REPORT OF THE PORTFOLIO COMMITTEE ON ENERGY ON ITS ACTIVITIES UNDERTAKEN DURING THE 4TH PARLIAMENT (MAY 2009 – MARCH 2014)  

 

TABLE OF CONTENTS

1.     INTRODUCTION

2.     EXECUTIVE SUMMARY

3.     OVERVIEW OF THE PORTOFLIO COMMITEE ON ENERGY DURING THE 4TH PARLIAMENT BY THE CHAIRPERSON – HON. SISA NJIKELANA

4.     OPERATIONAL  CONTEXT AND REPORT FRAMEWORK

4.1.   National policies and directives that have an impact on the energy sector

4.2.   A brief profile Department of Energy (DOE) 

4.2.1. SoE’s/SoC’s within the DoE 

4.2.1.1.          Regulators

4.2.1.2.          Research and DevelopmentEnergy security

4.2.2. Legislation

4.2.2.1.          Legislation that directly mandates the DoE

4.2.2.2.          Non-core legislation that also impacts on the DoE

4.2.3. Strategic outcomes of the department of energy 

4.2.4. Programmes of the Department of Energy

4.2.4.1.          Programme 1:  Administration

4.2.4.2.          Programme 2: Energy Policy and Planning

4.2.4.3.          Programme 3: Petroleum and Petroleum Products Regulation

4.2.4.4.          Programme 4: Electrification and Energy Programme and Project Management

4.2.4.5.          Programme 5: Nuclear Energy

4.2.4.6.          Programme 6: Clean Energy

4.2.5. Budget Allocations for the Department of Energy since 2010

4.2.6. Some of the key achievements of the Department of Energy - DoE (2009 – 2014)

5.     REFLECTION ON THE PCE PERFORMANCE

5.1.   Mandate and functions of the Portfolio Committee on Energy

5.1.1. The Portfolio Committee on Energy, as a Committee of the National Assembly, has as its mandate, in respect to the DoE, to:

5.1.2. The mandate of the Committee fulfils the following functions (derived from Parliament’s strategic objectives):

5.2.   Method of work of the committee

5.2.1. Committee category

5.2.2. Processing legislation

5.2.3. Oversight visits

5.2.4. Media Networking Sessions

5.2.5. Expert Testimonies- inviting experts/specialists

5.2.6. Energy Stakeholder Meetings

5.2.7. Roundtable discussions

5.2.8. Extra-Parliamentary Meetings

5.2.9. Mailing list  

5.3.   Committee focus areas during the 4th Parliament

5.4.   Reflection on the PCE performance as guided by its strategic objectives

5.5.    Reflection on the PCE oversight performance on annual basis and on whether the objectives of its programmes were achieved

5.5.1. 2009 to 2010

5.5.2. 2010 to 2011

5.5.3. 2011 to 2012

5.5.4. 2012 to 2013

5.5.5. 2013 to 2014

5.6.   Other activities the committee undertook in the period under review

5.6.1. Public hearings

5.6.2. Energy Stakeholder Meetings

5.6.3. Roundtables

5.6.4. Legislation

5.6.5. Oversight trips undertaken

5.6.6. Study tours undertaken

5.6.7. International Work

5.6.7.1.          General international work

5.6.7.2.          Engagement with international bodies

5.6.7.2.1.              Joint workshop with the Pan African Parliament (PAP) Committee on Energy

5.6.7.3.          International Agreements:

5.6.8. Statutory appointments

5.6.9. Interventions

5.6.10.   Petitions

5.6.11.   Obligations conferred on committee by legislation:

5.6.11.1.       Budget Review Process

5.6.11.2.       Various recommendations from the BRR Reports

5.6.12.   Role and contribution of the PCE on areas of non-achievement by the DoE

5.6.13.   Summary of outstanding issues   

5.6.13.1.       Outstanding issues from the minutes of the PCE

5.6.13.2.       Outstanding issues from the Energy Stakeholders Meetings

5.6.13.3.       Outstanding issues from engagements such as Climate Change, MDG’s, etc.

6.     MISCELLANEOUS

7.     KEY CHALLENGES EMERGING

8.     KEY AREAS FOR FUTURE WORK AS GUIDED BY PARLIAMENT’S STRATEGIC OBJECTIVES AND PCE MANDATE

9.     RECOMMENDATIONS

 


GLOSSARY OF ACRONYMS

 

