Questions and Replies
19 March 2021 - NW801
Singh, Mr N to ask the Minister of Mineral Resources and Energy
Whether the areas that are both supplied in bulk and billed by Eskom for energy provision are entitled to and receive a subsidy for the installation of prepaid meters as per relevant government programmes; if not, why not; if so, what are the relevant details? NW958E
Reply:
The only subsidy available from government is the electrification subsidy which is targeted at the electrification of indigent households. The subsidy covers the connection to the grid including the ready board and associated metering as per the technical designs of Eskom.
19 March 2021 - NW32
Ceza, Mr K to ask the Minister of Mineral Resources and Energy
What steps has his department taken to address the complaints of the Clewer Community in the eMalahleni Local Municipality, Mpumalanga, as submitted to his department on 1 August 2020, with regard to the blasting operations and dust at the Anglo American Khwezela Colliery which causes cracks in houses in Clewer? NW34E
Reply:
The Department investigated the complaints. The outcomes of the investigation were that Khwezela Colliery air blast and ground vibration exceeded the limits of 125dB and 5mm per second, respectively.
The Department issued Khwezela colliery with instruction to comply with the air blast limit of 115 dB and ground vibration limit 5 mm per second. Secondly, colliery was instructed to conduct a follow up structural survey on all the affected houses in proximity of the mine, determine if the damages to the houses were caused by blasting from the mine and fix all the houses that were damaged due to mine blasts. The mine must also review their blast design to ensure that they are able to comply with the air blast and ground vibration limits. The mine was also issued with an instruction to reduce the dust levels that were emanating from the dragline.
19 March 2021 - NW73
Nxumalo, Mr MN to ask the Minister of Mineral Resources and Energy
In light of the discovery of a second major gas find off the coast of South Africa that has put the Republic on the global energy map with even more discoveries expected in the future, how does his department intend to ensure that (a) it takes full advantage of the discovery and (b) the gas finds will be a significant boost for energy production in the Republic?
Reply:
a) The department is finalising the Upstream Petroleum Bill to further augment the regulations governing the oil and gas sector.
b) As per the Integrated Resource Plan (IRP 2019), South Africa continues to pursue a diversified energy mix that reduces reliance on a single or a few primary energy sources. Natural Gas forms part of the country’s energy mix.
19 March 2021 - NW182
Sarupen, Mr AN to ask the Minister of Mineral Resources and Energy
With reference to the informal settlement on Main Reef Road, in Brakpan, Gauteng, known as Plastic City what: a) steps are being taken by his department to seal off the old and inactive mines in the area, considering that it has become a hotbed of illegal mining and associated criminal activities, b) steps are being taken (i) to protect critical infrastructure from illegal mining in this area and (ii) jointly by his department and the Ekurhuleni Metropolitan Municipality to ensure that mineral rights and environmental legislation obligations are being met; and c) steps will his department be taking in future to stop illegal mining in the area? NW185E
Reply:
a) The department has sealed three shafts in and around Plastic City informal settlement in 2019.
b) Through the Department’s continuous monitoring and evaluation initiatives, it has been made aware that illegal miners have mined under some roads, causing it to collapse. To this end, the Department with the assistance of MINTEK is investigating this issue further. Furthermore, the SAPS together with Ekurhuleni Municipality will be consulted to have a lasting solution in this regard.
c) The Department will continue enforcing the laws that prohibit mining without the necessary authorisations (mining right and environmental authorisation) together with other law enforcement agencies. The Department is also participating in joint law enforcement forums aimed at strengthening investigations and prosecutions of these types of organised crimes that deprives the country of its mineral resources-based revenues, causing massive environmental damage with impacts on society.
19 March 2021 - NW234
Nxumalo, Mr MN to ask the Minister of Mineral Resources and Energy
Whether, with reference to the recent research by energy experts which found that there is currently 5000 MW that can be added to the grid and which can go a long way to stave off loadshedding, his department has plans to procure new capacity; if not, why not; if so, what are the further relevant details? NW237E
Reply:
The 5000 MW referred to in the question is in relation to potential from users generating their own power and not power available to be procured by the State.
With regard of procurement of additional power by the State, the Department is currently finalising the evaluation and appointment of preferred bidders for 2000 MW of power under the Risk Mitigation Independent Power Producer Programme.
The Department also plan to procure additional power in line with the already gazetted Section 34 Determination as follows:
19 March 2021 - NW427
Paulsen, Mr N M to ask the Minister of Mineral Resources and Energy
What action has he taken to discourage seabed mining, as bulk sediment mining of the deep seafloor is likely to have a severe and negative impact on sensitive seabed habitats and the ecosystem services that they provide, and given that the competency to consider and approve mining licences lies with his department? NW482E
Reply:
Although the primary aim lies along advancing development premised on the principles of sustainable development, where any proposed mining along and within seabed could potentially pose severe and/or irreversible damage to ecosystem in question even with mitigation measures in place such application cannot be granted or approved.
The provisions of section 48 of the MPDRA which list out area over which prospecting or mining is prohibited. If the area constitutes such an area as per the assessment made, the Minister can invoke the provisions of section 49 of the MPRDA and restrict or prohibit mining over such relevant seabed.
19 March 2021 - NW583
Lorimer, Mr JR to ask the Minister of Mineral Resources and Energy
Whether the general public is able to view the locality of applications, rights and permits made and/or held in terms of the Mineral and Petroleum Resources Development Act, Act 28 of 2002, via his department’s South African Mineral Resources Administration System; if not, (a) why not and (b) for how long has the View South Africa Geographic Information System facility not been available; if so, what are the relevant details? NW639E
Reply:
a) The general public can view the locality of applications. Members of the public will need to register as a user of the system, select relevant province and commodity/ies to able to view.
b) The South Africa Geographic Information System facility has always been available.
19 March 2021 - NW586
Mileham, Mr K to ask the Minister of Mineral Resources and Energy
With reference to the statements by the President of the Republic, Mr M C Ramaphosa, regarding hydrogen fuel cell technology and deployment in line with the Hydrogen South Africa Strategy, (a) which schools and hospitals are currently using hydrogen fuel cell technology to provide electricity, (b) what amount of electricity is generated in each case and (c) what are the future plans and timelines for implementation of hydrogen fuel cells at other government facilities? NW642E
Reply:
a) As part of government’s response to combating the COVID-19 pandemic, a temporary fuel cell system was deployed at 1 Military Hospital in Gauteng, which is utilised to support the Department of Defence. There is also one installed at the Science Center in Comimvaba (Eastern Cape).
b) The Seven Hydrogen Fuel Cells temporarily deployed at 1 Military Hospital has a total installed capacity of 35kW. The fuel cells deployed at a Science Centre in the Eastern Cape has a capacity of 5kW.
c) Post July 2021, the fuel systems currently at 1 Military Hospital will be redeployed as follows:
- One fuel cell system will remain at 1 Military Hospital for use by the Department of Defence (DOD) for training purposes;
- One fuel cell system at Mandeni Local Municipality, ILembe District in KZN, with a connection to the Youth Centre and Small, Medium and Micro Enterprises (SMMEs) Stalls;
- One fuel cell system at MINTEK with a connection to the Home Affairs offices in Randburg;
- One fuel cell system at Masia Village in Limpopo;
- One fuel cell system at the Department of Science and Innovation;
- One fuel cell system at the Trevenna Building, Department of Mineral Resources and Energy.
There is also ongoing work to incorporate the deployment of fuel cells in public buildings through the existing policy instruments, which include Energy Efficiency and Demand Side Management (EEDSM) grant programme and the Public Works and Infrastructure Green Building Policy.
19 March 2021 - NW589
Msimang, Prof CT to ask the Minister of Mineral Resources and Energy
Whether, with reference to a celebrated settlement agreement more than two years ago after the landmark class-action suit against nine gold mining companies that were ordered to compensate miners who suffered from insidious respiratory diseases like silicosis, he intends to intervene to ensure that the miners who still have not been paid out are paid out; if not, why not; if so, what are the full details outlining time lines? NW645E
Reply:
The Department of Mineral Resources and Energy is responsible for the regulation of the mining industry through the Mine Health and Safety Act (MHSA), No 29 of 1996. The Department of Health (DoH) governs the compensation of the mine employees diagnosed with Occupational Lung Diseases through Occupational Diseases in Mines and Works Act (ODMWA) 78 OF 1973 regulated by the Medical Bureau for Occupational diseases (MBOD).
Tshiamiso trust has been established to carry out the terms of the settlement agreement reached between amongst six mining companies and claimants to compensate current and ex-mineworkers for silicosis and TB. The trust works together with the MBOD in certification of mineworkers who have lodged claims. The certification process to identify ex-mineworkers with silicosis was apparently hampered by Covid-19 pandemic in 2020 as lung function tests could not be carried out because of the risk of increasing exposure to COVID-19 infection. Outreach programmes are reported to be carried out to cater for outstanding compensations in areas like the Eastern Cape.
19 March 2021 - NW614
Paulsen, Mr N M to ask the Minister of Mineral Resources and Energy
What steps has his department taken to ensure that Engen is held liable for the damage caused to homes and loss of property in Wentworth after the explosion at its oil refinery in Durban South in December 2020? NW730E
Reply:
The matter referred to in the question should be addressed to the Department of Environmental Affairs, Forestry and Fisheries who handle Environmental impact issues, as well as the Department of Employment and Labour as the responsible Department for the investigation of industrial accidents.
