINT VENTURE

PUBLIC WORKS

LIMPOPO

LAND PORTS OF ENTRY

STOCKPOORT

BORDER POST

LAND PORTS OF ENTRY: GROBLERS BRIDGE AND STOCKPOORT: APPOINT MENT OF CONSULTANTS: MAINTENANCE AND SERVICING OF BUILDING, CIVIL MECHANICAL AND ELECTRICAL INFRASTRUCTURE AND INSTALLA

052734

5B

2019/06/21

36

39933817,76

1647900,78

CALEDON RIVER PROPERTIES CC

PUBLIC WORKS

NORTH WEST

LAND PORTS OF ENTRY

VARIOUS CENTRES: NORTH WEST

BORDER POSTS

BRAY, MAKGOBISTAD AND SWARTKOPFONTEIN: MAINTENANCE, SERVICIN G AND REPAIR OF BUILDINGS, CIVIL, MECHANICAL AND ELECTRICAL INFRASTRUCTURE AND INSTALLATIONS

052982

5B

2019/03/29

36

21651162,97

2465000

CALEDON RIVER PROPERTIES CC

PUBLIC WORKS

NORTH WEST

LAND PORTS OF ENTRY

VARIOUS CENTRES: NORTH WEST

BORDER POSTS

RAMATLABAMA, KOPFONTEIN AND DERDEPOORT: 36 MONTHS MAINTENANC E, SERVICING AND REPAIR OF BUILDINGS, CIVIL, MECHANICAL AND ELECTRICAL INFRASTRUCTURE AND INSTALLATIONS

052983

5B

2019/06/21

36

41434266,46

2020437,51

CALEDON RIVER PROPERTIES CC

PUBLIC WORKS

MPUMALANGA

LAND PORTS OF ENTRY

OSHOEK

BORDER POST

CONSTRUCTION/IMPLEMENTATION OF CRASH CUSHIONS/BARRIERS

053327

5B

2015/12/09

6

2789409,8

304699,2

SHAICON TENDERING SERVICES

PUBLIC WORKS

MPUMALANGA

LAND PORTS OF ENTRY

JEPPES REEF

BORDER POSTS

MAINTANANCE,SERVICING AND REPAIRS OF BUILDINGS,CIVIL MECHANICAL AND ELECTRICAL INFRASTRUCTURE AND INSTALLATIONS

053366

5B

2019/08/30

36

14220232,26

0

LA NATURA (PTY) LTD

PUBLIC WORKS

NORTHERN CAPE

LAND PORTS OF ENTRY

MCCARTHYSRUST

BORDER POSTS

BCOCC: MAINTANANCE AND SERVICING OF BUILDINGS, CIVIL, MECHANICAL AND ELECTRICAL INFRASTRUCTURE AND INSTALLATIONS

053776

5B

2019/06/13

36

31107662,5

2650000

RUWACON (PTY) LTD

PUBLIC WORKS

NORTHERN CAPE

LAND PORTS OF ENTRY

VIOOLSDRIFT

BORDER POSTS

MAINTENANCE AND SERVICING OF BUILDINGS, CIVIL, MECHANICAL AN D ELECTRICAL INFRASTRUCTURE AND INSTALLATIONS AT ALEXANDER B AY AND VIOOLSDRIFT

053777

5B

2019/06/13

36

47699963,52

2940000

RUWACON (PTY) LTD

PUBLIC WORKS

NORTHERN CAPE

LAND PORTS OF ENTRY

GEMSBOK

BORDER POST

MAINTENANCE AND SERVICING OF BUILDINGS, CIVIL, MECHANICAL AN D ELECTRICAL INFRASTRUCTURE AND INSTALLATIONS AT GEMSBOK, TW EE RIVIEREN AND RIETFONTEIN PORTS OF ENTRY

053820

5B

2019/06/14

36

25240177,65

2200000

RUWACON (PTY) LTD

PUBLIC WORKS

NORTHERN CAPE

LAND PORTS OF ENTRY

NAKOP

BORDER POST

MAINTENANCE AND SERVICING OF BUILDINGS, CIVIL, MECHANICAL AN D ELECTRICAL INFRASTRUCTURE AND INSTALLATIONS AT NAKOP AND ONSSEEPKANS PORTS OF ENTRY

053821

5B

2019/06/13

36

22192989,34

2100000

RUWACON (PTY) LTD

PUBLIC WORKS

EASTERN CAPE

ACCESSIBILITY

BARKLY EAST

PRISON

COMPLETION OF CONTRACT 1

048402

5B

2017/08/07

3

772582,09

0

CONSA TRADING

  1. PMTE MAINTENANCE - PROJECTS ON CONSTRUCTION PHASE

CLIENT DEPT

PROVINCE

TOWN

COMPLEX

DESCRIPTION

WCS NO

STATUS

ANTICIPATED PRACTICAL COMPLETION

CONTRACT PERIOD

CONTRACTOR CASH FLOW AMOUNT

CONSULTANT CASH FLOW AMOUNT

CONTRACTOR'S NAME

PUBLIC WORKS

KWAZULU-NATAL

ESHOWE

OFFICE BLOCK

HERITAGE - REHABILITATION OF SANDF: JOHN ROSS HIGHWAY

046985

5B

2017/07/04

24

51976303,72

14318436,58

TAURIS GARDEN TRADING 500CC

PUBLIC WORKS

KWAZULU-NATAL

PIETERMARITZBURG

WORKSHOPS

REHABILITATION OF OLD DPW WORKSHOPS ON PRINCE EDWARD STREET

050033

5B

2019/06/01

30

247539864,2

45538151,41

EMB JOINT VENTURE

PUBLIC WORKS

GAUTENG

BRAKPAN

 

REHABILITATION OF OFFICES FOR ANY CLIENT DEPARTMENT (79 HIGH STREET)

049345

5B

2018/04/21

18

31412907,43

5811387,8

KWAGGA HOLDINGS (PTY)LTD

PUBLIC WORKS

NORTHERN CAPE

KIMBERLEY

 

REHABILITATION OF BUILDINGS FOR SAPS (ROODEPAN)

049340

5B

2018/02/27

12

5359602,27

1900000

MMANYANE CONSTRUCTION

PUBLIC WORKS

MPUMALANGA

NELSPRUIT

 