ACSA               Airports Company of South Africa

ADAM              Approach to Distribution Asset Management

AFS                  Annual Financial Statements

AG                   Auditor-General

AGSA               Auditor-General of South Africa

APP                 Annual Performance Plan

ATC                  Announcements Tablings Committee

BASA               Banking Association of SA

BEE                 Black Economic Empowerment

BBBEE Broad Based Black Economic Empowerment

BFP                  Basic Fuel Price

BRICS Brazil, Russia, India, China and South Africa

BRRR               Budgetary Review and Recommendations Report

BRP                 Budget Review Process

CDM                 Clean Development Mechanism

CEF                  Central Energy Fund

CoGTA             Department of Cooperative Governance and Traditional Affairs

COD                 Carbon Oxygen Demand

COP                 Conference of the Parties

CSP                 Concentrated Solar Power

DAFF               Department of Agriculture, Forestry and Fisheries

DBSA               Development Bank of Southern Africa

DEA                 Department of Environmental Affairs

DoE                 Department of Energy

DPME              Department of Monitoring and Evaluation

DPSA               Department of Public Service and Administration

DPW                Department of Public Works

DST                  Department of Science and Technology

DTi                   Department of Trade and Industry

DUT                  Durban University of Technology

EDC                 Energy Development Corporation

EDI                   Electricity Distribution Industry

EDIH                Electricity Distribution Industry Holdings

EE                    Energy Efficiency

ERA                 Electricity Regulation Act

ESETA Energy Sector Education and Training Authority

ESM                 Energy Stakeholder Meetings

EXCO               Executive Committee

FBE                  Free Basic Electricity

FBAE               Free Basic Alternative Energy

FNRBA Forum of Nuclear Regulatory Bodies in Africa

GDP                 Gross Domestic Product

GTL                  Gas to Liquid

HDSA               Historically Disadvantaged South Africans

IAEA                 International Atomic Energy Agency

IASTED            International Association for Science and Technology for Development

IDC                   Industrial Development Corporation

IEA                   International Energy Agency

IEC                   Integrated Energy Centre

IEP                   Integrated Energy Plan

INEP                 Integrated National Electrification Programme

IPAP                 Industrial Policy Action Plan

IPP                   Independent Power Producers

IPU                   Inter parliamentary Union

IRENA              International Renewable Energy Agency

IRP                   Integrated Resource Plan

ISMO                Independent System Market Operator

KZN                  Kwazulu Natal

LNG                  Liquefied Natural Gas

LPG                  Liquefied Petroleum Gas

MDG                Millennium Developmental Goal

MP                   Member of Parliament

MPAT               Management Performance Assessment Tool

MPRDA            Mineral and Petroleum Resource Development Act

MRGP              Maximum Refinery Gate Price

MTBPS Medium Term Budget Policy Statement

MTEF               Medium-Term Expenditure Framework

MTSF               Medium-Term Strategic Framework

MYPD              Multi Year Price Determination

MW                  Megawatts

NA                    National Assembly

NDP                 National Development Plan

NECSA             Nuclear Energy Corporation of South Africa

NERA               National Energy Regulator Act

NERSA             National Energy Regulator of South Africa

NEPAD New Partnership for Africa’s Development

NGO                 Non Governmental Organisation

NGP                 New Growth Path

NMPP               New Multi-Product Pipeline

NNEECC           Nuclear Energy Executive Coordination Committee

NNR                 National Nuclear Regulator

NPO                 Non Profit Organisation

NRWDI             National Radioactive Waste Disposal Institute

NT                    National Treasury

NUMSA            National Union of Mineworkers of South Africa

OAG                 Office of the Accountant-General

PAIA                 Promotion of Access to Information Act

PAP                 Pan African Parliament

PAPSAPEI        PAP-SA Parliament Energy Initiative

PASA               Petroleum Association of South Africa

PCE                 Portfolio Committee on Energy (in the National Assembly)

PFMA               Public Finance Management Act

PICC                 Presidential Infrastructure Coordinating Commission

PPA                 Petroleum Products Act

R&D                 Research and Development

RECORD          Renewable Energy Centre for Research and Development

RED                 Regional Electricity Distributors

REFIT               Renewable Energy Feed-In Tariff

REIPPP            Renewable Energy Independent Power Producers Programme

RET                  Renewable Energy Technologies

SABS               South African Bureau of Standards

SACC               SA Calcium Carbide

SADC               Southern African Development Community

SALGA South African Local Government Association

SANEDI            South African National Energy Research and Development Institute

SARS               South African Revenue Service

SASDA South African Supplier Development Agency

SCM                 Supply Chain Management

SETA                Sector Education and Training Authority

SFF                  Strategic Fuel Fund

SIP                   Strategic Integrated Projects

SMME Small, Medium and Micro Enterprises

SOC                 State Owned Company

SONA               State of the Nation Address

SOE                 State-Owned Entity

SOOG Strategic Outcomes-Oriented Goals

SWH                 Solar Water Heater

TcF                   Trillion Cubic Feet

TWh                  Terawatt hours

UN                    United Nations

UNDP               United Nations Development Programme

UWC                 University of Western Cape

 

1.     INTRODUCTION

 

Section 55 (2) of the Constitution provides for Parliament and its committees to have oversight over the executive and any state organ. Parliament’s committees are the engine room that gives effect to that constitutional imperative and section 56 (a) provides for the National Assembly (NA) or any of its committees to summon any person to appear before it to give evidence on oath or affirmation, or to produce documents. Section 56 (b) provides for any person or institution to report to it. During the 4th Parliament (2009-2014), the Portfolio Committee on Energy (Portfolio Committee on Energy) gave effect to those provisions through its role in legislating, oversight and hearing public submissions on energy related issues. This guides the role of the PCE in terms of Parliament and hence the PCE has at its mandate and mission.

 

The overarching aim of this report is to provide an account of the Portfolio Committee on Energy work during the 4th Parliament and to inform the members of the new Parliament of key outstanding issues pertaining to the oversight and legislative programme of the Department of Energy and its entities. It provides an overview of the activities the committee undertook during the 4th Parliament, the outcome of key activities, as well as any challenges that emerged during the period under review and issues that should be considered for follow up during the 5th Parliament. It summarises the key issues for follow-up and concludes with recommendations to strengthen operational and procedural processes to enhance the committee’s oversight and legislative roles in future.