19 March 2021 - NW622
Madokwe, Ms P to ask the Minister of Mineral Resources and Energy
Given that departmental entities are stuck in litigation matters that were started by persons who are no longer in his department and have never been held accountable, what (a) is the (i) breakdown of all legal matters against the various entities of his department and (ii) cost to the taxpayer in each case and (b) are the reasons that his department has not, to date, used its own internal processes against those individuals who offset the specified cases, such that they are personally liable for the specified legal costs? NW738E
Reply:
ENTITY |
what (a) is the (i) breakdown of all legal matters against the various entities of his department |
(a)(ii) cost to the taxpayer in each case |
(b) are the reasons that his department has not, to date, used its own internal processes against those individuals who offset the specified cases, such that they are personally liable for the specified legal costs |
NECSA |
On or about 12 August 2019, Mr Vusi Malebana, erstwhile Necsa Chief Legal Advisor filed an urgent application seeking a declaratory and interdicting order setting aside his suspension and stopping the disciplinary proceeding against him. The Labour Court ruled that the suspension of Mr. Malebana by the South Africa Nuclear Energy Corporation (Necsa) was declared to be unlawful and constitutes an occupational detriment. |
Necsa was ordered to pay the costs of Mr. Malebana in pursuing the urgent application, which costs were to include the costs of two (2) counsel. The bill of costs as per the Taxing Master certificate were R352 486.14 which Necsa honoured in full in January 2021. |
Following the court interdict, Mr. Malebana was subjected to a disciplinary hearing and eventually dismissed. He took the matter to the CCMA whereby the CCMA ordered that his dismissal was procedurally and substantively unfair and awarded six months compensation amounting to R679 444.86. Mr Malebana subsequently served Necsa with a Notice of Motion together with the founding affidavit on 12 December 2020 in essence outlining his intentions to review the arbitration award issued by CCMA on 26 October 2020. |
CGS |
The Council for Geoscience has no pending legal matters emanating from the scenario outlined in the question. |
N/A |
N/A |
MINTEK |
Mintek does not have any litigation matters that were started by persons who are no longer at the company. The only legal matters currently active relates to labour issues such as unfair dismissal and unfair labour practice. |
N/A |
N/A |
NNR |
No outstanding litigation against NNR |
N/A |
N/A |
NRWDI |
The National Radioactive Waste Disposal Institute (NRWDI) is not involve in any litigation matters and therefore the questions are not applicable to NRWDI. |
N/A |
N/A |
SDT |
The SDT has no litigation matters at present. No such matters were dealt with in the past. Consequently, the entity has incurred no costs in this regard. |
N/A |
N/A |
SADPMR |
The SADPMR has no former or current employees who were involved in any litigations of which the Regulator was responsible for paying their legal costs. |
N/A |
N/A |
SANEDI |
SANEDI is currently opposing one labour relation matter |
R253,998.25 |
Matter is still pending |
CEF (SOC) and its subsidiaries, NERSA and the MHSC responses listed separately below:
CENTRAL ENERGY FUND AND SUBSIDIARIES
ENTITY |
what (a) is the (i) breakdown of all legal matters against the various entities of his department |
(a)(ii) cost to the taxpayer in each case |
(b) are the reasons that his department has not, to date, used its own internal processes against those individuals who offset the specified cases, such that they are personally liable for the specified legal costs |
CEF (SOC) Ltd |
CEF SOC Ltd and SFF jointly handled the stock rotation litigation matter |
R11, 922, 752.15. |
After the A&O Report, Application was made for a declaratory order declaring that the sale of strategic stock was invalid. |
SFF |
Stock Rotation already reported as stated above. Krone is suing SFF for payment, which they allege, is due in terms of the contract. Krone was required to install a metering system, which was aimed at improving accuracy levels of measuring of oil volumes. In the recovery of proceeds for the sale of diesel to Line Petroleum, a default judgment was granted in favour of SFF, |
R4 500 685.00 R 43, 400.43 |
SFF is withholding payment on the grounds of non-performance under the contract. A legal opinion is being sought because Line Petroleum does not have attachable assets in South Africa. |
iGas |
No litigation to report on. |
N/A |
N/A |
PetroSA |
PetroSA is claiming damages from Odjfjell for the pipeline damages. PetroSA has instituted liquidation proceedings against Two Oceans for failing to honour payments for product sold PetroSA has obtained judgment against Fantastic View and a writ of execution has been issued |
R 11,462, 280.93 R 1,457,266.26 R 738,755.57 |
Judgment is pending |
AEMFC |
The supplier being Innovent was found to have misrepresented AEMFC on registration with the Financial Service Board. AEMFC concluded a settlement agreement with NUM in 2017 at the CCMA which was made an Arbitration award and amongst the item agreed upon was that AEMFC will pay the 13th cheque each December. In 2019 there was another agreement which states that it supersedes all the previous agreements and a new bonus scheme which was performance bonus was introduced. Bargaining employees in 2019 as per the new agreement received 50% of their CTC as performance bonus and the 13th Cheque was not paid. NUM has now obtained an Arbitration award against AEMFC demanding the 13th Cheque for December 2019. Persuant to the Arbitration award, NUM applied for enforcement order of R2.9M which was granted and AEMFC property was attached by the sheriff. AEMFC has applied to the Labour Court to stay the enforcement order pending the rescission of the of the Arbitration award. The argument by AEMFC is that, the 2017 agreement was superseded by the 2019 agreement and further that the 13th Cheque must be from the employee’s salary and not at employers costs. An AEMFC former Senior Employee concluded a collecting Agreement with NUM in terms of which AEMFC will pay the risk allowance to employees who worked during the lockdown. In terms of the AEMFC LOA the collective agreement must be recommended by EXCO to the board for approval. The submission to the board by the former employed did not disclose that a collective agreement is already signed but created the impression that AEMFC must make a once off payment of R2.6 million for 5 weeks lockdown. AEMFC made a once off payment and the union lodge a grievance with the CCMA to enforcement the collecting agreement signed with the former employee. AEMFC disputed the validity of the collective agreement since it was not approved by EXCO and board and an urgent court application was filed to interdict CCMA to proceed with the matter pending review of the decision by AEMFC former employee to sign a collective agreement without authority. |
R 241 016.43 R 192, 510.00 R 283,496. 62 |
The contract was classified as Irregular expenditure by National Treasury. |
NATIONAL ENERGY REGULATOR OF SOUTH AFRICA (NERSA)
No. |
|
|
|
|
1. |
Judicial review |
ESKOM- Case arises from the decision of the Energy Regulator approving the MYPD3 RCA5 and Eskom is unhappy with the outcome. Eskom has taken the decision on judicial review. |
R1 750 000.00 |
Only lawyers in the practising roll can appear in court. Despite NERSA legal advisors are all admitted attorneys/advocates, they cannot appear in court. |
2. |
Judicial review |
AFGRI/PHILAFRICA- The judicial review case arises from the decision of the Energy Regulator not to amend or revoke the distribution licence of Maluti a Phofung Local Municipality licence. |
2 900 000.00 |
Only lawyers in the practising roll can appear in court. Despite NERSA legal advisors are all admitted attorneys/advocates, they cannot appear in court. |
3. |
Judicial review |
Drakenstein Local Municipality. The judicial review arises from the decision of the Energy Regulator not to approve some of the tariffs of the municipality during 2019/20 because of the impact that it would have had on the customers. |
R2 200 000.00 |
Only lawyers in the practising roll can appear in court. Despite NERSA legal advisors are all admitted attorneys/advocates, they cannot appear in court. |
4. |
Judicial review/ Implementation of order pending appeal/ leave to appeal |
Eskom- The appeal follows the judgement of the Pretoria High Court to substitute the decision of the Energy Regulator on the Eskom MYPD4 Year 3. This case has already had three judgements (review judgement, leave to appeal judgement and implementation of review judgement pending appeal judgement) |
R7 400 000.00 |
Only lawyers in the practising roll can appear in court. Despite NERSA legal advisors are all admitted attorneys/advocates, they cannot appear in court. |
5. |
Judicial review |
Sunrise- the matter arises from the judicial review brought by Sunrise against what they call improper formulation and reading of the Petroleum Pipelines Operating licence issued by NERSA to Avedia |
R2 200 000.00 |
Only lawyers in the practising roll can appear in court. Despite NERSA legal advisors are all admitted attorneys/advocates, they cannot appear in court. |
MINE, HEALTH AND SAFERY COUNCIL (MHSC)
what (a) is the (i) breakdown of all legal matters against the various entities of his department |
(a)(ii) cost to the taxpayer in each case |
(b) are the reasons that his department has not, to date, used its own internal processes against those individuals who offset the specified cases, such that they are personally liable for the specified legal costs |
Investigation into allegations of financial misconduct |
1 006 475,00 |
The matter is not finalised |
Dispute at the Labour Court between employer an employee |
233 770,00 |
Recovery if any will be based on outcome of the labour court |
Challenging the recruitment process of the HR head at the Labour Court |
45 007,55 |
Recovery if any will be based on outcome of the labour court |
Termination of the Contract and recovery due to non performance |
456 046,00 |
The matter is not finalised |
Dispute at the Labour Court between employer an employee |
301 357,44 |
Recovery if any will be based on outcome of the labour court |
Dispute at the Labour Court between employer an employee |
86 766,63 |
Settlement paid by MHSC |
Dispute over employment Contract |
153 060,00 |
Assessment still to be done pending the outcome of disciplinary hearing- employee on suspension |
19 March 2021 - NW677
Basson, Mr LJ to ask the Minister of Mineral Resources and Energy
Whether (a) his department and/or (b) any entity reporting to him makes use of private security firms; if not, what is the position in this regard; if so, in each case, what is the (i) name of each firm, (ii) purpose, (iii) value and (iv) duration of each specified contract? NW795E
Reply:
ENTITY |
(b) entity reporting to him makes use of private security firms |
(i) name of each firm, |
(ii) purpose |
(iii) value |
(iv) duration of each specified contract? |
CEF (SOC) Ltd |
CEF, iGas and SFF do not make use of private security firms. PetroSA and AEMFC utilise the services of private security firms. |
PetroSA: Quattro Security (Bloemfontein and Tzaneen depots); Fidelity Security Services (Parow Offices) Excellerate Security Services at the GTL Refinery and surrounding sites in Mossel Bay AEMFC: Protea coin t/s Bidvest Security |
PetroSA is making use of private security guards armed and unarmed in its Depots (Bloemfontein and Tzaneen), GTL Refinery and its surrounding sites in Mossel Bay and Parow (Head Office). |
PetroSA: Quattro Security (Bloemfontein and Tzaneen depots) – R1,243,371,41 Fidelity Security Services (Parow Offices) – R,414,893,84 Excellerate Services (GTL Refinery and sites around Mossel Bay) – R70 000 000.00 AEMFC: R 25,847,324.00 |
PetroSA: Quattro and Fidelity – 01 October 2018 – 30 September 2021 GTL Refinery and surrounding sites in Mossel Bay – 15 January 2021 – 14 January 2024 with an option to extend for one year. AEMFC: 01 December 2020 – 30 November 2023 |
NECSA |
The South African Nuclear Energy Corporation (NECSA) does not make use of private security firms. |
N/A – NECSA uses in-house security |
N/A |
N/A |
N/A |
CGS |
Yes. The Council for Geoscience has established an in-house security capacity in Head Office, Donkerhoek Core shed and Bellville regional office through mass in-housing process, whilst other regional offices are still protected through contract security |
Polokwane regional office: Field Security Services
Upington regional office: ADT Fidelity Security Services Pietermaritzburg regional office: Peter Security Services
|
Polokwane Regional Office: 24/7 Security guarding services – one grade C armed guard during the day shift and similar during the night shift. Upington regional office: Providing armed response services only– alarm monitoring services Pietermaritzburg regional office: Providing armed response services only – alarm monitoring services |
Polokwane Regional Office: R345, 000.00 Upington regional office: R88,252.04 Pietermaritzburg regional office: R19, 297.80 |
Polokwane Regional Office: 26 September 2020 – 26 September 2021 Upington regional office: 01 December 2020 – 30 November 2023 Pietermaritzburg regional office: 01 October 2019 to 30 September 2022 |
MINTEK |
Mintek utilizes the services of three (3) companies for their security |
|
Protection of Mintek’s Technology demonstration plant (Savmin) at Sibanye Gold Randfontein
|
MI 7 Security Group: R19m (total contract value. Payment based on use)
|
|
MHSC |
The MHSC does not make use of Private Security firm |
N/A |
N/A |
N/A |
N/A |
NERSA |
Yes |
Imvula Security Services (Sub-contracted by AFMS Group) |
Building Security |
R2,347,538 |
2 years |
NNR |
Yes |
RAMS Fire, Security and Cleaning Services (Pty) Ltd |
Building security |
R5 268,218.20 |
01 May 2018 – 30 April 2021 |
NRWDI |
NRWDI does not make use of private security firms. |
N/A |
N/A |
N/A |
N/A |
SDT |
Yes |
Rise Security Services (Pty) Ltd |
For the provision of armed guarding services for its diamond premises, and to provide access control services |
R38 934.36 monthly, VAT inclusive |
Three (3) years (1 September 2018 to 21 August 2021) |
SADPMR |
Yes |
Fidelity Securities EOS Empire All System |
Fidelity Securities: Armed response and static guard services EOS Empire All System: Maintenance of security equipment |
Fidelity Securities: R1,284,126,.72 EOS Empire All System: R70 000 plus R345.00 call out, excluding travel claims |
Fidelity Securities: 12 months EOS Empire All System: 6 months |
SANEDI |
SANEDI does not make use of the services of a private security firm. |
N/A |
N/A |
N/A |
N/A |
19 March 2021 - NW709
Mileham, Mr K to ask the Minister of Mineral Resources and Energy
1) Whether, with reference to the proposed new nuclear build, his department conducted any (a) feasibility studies and/or (b) business or financial case studies for new nuclear generation in the past two years; if not, why not; if so, in each case, what are the relevant details; 2) In view of the fact that the Integrated Resource Plan 2019 (IRP 2019) makes no provision for the procurement of new nuclear generation as indicated on table 5 on page 42 of the gazetted IRP, on what basis has he committed to procure 2500MW of new nuclear generation by 2024 in his Ministerial Performance Agreement; 3) Why is he prioritising nuclear power generation ahead of other generation solutions despite ESKOM’s admission that nuclear energy is neither a least-cost, nor a short-term solution to the electricity crisis in the Republic? NW828E
Reply:
1. Whether, with reference to the proposed new nuclear build, his department conducted any (a) feasibility studies and/or
The Department has in the past, conducted at least 13 feasibility studies towards a framework for the realisation of the Nuclear New Build Programme. These include amongst others the International Atomic Energy Agency’s peer review expert mission on Integrated Nuclear Infrastructure Review. As result of this, a number of studies and strategies were developed to address identified issues raised for preparation toward procurement of the 9600MW nuclear programme previously. These feasibility studies provided the necessary foundation from which to prepare for the procurement of the 2500MW nuclear new build programme. Some of the relevant feasibility Studies included:
- Study on comparative analysis of Shale Gas to power versus Nuclear Power in SA
- Benchmark of Procurement Framework
- Cost of Nuclear Power
- Owner-Operator and Financing Structures
- Finance Options Models Solutions
- Economic Impact of Localisation of Nuclear New Build Programme
(b) business or financial case studies for new nuclear generation in the past two years; if not, why not; if so, in each case, what are the relevant details;
Having those relevant studies as a basis, following the IRP2019 call for the smaller capacity of 2500MW the Department sought to update its information with the latest developments in the nuclear industry by testing the market appetite for the deployment of the Nuclear New Build Programme in South Africa. In June 2020, Department went out to test the market by issuing a non-binding Request for Information (RFI) for the 2500 MW of nuclear capacity. The process of finalising the RFI assessment is underway and this will culminate to into the implementation strategy, roadmap and procurement framework.