REHABILITATION OF OLD PRISON IN ERMELO,ERF NO.73IT

050782

5B

2017/12/28

18

26246002,61

6790852,38

MUSAN TRADING ENTERPRISE CC

PUBLIC WORKS

LIMPOPO

TZANEEN

LABOUR BUILDING

HERITAGE - REHABILITATION OF EXISTING BUILDING FOR SAPS

044323

5B

2012/07/16

18

3447230,7

1299845,34

MEONDO JV QCOBS

PUBLIC WORKS

GAUTENG

PRETORIA

CENTRAL GOVERNMENT OFFICES

HERITAGE - UPGRADING

041384

5B

2008/03/05

18

41384120,18

9158472,98

SIGHT LINES PIPE SURVEY SERVICES (PTY) LTD

PUBLIC WORKS

GAUTENG

PRETORIA

 

HERITAGE - 38 CHURCH SQUARE (OLD RESERVE BANK BUILDING): UPG RADING

044271

5B

2016/02/27

10

65000000

22252981,17

MORONGWA BUSINESS ENTERPRISE AND VICMOL CONSTRUCTION

PUBLIC WORKS

GAUTENG

PRETORIA

CENTRAL GOVERNMENT OFFICES

INSTALLATION OF INTERIM SECURITY MANAGEMENT EQUIPMENT

046538

5B

2019/11/22

36

38032190,58

3691013,6

COOL BREEZE AIRCONDITIONING & REFRIGERATION CC

PUBLIC WORKS

GAUTENG

PRETORIA

MAGISTRATE'S OFFICE

RESTORATION OF OLD MAGISTRATE COURT

049065

5B

2018/04/25

18

173163445,1

23667022,51

LUBBE CONSTRUCTION (PTY) LTD

ARTS AND CULTURE

WESTERN CAPE

CAPE TOWN

 

HERITAGE - ROBBEN ISLAND: INTERVENTION STRATEGY FOR A COMPRE HENSIVE FACILITIES MANAGEMENT CONTRACT

054104

5B

2019/04/13

48

112000000

0

COEGA DEVELOPMENT CORP (PTY) LTD

CORRECTIONAL SERVICES

FREESTATE

VENTERSBURG

PRISON

REPAIR AND RENOVATIONS

040824

5B

2018/05/25

17

7000286,4

1172300

JUA DEVELOPERS CC

CORRECTIONAL SERVICES

WESTERN CAPE

SWELLENDAM

BUFFELSJACHTRIVER PRISON

REPAIRS TO BUILDINGS, AND RELATED SERVICES

040703

5B

2014/01/17

24

24126852

4000704,68

SEBATA SEBATANA VISION BUILD

CORRECTIONAL SERVICES

WESTERN CAPE

CALEDON

PRISON

REPAIR OF BUILDINGS AND RELATED SERVICES

040706

5B

2014/01/17

24

37768062,54

3391967,36

SEBATA SEBATANA VISION BUILD

CORRECTIONAL SERVICES

WESTERN CAPE

PAARL

DRAKENSTEIN PRISON

REPAIR AND MAINTENANCE OF PRISON BUILDINGS AND RELATED SERVICES

040714

5B

2017/12/08

24

44828728,51

6083350

NOLITHA ELECTRICAL (PTY) LTD

CORRECTIONAL SERVICES

WESTERN CAPE

PORTERVILLE

VOORBERG PRISON

REPAIR OF HOUSING ACCOMMODATION, BUILDINGS AND RELATED SERVICES

040842

5B

2014/02/21

24

19418527,65

3894700

SEBATA SEBATANA VISION BUILD

CORRECTIONAL SERVICES

WESTERN CAPE

GOODWOOD

PRISON

:REPAIRS TO BUILDINGS AND WET SERVICES

044464

5B

2019/09/28

36

52431123,77

5414475,27

NOLITHA ELECTRICAL (PTY) LTD

CORRECTIONAL SERVICES

WESTERN CAPE

CAPE TOWN

PRISON

VOORBERG, OBIQUA, DWARSRIVIER PRISONS:REPAIR, MAINTENANCE & OPERATION OF WATER & SEWERAGE WORKS

050784

5B

2018/07/13

24

32525866,68

2803529,6

ZANA MANZI SERVICES PTY LTD

CORRECTIONAL SERVICES

EASTERN CAPE

UMZIMKULU

PRISON

REPAIRS AND RENOVATIONS FOR BUILDING RELATED SERVICES.

040818

5B

2017/03/12

24

10839301,79

4990394,37

SIFIKILE BUSINESS ENTERPRISE CC

CORRECTIONAL SERVICES

KWAZULU-NATAL

GLENCOE

HOUSES

REPAIRS AND RENOVATIONS TO 48 HOUSES

041219

5B

2018/06/14

18

26502630

10005088,14

CRYSTAL LAGOON INVESTMENTS 44 CC

CORRECTIONAL SERVICES

KWAZULU-NATAL

EMPANGENI

PRISON

REPAIR AND MAINTENANCE OF ELECTRICAL AND MECHANICAL INSTALLA TION

044012

5B

2012/02/25

36

65755285,4

9758027,59

AERO-DUCT MOYA CC

CORRECTIONAL SERVICES

KWAZULU-NATAL

DURBAN

PRISON

WESTVILLE REPAIR AND MAINTENANCE FOR STEAM LINES, CALORIFIED BOILERS AND KITCHEN EQUIPMENT

044257

5B

2015/01/23

36

106097943,9

11700000

TOKOLOGO TECHNICAL ASSIGNMENTS

CORRECTIONAL SERVICES

KWAZULU-NATAL

PIETERMARITZBURG

PRISON

PIETERMARITZBURG OLD AND NEW PRISON : MAINTENACE FOR BULK ELECTRICAL AND MECHANICAL INSTALLATIONS

044487

5B

2017/09/07

36

70634555,84

13542495,47

MISHOE TRADING AND PROJECTS (PTY) LTD

CORRECTIONAL SERVICES

GAUTENG

BOKSBURG

PRISON

GROUP 4 PRISONS:REPAIR AND UPGRADE OF BUILDINGS AND RELATED SERVICES:CONTRACT 1(PRISON PRECINT)

037448

5B

2018/07/27

24

88723368,97

24370697,12

LETLAPA BORWA CIVIL

CORRECTIONAL SERVICES

GAUTENG

DEVON

PRISON

DEVON PRISON: CONDITION BASED MAINTENANCE FOR WATER AND SEWE R PLANT

050236

5B

2018/03/06

10

6881729,7

1824244,97

NICKELODIA TRADING (PTY) LTD

CORRECTIONAL SERVICES

GAUTENG

HEIDELBERG (GAUTENG)