 

Prior to highlighting the work that the Committee has done over the past five years, it is imperative to first provide an overview of the national policies that have an impact on the energy sector. In one way or the other these policies also, whether directly or indirectly, guided the work of the Committee. Secondly, key achievement of the Department of Energy (DoE) over the five year period will be highlighted. Thirdly, the key strategic objectives of the Portfolio Committee on Energy and the implementation thereof will be detailed in this document – this is the main focus of this document. The fourth and last part of this document will highlight some of the focus areas of the Committee, key areas for future work, key challenges and recommendations.

 

2. EXECUTIVE SUMMARY

Operational Context and Report Framework are presented where firstly National Policies and directives that have an impact on the energy sector are presented. These include the National Development Plan (NDP), the Industrial Policy Action Plan (IPAP), the New Growth Path (NGP) and the Medium Term Strategic Framework (MTSF) (2009-2014), Medium Term Budget Policy Statements (MTBPS) and the State of the Nation Addresses (SONA’s 2009-2014).

 

A summary of key information from the annual performance plans and the strategic plans of the Department of Energy (DoE) and a brief profile of the DoE is provided. On 10th May 2009, President Zuma announced his new Cabinet and the appointment of, amongst others, the Minister of Energy. The new portfolios of some of the Ministers necessitated a re-organisation, renaming and establishment of new departments. Subsequent to the above announcement, the DoE was established following the split of the Department of Minerals and Energy, which resulted in two independent Departments. The aim of the DoE is to formulate energy policies, regulator frameworks and legislation, and oversee their implementation to ensure energy security, promotion of environmentally-friendly energy carriers and access to affordable and reliable energy for all South Africans. Hence this report focuses on the DoE, its entities, programmes, budget and some key achievements of the DoE from 2009. 

 

With regards to the PCE Performance, the method of work of the committee is discussed. The committee meetings were predominantly scheduled on a Tuesday morning but other days were utilized if there were no plenaries. The PCE also processed legislation which was given priority in terms of Committee obligations. Other activities of the PCE included oversight visits where the PCE visited various projects and programmes. The PCE also conducted study tours as a whole or as a delegation of PCE MP’s. The Committee was also involved in Media Networking Sessions to build and foster relations with journalists that report about issues affecting Parliament. The PCE also invited expert testimonies from time to time by inviting experts in areas to present to the PCE as and when necessary. The PCE was also responsible for initiating Energy Stakeholder Meetings which was to create a platform for public discourse in the energy sector. There were four held. The PCE also held round table discussions which were more informal meetings as compared to the Energy Stakeholder Meetings. Finally the PCE also held public hearings.

 

The key focus areas of the PCE are also discussed in this report. In terms of the key focus areas of the PCE in the 4th Parliament is summarised in this section. Also included are details of the oversight over the DoE and the State Owned Entities’ (SOE’s) activities and programmes as well as financial and operational oversight. The PCE also focused on the Energy Policy of the DoE, focusing on the Independent System and Market Operator Bill, outstanding legislation and policy documentation with regard to energy planning in general. The PCE assessed Petroleum Regulation and looked at petroleum licensing, pricing and compliance to policies. The PCE also focused on Electrification programmes, the industry transformation, infrastructure and community uplift programmes. Another area the PCE also focused on clean energy including energy efficiency, renewable energy and climate change issues. In terms of nuclear the PCE conducted oversight on nuclear energy including the envisaged 9600MW nuclear roll out programme, nuclear safety, waste management including the National Radioactive Waste Disposal Institute and nuclear policy. This report then proceeds to discuss how the PCE met the key strategic objectives it had defined itself. This section looks at the committee activities, including Committee Meetings and oversight visits from the period 2009 to 2014 for each of the strategic objectives.

The report also highlight, other areas that the PCE was involved in and details the public hearings, energy stakeholder meetings, round table discussions and workshops.

 In terms of Legislation, the Independent System and Market Operator (ISMO) Bill was the only legislation handled by the PCE, the bill was compiled and submitted to the house for adoption but was not adopted during the 4th Parliament. The oversight trips of the PCE covered areas of; the oil and gas industry, energy efficiency, safety, renewable energy, the Integrated National Electrification Programme, energy from waste and the Solar Water Heater programme.

 

Regarding study tours – the PCE undertook a study tour to Mozambique in 2009 where energy security and the impact of climate change were assessed. Again in 2010, the PCE undertook a visit to Mozambique to look at clean energy sources. In 2010; Members of the Committee attended a renewable energy conference in Botswana and a study tour was undertaken to France the aim of which was to gain an insight on the nuclear energy programme. In 2012 the PCE conducted a study tour of energy efficiency initiatives by visiting businesses in Cape Town. The Committee also looked at Petroleum research by visiting the PetroSA Synthetic Fuel Centre University of the Western Cape (UWC). In August 2013, the PCE conducted oversight on Liquefied Petroleum Gas (LPG) by visiting industrial site as well as household supply facilities. The PCE also conducted study tours on co- and tri-generation at ABSA Towers and MTN in Gauteng and studied the potential of landfill gas by visiting the Johannesburg Metro Municipality Landfill Gas to Energy Project in 2013.