2. In view of the fact that the Integrated Resource Plan 2019 (IRP 2019) makes no provision for the procurement of new nuclear generation as indicated on table 5 on page 42 of the gazetted IRP, on what basis has he committed to procure 2500MW of new nuclear generation by 2024 in his Ministerial Performance Agreement;
The Department has been implementing the IRP2019 since it was promulgated in 2019 to provide sustainable energy mix to address the country energy needs with various energy technologies that are being rolled out. The IRP does not pronounce on procurement. It is a plan for electricity that is based on least cost calculations and policy adjustments. There are a number of steps in the IRP development process, one of the final steps is policy adjustment. The policy adjusted decision of an approved Integrated Resource Plan of 2019, Decision 8 states: “Commence preparations for a nuclear build programme to the extent of 2500 MW at a pace and scale that the country can afford because it is a no-regret option in the long term”. The Minister’s Section 34 Determination in terms of the Electricity Regulations Act No. 4 of 2006, as amended, is where provision for procurement of electricity generation is made. The policy Decision 8 of the IRP2019 provides the basis upon which the Minister has committed to procure 2500MW of new nuclear generation by 2024 in his Ministerial Performance Agreement;
The preparations leading to the procurement in 2024 have already started taking into account:
- That the 2500 MW Nuclear Build Programme is contained in the DMRE 2020-2025 Strategic Plan and the Annual Performance Plan
- That the 2500 MW Nuclear Build Programme is contained in Policy Position 8 of the IRP 2019
- That the 2500 MW Nuclear Build Programme is contained in the Performance Agreement of the Minister.
- That the 2500 MW Nuclear Build Programme is contained in the 2019-2024 MTSF Priorities.
The preparation for nuclear power plant is long lead-time infrastructure project and takes up to about 12 years from the planning until the commission power plant to the grid to generate electricity. These preparatory activities include but are not limited to design, siting, procurement, construction and commissioning of the nuclear power station beyond 2030. Most of the baseload coal fired power plants will be decommissioned beyond 2030 and based on the long lead times for a nuclear programme, starting the process early will yield a no regret option taking into account that nuclear is a clean baseload source of power.
3. Why is he prioritising nuclear power generation ahead of other generation solutions despite ESKOM’s admission that nuclear energy is neither a least-cost, nor a short-term solution to the electricity crisis in the Republic? NW828E
The Department has a responsibility to implement the approved IRP in totality to ensure security of energy supply for the country. It is not true that nuclear is being prioritised. Since the promulgation of the initial IRP 2010-30 and the subsequent revised IRP 2019, the only other technologies to be commissioned in line with these plans have not included nuclear. We have procured more renewable energy technologies and we continue to do so and nuclear has not been one of those. Even with the section 34 determinations following the IRP 2019, Nuclear energy is being subjected to a robust public participation process prior to NERSA’s concurrence. It is therefore not true to imply that nuclear is brought in as short-term solution despite it having policy adjusted into the IRP post the modelling process. It must be noted that the IRP does not factor in a number of issues such as hidden costs including the grid costs, balancing costs, systems costs, job creation, local industry development, geopolitics, labour movement dynamics and other related aspects. In addition, the IRP modelling process used the average capital cost of nuclear projects as US$5000/kWe whilst unlike other energy sources, nuclear projects have shown to have a wide range from as low as US$2000. After testing the market, we may arrive at a cost far lower than any other energy source possible, and this is the reason why it will be prudent to move forward with procurement of nuclear power. In addition, unlike most other energy sources which have lifetimes and loans suit limited private investor positions of short-term returns, nuclear power plants have lifetimes exceeding 60 years. Koeberg is a prime example of this and has shown to be the cheapest of all energy sources currently on the grid. Even after 20 years when a nuclear plant has been paid off (due to market limitations on loan durations), the plants will continue to generate electricity at the lowest operational cost. Each energy source must be looked at for its merits, and hence a balanced energy mix of all sources is good for South Africa.
19 March 2021 - NW726
Lorimer, Mr JR to ask the Minister of Mineral Resources and Energy
Whether, as part of the mechanisms to combat corruption and state capture and thereby increasing the attractiveness of the mining industry of the Republic to investors, he intends to apply for the Republic to be an implementing country of the Extractive Industries Transparency Initiative; if not, why not; if so, what are the relevant details? NW847E
Reply:
No.
South Africa has not taken a decision to be part of the Extractive Industries Transparency Initiative.
09 December 2020 - NW2548
Van Dyk, Ms V to ask the Minister of Mineral Resources and EnergyMr
(1) (a) What (i) total number of mining permits in heritage sites has his department granted in the Republic since 1994 and (ii) is the name of each heritage site, (b) where is the site located in each province and (c) what is the name of the person who received the mining rights in each case; (2) whether any impact studies and/or public consultation processes were undertaken; if not, what is the position in this regard; if so, (3) whether she will furnish Mrs V van Dyk witha copy of each impact study and/or public consultation; if not, what is the position in this regard; if so, what are the relevant details?
Reply:
(1)(a)(i) The Department‘s records reveal that no mining permit or mining right has ever been issued over an area that constitutes a proclaimed heritage site. The records however shows that only one prospecting right was erroneously issued within the core of the Mapungubwe World Heritage site, but there is no evidence of any activities having been undertaken.
(ii)The Department‘s records reveal that no mining permit or mining right has ever been issued over an area that constitutes a proclaimed heritage site. The records however shows that only one prospecting right was erroneously issued within the core of the Mapungubwe World Heritage site, but there is no evidence of any activities having been undertaken.
(b)The Department‘s records reveal that no mining permit or mining right has ever been issued over an area that constitutes a proclaimed heritage site. The records however shows that only one prospecting right was erroneously issued within the core of the Mapungubwe World Heritage site, but there is no evidence of any activities having been undertaken.
(c)The Department‘s records reveal that no mining permit or mining right has ever been issued over an area that constitutes a proclaimed heritage site. The records however shows that only one prospecting right was erroneously issued within the core of the Mapungubwe World Heritage site, but there is no evidence of any activities having been undertaken.
(2)As indicated above, other than the prospecting permit that was issued erroneously, no mining permits were issued within a heritage site.
(3)As there were no permits within the heritage sites, there are no studies for mining within heritage sites.
09 December 2020 - NW2899
Madokwe, Ms P to ask the Minister of Mineral Resources and Energy
(a) What are the reasons that his department has not ensured that when municipalities, especially in poor and rural municipalities, enter into contracts with independent power producers, one of the requirements is to provide free electricity for the indigent, (b) how will his department ensure that service providers provide free electricity for the indigent and (c) by what date will this be remedied?
Reply:
a) It is government policy to provide free basic electricity to the indigent through licensed electricity distributors (Eskom and Municipalities). The free basic electricity provision is independent of the source of generation of the electricity (Eskom or IPPs).
b) See response to (a.) above.
c) See response to (a.) above.
09 December 2020 - NW2898
Madokwe, Ms P to ask the Minister of Mineral Resources and Energy
What (a) proportion of persons employed by his department fall under the category of (i) women, (ii) youth and (iii) persons with disabilities, (b) provisions are made by his department to ensure employment equity, especially of persons with disabilities and (c) is the name of each entity reporting to him that has not complied with the provisions of employment equity with regard to the employment of persons with disabilities?
Reply:
(a) (i) 55.23% women,
(ii) 20.11% youth,
(iii) 0.94% persons with disabilities,
(b) The Department has made the following provisions to ensure employment equity, especially of persons with disabilities:
- Employed a dedicated focal point responsible for Gender, Disability Transformation and one for Youth,
- In the process of appointing the Employment Equity Committee for the newly established Department of Mineral Resources and Energy,
- In the process of appointing an Employment Equity Manager for the Department
- Responsibility for EE will be incorporated in the Performance Agreements of Branch Heads,
- Drafted an EE Policy and Plan.