PRISON

HEIDELBERG PRISON: REPAIR MAINTENANCE OF ELECTRICAL AND MECHANICAL INSTALLATIONS

051550

5B

2018/01/26

24

28378826,38

2847699,21

SEBUSHI SOMO CONSTRUCTION AND PROJECTS

CORRECTIONAL SERVICES

GAUTENG

NIGEL

PRISON

NIGEL PRISON: REPAIR AND MAINTENANCE OF ELECTRICAL AND MECHA NICAL INSTALLATIONS FOR 24 MONTHS

051555

5B

2018/04/24

24

43768378,55

4787490

SEBUSHI SOMO CONSTRUCTION AND PROJECTS

CORRECTIONAL SERVICES

GAUTENG

VEREENIGING

PRISON

VEREENIGING PRISON: REPAIR AND MAINTENANCE OF ELECTRICAL AND MECHANICAL INSTALLATIONS

051558

5B

2017/09/29

24

36235923,33

4914418,35

SEBUSHI SOMO CONSTRUCTION AND PROJECTS

CORRECTIONAL SERVICES

NORTH WEST

MOGWASE

PRISON

REPAIR AND UPGRADING OF THE ENTIRE CENTRE

037481

5B

2019/04/24

36

130026531,1

33144817

SEBUSHI SOMO CHUENE MATLALA JV

CORRECTIONAL SERVICES

NORTH WEST

ROOIGROND

PRISON

REPAIR, MAINTENANCE AND OPERATIONS OF WATER SEWERAGE

045603

5B

2018/05/10

24

38248128

5503651,67

EXILITE 454 CC

CORRECTIONAL SERVICES

EASTERN CAPE

GRAAFF-REINET

PRISON

REPAIR AND RENOVATIONS OF BUILDINGS,RELATED SERVICES, ELECTR ICAL AND MECHANICAL INSTALLATIONS AND CIVIL INFRSTRUCTURE

037464

5B

2017/05/11

14

21808636

7310000

RUWACON (PTY) LTD

CORRECTIONAL SERVICES

EASTERN CAPE

COFIMVABA

PRISON

COFIMVABA, NQAMAKWE,GOEDEMOED, WILLOWVALE PRISON:REPAIR MAINTENANCE AND OPERATIONS OF WATER AND SEWERAGE WORKS

044114

5B

2020/03/07

36

30627895,44

4341000

WATER SOLUTIONS SA HEAD OFFICE

CORRECTIONAL SERVICES

EASTERN CAPE

BARKLY EAST

PRISON

REPAIR AND MAINTENANCE BUILDINGS, RELATED SERVICES, ELECTRICAL AND MECHANICAL INSTALLATIONS AND CIVIL INFRASTRUCTURE

040693

5B

2011/12/09

36

7186332,97

3134119,8

SOMANA CONSTRUCTION CC

CORRECTIONAL SERVICES

EASTERN CAPE

MOUNT AYLIFF

PRISON

MOUNT AYLIFF PRISON: MAINTENANCE FOR BUILDINGS RELATED AND WET SERVICES, MECHANICAL, ELECTRICAL AND CIVIL INFRASTRUCTURE

044483

5B

2017/02/01

12

19357796,52

6939870,6

BITUPQUIP CONSTRUCTION CC

CORRECTIONAL SERVICES

EASTERN CAPE

UMTATA

PRISON

REFURBISHMENT OF DOMESTIC WATER RETICULATION AND CIVIL INSTA LLATION

050594

5B

2018/06/07

15

58910461,15

6547329,11

SISONKE / LEBAKA JV

DEFENCE

FREESTATE

BLOEMFONTEIN

 

DE BRUG COMPLEX: REPAIRS AND MAINTENANCE OF SEWER SYSTEM

047317

5B

2018/05/27

12

7629595,37

800000,01

REDER CONSTRUCTION

DEFENCE

FREESTATE

BLOEMFONTEIN

 

BLOEMSPRUIT COMPLEX: REPAIRS AND RENOVATIONS OF SEWER SYSTEM

047318

5B

2018/06/25

23

22274635,92

3215443

BBT ELECTRICAL AND PLUMBING CONSTRUCTION AND MAINTENANCE

DEFENCE

FREESTATE

BLOEMFONTEIN

 

REPAIRS AND RENOVATION TO BUILDING 1,2,5, TO 8 AND 21 AT MPA TEMPE

049859

5B

2018/03/02

12

3507568,98

1161900

SOLOMON & SMITH PROPERTY DEVELOPERS AND BUILDERS

DEFENCE

FREESTATE

BLOEMSPRUIT

BLOEMSPRUIT AIR FORCE BASE

REPAIR & RENOVATION TO BUILDINGS 70, 81, 82, 83, 95, 104, 105, 107 AND 318: GROUP 5

049921

5B

2017/11/21

12

15858002,28

2684100

MBIKIZA GROUP OF COMPANIES (PTY) LTD

DEFENCE

WESTERN CAPE

LANGEBAAN

AIR FORCE BASE

BUILDING 116: REPAIR OF LEAKING ARMOUR ROOF

047471

5B

2018/02/28

7

4350627,76

2737316

T.R. MECHANICALS 786 CC

DEFENCE

WESTERN CAPE

CAPE TOWN

WINGFIELD MILITARY BASE

REPAIR AND MAINTENANCE OF BUILDINGS

048960

5B

2017/11/09

14

7194229,68

4007908

ILITHA PAINTERS AND DECORATORS CC

DEFENCE

WESTERN CAPE

CAPE TOWN

NAVAL BASE

SIMONSTOWN NAVAL BASE: REPAIRS TO FMU BUILDING 1032 EAST YARD

052086

5B

2018/05/23

12

41383305,67

4180191,17

NOLITHA ELECTRICAL (PTY) LTD

DEFENCE

KWAZULU-NATAL

DURBAN

S A N D F COMPLEX

SMITH STREET:REPAIRS AND RENOVATIONS INCLUDING ELECTRICAL AND FENCING

028207

5B

2018/01/25

13

18131499,28

6538095,18

SERENGETI INTERIORS CC

DEFENCE

GAUTENG

JOHANNESBURG

MILITARY BASE

46 BRIGADE: REPAIR AND RENOVATIONS TO MILITARY BASE

046946

5B

2018/08/23

18

44714673,9

7650000

ZIDLAPHI KGOMO AND ASSOCIATES CC

DEFENCE

GAUTENG

HEIDELBERG (GAUTENG)

HOUSES

REPAIR AND RENOVATIONS TO MILITARY HOUSE

046952

5B

2018/01/27

18

82283420,28

15222432,74

LETLAPA BORWA CIVIL

DEFENCE

GAUTENG

ZUURBEKOM

HOUSES

REPAIR AND RENOVATION TO MILITARY HOUSE

046954

5B

2017/11/01

12

21866112,27

3624240,87

TCT CIVIL AND CONSTRUCTION CC

DEFENCE

GAUTENG

JOHANNESBURG

 