 

The report covers the international work of the Committee. The PCE held a joint workshop with the Pan African Parliament. The establishment of PAP-SA Parliament Energy Initiative provides a platform for Parliamentarians dealing with energy issues to share information on the best practices to foster oversight and legislate laws in their respective countries to attain universal access to energy and energy security.

International agreements, statutory appointments and Petitions are highlighted in the report. In terms of Petitions, the Chairperson, Hon SJ Njikelana did receive a petition from the Office of the Speaker relating to concerns/challenges raised by the community of Matatiele Local Municipality (KZN) focusing on inter alia, energy issues.

 In terms of future focus areas of work for the Committee, there are various pieces of legislation and policy documents that are still outstanding and this need to be presented to the PCE for deliberation and comment. There are policies and bills outstanding, example,

·         The DoE has a new draft Integrated Energy Plan and Integrated Resource Plan and these needs to be finalized.

·         The Independent System Market Operator (ISMO) Bill was deliberated in the Committee and submitted to the House for Adoption. This was not adopted in the 4th Parliament and 5th Parliament needs to follow up on this.

·         From the Energy Stakeholder Meeting on the upstream sector, it emerged that policy challenges e.g. with some of the amendments of the proposed Minerals and Petroleum Resources Development (MRPDA) bill to the upstream sector, that need to be addressed as clear policy directives are needed and the DoE is to formulate a plan on identifying the challenges and a mechanism to address them.

 

 

  1. OVERVIEW OF THE PORTFOLIO COMMITEE ON ENERGY DURING THE 4TH PARLIAMENT BY THE CHAIRPERSON – HON. SISA NJIKELANA 

 

The PCE – a Parliamentary Committee born during this term - has operated fairly well over the past 5 years notwithstanding that it conducted oversight on a literally new department – an attribute that may ascribed to a maturing Parliament. The DoE started operating independently 2010 whilst the PCE started meaningfully operating in the same year. The first Chairperson, (currently) Deputy Minister Elizabeth Thabethe, took office from 2009 to 2010 and was replaced by Hon Sisa Njikelana from late 2010 until the end of the term.

The Committee (and the Parliament as a whole) operated in a hostile global environment when it comes to oil and gas specifically and the international economy generally. This implied that whilst there were expectations on the DoE to deliver on its programmes and meet targets that was not to be easy due to such an unfavourable environment.

Compilation of this legacy report has been enabled by a number of policy instruments, guidelines and directives viz.:

It is due to such enabling instruments that the legacy report will be value to the 5th Parliament especially when it comes to planning and guiding the activities of the PCE for the next five years.

 

The character of activities of the PCE has been anchored around and was guided by the 5 core objectives of Parliament, the Strategic Plan of the PCE over and above its statutory mandate. Cancellation of meetings and plans was minimal and such has helped the PCE to attain it s goals. Cooperation amongst various members as well as between the Chairperson and the rest of the Committee were relatively positive.

Consistent participation of members has assisted in running the meetings fairly well and also optimising fulfilment of the objectives of the Committee. Scrutiny of DoE work was enhanced by the Budget Review Process given the additional tools that were introduced by the Money Bill Amendment Act. Furthermore the introduction of the practice of engaging the entities such as the Office of Auditor General, the Department of Performance Monitoring and Evaluation, the Finance and Fiscal Committee, the Audit and Risk Committee and conducting Quarterly Performance Reports has strengthened the PCE’s oversight capacity and effectiveness.

A number of innovative ways of advancing the work of the PCE were also introduced and such induced a positive response from the stakeholders and the public at large. Such activities were:

Overall challenges range from the struggle to maximise the impact of the PCE (including lack of assessment thereof) as well as the partial responsiveness of DoE to issues recommended by the PCE through Parliament. Multiple memberships of MP’s to various Parliamentary Committees has deprived the PCE of opportunities to maximise its performance. Staffing has unfortunately not been that stable viz.:

Utilisation of the Oversight and Accountability Model still has to be fully exploited given the potential depicted by the model. The late introduction of the Audit and Risk Committee by the Office of the Auditor General to participate in the Budget Review Process coupled with the intermittent invitation and involvement of the Audit and Risk Committee (due to lack of experience and low familiarity) means that this aspect has to be strengthened. Hence the impact of the Audit and Risk Committee, amongst a host of oversights tools could not be verified.

The PCE performed its duties and functions in keeping with its strategic plan although some of the tools and enablers in the strategic plan were not exploited.

The work that the Portfolio Committee on Energy has dutifully done, the experience it amassed, the legacy it is leaving behind will serve as valuable lessons and stepping stone for the PCE into the 5th Parliament.

 

4.     OPERATIONAL CONTEXT AND REPORT FRAMEWORK

 

4.1. National Policies and directives that have an impact on the energy sector

 

Below are the energy issues as identified in the National Development Plan (NDP), the Industrial Policy Action Plan (IPAP), the New Growth Path (NGP) and the Medium Term Strategic Framework (MTSF) (2009-2014) and the State of the Nation Addresses (SONA’s 2009-2014).