(c) The name of each entity reporting to the Minister who has not complied with the provisions of employment equity with regard to the employment of persons with disabilities:
Entity |
(a)(i) |
(a)(ii) |
(a)(iii) |
(b) |
(c) |
CGS |
214 |
153 |
7 |
N/A |
N/A |
MINTEK |
268 |
228 |
12 |
N/A |
N/A |
MHSC |
40% |
21% |
2% |
N/A |
N/A |
NERSA |
57% |
26% |
1.3% |
N/A |
N/A |
NNR |
50% |
18.3% |
2.7% |
N/A |
N/A |
NRWDI |
62.5% |
21.9% |
6.25% |
N/A |
N/A |
SDT |
10 |
7 |
3 |
N/A |
N/A |
SANEDI |
23 |
11 |
0 |
N/A |
SANEDI currently has no employees who are persons of disabilities |
SADPMR |
68 |
20 |
1 male |
N/A |
N/A |
CEF Group and its subsidiaries
Entity |
(a)(i) % of Women |
(a)(ii) % of youth |
(a)(iii) % of People living with Disabilities |
(b) Provisions or strategy per entity to ensure employment equity, especially of persons with disabilities is achieved |
PetroSA |
30% |
19% |
1.7% |
|
AEMFC |
26% |
55% |
0.22% |
|
PASA |
31% |
27% |
2% |
|
SFF |
31.2% |
28% |
Current exercise underway internally to establish number of persons with disability |
|
CEF SOC |
45% |
40% |
2% |
|
CEF Group |
31% |
28% |
1% |
|
Necsa and its subsidiaries
Necsa
(a) (i) Proportion of person employed by the institution who are women is 673, which represent 37.7%
(ii) Persons who are youth, herewith defined as employees who are not older than 35 years of age - 461
(iii) Persons with the disabilities – 25
NTP
(a) What proportion of persons employed by NTP fall under the category of:
(i) Women: 41%
(ii) Youth: 32%
(iii) Persons with disabilities: 0.26%
Pelchem
(a) What proportion of persons employed by NTP fall under the category of:
(i) Women: 30
(ii) Youth: 0; permitted 10 students
(iii) Persons with disabilities: 1
27 November 2020 - NW2708
Waters, Mr M to ask the Minister of Mineral Resources and Energy
1) (a)What number of audits has the National Energy Regulator of South Africa (NERSA) conducted of the City of Ekurhuleni since its establishment, (b) on what date was each audit report submitted to the specified city, (c) what were the recommendations contained in each audit report and (d) what number of new electricity connections have taken place within the city since the last audit was conducted by NERSA; 2) Whether NERSA has ensured that its recommendations have been implemented by the city; if not, why not; if so, which recommendations have been implemented? NW3476E
Reply:
1.
a) An independent technical audit of Ekurhuleni was done in January 2006. Another audit was done in 2020 but the focus was on the business assessment.
b) The report on the independent technical audit was submitted in the same year in May 2006. Due to COVID induced travel restrictions that was in place when the business assessment was done, the site inspection on the audit conducted in 2020 will be done in early 2021.The draft report of the business assessment will be sent to the Licensee by the end of November 2020.
c) It was recommended that:
- There must be investment in the maintenance and the refurbishment of the networks and on skilled staff.
- The Department must operate as an integrated entity.
- The maintenance and refurbishment plans must also be integrated.
d) According to our knowledge, there were 45 intake points in 2005/6 and there are now 55 intake points.
Increased Infrastructure
The Department of Energy has since 2006 increased its infrastructure in the various Depots in Ekurhuleni as follows:-
Electrification of Subsidized Households |
High Mast Lights |
Street Lights |
Substations |
92 161 |
977 |
15 458 |
Upgrading/Construction of 13 Substations |
The 92 161 additional connections excludes town planning development connections for non-subsidized households, which also forms part of the electricity grid and infrastructure to be maintained by the Department.
2. NERSA requests all audited licensees to develop Corrective Action Plans so that this can be monitored. The same will happen with Ekurhuleni Metro when the site inspection has been done and a final report has been shared with the Licensee. One of the objectives of the NERSA audits is to encourage licensees to do self-monitoring so that the networks do not deteriorate.
27 November 2020 - NW2237
Krumbock, Mr GR to ask the Minister of Mineral Resources and Energy
1) Whether, with reference to his reply to question 1709 on 27 August 2020, he will furnish Mr G R Krumbock with copies of the Standards of Service (NRS 047) and Quality (NRS 048); if not, what is the position in this regard; if so, on what date; 2) on what date did the City of Ekurhuleni last submit their maintenance schedules; and 3) whether he will furnishMr G R Krumbock with a copy of the maintenance schedules of the City of Ekurhuleni; if not, what is the position in this regard; if so, on what date? NW2809E
Reply:
1. Yes, the NRS 047 and the relevant NRS 048 specifications are attached.
2. In terms of the license condition 5.4.1 the Energy Regulator is entitled to collect information such as the maintenance plans of the licensee, the process of collecting and examining such information is always undertaken during the annual compliance audits that the Regulator conducts on selected licensees each year. The City of Ekurhulenihad not been audited before, and had therefore not submitted its maintenance plants. It is however on the list of the licensees to be audited during this financial year.
3. According to license condition 5.3.2, the licensee is required to always prepare the maintenance plans annually and adhere to this, however it is not the requirement for the licensee to submit the report to the regulator annually. The maintenance plans are scrutinised when the licensee is selected for a compliance audit.
27 November 2020 - NW2820
Mileham, Mr K to ask the Minister of Mineral Resources and Energy
(1) For each storage facility owned, leased and/or operated by the Strategic Fuel Fund, (a) on what date was the last (i) maintenance and (ii) refurbishment undertaken on the storage tanks and (b) what was the cost of such maintenance and/or refurbishment in each case; (2) (a) on what date was each specified facility last audited for environmental compliance and (b) what were the findings of the last environmental audit in each case; (3) whether there are any indications of seepage into the ground and/or the groundwater table; if not, what is the position in this regard; if so, what are the relevant details of the seepage?
Reply:
1. Saldanha Terminal
(1) For each storage facility owned, leased and/or operated by the Strategic Fuel Fund, (a) on what date was the last (i) maintenance and (ii) refurbishment undertaken on the storage tanks and (b) what was the cost of such maintenance and/or refurbishment in each case;
- Saldanha Terminal is made of Concrete Underground Closed tanks which do not require maintenance or refurbishments on the Saldanha tanks. There are however scheduled inspections to test the tanks structure and roof supports. In all inspections done to date there were NO abnormalities that were detected. This include the tank settlement test that was done in 2016, where no discernible changes since commissioning were observed.
(2) (a) on what date was each specified facility last audited for environmental compliance and (b) what were the findings of the last environmental audit in each case;
(a) The last full recertification Audit was conducted by SABS on ISO14001 2015 on the 10TH to the 13TH March 2020
(b) One “minor” finding was issued and cleared by SFF Saldanha and we have thus been recertified under the new ISO 140001 2015 StandardCertificate}.
(3) whether there are any indications of seepage into the ground and/or the groundwater table; if not, what is the position in this regard; if so, what are
the relevant details of the seepage?
A “Ground water sampling” exercise is done bi-annually and the last one was done in May 2019 and there is no seepage detected to date.
​​2. ​Milnerton Terminal
1. For each storage facility owned, leased and/or operated by the Strategic Fuel Fund;
a) on what date was the last Maintenance:
(i) Maintenance of the SFF Milnerton tank farm is an on-going exercise based on a schedule created as per the operating and manufacturers specification of a particular equipment. These schedules are distributed from the Maintenance planner’s office to the relevant staff (electrical or mechanical). Another form of maintenance is “adhoc” as and when a breakdown occurs it is attended to.
(ii) 1999 - 2002
- During this period 11 tanks were refurbished.
​b) For each storage facility owned, leased and/or operated by the Strategic Fuel Fund, what was the cost of such maintenance and/or refurbishment in each case:
- SFF paid market related costs as obtained following its approved tender process.
2. On what date was each specified facility last audited for environmental compliance:
a) An “Environmental Legal Compliance Audit” is conducted bi-annually and the last audit was done in June 2019.
b) The results of these audit was 2 minor findings that were closed-off and terminal received certification.
3. Whether there are any indications of seepage into the ground and/or the groundwater table; if not, what is the position in this regard; if so, what are the relevant details of the seepage?
- A “Ground water sampling” exercise is done bi-annually and the last one was done in December 2019 and there is no seepage detected to date,
27 November 2020 - NW2740
Mileham, Mr K to ask the Minister of Mineral Resources and Energy
(1) Whether any environmental audit and/or inspection has been conducted by his department and/or any other relevant government entity at the Astron refinery in Milnerton in the past nine months before and/or after the explosion on 2 July 2020 that caused the loss of two lives; if not, why not; if so, what (a) were the findings of the audit and/or inspection in each case and (b) actions have been taken based on the findings of the audit and/or inspection; (2) whether the refinery is still compliant with its licensing conditions; if not, what is the position in this regard; if so, what are the relevant details?
Reply:
1. The Department of Mineral, Resources and Energy does not conduct any environmental audits, as these fall under different departments.
2. The refinery is not operational at the moment, however in terms of the Petroleum Products Act, the refinery was compliant prior to the incident.
27 November 2020 - NW2723
Mileham, Mr K to ask the Minister of Mineral Resources and Energy
(1) Whether the Astron Energy refinery in Milnerton intends to return to operational service in the near future; if not, what is the position in this regard; if so, by what date is the refinery envisaged to return to full production capacity; (2) whether (a) a safety and (b) environmental inspection and/or audit will be conducted prior to the facility returning to operational status; if not, why not; if so, what are the relevant details?
Reply:
- The Department does not have specific date at which the refinery is scheduled to start operating, what was shared with the Department from Astron Energy is that the assessments of the incident arestill ongoing and there is no firm date of when the refinery would come back to be operational.
- Safety and environmental inspectionsand/or audit do not fall within the ambit of the Department of Mineral, Resources and Energy.
27 November 2020 - NW2707
Waters, Mr M to ask the Minister of Mineral Resources and Energy
What are thereasons that the (a) (i) City of Ekurhuleni is still operating on a temporary electricity license 20 years after it was established and (ii) National Energy Regulator of South Africa has failed to provide the specified city with a permanent license; and (b) legal implications for the city of operating with a temporary licence for 20 years? NW3475E
Reply:
a) (i) The temporary electricity distribution licence granted to City of Ekurhuleni is still valid as it has two extension letters of which the second extension letter, dated 8 May 2007, extents the licence until 36 months after the promulgation of the Licensing Regulation made under the Electricity Regulation Act, 2006 (Act. No 4 of 2006). Until the Minister of Mineral Resources and Energy promulgates the Licensing Regulations, the temporary licences remain valid.
(ii)Refer to (i) above.
b) There are no legal implications for the City of Ekurhuleni operating with a temporary licence, as it was issued and extended by NERSA in line with section 4 (a) of the Electricity Regulation Act, 2006 (Act. No 4 of 2006).
27 November 2020 - NW2569
Graham, Ms SJ to ask the Minister of Mineral Resources and Energy
(1) With reference to borrow pits being required to meet certain statutory requirements, (a) what pre-planning and licensing requirements exist where borrow pits are being mined on land belonging to a traditional authority, (b) how does this differ from borrow pits on state-owned land, (c) who is responsible for monitoring compliance of borrow pits, (d) what measures are taken against the company responsible for the borrow pit where there is material non-compliance and (e) what measures should be taken against the company by the family of the injured and/or deceased where there is injury and/or loss of life as a result of a borrow pit that does not comply;
Reply:
a) The requirements as it relates to borrow pits are not informed by the nature of ownership of the land over which they are to be undertaken, but the distinction revolves around the entity that intends to undertake such borrow pit activities. The distinction is in the following manner.;If a natural person or an entity that intends to undertake the borrow pit activities does not form part of those that are not exempted in terms of Section 106 of the Mineral and Petroleum Resources Development Act (Act 28 of 2002), they will be required to lodge an application for either a mining permit(Where the area does not exceed 5 hectares and the period of activities may not be longer than the period for which a mining permit can be valid for) or a Mining right (Where the area exceeds 5 hectares and the activities may take longer than the period provided for mining permit). It is important to highlight that the applications for either mining permit or mining right are to be lodged simultaneously with the application for Environmental Authorization in terms of the National Environmental Management Act (Act 107 of 1998).