SA IRISH MILITARY BASE: REPAIRS AND RENOVATIONS TO ENTIRE MI LITARY BASES

046956

5B

2018/06/14

18

28550136,28

5955061

SHUMANIE PROPERTY MANAGEMENT SERVICES

DEFENCE

NORTHERN CAPE

KIMBERLEY

3 S A I BATALION

REPAIRS AND RENOVATIONS TO THE MESS COMPLEX

046877

5B

2017/04/12

8

6821988,47

1740826,9

COURTESY CATERS MANAGEMENT CC

DEFENCE

NORTHERN CAPE

DE AAR

97 AMMUNITION DEPOT

REPAIRS AND RENOVATION TO 184 AMMUNATION STORE DOORS

049863

5B

2018/09/13

18

2510526,5

950000

SELOANA CONTRACTORS (PTY)LTD

DEFENCE

NORTHERN CAPE

JAN KEMPDORP

93 AMMUNITION DEPOT

REPAIR AND RENOVATION TO NON COMMISSIONED OFFICERS MESS

049879

5B

2018/07/27

12

13552936,45

1974366,24

MBIKIZA GROUP OF COMPANIES (PTY) LTD

DEFENCE

NORTHERN CAPE

JAN KEMPDORP

93 AMMUNITION DEPOT

REPAIRS AND RENOVATIONS TO SINGLE QUARTERS, BUILDINGS 132, 1 33, 134 AND 138

049881

5B

2017/08/31

12

9288950,55

1374580,01

DIMENGE S PROJECTS CC

DEFENCE

MPUMALANGA

NELSPRUIT

MILITARY BASE

SANDRIVER: REPAIRS AND RENOVATION OF THE BASE

050600

5B

2018/07/01

24

15782234,87

4300000

MUSAN TRADING ENTERPRISE CC

DEFENCE

MPUMALANGA

NELSPRUIT

MILITARY BASE

REPAIRS AND RENOVATION OF 55 GRANIET NELSPRUIT CLUB

050601

5B

2017/09/24

24

34104928,13

9781968

MUSAN TRADING ENTERPRISE

DEFENCE

EASTERN CAPE

PORT ELIZABETH

MILITARY BASE

REPAIR AND RENOVATION OF THE HANGAR: AIRCRAFT HANGAR NO. 169 : 15 SQUADRON

051677

5B

2017/10/30

12

28522704,45

1813918,41

BLUE DISA TRADING 754 CC

DEFENCE

EASTERN CAPE

UMTATA

MILITARY BASE

14 SAI: REFURBISHMENT OF INTERNAL WATER RETICULATION AND SEW ERAGE SYSTEM

049605

5B

2018/12/08

18

26991899,35

4000000,1

BLUE DISA TRADING 754 CC

DPW - PRESTIGE

WESTERN CAPE

CAPE TOWN

PARLIAMENTARY COMPLEX

HERITAGE - REFURBISHMENT OF NCOP BUILDING, INCLUDING HVAC, ELECTRICAL AND ELECTRONIC INSTALLATIONS

044232

5B

2019/04/17

24

103200034,1

15605259,84

NOLITHA ELECTRICAL (PTY) LTD

DPW - PRESTIGE

WESTERN CAPE

CAPE TOWN

PARLIAMENTARY VILLAGES

REFURBISHMENT OF RESIDENCES OF SESSIONAL OFFICIALS IN THE TH REE PARLIAMENTARY VILLAGES.

045661

5B

2018/07/30

36

140012045,5

34140890,51

VUSELA CONSTRUCTION (PTY)LTD

DPW - PRESTIGE

WESTERN CAPE

CAPE TOWN

PARLIAMENTARY COMPLEX

CT: OFFICIAL OFFICE ACCOMMODATION: PROVIDE INTEGRATED FACILITIES MANAGEMENT SERVICES (FOR A 5 YEAR PERIOD)

046547

5B

2019/08/19

60

561021815,1

10912538,62

ARCUS FACILITIES MANAGEMENT (PTY) LTD

DPW - PRESTIGE

WESTERN CAPE

CAPE TOWN

PARLIAMENTARY VILLAGES

CT: OFFICIAL RESIDENTIAL ACCOMMODATION: PROVIDE INTEGRATED FACILITIES MANAGEMENT SERVICES. (FOR A 5 YEAR PERIOD)

046548

5B

2019/08/19

60

541033745,5

21657079,87

BROLL PROPERTY GROUP (PTY) LTD - FACILITIES

DPW - PRESTIGE

WESTERN CAPE

CAPE TOWN

PARLIAMENTARY COMPLEX

HERITAGE - TUYNHUYS: PROPOSED NEW FURNITURE AND ANCILLARY ST ORE, BUSINESS HUB, PARAPLEGIC PLATFORM STAIR LIFT AND SECURI TY INSTALLATIONS

049416

5B

2017/09/06

12

57971580,66

12631630

PREMA RACITI CONSTRUCTION CC

DPW - PRESTIGE

WESTERN CAPE

CAPE TOWN

PARLIAMENTARY COMPLEX

HERITAGE - MARKS BUILDING: EXTERNAL RENOVATIONS TO THE BUILD ING

050720

5B

2018/07/05

18

40097200,45

6011978,05

PREMA RACITI CONSTRUCTION CC

DPW - PRESTIGE

WESTERN CAPE

CAPE TOWN

GROOTE SCHUUR ESTATE

HERITAGE - BAIE DANKIE/WAG'N BIETJIE/RHEEZICHT: REPLACE EXISTING THATCH ROOF

050768

5B

2017/02/11

6

728368,8

0

ELIM ROOFTHATCHERS CC

DPW - PRESTIGE

GAUTENG

PRETORIA

 

HERITAGE - REFURBISHMENT OF HOUSE 23

044661

5B

2007/12/14

6

351368

368822,81

DIRHAM CONSTRUCTION MANAGEMENT CC

DPW - PRESTIGE

GAUTENG

PRETORIA

 

HERITAGE - REFURBISHMENT OF HOUSE 15

044662

5B

2007/12/14

6

228979

372879,02

DIRHAM CONSTRUCTION MANAGEMENT CC

DPW - PRESTIGE

GAUTENG

PRETORIA

 

INTERNAL & EXTERNAL MAINTENANCE OF HOUSE 205 ORION IN WATERK LOOF

053320

5B

2016/03/02

12

2941402,9

2941402,9

COEGA DEVELOPMENT CORP (PTY) LTD

DPW - PRESTIGE

GAUTENG

PRETORIA

 