 


                The National Development Plan  (NDP)

The NDP sets the vision of the country for the next 20 years from 2011 to 2030. Amongst other things, the plan outlines measures that have to be taken to eradicate poverty, increase employment and reduce inequality by 2030. Regarding electricity the NDP envisages that by 2030 South Africa will have an adequate supply of electricity and liquid fuels to ensure that economic activity and welfare are not disrupted, and that at least 95 per cent of the population should have access to grid or off grid electricity. The plan proposes that gas and other renewable resources like wind, solar and hydro-electricity will be viable alternatives to coal and will supply at least 20 000MW of the additional 29 000MW of electricity needed by 2030. Other recommendations of the plan include diversifying power sources and ownership in the electricity sector, supporting cleaner coal technologies, and investing in human and physical capital in the 12 largest electricity distributors

 

With regards to energy carriers, the NDP proposes that the following be done on each of the following:

 

·         Coal: “Ensure domestic security of coal supply for existing power stations through industry compact, more comprehensive coal field planning and opening up the Waterberg for coal mining.”

·         Gas: “Enable exploratory drilling to identify economically recoverable coal seam and shale gas reserves, while environmental investigations will continue to ascertain whether sustainable exploitation of these resources is possible. If gas reserves are proven and environmental concerns alleviated, then development of these resources and gas-to-power projects should be fast -tracked. Incorporate a greater share of gas in the energy mix, both through importing liquefied natural gas and if reserves prove commercial, using shale gas. Develop infrastructure for the import of liquefied natural gas, mainly for power production, over the short to medium term. Constructing infrastructure to import liquefied natural gas and increasing exploration to find domestic gas feedstock (including investigating shale and coal bed methane reserves) to diversify the energy mix and reduce carbon emissions.”

·         Electricity: “Move to less carbon-intensive electricity production through procuring at least 20 000MW of renewable energy, increased hydro-imports from the region and increased demand-side measures, including solar water heating. Move Eskom's system operator, planning, power procurement, power purchasing and power contracting functions to the independent system and market operator and accelerate procurement of independent power producers. Ring-fence the electricity distribution businesses of the 12 largest municipalities (which account for percent of supply), resolve maintenance and refurbishment backlogs and develop a financing plan, alongside investment in human capital. Revise National Electrification Plan and ensure 90 percent grid access by 2030 (with balance met through off-grid technologies).”

·         Liquid fuels: “Upgrade fuel refineries to ensure they meet new fuel quality standards and insist on larger strategic fuel stocks to ensure security of supply. Continue to import refined fuels, ensuring that the growing deficit in petroleum products is met, and defer decision on a new refinery to

Moreover, in terms of the Region, the NDP indicates the following:

 

·         “The continent's massive infrastructure deficit, though debilitating, also presents great opportunities. Africa has the weakest infrastructure in the world – average electricity costs of US$0.18 per kilowatt-hour are about double those of other developing countries. The largest infrastructure gaps are in energy, with citizens in 30 of the 47 countries in sub-Saharan Africa facing regular power shortages and power interruptions. Power outages are responsible for a loss of between 1 percent and 6 percent of potential GDP every year.”

·         “Several of South Africa’s challenges can only be addressed through regional cooperation. While South Africa is a water-scarce country, several neighbouring countries have abundant supply. There are other areas in which complementary national endowments offer opportunities for mutually beneficial cooperation. For example, South Africa should invest in and help exploit the wide range of opportunities for low-carbon energy from hydroelectric and other clean energy sources in Southern Africa.

·         Renewable energy sources will become increasingly important. Sub-Saharan Africa is particularly well positioned to develop solar and hydro-energy, and to produce bio-fuels. The Grand Inga project could provide sufficient electricity for Africa and allow it to export energy through interconnecting links to southern Europe. Angola, Mozambique and Tanzania, among other countries, have the potential to produce ethanol profitably from sugar cane on land that is not used for food crops. Africa also has the potential to reduce emissions by protecting its forests.”

 

                The Industrial Policy Action Plan (IPAP)

 

From the IPAP, the following issues relating to the energy sector can be drawn – issues are quoted as per the IPAP document:

 

·         The IPAP also “offers the possibility of substantially increasing aggregate demand for the key inputs that will be required and, crucially, for the localisation of a wide range of manufactured inputs into the infrastructure build – particularly in the construction, metals, capital and rail transport equipment and renewable energy sectors.” Regarding the latter, under Public Procurement 2 the, Renewable Energy Independent Power Producer Procurement Programme (REIPPP) is mentioned and it is indicated that “Forty-seven bids awarded, with minimum levels of local content ranging from 25% to 45%; set to rise to maximum 65% in solar, wind and Concentrated Solar Power (CSP) and a local content hotline and e-mail address have been established both at the Department of Trade and Industry (DTI) and the South African Bureau  of Standard (SABS) to deal with non-compliance on local content”.

·         Furthermore, under Industrial Financing 1, “R5 billion private ‘green bond’ (must be) concluded with the Public Investment Corporation to facilitate funding for businesses looking to invest in clean energy infrastructure developments”.

·         The IPAP recognised Biofuels, green industries, renewable energy, energy efficiency and Nuclear Energy as some key areas to focus on and has developed key action programmes to accelerate development in these sectors.