In case of entities, that are exempted from applying for either a mining permit or a mining right in terms of Section 106 of the MPRDA, they were previously only required to submit the application for an environmental authorization, however following the delisting of this activity from the listing notices, they are currently under no obligation to submit such unless if any of the activities to be undertaking over and above the mining of material may fall under the listing notices.
b) As indicated above, the requirements are not informed by the nature of land ownership. Whether it’s Private or State-owned land, the requirements as outlined above would apply.
(c) The Department of Mineral Resources and Energy is the authority responsible for ensuring compliance by the entities/persons that are undertaking borrow pits activities. It is however imperative to highlight that following the delisting of activities exempted in terms of Section 106 of the MPRDA IN 2017, the activities that are currently undertaken by the exempted State Owned Entities are excluded from this compliance monitoring, although the DMRE and the Department of Environment, Forestry and Fisheries have now embarked on a process of effecting the amendments to overcome this gap. The draft documents are already in place and DEFF is in the process of finalizing the same to enable the DMRE to resume this responsibility of regulating the entities that are exempted from applying for either mining permits or mining rights.
d) The measures to ensure compliance are invoked as necessitated by the nature of non-compliance and differs from one case to the other. This may amongst others include, a Compliance Notice being issued in terms of Section 31L of NEMA with the instructions for corrective measures/steps to be effected. Failure to adhere to these administrative measures in terms of NEMA may also lead to Criminal measures being invoked.
In a case where the said borrow pit would have necessitated that the mining permit or mining right be issued (those that are not exempted in terms of Section 106 of the MPRDA), the said activity may also be suspended in terms of MPRDA. In severe cases of non-compliance, such a mining permit or mining right may be cancelled in terms of Section 47 of the MPRDA, after all the due administrative processes have been followed.
e) Firstly, if the nature of non-compliance warrants that the DMRE should take the appropriate steps as provided for in the legislation, such a family may bring the aspect to the Department’s attention, so that the measures as outlined above can be considered.
(2) With regard to the six children who have reportedly died in three borrow pits in the Moretele Local Municipality, North West, in the past few years, what (a) measures is his department taking to ensure that there is stricter compliance and enforcement and (b) support will his department provide to the families of the deceased children if the deaths were found to have been preventable and due to negligence and/or non-compliance?
Reply
- The Department will conduct an investigation to establish the facts before responding comprehensively.
(b) It is imperative to be familiar with the actual circumstances in order to offer appropriate assistance.
27 November 2020 - NW2523
Mthenjane, Mr DF to ask the Minister of Mineral Resources and Energy
Given that the recent murder of an environmental activist (Fikile Ntshangase) is indicative of deep tensions between communities and mining companies who want to take over their land, what programmes has his department initiated to ensure that mining companies respect communities and their rights to land which may be of interest to mining companies?
Reply:
Before a mining right is granted, a thorough consultation with interested and affected parties including other government department is conducted. In a situation where there are communities, and are to be relocated, a consultation process/Public participation should be undertaken by the mine or by an applicant for a mining right.
An all-inclusive method(s) should be utilised to ensure that community groups can take part in the consultation process in a fair and transparent manner.
13 November 2020 - NW2503
Boshoff, Dr WJ to ask the Minister of Mineral Resources and Energy
(1)Whether, with reference to the report of the Council for Scientific and Industrial Research which indicates that the Republic faces load shedding for at least the next 18 months unless the Government and Eskom make the decision this year to bring the cheapest and most reliable energy on to the grid within the next three years, and Government’s approval that consumers may generate their own renewable energy, he will consider the possibility of allowing access by default to the national power grid so as to allow private instances who generate renewable energy, to be in a position to load surplus energy onto the national power grid, subject to the required safety conditions; if not, why not; if so, what are the further relevant details; (2) whether he will make a statement on the matter?
Reply:
1. In line with similar prognosis on supply and demand, the IRP2019 recognises that there is risk of load shedding in the next 18 to 24 months.
It is for this reason that as one of the 9 (nine) decisions in the IRP2019 we committed to the following:
Decision 1:Undertake a power purchase programme to assist with the acquisition of capacity needed to supplement Eskom’s declining plant performance and to reduce the extensive utilisation of diesel peaking generators in the immediate to medium term. Lead-time is therefore key.
Decision 2: Koeberg power plant design life must be extended by another 20 years by undertaking the necessary technical and regulatory work.
Decision 3: Support Eskom to comply with MES over time, taking into account the energy security imperative and the risk of adverse economic impact.
We in addition to these decisions made provision for distributed generation by allowing electrify consumers to generate their own electricity. We have in this regard taken following steps:
-
- The department has enabled generation for own use by removing the licensing requirements for certain category of generation facilities under one megawatt (1 MW). 139 requests for registration have been processed by NERSA to date with capacity of 59. This capacity excludes installations under 1MW that register direct with local municipalities.
- The department has also eased the licensing of generation for own use above 1 MW which is mainly to supplement power supply to commercial and industrial customers including the mines. The IRP 2019 now makes provision for distributed generation for own use above 1MW, which takes away the need for a Ministerial approval for deviation from the IRP before NERSA can process a generation license application. 5 Licences have been issued to date. The Department has invited applicants experiencing challenges to engage DDG responsible for Programmes and Projects.
2. These initiatives have already beenpublicly pronounced.
30 October 2020 - NW2178
Singh, Mr N to ask the Minister of Mineral Resources and Energy
(1) What total number of households (a)(i) nationally and (ii) provincially have benefited from the Integrated National Electrification Programme (INEP) over the past five financial years and (b) who initially benefited from infrastructure under the mixed development category, no longer qualify for subsidisation of INEP and free basic electricity; (2) what is (a) total number of electricity meters have been installed under the INEP programme in the past financial year and (b) total amount is still outstanding for the installation of the electricity meters?
Reply:
(1)(a)
(i) The total number of households electrified over the past five financial years is 1,266,240.
(ii) Provincial breakdown of number of indigent households electrified in last 5 years:
(b) The Mixed Developer Policy Guideline was introduced in October 2018. Before this date, all applications received by the Department on mixed developer projects were treated as normal Bulk and Households applications. Funding for infrastructure under the mixed development category is provided for on a pro-rata basis based on the percentange consumption of indegent customers within the development. If the percentage power consumption of indegent customers within the development is 70% and above, the bulk infrastructure qualifies for fullfunding through the INEP Grant.
All indigent customers qualify for free basic electricity as per the Free Basic Electricity policy.
(2)
(a) A total of 214 517 households were electrified in the past financial and these households have electricity meters installed.
(b) No outstanding meter installations have been reported by our electrification programme implementing agents (Eskom and Municipalities).
30 October 2020 - NW2486
Phillips, Ms C to ask the Minister of Mineral Resources and Energy
Whether he will provide Mrs C Phillips with a list of any companies that provide mining companies with goods and/or services that (a) he and (b) his immediate family are shareholders in or benefit from financially; if not, why not; if so, what are the further relevant details?
Reply:
The Minister makes annual declaration of Financial Interest to Parliament through Parliamentary Ethics Committee. The Member can, if she is interested, make a request to access such declaration from the Committee.
30 October 2020 - NW2485
Phillips, Ms C to ask the Minister of Mineral Resources and Energy
Whether he will provide Mrs C Phillips with a list of any companies that (a) he and (b) his immediate family members are shareholders in and/or benefit from financially, that have applied for prospecting and/or mining rights; if not, why not; if so, what are the further relevant details?
Reply:
The Minister makes annual declarations to Parliament through the Parliamentary Ethics Committee. The Member can, if she is interested, make a request of the Ministers Declaration of Financial Interests from the Committee.
02 October 2020 - NW2100
Phillips, Ms C to ask the Minister of Mineral Resources and Energy
What total number of regional offices of his department are still closed under Level 2 of the lockdown to curb the spread of the coronavirus?
Reply:
(a) No Regional Offices of DMRE are still closed under Level 2.
All sixteen (16) Regional Offices of the Department of Mineral Resources and Energy are operating during lock down level 2. However, these offices are operating at the capacity of 30% to curb the spread of Covid-19.
02 October 2020 - NW1822
Mthenjane, Mr DF to ask the Minister of Mineral Resources and Energy
Whether any person has applied to his department for prospecting rights of diamond mines in Limpopo in the past two years; if not, what is the position in this regard; if so, who is the applicant?