HERITAGE - IMPLEMENTATION OF CRACKS REPAIR AND OF UNDERPIN- NING OF GOEDEHOOP HOUSE

049724

5B

2016/03/02

12

3000000

4854296,7

COEGA DEVELOPMENT CORP (PTY) LTD

DPW - PRESTIGE

GAUTENG

PRETORIA

 

REPAIRS AND RENOVATIONS AT 259 ACQUILA IN WATERKLOOF

054032

5B

2015/06/02

3

3843476,85

3843476,85

COEGA DEVELOPMENT CORP (PTY) LTD

DPW - PRESTIGE

GAUTENG

PRETORIA

 

REPAIRS AND RENOVATIONS AT 307 NICHOLSON IN WATERKLOOF

054036

5B

2015/12/02

9

2655407,51

2655407,51

COEGA DEVELOPMENT CORP (PTY) LTD

ENVIRONMENTAL AFFAIRS

WESTERN CAPE

CAPE TOWN

 

SALDANA BAY HARBOUR & PEPPER BAY AREA: STABILIZATION OF EROD ED EMBANKMENTS: REPAIR

050712

5B

2018/02/09

12

39986438,89

3200000

GUERRINI MARINE CONSTRUCTION CC

ENVIRONMENTAL AFFAIRS

WESTERN CAPE

CAPE TOWN

 

MARION ISLAND: MAINTENANCE TO THE RESEARCH BASE

053795

5B

2016/02/15

12

4746530,74

0

STARLIGHT WHOLESALE ELECTRICAL SUPPLIERS

ENVIRONMENTAL AFFAIRS

WESTERN CAPE

CAPE TOWN

 

ANTARTICA ISLAND: MAINTENANCE TO THE RESEARCH BASE: SANAE IV

053796

5B

2017/11/06

36

3691513,18

0

CCK BUILDING AND SCAFFOLDING HIRE

ENVIRONMENTAL AFFAIRS

WESTERN CAPE

CAPE TOWN

 

GOUGH ISLAND: MAINTENANCE TO THE RESEARCH BASE

054041

5B

2018/08/06

36

1853566,89

0

BLUE ICE REFRIGERATION CC

GOVERNMENT PRINTING WORKS

GAUTENG

PRETORIA

 

REPAIR OF LEAKING ROOF AND STRUCTURAL WORK FOR GOVERNMENT PRINTERS AS WELL AS HERITAGE

048332

5B

2017/10/04

12

47046045,9

15117858,06

BONO INFRASTRUCTURE FACILITIES AND PROJECT MANAGEMENT

HOME AFFAIRS

EASTERN CAPE

UMTATA

 

REPAIR & REFURBISH MECHANICAL, ELECTRICAL,BUILDING &CIVIL

045609

5B

2017/06/30

12

12465720,04

4490705,61

AZCON PROJECTS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

FREESTATE

TSEKI

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS

048335

5B

2017/11/07

12

10603316,67

2578539,47

MADIGA PROJECTS AND SECURITY

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

FREESTATE

BLOEMFONTEIN

HIGH COURT

REPAIR OF ROOF, CEILINGS AND FLOORS AS WELL AS PLASTERING OF WALLS AND PAINTING OF WALLS

048352

5B

2017/11/02

18

19443945,97

4474719,86

VARYMIX NINETEEN (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

FREESTATE

BOTHAVILLE

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS OF BOTHAVILLE MAGISTRATE OFFICE

048364

5B

2017/05/22

8

3598691,69

921576,52

MBIKIZA GROUP OF COMPANIES (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

FREESTATE

DEWETSDORP

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS OF MAGISTRATE COURT

048367

5B

2017/09/20

13

4433808,21

1547042

PHUTHALUSHAKA CIVIL PROJECTS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

FREESTATE

FRANKFORT(FREE STATE)

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS OF MAGISTRATE OFFICE

048368

5B

2018/06/04

12

3554444,82

775000

DJ AND SS CLEANING SERVICES CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

FREESTATE

SPRINGFONTEIN

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS OF MAGISTRATE OFFICE

048371

5B

2017/11/06

11

2321990,78

803147,84

LEBURU FETSI CONSTRUCTION

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

FREESTATE

HEILBRON

 

HEILBRON MAGISTRATE OFFICE, CONDITION BASED MAINTENANCE

050800

5B

2018/06/11

18

20860791,01

3845497,25

WHITE LEOPARD TRADING CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

WESTERN CAPE

CAPE TOWN

MAGISTRATE'S OFFICE

REPAIRS AND RENOVATIONS

048538

5B

2018/01/11

24

76855357,88

9520900

NOLITHA ELECTRICAL (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

WESTERN CAPE

PAARL

REGIONAL COURT

HERITAGE- RESTORATION

049038

5B

2017/04/12

12

18510546,19

4237800

ABDA BUILDING AND INTERIOR PROJECTS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

KWAZULU-NATAL

UMLAZI

COMPLEX

HERITAGE - REPAIRS AND RENOVATIONS TO OFFICE BUILDING

040855

5B

2019/06/21

32

88425000

19877000

AFRISCAN CONSTRUCTION (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

KWAZULU-NATAL

HLABISA

MAGISTRATE'S OFFICE

VARIOUS BUILDING REPAIRS

048453

5B

2017/10/31

8

1416037,59

789071,77

MABHULANE CONSTRUCTION

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

MIDDELBURG (MPU)

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS: ROOF LEAKS; CRACKED WALLS; WINDOW PANES; ETC.

036169

5B

2017/04/06

18

27730856,91

13200000

ASATICO CIVIL AND CONSTR P/L

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

MPUMALANGA

WITBANK

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS OF BUILDING

048621

5B

2017/12/13

12

8219565,59

3361180,21

LA NATURA (PTY) LTD

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

LIMPOPO

MANKWENG

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS

048596

5B

2017/01/04

9

10919238,28

2187117,58

NKOLELE PROJECTS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

LIMPOPO

NAMAKGALE

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS TO BUILDING

048603

5B

2017/02/08

8

7679850,82

1911437,14

NKOLELE PROJECTS CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

LIMPOPO

LULEKANI

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS

048604

5B

2017/11/20

12

19936796,35

7420393,38

SEGABOKENG BUILDING CONSTRUCTION CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

LIMPOPO

HLANGANANI (NP)