·         For the renewable energy industry, SA needs to “revise the minimum local content requirements for the REIPPP and small-scale programmes” and increase the local content threshold. “To identify and quantify energy-efficiency products, services and components procured by central, provincial and local government and State Owned Companies - SOCs (such as public space lighting, street lighting, traffic lights and lights in Government buildings) and to designate these items for local production as appropriate” was identified as the intervention for energy efficiency.

 

                The New Growth Path (NGP)

 

This is South Africa’s vision to place jobs at the centre of the economy, with the aim of creating 5 million new jobs by 2020. The focus is on economic growth, rebuilding the productive sectors of the economy, infrastructure development and rural development. In the Green Economy Accord (which forms part of the NGP), government has committed to the following:

 

Commitment One: Rollout of Solar Water Heaters: In this commitment; Government wishes to increase the rollout to one million units by 2014, improve the localization of components, secure support from the insurance industry for replacement of units, secure guarantees on installed units, promote the marketing of solar-water heating systems and further promote uniform technical and performance standards for SWH.

 

Commitment Two:  Invest in the Green Economy: The Industrial Development Corporation (IDC) will set aside a capital allocation of R22 billion for green projects over the next five years and a further R3 billion will be made available for manufacturing of green products and components. Organised labour committed to establish social enterprises and investment vehicles that will create jobs and support the goals of the green economy, whereas business agreed to market opportunities within the investor communities.

 

Commitment Three: Rollout of Renewable Energy: The government has committed to the procurement of 3725MW of renewable energy by 2016, being the first step in meeting the Integrated Resource Plan (IRP) goals. Through this also achieve a 75% localization of component manufacturing; promote technology development and strengthen skills development.

 

Commitment Four: Energy Efficiency: In this, develop a roadmap for improved energy efficiency (in line with the National Energy Efficiency Strategy), develop internal energy efficiency targets, develop skills and ensure behavioural changes within and outside the workplace. Set benchmarks and focus on energy efficiency awareness campaigns.

 

Commitment Five: Waste Recycling, Re-Use and Recovery: Government noted that although it aims to reduce waste, especially from industries, waste can be used as a feedstock especially for the generation of energy.

 

Commitment Six: Biofuels: With the aim of lowering carbon emissions, government has published mandatory blending regulations in petrol (2%) and diesel (5%). Hence there is a commitment from government to provide a supportive regulatory environment to facilitate the development of a local biofuels industry. A Biofuels Regulatory Framework was published in January 2014 by the DoE for public comments. Monitoring progress on this is essential for the 5th Parliament.

 

Commitment Seven: Clean coal Initiatives: Government has established a Carbon Sequestration Leadership Forum to develop clean coal technologies and this includes underground coal gasification initiative at Eskom and the Carbon Capture and Storage Initiative under South African National Energy Development Institute (SANEDI).

 

Commitment Eight: Retrofitting: Apart from the retrofitting of incandescent lighting, Eskom will consider new technologies that can improve the energy efficiency of its existing coal-fired power stations and commercial buildings will benefit from new heating and insulation systems.

 

Commitment Nine: Reducing Carbon-Emission on our roads: Here government committed to invest in mass transport systems; this includes road and rail and ensures greater usage thereof. Government further committed to being the first adaptors with respect to purchase and use of domestically manufactured electric vehicles.

 

Commitment Ten: Electrification of Poor Communities and Reduction of fossil fuel Open fire cooking and heating: Government committed to accelerate programmes to increase access to electricity and appropriate modern thermal carriers like Liquid Petroleum Gas (LPG) for cooking and heating. Also recognised was the need to clean cooking stoves.

 

Commitment Eleven: Economic Development in the Green Economy: Promotion of localization, Youth Development, Cooperation and Skills Development: The green economy will provide significant opportunities to create jobs and at least 80% of new employees in the manufacturing and installation of solar water heating systems will be young people. The skills requirement will need to be elevated as a priority in the National Skills Framework.

 

Commitment Twelve: Cooperation around the United Nations COP17 and its follow up Government will work with labour, business and community organisations to communicate the message of partnership on the green economy as set out in the accord.

 

                Medium Term Strategic Framework (2009-2014)

 

The energy related issues noted in the Medium Term Strategic Framework (MTSF) include:

 

·         It is indicated that one of the critical activities that can drive faster economic recovery is “large investment projects of the private sector especially projects with high labour-absorbing impact, including security of fuel supply, environment-friendly energy and other such products and services as well as supplier industries for infrastructure projects”

·         It is further noted that to “to ensure longer-run growth, government must refine and scale up implementation of its Industrial Action Plan to support broad-based industrialisation including more advanced manufacturing, as well as encouraging cleaner, lower-energy technologies and green jobs.”

·         Research and Development into alternative energy technologies were also identified as a measure to put in place to ensure industrial competitiveness and sustained growth.

·         It is noted in the framework that the infrastructure programme will include, among others; “Continuing with the programme to build, revamp and maintain electricity infrastructure, including generation, distribution and reticulation to ensure sufficiency and sustainability of supply and development of alternative energy sources.

·         Continuing to expand pipelines for the supply of liquid fuel to inland provinces and the country at large and improving logistics infrastructure (road and particularly rail) for the transportation of goods and services including agrologistics for farming and agricultural products – this will include more systematic efforts to encourage movement from road to rail.”