Reply:
List of application for Prospecting Rightlodged in Limpopo for the past two years
DATE LODGED |
COMPANY |
MINERAL |
16 Feb 2018 |
KADOSH MINING PTY LTD |
COPPER,DIAMOND (GENERAL),DIAMOND,DIAMOND (ALLUVIAL),GEMSTONE EXCEPT DIAMONDS,GOLD,PHOSPHATE,PGM |
01 March 2018 |
DE BEERS CONDOLIDATED MINES PTY LTD |
DIAMOND (INKIMBERLITE) |
14 Nov 2018 |
RAZORBILL PROPERTIES 12 (PTY0 LTD |
DIAMOND,DIAMOND(GENERAL),DIAMOND (KIMBERLITE) |
14 Nov 2018 |
RAZORBILL PROPERTIES 12 (PTY0 LTD |
DIAMOND,DIAMOND(GENERAL), DIAMOND(KIMBERLITE) |
27 Nov 2018 |
BOLDMAN MINING ENTERPRISE (PTY) LTD |
COAL,COPPER,DIAMOND,MAGNESITE,URANIUM |
15 March 2019 |
GABBINS HOLDINGS PTY |
DIAMOND (GENERAL),DIAMOND,DIAMOND (INKIMBERLITE),DIAMOND ALLUVIAL),GOLD,PGM,SILVER |
09 April 2019 |
KDB MINING PTY LTD |
DIAMOND (GENERAL) |
15 April 2019 |
WIZA MINING PTY LTD |
Chrome,andalusite,diamondgeneral,iron,manganese,pgm |
15 April 2019 |
BASADZI PELE MANAGEMENT CONSULTING AND PROJECTS |
Chrome,andalusite,diamondgeneral,iron,manganese,pgm |
27 May 2019 |
ANGLO EXPLORATION HOLDINGS PTY LTD |
CHROME,COPPER,DIAMOND(GENERAL),GOLD,IRON,LIMESTONE,MAGNESITE,MANGANESE,SILVER,TIN,ZINC |
03 June 2019 |
VHARANANI MINING PTY LTD |
DIAMOND, GOLD |
22 Aug 2019 |
NKUZI YA MANANGA GROUP PTY LTD |
GEMSTONES EXCEPT DIAMONDS, GOLD ORE, TUNGSTEN ORE, ZINC ORE |
21 Oct 2019 |
YUGASET PTY LTD |
DIAMOND (ALLUVIAL) |
22 Oct 2019 |
Atok Mining House Pty Ltd Limpopo |
COPPER ORE , DOLOMITE, GEMSTONES EXCEPT DIAMONDS, SILICA SAND (GENERAL) |
10 Dec 2019 |
ANOITED MINING (PTY) LTD |
CHROME,COPPER,DIAMOND (GENERAL),DIAMOND,DIENSION STONE, GOLD,IRON,MAGNESITE,MANGANESE,METALLURGICAL,NICKEL,PGM,SILICA SAND (GENERAL),SILICA SAND (SILICA) SILICON,SILVER |
17 Dec 2019 |
BARWA BA PHALADI MINING AND PROJECTS CC |
DIAMOND,DIAMOND (ALLUVIAL),DIAMOND(KIMBERLITE),GRAPHITE,MAGNESITE |
17 Dec 2019 |
ON REEF INVESTMENTS (PTY) LTD |
DIAMOND,DIAMOND (ALLUVIAL),DIAMOND(KIMBERLITE),GRAPHITE,MAGNESITE |
25 Feb 2020 |
BOO WANDO HOLDINGS |
AGGREGATE,CHRONME,COBALT,COPPER,DIAMON (GENERAL),DIAMOND,DIAMOND (KIMBERLITE),GOLD,GRAVEL,IRON,NICKEL,PGM,RARE EARTHS,SILVER,SULPHUR(IN PYRITE) |
27 Feb 2020 |
SAMIN GROUP (PTY) LTD |
BRYTES,CHROME,COAL,COBALT,COPPER,DIAMOND (GENERAL),DIAMOND,DIAMOND (ALLUVIAL),DIAMOND (KIMBERLITE,GOLD,GRAPHITE,IRON,NICKEL |
27 Feb2020 |
SAMIN GROUP (PTY) LTD |
BRYTES,CHROME,COAL,COBALT,COPPER,DIAMOND (GENERAL),DIAMOND,DIAMOND (ALLUVIAL),DIAMOND (KIMBERLITE,GOLD,GRAPHITE,IRON,NICKEL |
04 Mar 2020 |
MIHLOTI MINING (PTY) LTD |
DIAMOND, DIAMOND (ALLUVIAL), DIAMOND (IN KIMBERLITE) |
27 Mar 2020 |
TSHIKUNDA MINING (PTY) LTD |
NICKEL,LEAD,IRON,GRAPHITE,GOLD,GARNET(GEMSTONE),GARNET(ABBASIVE),DIAMOND (KIMBERLIET), DIAMOND (ALLUVIAL), DIAMOND, DIAMOND (GENERAL),COPPER,CORUNDUM, COBALT,BRYTES |
24 April 2020 |
MAFURI MINING CONSTRUCTION (MPUMALANGA) PTY LTD |
COPPER, GEMSTONES EXCEPT DIAMONDS, GOLD, Phosphate, URANIUM, |
09 July 2020 |
MBOKOTO MIINING GROUP (PTY) LTD: |
BRYTES, COBALT, COPPER ORE, CORUNDUM, DIAMOND (ALLUVIAL), DIAMOND (IN KIMBERLITE), GARNET (ABRASIVE) ,GARNET (GEMSTONE) ,GOLD ORE ,IRON ORE, LEAD, NICKEL ORE |
10 July 2020 |
MAKANYAGO GENERAL BUSSINESS ENETERPRISE |
DIAMON (GENERAL) |
17 July 2020 |
MAMPURU RED GRANITE INVESTMENTS |
COBALT, COPPER ORE, DIAMON (GENERAL), DIAMOND, DIAMOND (IN KIMBERLITE), GOLD ORE, IRON ORE, MANGANESE ORE, NICKEL ORE QUARTZ (GEMSTONE), SILCRETE (SILICA), SILICA SAND (GENERAL) URANIUM ORE, VANADIUM ORE, VERMICULITE, ZINC ORE |
29 July 2020 |
MARALE COMPANY PTY LTD |
AGGREGATE, COAL, DIAMOND, PSEUDOCOAL, TORBANITE/OIL SHALE |
02 October 2020 - NW1501
Phillips, Ms C to ask the Minister of Mineral Resources and Energy
(1) What is the exact location and/or GPS co-ordinates of the national monument and memorial commissioned by the Mine Health and Safety Council in 2017; (2) Whether he will furnish Mrs C Phillips with the (a) confirmation of the total allocated budget of R4 800 000,00 including value-added tax and (b) total amount paid to a certain service provider (name furnished); if not, why not, in each case; if so, what are the further relevant details in each case?NW1872E
Reply:
1. Answer:The GPS co-ordinates, MHSC has experienced various delays in the finalisation of the projects especially on the approval of site location after the City of Joburg change in position on their original approval of site location for the projects. The details will be provided at the later stage the location of new MHSC offices is confirmed.
2. Answer: (a) Initial total project amount is confirmed to be R4 800 000,00 inclusive of value added Tax.
(b) Total amount paid to the service provider is R4 457 741.14 on original project plan. This excludes the additional costs incurred for additional technical R 191 291.32 for more technical work and storage costs.R 104 291.32 was spent onNew Site Additional Costs (Drawings, Design & Artworks) for Johannesburg Land Company application requirements R 87 000.32 Storage Costs as Result of Delays in Installation of the Monument. Therefore the total amount paid to date on the project is R 4 649 032,46.
02 October 2020 - NW1403
Phillips, Ms C to ask the Minister of Mineral Resources and Energy
(1)What number of (a) prospecting rights were issued since 1 April 2020 by each regional mineral resources and energy office and (b) the specified rights were issued within the stipulated time frame; (2) of the prospecting rights that were not issued within the stipulated time frame, how long did it take for each such right to be issued; (3) what number of (a) mining rights were issued since 1 April 2020 by each regional mineral resources and energy office and (b) the specified rights were issued within the stipulated time frame; (4) of the mining rights that were not issued within the stipulated time frame, how long did it take for each such right to be issued?
Reply:
(1) Two prospecting rights were issued
(b) There is no specified timeframe with regard to issuing of rights.
(2) Please see (1)(b) above
(3) No mining rights were issued since 01 April 2020
(4) Please see (3) above
DDG: MR
Date:
Recommended / Not Recommended
Advocate TS Mokoena
Director General: Department of Mineral Resources and Energy
………………/………………/2020
Approved/Not Approved
Mr SG Mantashe
Minister of Mineral Resources and Energy
Date Submitted:-……………/………………/2020
27 August 2020 - NW1747
Singh, Mr N to ask the Minister of Mineral Resources and Energy
(1) Whether his department currently provides free basic electricity under programmes other than the Free Basic Electricity programme; if not, why not; if so, (a) to whom and (b) what are the relevant details; (2) whether the installation and maintenance of electricity prepaid meters would be (a) subsidised or (b) free under certain parameters; if not, why not; if so, (i) under what parameters and (ii) what are the relevant details; (3) whether his department prescribes electricity tariffs and rates to municipalities in order to ensure that the most vulnerable and indigent communities receive free basic electricity; if not, why not; if so, (a) in what manner and (b) what are the relevant details?
Reply:
1. The Department have developed a Free Basic Electricity (FBE) Policy which aims to protect the indigents by provision of lifeline tariff to indigent households as part of government initiative of poverty alleviation. The amount of free basic electricity provided is deemed sufficient to provide basic lighting, basic media access, cooking and basic water heating. The following measures are also available to protect the poor:
- The Department isfacilitating access to electricity through government subsidised Integrated National Electrification Program (INEP) that is improving the quality of life of all citizens through electricity infrastructure and provision of FBE to indigents;
- Free connections provided to Eskom’s low consumption residential customers;
- Lower price increases applied to low consumption domestic customers; and
- Inclining block tariffs (IBT) prescribed in the Electricity Pricing Policy and being implemented by municipalities.
2. Installation and maintenance of electricity prepaid meters is provided by the utility or distribution licence holder.
3. The Free Basic Electricity Policy provide for targeting of indigents or targeted customers by giving them limited free basic electricity. Municipalities develop indigent register or use targeting criteria as prescribed by the Free Basic Electricity. The proposed level of service is for a grid based system for qualifying domestic customers.Terms of use and distribution are different in every Municipality;however, municipalities restrict FBE to a minimum of 50kwh per household per month as prescribed by the policy homes while other Municipalities uses 20 Amps meters as the qualification criteria for Free Basic Electricity.
27 August 2020 - NW1823
Ceza, Mr K to ask the Minister of Mineral Resources and Energy
What amount (a) do the residents of the City of Tshwane pay for a kilowatt unit of prepaid electricity and (b)is the metering company paid for each unit sold?NW2218E
Reply:
a) After consultation with Nersa the following information, relating to the prepaid charge on prepaid electricity was provided:
1.1 Domestic Tariffs
-
- Domestic Standard Supply Single & Three Phase: Conventional & Prepaid
Tariff blocks |
c/kWh |
Block 1 (0-100 kWh) |
170.28 |
Block 2 (101 – 400 kWh) |
199.28 |
Block 3 (401 – 650 kWh) |
217.11 |
Block 4 (>650kWh) |
234.06 |
1.2 Domestic Indigent: Conventional & Prepaid
Tariff blocks |
c/kWh |
Block 1 (0-100 kWh) |
169.89 |
Block 2 (101 – 400 kWh) |
195.43 |
Block 3 (401 – 650 kWh) |
214.42 |
Block 4 (>650kWh) |
228.79 |
1.3 Lifeline: Prepaid
Tariff blocks |
c/kWh |
Block 1 (0-100 kWh) |
169.89 |
Block 2 (101 – 400 kWh) |
195.43 |
Block 3 (401 – 650 kWh) |
214.42 |
Block 4 (>650kWh) |
228.79 |
1.4 Domestic Three Phase Demand Supply: Convention & Prepaid
Domestic Three Phase Demand Supply
- Basic charge: R644.89/month
- Energy charge:130.76c/kWh
- Demand charge: R120.29/kVA
2. Agriculture and Farm Land: Conventional & Prepaid
2.1 Agriculture Tariffs Conventional
- Energy charge: 211.21c/kWh
3. Non - Domestic Single - Phase: Prepaid
3.1 Single Phase: Prepaid (≤ 60A)
- Basic charge: R1 047.12/month
- Energy charge:181.19c/kWh
3.2 Single Phase: Prepaid (≥ 60A)
- Basic charge: R1 309.18/month
- Energy charge: 181.19c/kWh
b) The metro has indicated that it does not pay metering companies for the sale of electricity. However, resellers buy electricity in bulk and resell to their customers.
27 August 2020 - NW1820
Mthenjane, Mr DF to ask the Minister of Mineral Resources and Energy
(1) Whether the generation capacity under Eskom will be sold and electricity generation will be opened to the private sector; if not, what is the position in this regard; if so, (2) whether a new company will be created and/or it will happen under Eskom; if not, what is the position in this regard; if so, what will be the role of Eskom? NW2215E
Reply:
1. Government does not have intentions or policy to sell Eskom, however, several interventions to date have been undertaken to restore Eskom Balance Sheet, recovery losses and deal with inefficiencies. Establishing a new company will require a review of the current existing legislation, the government and Eskom have focused on seeing through the turnaround strategy of Eskom to see its full implementation. Also, plans are ongoing on the two new build power stations to be fast tracked for the completion and commission. The Government has also allowed for small scale embedded generators to be installed, allowed for procurement of new generation capability under the IPP program. The current Eskom financial burden and the Covid 19 pandemic might delay the recovery. Municipalities will also be allowed to do their own procurement. This is to help with electricity interruptions as the government commitment in ensuring electric supply. The approved IRP acknowledges the need for new additional capability which will be needed and which type of technology.
2. Eskom as a generator can participate in new generation bidwindows to address some of their inefficiencies. In terms of capacity needed going forward,Government has opened the door for Private participants, that include Eskom and private sector is part of the program. Government will continue to look at existing legislation in order to enable Eskom and other stakeholder’s advances in a manner that benefits Eskom, customers and investors.