MAGISTRATE'S OFFICE

REPAIR AND RENOVATIONS OF BUILDING

048605

5B

2017/03/24

12

13921885,98

3764862,89

BITUPQUIP CONSTRUCTION CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

QUEENSTOWN

MAGISTRATE'S OFFICE

QUEENSTOWN MAGISTRATE COURT - CONDITION BASED MAINTENANCE

050840

5B

2017/12/14

18

31345834

8518662

NATHAN ALEC DATNOW T/A SHAWSHANK CONSTRUCTION

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

DORDRECHT

MAGISTRATE'S OFFICE

CONDITION BASED MAINTAINANCE

046756

5B

2017/11/06

14

9256645,61

4605274,02

T.P.CONSTRUCTION CC

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

MOUNT FRERE

MAGISTRATE'S OFFICE

CONDITION BASED MAINTAINANCE

046766

5B

2018/10/11

13

20900460,5

8452279,91

TP CONSTRUCTION JV MC BAVU CONSTRUCTION

JUSTICE AND CONSTITUTIONAL DEVELOPMENT

EASTERN CAPE

TABANKULU

MAGISTRATE'S OFFICE

CONDITION BASED MAINTENANCE

046769

5B

2019/01/18

18

24670081,72

4977500

SIVIWE JAYIYA CONSTRUCTION CC

PUBLIC WORKS

FREESTATE

VARIOUS CENTRES (FS)

 

REPAIRS AND RENOVATIONS TO LIFT INSTALLATIONS IN VARIOUS GOVERNMENT BUILDINGS

051540

5B

2018/10/23

56

22887527,27

2881975,79

SIGMA LIFTS AND ESCALATORS (PTY) LTD

PUBLIC WORKS

WESTERN CAPE

CAPE TOWN

 

CONTRACT A, MODERNIZATION, REPAIRS AND MAINTENANC E OF LIFTS IN THE WESTERN CAPE

052134

5B

2018/01/28

24

64117755,64

1899612

OTIS (PROPRIETARY) LTD

PUBLIC WORKS

WESTERN CAPE

CAPE TOWN

 

CONTRACT B, MODERNIZATION, REPAIRS AND MAINTENANC E OF LIFTS IN THE WESTERN CAPE

052156

5B

2017/11/19

24

65896378,25

2269652

SCHINDLER LIFTS (SA) (PTY) LTD

PUBLIC WORKS

WESTERN CAPE

CAPE TOWN

 

SERVICE CONTRACTS FOR MEDIUM VOLTAGE(11 000 VOLT)SUBSTATION AND RETICULATION SYSTEM TO VARIOUS GOVERNMENT OWMNED COMPLEX ES

052348

5B

2019/07/26

36

21296897,58

0

ABRIE ERASMUS ELEKTRIES BK

PUBLIC WORKS

NORTHERN CAPE

KIMBERLEY

 

ADDITIONS TO THE AIRCONDITIONIONG SYSTEM IN THE NEW PUBLIC O OFFICE UTILISED BY DEPARTMENT OF JUSTICE

050838

5B

2016/01/15

12

18194236,83

3274962,48

MAGIC LABOUR HIRE & SECURITY SERVICES CC

PUBLIC WORKS

NORTHERN CAPE

KIMBERLEY

 

REPAIR AND MAINTENANCE FOR VARIOUS LIFTS IN THE NORTHERN CAP E REGION

053772

5B

2020/09/13

36

21861193,9

4229426,68

SIGMA LIFTS AND ESCALATORS (PTY) LTD

PUBLIC WORKS

NORTHERN CAPE

KIMBERLEY

MAGISTRATE'S OFFICE

KIMBERLEY NEW PUBLIC OFFICES BUILDING: REPAIRS TO ROOF AND WALLS CAUSED BY WATER PENETRATION

054347

5B

2018/03/07

6

822034,5

280821,9

SELOANA CONTRACTORS (PTY)LTD

PUBLIC WORKS

EASTERN CAPE

PORT ELIZABETH

 

REPLACEMENT OF FENCE AT HUMEWOOD MILITARY BASE

048686

5B

2018/02/02

9

8766083,94

1200000

CRYSTAL SPARKLE TRADING 98 CC

PUBLIC WORKS

GAUTENG

PRETORIA

SAMS COLLEGE

EMERGENCY WORK - REPAIR/REPLACE LEAKING PIPES, TILES, TOILET S AND SHOWERS IN BLOCKS G, H, I, J & K

046021

5B

2008/04/15

1

3600000

0

SAKYA'S BUILDING CONSTRUCTION CC

PUBLIC WORKS

GAUTENG

PRETORIA

OFFICE BLOCK

PTA-VARIOUS GOVT BUILDINGS:FOLLOW ON CONTRACT WCS 046918 FOR THE REPAIRS AND MAINTENANCE OF THE LIFTS

051920

5B

2018/03/06

36

21483889,65

2925586,56

KONE ELEVATORS SOUTH AFRICA (PTY) LTD

PUBLIC WORKS

GAUTENG

PRETORIA

 

FOLLOW ON CONTRACT WCS 046919 ON REPAIR AND MAINTENANCE OF L IFTS FOR THE VARIOUS GOVERNMENT BUILDINGS IN PRETORIA

052574

5B

2018/02/26

36

34063599,91

3610740,69

NGAATENDWE TRADING CC

SA POLICE SERVICE

FREESTATE

HERTZOGVILLE

POLICE STATION AND HOUSING UNITS

HERTZOGVILLE POLICE STATION: REPAIR AND MAINTENANCE TO ELECT RICAL,CIVIL,STRUCTURAL AND MECHANICAL ELEMEMNTS TO THE STATI ON AND HOUSES

051847

5B

2018/06/22

12

9675399,49

2714260

ESOERENS CIVIL CONTRACTORS (PTY) LTD

SA POLICE SERVICE

FREESTATE

SENEKAL

POLICE STATION

SENEKAL POLICE STATION: REPAIR AND MAINTENANCE TO ELECTRICAL CIVIL, MECHANICAL AND STRUCTURAL ELEMENTS TO THE STATION

051850

5B

2018/03/02

9

3249735,53

587000,01

ESOERENS CIVIL CONTRACTORS (PTY) LTD

SA POLICE SERVICE

FREESTATE

WANDA

POLICE STATION AND HOUSING UNITS

WANDA POLICE STATION: REPAIR AND MAINTENANCE TO ELECTRICAL, CIVIL,MECHANICAL AND STRUCTURAL ELEMENTS TO THE STATION AND HOUSES

051855

5B

2017/05/30

12

9296037,01

1750565,77

VINO BUILDING CONSTRUCTIONS AND MULTI P

SA POLICE SERVICE

FREESTATE

VREDE

POLICE STATION AND HOUSING UNITS

CONDITION BASED MAINTENANCE ON STRUCTURAL, ELECTRICAL AND CI VIL ELEMENTS OUSES

051856

5B

2016/08/12

18

13339817,05

3451486,86

CENTRAL BRIDGE TRADING 389 CC

SA POLICE SERVICE

WESTERN CAPE

OUDTSHOORN

GARAGE

REPAIRS AND RENOVATIONS INCLUDING, ELECTRICAL INSTALLATIONS, WATER SUPPLY, SEWERAGE SERVICES AND STRUCTURAL WORKS

050477

5B

2018/03/19

18

57375113,13

7383932,58

REDER CONSTRUCTION

SA POLICE SERVICE

KWAZULU-NATAL

JOZINI

S A POLICE QUARTERS

COMPLETE REPAIRS AND RENOVATION TO 6HOUSES AND 24 MARRIED QU ARTERS

035854

5B

2015/09/10

21

23783788,24

9850000

SETHEO INVESTMENTS PTY LTD

SA POLICE SERVICE

KWAZULU-NATAL

KWAMSANE

POLICE STATION

KWAMSANE: COMPLETE R&R TO STATION COMPLEX AS WELL LIVING QUA RTERS.