·         Further, in developing physical infrastructure in rural areas; Government will invest in, among others, in energy. This is also a key area in improving service delivery to ensure quality of life.

·         It is also noted that “the main objective of government is to encourage sustainable resource management and use by focusing on various interventions including the diversification of the energy mix in pursuance of renewable energy alternatives and promotion of energy efficiency

·         Furthermore, it is stated that, “efforts to meet the energy efficiency target of 12% by 2015 and renewable energy target of 10 000 GWh by 2013, will be enhanced by creating an enabling environment for renewable energy, through for example implementing the renewable energy feed-in tariff and building the local renewable energy manufacturing capacity”

 


        Medium Term Budget Policy Statements (MTBPS)

 

The following is noted from the MTBPS in terms of energy (from 2009):

 

In 2009 the question was being asked, how do we address the country’s future energy needs and how do we reduce the county’s future carbon emissions? In response to the question, the following interventions were highlighted (from 2009 – 2013):

·         To boost industrial development, assist enterprises and accelerate job creation, the Minister noted that “the MTBPS proposes a competiveness support package of R25 billion over the next six years to boost industrial development” with “continuing investment in energy, water, transport and communications and infrastructure” and “alignment of trade, investment and energy policies to support the transition to a green economy, including private sector participation in our renewable energy production programme.”

·         SA involvement in the 17th Conference of the Parties to “seek to make progress in a most difficult global coordination challenge: how to invest in a clean energy future, and how to share the costs of this transition.”

 

                State of the Nation Addresses (SONA’s 2009 -2014)

 

·         In 2009 the President highlighted the right of rural people to basic services like electricity and that we need to improve our energy efficiency and reliance on renewable energy.

·         In 2010 it was announced the establishment of the Inter-Ministerial Committee on Energy to develop the 20 year Integrated Resource Plan. The participation of the independent power producers was also mentioned and the establishment of ISMO, separate from Eskom. The President also highlighted that the Municipalities must improve the provision of basic services including electricity. More importantly, he mentioned that the poor must be protected from rising electricity prices.

·         In the 2011 SONA, the President acknowledged the delivery of basic services (including electricity) to the people of the country but indicated that there are many still waiting. In this regard he highlighted the infrastructure development programme to enable greater access to basic services. The Eskom build programme was once again highlighted as the President noted that energy security is critical for economic development and job creation. He also indicated that SA needs ensure we save electricity so we do not resort to load shedding again.

·         The President noted the ongoing concern about high electricity cost from business and communities in 2012 and indicated that Eskom was asked to “seek options on how the price increase requirement may be reduced over the next few years, in support of economic growth and job creation and give him proposals for consideration.” The President in 2102 also highlighted the Eskom build programme, load shedding and that 220 000 solar water geysers were installed to date. He also mentioned the NEPAD Presidential Infrastructure Championing Initiative which includes various inter-related projects including energy.

·         In the 2013 SONA the President highlighted some successes in the energy sector including the roll out of transmission infrastructure, the renewable energy programme, the roll out of the 315 000 solar water heaters, the fact that close to 200 000 households have been connected to the national electricity grid in 2012 and that 85% (or 12.1. million) of households have access to electricity. The President noted the slowdown of GDP growth which could negatively affect the economy and hence the envisaged target of creating 11 million jobs by 2030. But the President also highlighted the rapid rate of urbanization taking place in SA.

·         In the 2014 SONA, the President noted that this SONA was a “report of the past five years in particular and over the past 20 years in general.” The President indicated in this SONA that the programme of action for this financial year will be presented by the new government after the elections. The President also noted that “over the past 20 years, remarkable achievements have been made in increasing access to services such as water, sanitation and electricity” in terms of provision of basic services to the people of South Africa. The President noted that there is a plan to create 6 million jobs and apart from mining, “we had identified five other job drivers in 2009. These are tourism, agriculture, the green economy, infrastructure development and manufacturing.” All of these impact the energy needs and dynamics of South Africa. The President noted that “nearly 500 informal settlements have been replaced with quality housing and basic services over the past five years;’ but noted that some communities still do not have basic services especially in informal settlements and rural areas. He indicated that “we are therefore working with all spheres of government to ensure the provision of these services, especially in the 23 municipalities with the greatest number of backlogs.” This will have a direct bearing on energy.

 

4.2. Brief profile of the Department of Energy (DoE)

 

On 10 May 2009 President Zuma announced his new Cabinet and the appointment of, amongst others, the Minister of Energy in terms of Chapter 5 (The President and National Executive), Section 91(2) of the Constitution of the Republic of South Africa, 1996 (the Constitution). The new portfolios of some of the Ministers necessitated a re-organisation, renaming and establishment of new departments. Subsequent to the above announcement, the DoE was established following the split of the Department of Minerals and Energy, which resulted in two independent Departments. The President, in terms of Chapter 5 (The President and National Executive), Section 97, of the Constitution, 1996, transferred the administration and powers and functions entrusted by specified legislation to, amongst others, the Minister of Energy by Proclamation No. 44, 2009.

 

The aim of the DoE is to formulate energy policies, regulator frameworks and legislation, and oversee their implementation to ensure energy security, promotion of environmentally-friendly energy carriers and access to affordable and reliable energy for all South Africans. The mandate of the Department is to ensure secure and sustainable provision of energy for socio-economic development.