27 August 2020 - NW1709
Waters, Mr M to ask the Minister of Mineral Resources and Energy
(1) What are the licence conditions between the National Energy Regulator of South Africa Authority (Nersa) and the City of Ekurhuleni (CoE)? (2) whether he will furnish Mr M Waters with a copy of the licence agreement and conditions between NERSA and CoE; if not, what is the position in this regard; if so, on what date? NW2099E
Reply:
1. See Conditions of Licence: Section 5 (5.1 – 5.4) as reproduced below.
2. Distribution Licence attached as Annexure “A”.
CONDITIONS OF LICENCE
The licensee shall be bound by the following conditions to this licence:
5.1. LEGAL CONDITIONS
5.1.1 The licensee shall supply electricity within the area of supply mentioned in schedule I below to every applicant who is in a position to make satisfactory arrangements for payment thereof.
5.1.2 The licensee shall not reduce or discontinue the supply of electricity to a consumer unless -
(i) the consumer is insolvent; or
(ii) the consumer has failed to pay the agreed charges or to comply with the conditions of supply and has failed to remedy the default within 14 days after receiving from the licensee a written notice by post calling upon him to do so.
5.1.3 Where the licensee is undertaking an electrification programme which has been approved based on a one year fixed and three year rolling programme in terms of the Integrated National Electrification Programme, the licensee's programme shall set out the approximate dates on which potential consumers will receive their electricity supply, the licensee shall supply electricity to such potential consumers in accordance with the approved electrification plan.
5.1.4 The National Electricity Regulator shall be entitled to settle disputes between the licensee and another supplier, or between the licensee and its consumers or prospective consumers regarding -
i. the right to supply;
ii. the quality of such supply and the provision of services in connection therewith;
iii. the condition on and prices at which electricity is supplied;
iv. the installation and functioning of meters;
v. the suitability of the equipment of the licensee;
vi. delays in or refusal to supply by the licensee;
vii. any other matter in respect of which the licensee or its consumers requests the National Electricity Regulator to act as mediator.
5.1.5 Any decision of the regulator on a dispute as contemplated in 5.1.4 above is binding on the parties to the dispute.
5.1.6. This licence is not transferable without the approval of the National Electricity
Regulator.
5.2. FINANCIAL CONDITIONS
5.2.1 The licensee shall maintain separate electricity distribution business affairs from the licensee's other affairs so that the revenues; cost; assets; liabilities; reserves and provisions for the electricity business are separately identifiable in the books of the licensee from those of any other business.
5.2.2 The licensee shall prepare on a consistent basis from such accounting records in respect of the financial year of the licensee, and each subsequent financial year, accounting statements comprising -
i. an income statement;
ii. a balance sheet.
together with notes thereto, and in appropriate detail the amounts of any revenue, cost, asset, liability, reserve or provision which has been charged from or to any other business together with a description thereof.
5.2.3. The licensee shall annually submit audited copies of such accounting statements to the National Electricity Regulator within 180 days of the end of the licensee’s financial year. This shall include an asset register, purchase value and current value.
5.2.4. The National Electricity Regulator shall determine the prices at which the licensee shall supply electricity to its consumers.
5.2.5. The licensee is not permitted to charge any consumers with other tariffs than those specified in the schedule of approved tariffs set out in schedule 2 hereto, as revised from time to time, without the approval of the National Electricity Regulator.
5.2.6. The licensee shall pay the bulk supplier from whom it purchases its electricity.
5.2.7. Ensure that monies allocated for statutory National Electricity Regulator purposes in the licensees’ budget are utilised for such purposes.
5.2.8. Ensure that electricity tariffs increases are promulgated through appropriate media.
5.3 TECHNICAL CONDITIONS
5.3.1 The licensee shall supply electricity to its consumers in compliance with quality standards/criteria as the National Electricity Regulator may from time to time prescribe. Currently such applicable standards are, NRS 048 and NRS 047.
5.3.2 Prepare and adhere to plans, which protect customers and ensure the effectiveness of the industry such as:
i. Maintenance Schedules;
ii. Standards of Service (NRS 047) and Quality (NRS 048);
iii. enquiries and complaints management;
iv. licence compliance management;
v. consumer/public and staff safety/education; and
vi. system losses reduction.
5.3.3 Explore demand management strategies before augmentingor expanding a distribution system.
5.3.4 Ensure that metering, billing and revenue collection are effective, efficient and accurate.
5.4 GENERAL CONDITIONS
5.4.1 The National Electricity Regulator shall be entitled to collect such information from the licensee or its consumers as it deems necessary.
5.4.2. The licensee shall supply the NER on a quarterly basis with new electrification connections completed during the previous three months, starting in April of each year.
5.4.3. The National Electricity Regulator, or any person authorised by it in writing, may enter upon premises of the licensee and inspect any plant, machinery, books, accounts and other documents found there.
5.4.4. The National Electricity Regulator may call upon the licensee to furnish to it such periodical or other returns in such form as the National Electricity Regulator may from time to time prescribe, and such particulars in respect of the undertaking as the National Electricity Regulator may from time to time demand.
END
02 July 2020 - NW999
Nxumalo, Mr MN to ask the Minister of Mineral Resources and Energy
(1)Given the reports of positive cases of Covid-19 at some mines, what steps does his department intend to take to better manage the situation at mines; (2) what is his current position on the Covid-19 testing of miners, in light of guidelines that his department published last week that did not involve physical testing, but only the screening of patients which involves only questioning the patients about their movement and coming into contact with the virus and ignoring asymptomatic patients?
Reply:
1. The Department has promulgated a Guideline for the Compilation of a Mandatory Code of Practice for the Mitigation and Management of Covid-19 Outbreak. For instance, the Guideline requires the employers to ensure that employees returning from areas which are regarded as hotspots of COVID-19 are quarantined for 14 days before they return to work. Also, there must be vigorous screening and testing at the mines as well as to ensure that hygiene practices and the provision of adequate personal protective equipment (PPE) are maintained.
Further, the Department conducts inspections to ensure that effective measures are implemented on the mitigation and management of COVID-19 and issue instructions where necessary to ensure compliance with the legal provisions.
2. The Guideline issued by the Department does not require for only screening to be done but for employees to also be tested. In fact, most of the cases reported by the sector were asymptomatic and were as a result of the DMRE requirement for testing to be done.
The mines are also required through the Guideline to work in collaboration with the Department of Health (DOH) when conducting contact tracing.
Chief Inspector Mines
Date:
Recommended / Not Recommended
Advocate T S Mokoena
Director General: Department of Mineral Resources and Energy
………………/………………/2020
Approved/Not Approved
Mr SG Mantashe, MP
Minister of Mineral Resource and Energy
Date Submitted:-……………/………………/2020
02 July 2020 - NW928
Boshoff, Dr WJ to ask the Minister of Mineral Resources and Energy
Whether his department awarded any tenders connected to the Covid-19 pandemic; if not, what is the position in this regard; if so, fat (a) are the names of the businesses to whom these tenders were awarded, (b) are the amounts of each tender awarded and (c) was the service and/or product to be supplied by each business;
Reply:
- The department did not award tenders for Covid-19
Not applicable
Not applicable
Not applicable
- The is no procurement facilitated through deviations for Covid-19
Not applicable
Not applicable
- There were no tenders awarded
02 July 2020 - NW1239
Boshoff, Dr WJ to ask the Minister of Mineral Reurces and Energy.Mr
1 What are the current fuel reserves at all the Republic’s fuel refineries and depot5; 2 whether domestic shortages are foreseen; if not, what is the position in this regard; if so, 3 whether fuel is currently being exported to neighbouring countries; if not, what is the position in this regard; if so, what are the relevant details? NW1605E
Reply:
- The feel reserves at each of the refineries and depots are a function of the market share of each of the oil companies as well as company policy.
- No domestic shortages are foreseen, Currently all the refineries are operational with the exception of the Milnerton Refinery which is on a planned maintenance shutdown. It is expected to be back online by the first week of July 2020.
- Yes. Oil Companies have individual contracts with neighbouring countries such as Namibia, Lesotho, Swaziland and Botswana, and they supply them accordingly
02 July 2020 - NW1188
Van Dyk, Ms V to ask the Minister of Mineral Resources and Energy
(a) How will the Government assist to create opportunities for illegal miners in Namaqualand to mine legally and (b) what proposals are being put in place in this regard?
Reply:
(a) The Mineral and Petroleum Resources Development Act, 2002 (Act 28 of 2002) as amended, allows any person (legal/natural) to apply for either mining rights, prospecting rights or mining permits. The department has a Small Scale Mining Section which is responsible to assisting those who are struggling financially to apply for permits or rights. Applications can be accepted and processed only where there is no existing applications or rights issued for the same mineral and land. Illegal activities that are taking place in Namaqualand are in respect of areas that are part of rights already issued to other entities. It is unfortunate that others resort to conducting illegal mining instead of approaching the Department for assistance.
(b) There was a process initiated by the department to engage the legal right holders before national lockdown to work on a plan to accommodate the illegal miners in the area. The department also advised the illegal miners to form Cooperatives so that they can be collectively assisted (where possible), and only on areas where no entity holds a right or permit. NW1493E
DDG: MR
Date:
Recommended / Not Recommended
Advocate TS Mokoena
Director General: Department of Mineral Resources and Energy
………………/………………/2020
Approved/Not Approved
Mr SG Mantashe
Minister of Mineral Resources and Energy
Date Submitted:-……………/………………/2020
02 July 2020 - NW1115
Van Dyk, Ms V to ask the Minister of Mineral Resources and Energy
(a) Who are the directors of Ghunu Diamonds at the Brazil mine in Namaqualand, (b) which licence rights (i) have they applied for and (ii) have been afforded to them, (c) for how long will the licence be valid and (d) what total amount has the company put aside for rehabilitation?
Reply:
a) The members in Ghunu Diamonds CC are Martins Bernardo Paolo Sergio who is a 50% member’s interest holder and Cloete Ghusain who is also a 50% member’s interest holder. All members are South African residence.
b) The corporation holds a prospecting rights with bulk sampling to prospect for diamonds.
c) The right was issued on the 10th September 2015 under reference number NC 30/5/1/1/2/10090 PR to prospect for Diamond (Alluvial) in respect of a Portion of the farm Brazil No 329, in extent of 4043.9282 hectares, situated within the administrative district of Namaqualand. The right was issued for a period of two years ending on the 9th September 2019. The corporation applied for a renewal under reference number NC 30/5/1/1/2/12024, which is now granted pending execution.
d) The rehab amount requested is R210 000.00 and is deemed adequate.
DDG: MR
Date:
Recommended / Not Recommended
Advocate TS Mokoena
Director General: Department of Mineral Resources and Energy
………………/………………/2020
Approved/Not Approved
Mr SG Mantashe
Minister of Mineral Resources and Energy
Date Submitted:-……………/………………/2020
08 June 2020 - NW328
Mileham, Mr K to ask the Minister of Mineral Resources and Energy
Whether the proposal as stated by him at the 26th Investing in African Mining Indaba that the Government seeks to establish an alternative power generation entity outside of Eskom has been (a) discussed and (b) approved by the Cabinet; if not, why not; if so, on what date did this discussion and approval take place; 2) Where did the specified proposal originate from; 3) What is the proposed (a) structure, (b) mandate and (c) time line for the establishment of the new entity; 4) What are the relevant details of the envisaged reporting line of the entity to the national executive? NW482E
Reply:
2.. The single buyer model cannot be sustained, in respect of which Eskom is the sole aggregator and dispatcher of all the energy generated in the interconnected power system. This is due to Eskom’s poor balance sheet and its inability to carry the risks relating to long term power purchase agreements with other generators, without further encumbrance of the national revenue fund.