046041

5B

2016/03/21

14

14875048,73

6478799,02

EMCAKWINI CONSTRUCTION AND FENCING CC

SA POLICE SERVICE

KWAZULU-NATAL

NONGOMA

 

REPAIRS AND RENOVATIONS TO NONGOMA ROYAL PROTECTION UNIT BUI LDING

050159

5B

2018/04/19

24

12214485,82

5300000

LAKHIMU INVESTMENTS CC

SA POLICE SERVICE

KWAZULU-NATAL

LADYSMITH (KZN)

 

REPAIRS AND RENOVATION TO LADYSMITH POLICE STATION COMPLEX

050160

5B

2018/01/11

24

69578664

24346550

SIYAXHASANA CONSTRUCTION CC

SA POLICE SERVICE

GAUTENG

KEMPTON PARK

POLICE STATION

17 MONUMENT RD: REPAIR AND RENOVATION OF ALL BUILDINGS: INCL UDING THE PROVISION OF ALTERNATIVE ACCOMMODATION FOR THE DUR ATION OF THE PROJECT

033313

5B

2017/08/23

15

30258249,2

5586357,44

SHUMANIE PROPERTY MANAGEMENT SERVICES

SA POLICE SERVICE

GAUTENG

VANDERBIJLPARK

POLICE STATION

BARRAGE & VANDERBIJLPARK POLICE STATIONS: REFURBISHMENT OF CORRIDORS, INSTALLATION OF DISABILITIES TOILETS & REPAIRS OF BUILDING(MECHANICAL & ELECTRICAL)

046651

5B

2017/11/10

12

35605733,05

5337132,44

KWAGGA HOLDINGS (PTY)LTD

SA POLICE SERVICE

GAUTENG

JOHANNESBURG

MARRIED QUARTERS

REPAIR AND RENOVATIONS OF OFFICIAL QUARTERS INCLUDING FINDIN G ALTERNATIVE ACCOMMODATION

046652

5B

2018/02/02

24

72006562,6

14871401,51

YIKUSASA BUILDING CONTRACTORS

SA POLICE SERVICE

GAUTENG

SOWETO

 

REPAIRS AND MAINTENANCE OF DIEPKLOOF CRIME COMBATING UNIT BU ILDINGS

050179

5B

2018/09/28

18

29364678,5

5428661,24

H B C CONSTRUCTION PTY LTD

SA POLICE SERVICE

GAUTENG

ALEXANDRA

SINGLE QUARTERS

REPAIRS AND MAINTENANCE

050188

5B

2018/08/27

25

67379915,54

12347582,72

LETLAPA BORWA CIVIL

SA POLICE SERVICE

NORTHERN CAPE

LOUISVALE

S A POLICE COMPLEX

REPAIR OF DOG UNIT AND MARRIED QUARTERS

046890

5B

2017/09/09

12

8037726,06

1711345,82

MBIKIZA GROUP OF COMPANIES (PTY) LTD

SA POLICE SERVICE

NORTHERN CAPE

COLESBERG

POLICE STATION AND QUARTERS

REPAIR OF STATION AND MARRIED QUARTERS (8A-, 8B- AND 8C STOC KENSTROOM PLEIN, DWELLING 8630H AND 8631E)

046895

5B

2017/08/14

18

6738285,38

2013220

DAVID DIVA JV PILONITE

SA POLICE SERVICE

NORTHERN CAPE

COLESBERG

MARRIED QUARTERS

REPAIR OF MARRIED QUARTERS AT 1 AND 3 BAINS ROAD, 1,3,5,7 AN D 9 LELIE STREET, 5 EARL HAIG STREET, 3 GOUSBLOM STREET, 8 A ND 9 TOERENBERG STREET AND 7 DE JAGER STREET

046896

5B

2017/10/20

12

7939570,47

1590000

MF ADAMS

SA POLICE SERVICE

NORTHERN CAPE

KIMBERLEY

OFFICE BLOCK

REPAIR OF GLADSTONE BUILDING OFFICES

046897

5B

2016/12/05

18

7412266,35

1346699,73

VINO BUILDING CONSTRUCTIONS AND MULTI P

SA POLICE SERVICE

NORTHERN CAPE

HONDEKLIP BAY

POLICE STATION, SINGLE QUARTERS AND DWELLING

REPAIR OF STATION, MARRIED QUARTERS AND BACHELOR FLAT

046898

5B

2016/10/13

15

8437252,16

3762000

DAWID OOR BOUKONTRAKTEURS

SA POLICE SERVICE

NORTHERN CAPE

NOENIEPUT

POLICE STATION AND QUARTERS

REPAIR OF STATION AND MARRIED QUARTERS

046903

5B

2016/07/15

12

7625371,95

2650000

DAWID OOR BOUKONTRAKTEURS

SA POLICE SERVICE

NORTHERN CAPE

KENHARDT

 