In the circumstances, it has become critical to find alternative models for the delivery of new generation capacity as required under the integrated resource plan. The entity that the Minister referred to at the Mining Indaba is aimed at complimenting the role that Eskom is unable to fulfil, in relation to new generation capacity. It is noteworthy that the entity could play the role of Buyer as well as developer of new power capacity, with or without private sector partners.
3. (a) (b)(c) work in regard to the structure has not been finalized and it would be premature to answer questions like mandate and timelines.
4. See (4) above
08 June 2020 - NW732
Mileham, Mr K to ask the Minister of Mineral Resources and Energy
(1) Whether any payments were made to certain companies (names furnished) in terms of bid number BAC 10/16 for the nuclear new build; if so, (a) what was the amount of each payment made, (b) what value was received from the supplier with regard to each specified payment and (c) from which budget line item and programme was the payment drawn in each year in which a payment was made; (2) what role did certain persons (names furnished) play in the negotiations, implementation and/or facilitation of the specified deal; (3) whether either of the specified persons received any remuneration, commission and/or other fees as a result of the deal; if so, what is the quantum thereof; (4) what are the relevant details of the process that was followed in the awarding of the contract; (5) whether the Auditor-General has made any findings with regard to the specified process that was followed in awarding the contract; if so, what were the findings? NW936E
Reply:
1. Payments were made to (a) (b) Central Lake 149 Trading / Empire Technology (Pty) Ltd, no payment were made to (c) Edson power group
- (i) R 22 800 000 (ii) 01/07/2016
- (i) R 23 940 000 (ii) 28/09/2017
- (i) R 51 642 000 (ii) 03/02/2017
- (i) R 12 500 000 (ii) 19/092019
- (i) R 51 568 000 (ii) 12/02/2019
- (i) R 4 275 000 (ii) 26/03/2020
- (i) R 4 275 000 (ii) 31/03/2020
(iii) Programme 5: Nuclear Energy
Responsibility CD: Nuclear Safety & Technology
Objective: Nuclear Safety & Technology
Item: CNS: BUS & ADV SER RESE & ADVISORY
2. The Department does not know the role the certain individual played because the Department participated in terms of Treasury Regulations Section 16A6.6. on the contract which was secured by another organ of State, i.e. Provincial Treasury in Free State
3. Please refer to response in under 2 above.
4. what are the relevant details of the process that was followed in the awarding of the contract;
- The Department participated in terms of Treasury Regulations Section 16A6.6. on the contract which was secured by another organ of State, i.e. Provincial Treasury in Free State
5. whether the Auditor-General has made any findings with regard to the specified process that was followed in awarding the contract; if so, what were the findings? NW936E
- Yes - The Auditor General raised an audit finding in the 2016/17 financial year
08 June 2020 - NW677
Mileham, Mr K to ask the Minister of Mineral Resources and Energy
(1) What (a) total number of fuel storage tanks are owned by the Strategic Fuel Fund (SFF), (b) number of the specified storage tanks are in an operational condition and (c) is the volume of the tanks that are (i) in an operational condition and (ii) not in an operational condition; (2) what (a) number of the storage tanks are utilised by the SFF for strategic fuel reserves and (b) is the volume thereof; (3) what (a) number of the storage tanks are leased to other companies and (b) is the volume thereof?
Reply:
(1) (a) 45 Tanks;
(b) 6 Tanks operational;
(c) (i) 45 Million barrels operational;
(ii) 7,8 Million barrels not operational;
(2) (a) 2 tanks;
(b) 15 Million barrels;
(3) (a) 4 tanks;
(b) 30 Million barrels;
08 June 2020 - NW876
Bozzoli, Prof B to ask the Minister of Mineral Resources and Energy
(1)Whether his department will offer any form of Covid-19 financial or other relief to small businesses; if not, why not; if so, what are the relevant details; (2) whether the Covid-19 financial or other relief will only be allocated to qualifying small businesses according to the Broad-Based Black Economic Empowerment Act, Act 53 of 2003, as amended; if not, what is the position in this regard; if so, (a) on what statutory grounds and/or provisions does he or his department rely to allocate Covid-19 financial or other relief only to small businesses according to the specified Act and (b) what form of Covid-19 financial or other relief, if any, will be made available to other small businesses?
Reply:
1. Yes, the department will offer some form of relief/ assistance.
2. (a) The Covid 19 assistance will be allocated to qualifying businesses in line with the Small-Scale Mining Implementation Framework.
(b) All qualifying small scale mining companies will be assisted.
DDG: MPPP
Date:
Recommended / Not Recommended
Advocate T Mokoena
Director General: Department of Mineral Resources and Energy
………………/………………/2020
Approved/Not Approved
Mr SG Mantashe
Minister of Mineral Resources and Energy
Date Submitted:-……………/………………/2020
08 June 2020 - NW675
Mileham, Mr K to ask the Minister of Mineral Resources and Energy
(1) What is the current status of the investigation into the sale, also known as stock rotation, of the strategic fuel stocks of the Strategic Fuel Fund; (2) whether the report of the investigation will be submitted to the Portfolio Committee on Mineral Resources and Energy; if not, why not; if so, by what date; (3) has any (a) disciplinary, (b) criminal and/or (c) civil action been instituted against each person who is implicated; if not, in each case, why not; if so, what are the relevant details in each case?
Reply:
(1) SFF has filed the papers and supplementary papers after the investigation. Report has been handed to the Law Enforcement Agency (Hawks) for further criminal investigation;
(2) At this stage the report cannot be shared with any member of the public as advised by the Law Enforcement Agency (Hawks);
(3) (a) Report is being reviewed internally for any evidence of misconduct and any recommendations will be implemented;
(b) As in (1) above the investigation is still with the Hawks;
(c) Report is being investigated by the Hawks and also internal review for any misconducts. Recommendations from the 2 investigations will be implemented;
NW877E
25 May 2020 - NW676
Mileham, Mr K to ask the Minister of Mineral Resources and Energy
Whether there are any national standards for the quality, installation and maintenance of mining equipment and/or assets; if not, what is the position in this regard; if so, (a) what are the details of the standards, (b) who is responsible for the enforcement thereof, (c) what total number of compliance inspections were undertaken in the (i) 2016-17, (ii) 2017-18 and (iii) 2018-19 financial years and (d) what were the outcomes thereof?
Reply:
a) There are 36 South African National Standards (SANS) and 2 South African Bureau of Standards (SABS) referenced in the Mine Health and Safety Act No 29 of 1996, as amended. The list is in Annexure 1.
b) The monitoring and enforcement is done by the Department’s Engineering Inspectors.
c) (i) The total number of compliance inspections conducted in 2016/2017 was 9 363 which included the mine equipment inspections.
(ii) Similarly, the total number of compliance inspections conducted in 2017/2018 was 9 425.
(iii) The total number of inspections conducted in 2018/2019 was 8567.
d) Where there were non-compliances observed during the inspections, to deal with dangerous conditions or non-compliance with mine standards or provisions under the Act, Inspectors issued sections 55 and 54 instructions as per the Mine Health and Safety Act, No. 29 of 1996 as amended. For instance, during the reporting period 2018/2019, there were 1399 section 55 instructions and 963 section 54 instructions issued, respectively.
Chief Inspector Mines
Date:
Recommended / Not Recommended
Advocate T S Mokoena
Director General: Department of Mineral Resources and Energy
………………/………………/2020
Approved/Not Approved
Mr SG Mantashe, MP
Minister of Mineral Resource and Energy
Date Submitted:-……………/………………/2020
25 May 2020 - NW587
Montwedi, Mr Mk to ask the Minister of Mineral Resources and Energy
What measures did his department put in place to monitor working conditions in mines to ensure that workers are protected from COVID-19 before granting Sibanye Mine in Rustenburg and other mining companies permission to resume work?
Reply:
1. The Department has consulted with organised labour and organised business regarding the possible impact of COVID-19 in the mining sector.
2. The Department has made inputs into the recent amendments of the Regulations of the Disaster Management Act (DMA), issued in terms of Section 27(2) of the same Act and published by the Minister of COGTA on the 17th April 2020. Please take particular note of the insertion of Regulation 11K which deals with Mining Operations.
2.1 Regulation 11K.(1) of DMA states:
Mining operations, as referred to in paragraph 22 of Part B of Annexure B, must be conducted at a reduced capacity of not more than 50% during the period of lockdown, and thereafter at increasing capacity as determined by direction issued by the Cabinet member responsible for mineral resources and energy.
2.2 Regulation 11K.(2) of DMA states:
The following conditions apply to the starting and increasing of capacity:
a) A rigorous screening and testing program must be implemented as employees return to work;
b) The mining industry must provide quarantine facilities for employees who have tested positive for the COVID-19;
c) Data collected during the screening and testing programme must be submitted to the relevant authority;
d) Mining companies must make arrangements to transport their South African employees from their homes to their respective areas of operations;
e) Workers from neighbouring Southern African Development Community countries must be recalled to their place of employment at the end of lockdown in their respective countries in accordance with these Regulations and regulations applicable in those countries.
2.3 Regulation 11K.(3) of DMA states:
The monitoring and impact assessment of seismicity through the Council for Geoscience must be intensified with immediate effect.
3. The Department through the Chief Inspector of Mines has also directed the South African Mining Industry (SAMI) to prevent the spread of COVID-19 in the following communique issued to mining companies:
3.1 Guiding principles on prevention & management of COVID-19 in SAMI
3.2 Request for protocol on prevention & management of COVID-19 in SAMI
3.3 Safe start-up procedure of mines by employers and employees.
4. The Department has identified all Inspectors of Mines as essential service and were issued with Lockdown Permits to ensure that health and safety of mineworkers is not compromised even during this pandemic.
5. Inspectors of Mines remain on duty during the lockdown and conduct mainly unannounced visits at various mines particularly at high risk mines, to check the mines compliance to the Mine Health and Safety Act and other relevant prescripts such as “Lockdown” regulations.
Chief Inspector Mines
Date:
Recommended / Not Recommended
Advocate T S Mokoena
Director General: Department of Mineral Resources and Energy
………………/………………/2020
Approved/Not Approved
Mr SG Mantashe, MP
Minister of Mineral Resource and Energy
Date Submitted:-……………/………………/2020
09 March 2020 - NW157
Ismail, Ms H to ask the Minister of Mineral Resources and Energy
Whether his department received any applications for mining licences in the City of Ekurhuleni; if so, (a) what number of applications have been (i) received (aa) in each of the past five years and (bb) since 1 April 2019 and (ii) issued in each case and (b) where is the mining taking place?
Reply:
Reply
- (i)The number of applications received in the last five years from 2015 to 31 March 2019 are 56
Year |
Total No of Applications |
Applications issued |
2015 |
15 |
04 |
2016 |
07 |
01 |
2017 |
17 |
03 |
2018 |
10 |
01 |
2019 |
08 |
01 |
(bb)
(bb) Applications received from 1 April 2019 are 08
(ii) There are no applications issued in this category
(ii) There are no applications issued in this category
(b) Nigel, Brakpan and Benoni.
DDG: MR
Date: 27 FEB 2020
Recommended
Advocate TS Mokoena
Director General: Department of Mineral Resources and Energy
Approved
Mr SG Mantashe
Minister of Mineral Resources and Energy
Date submitted: 09/03/2020