REPAIRS AND MAINTENANCE OF THREE HOUSES NO 1393,1386 AND 140 0

050163

5B

2017/12/15

12

3002958,19

612871,96

P AND E ARTISANS BK

SA POLICE SERVICE

NORTHERN CAPE

BARKLY WEST

DETECTIVE BRANCH

HERITAGE - REPAIRS AND MAINTENANCE OF THE SAPSBUILDING

050164

5B

2017/10/12

12

6647674,38

1198761,6

BITUPQUIP CONSTRUCTION CC

SA POLICE SERVICE

NORTHERN CAPE

KIMBERLEY

POLICE STATION

KIMBERLEY: REPAIR AND MAINTENANCE OF LCRC IN DE AAR, UPINGTO N, KURUMAN

051826

5B

2018/07/24

24

4097051,54

1243968,85

MISHOE TRADING AND PROJECTS (PTY) LTD

SA POLICE SERVICE

NORTHERN CAPE

DOUGLAS

POLICE STATION

REPAIRS AND MAINTENANCE TO ELECTRICAL, CIVIL AND STRUCTURAL ELEMENTS OF STATION AND OFFICIAL QUARTERS

051904

5B

2017/11/20

12

12881478,68

1470000

MF ADAMS

SA POLICE SERVICE

NORTH WEST

SANNIESHOF

POLICE STATION

CONDITION BASED MAINTENANCE ON STRUCTURAL, ELECTRICAL AND CI VIL ELEMENTS

051872

5B

2018/08/03

16

6429031,88

0

TECH-COM SOLUTIONS CC

SA POLICE SERVICE

NORTH WEST

GANYESA

POLICE STATION

GANYESA:REPAIR AND MAINTANANCE OF CIVIL, ELECTRICAL, AND STRUCTURAL ELEMENTS TO STATION, FACILITIES FOR THE DISABLED AND FOUR HOUSES

051875

5B

2017/11/15

12

8088788,3

2277823,59

GMD PROJECTS CC T/A GDM SERVICE

SA POLICE SERVICE

NORTH WEST

BIESIESVLEI

POLICE STATION

CONDITION BASED MAINTENANCE ON STRUCTURAL, ELECTRICAL AND CIVIL ELEMENTS AND FACILITIES FOR THE DISABLED

051894

5B

2019/01/14

18

5992153,44

0

BOTHO SOCIETE

SA POLICE SERVICE

MPUMALANGA

KABOKWENI

POLICE STATION

REPAIR AND RENOVATIONS OF POLICE STATION AND ALL OFFICIAL QU ARTERS.

038133

5B

2017/11/06

18

13900014,04

5998249,86

ENZAR TRADING 23 CC

SA POLICE SERVICE

MPUMALANGA

STANDERTON

POLICE STATION

STANDERTON P STATION REPAIRS AND MAINTENANCE OF STATION AND OFFICIAL QUARTES ELECTRICAL,CIVIL,STRUCTURAL ELEMENTS

051786

5B

2018/08/16

24

28872578,33

6000000

BITUPQUIP CONSTRUCTION CC

SA POLICE SERVICE

MPUMALANGA

KWAMHLANGA

POLICE STATION

MPUMALANGA: REPAIR AND MAINTENANCE OF LCRC IN KWA-MHLANGA, S ECUNDA, NELSPRUIT & ULUKWATINI

051821

5B

2018/08/31

24

9700574,91

4671970,42

BUREWA TRADING 84 CC

SA POLICE SERVICE

LIMPOPO

SIBASA

 

REPAIRS AND RENOVATION TO SIBASA CLUSTER COMMANDER'S OFFICE: SOUTH AFRICAN POLICE SERVICES

050207

5B

2017/12/06

18

20383796,47

3600000

DITLOU SUPPLIERS AND SERVICES CC 2006/0

SA POLICE SERVICE

LIMPOPO

THOHOYANDOU

POLICE STATION

THOHOYANDOU POLICE STATION: REPAIRS & MAINTENANCE OF CIVIL, ELECTRICAL, MECHANICAL & STRUCTURAL ELEMENTS OF THE STATION

051773

5B

2018/02/13

12

14306305,18

2490000

KGALEMO CONSTRUCTION CC

SA POLICE SERVICE

EASTERN CAPE

GRAAFF-REINET

 

REPAIRS AND MAINTENANCE OF LEAKING ROOF IN THE OFFICIAL QUAT ERS AND DRAINAGE SYSTEM FOR GRAAF REINET POLICE COLLEGE

050218

5B

2018/05/29

12

123888022,6

19956000

SUPERWAY CONSTRUCTION (PTY) LTD

SA POLICE SERVICE

GAUTENG

PRETORIA

HEAD QUARTERS

INTERIM FACILITIES MANAGEMENT CONTRACT FOR TELKOM TOWERS COM PLEX (SAPS NHQ)

054635

5B

2016/12/31

12

20803381,12

0

BIDVEST FACILITIES MANAGEMENT (PTY) LTD

SA POLICE SERVICE

EASTERN CAPE

NQAMAKWE

POLICE STATION

STATION,CELLS,DETECTIVE OFFICE,HOUSES AND COMPLETE REPAIRS

021158

5B

2013/05/15

18

16234267,07

18653487,32

SOMANA CONSTRUCTION CC

SA POLICE SERVICE

EASTERN CAPE

LUSIKISIKI

POLICE COMPLEX

COMPLETE REPAIRS INCL ELECT REPAIRS AND NEW ESKOM POWER

025459

5B

2009/03/01

18

12940906,91

4628987,05

DEMO CONSTRUCTION (PTY) LTD

SA POLICE SERVICE

EASTERN CAPE

MT FLETCHER

POLICE STATION

COMPLETE REPAIRS AND RENOVATIONS

025500

5B

2015/05/08

15

14354759,28

6043556,99

INTELLEC CONSTRUCTION__CC

SA POLICE SERVICE

EASTERN CAPE

COFIMVABA

POLICE COMPLEX

REPAIRS AND RENOVATIONS OF THE ENTIRE COMPLEX INCLUDING ELEC RICAL AND CIVIL WORKS

046703

5B

2016/12/24

11

6564501,57

2930627,23

MABONVINI TRADING ENTERPRISE CC

SA POLICE SERVICE

EASTERN CAPE

UMTATA

POLICE COMPLEX

REPAIRS AND RENOVATION OF POLICE CAMP INCLUDING ELECTRICAL A ND CIVIL WORKS

046705

5B

2013/03/02

24

105090881,8

26999450,02

MABONVINI TRADING ENTERPRISE CC

SA POLICE SERVICE

EASTERN CAPE

MOUNT AYLIFF

POLICE STATION

REPAIRS AND RENOVATION OF POLICE STATION INCLUDING ELECTRICA L AND CIVIL WORKS

046711

5B

2018/01/31

18

36482749,28

8446368,91

CONDOR CONSTRUCTION (PTY) LTD

SA POLICE SERVICE

EASTERN CAPE

ELLIOT

POLICE STATION

ELLIOT POLICE STATION REPAIRS AND MAINTENCE OF ELECTRICAL,ST RUCTURAL AND CIVIL ELEMENTS OF STATION AND OFFICIAL QUARTERS

051745

5B

2019/01/17

18

16452332,9

3640000,02

FEZ BUILDING CONSTRUCTION CC

PUBLIC WORKS

WESTERN CAPE

CAPE TOWN

 

WATER TREATMENT

053096

5B

2018/08/30

36

1028798,47

0

TREATCO WATER CC