 

4.2.1. State Owned Entities/State Owned Companies within the DoE

 

The Minister of Energy is responsible for overseeing the following five State-Owned Entities (and their subsidiaries), which are either classified as Schedule 2 or 3A institutions in terms of the Public Finance Management Act, 1999 (Act 1 of 1999), as amended (PFMA):

 

4.2.1.1. Regulators

 

 

 

4.2.1.2. Research and Development

 

 

4.1.1.3. Energy Security

 

·         South African Nuclear Energy Corporation (NECSA) – NECSA’s functions, as outlined in section 13 of the National Energy Act, are to: - undertake and promote research on nuclear energy, radiation sciences and technology; - process source, special nuclear and restricted material including uranium enrichment; and - collaborate with other entities

·         The Central Energy Fund (CEF) Group of Companies (SOC) Ltd - CEF (SOC) Ltd is involved in the search for appropriate energy solutions to meet the future energy needs of South Africa, the Southern African Development Community and the sub-Saharan African region, including oil, gas, electrical power, solar energy, low-smoke fuels, biomass, wind and renewable energy sources. CEF also manages the operation and development of the oil and gas assets of the South African Government. CEF is also mandated to manage the Equalisation Fund, which collects levies from the retail sales of petroleum products to eliminate fluctuations in the retail price of liquid fuel and to give tariff protection to the synthetic fuel industry.

 

 

·         Electricity Distribution Industry (EDI) Holdings – EDI was a company wholly owned by the South African Government, was establishment in March 2003, through the then Department of Minerals and Energy, to facilitate the process of restructuring the electricity distribution industry in South Africa. As at the end of the 2012/13 financial year, all transactions towards the closing down of the company as directed by Cabinet on 08 December 2010 were finalized. The Department, in the 2012/13 year was awaiting the close-out audit report from the Auditor-General and the Board.

 


4.2.2. Legislation

 

4.2.2.1. Legislation that directly mandates the DoE

 

·              The National Energy Act, 2008 (Act No. 34 of 2008)

·              The Petroleum Products Act, 1977 (Act No. 120 of 1977), as amended

·         The Electricity Regulation Act, 2006 (Act No. 4 of 2006), as amended

·         The Central Energy Fund Act, 1977 (Act No. 38 of 1977), as amended;

·         The Nuclear Energy Act, 1999 (Act No. 46 of 1999);

·         The National Nuclear Regulator Act, 1999 (Act No. 47 of 1999);

·         The National Radioactive Waste Disposal Institute Act, 2008 (Act No. 53 of 2008);

·         The Petroleum Pipelines Act, 2003 (Act No. 60 of 2003);

·         The Petroleum Pipelines Levies Act, 2004 (Act No. 28 of 2004);

·         The Gas Act, 2001 (Act No. 48 of 2001);

·         The Gas Regulator Levies Act, 2002 (Act No. 75 of 2002);

·         The National Energy Regulator Act, 2004 (Act No. 40 of 2004);

·         The Abolition of the National Energy Council Act, 1991 (Act 95 of 1991);

·         The Liquid Fuel And Oil Act Repeal Act, 1993 (Act 20 of 1993); and

·         The Coal Act Repeal Act, 1991 (Act 124 of 1991).

 

4.2.2.2. Non-core legislation that also impacts on the DoE

 

·         The National Environmental Management Act, 1999 (Act No. 107 of 1999),

·         The Mineral and Petroleum Resources Development Act, 2002 (Act No. 28 of 2002),

·         The Disaster Management Act, 2002, (Act No. 57 of 2002),

·         The Hazardous Substances Act, 1973, (Act No. 16 of 1973),

·         The National Ports Act, 2005 (Act No. 12 of 2005

 

4.2.3. The DoE’s Strategic Orientated Outcomes Goals are as follows:

 

·         Regulation and Competition: Improved energy regulation and competition.

·         Infrastructure: An efficient, competitive and responsive energy infrastructure network.

·         Environmental Assets: Environmental assets and natural resources protected and continually enhanced by cleaner energy technologies.

·         Climate Change: Mitigation against and adaptation to, the impacts of climate change.

·         Corporate Governance: Good corporate governance for effective and efficient service delivery.

 

Goal

Government outcome

Goal statement

1. Universal Access and Transformation

 

Outcome 2 – A long and healthy life for all South Africans; and

Outcome 8 – Sustainable human settlement and improved quality of household life.

Efficient and diverse energy mix for universal access within a transformed energy sector.

 

2. Security of Supply

 

 

 

 

Outcome 4 – Decent employment through

inclusive economic growth.

Energy supply is secure and demand is well managed.

3. Regulation and Competition Improved energy regulation and competition.

 

Improved energy regulation and competition.

4. Infrastructure

 

Outcome 6 – efficient, competitive and responsive economic infrastructure network.

An efficient, competitive and responsive energy infrastructure network.

 

5. Environmental Assets

 

 

 

Outcome 10 – Environmental assets and natural resources that are well protected and continually enhanced.

.

 

Environmental assets and natural resources protected and continually enhanced by cleaner energy technologies.

 

6. Climate Change Mitigation against, and adaptation to, the impacts of climate change

Mitigation against, and adaptation to, the impacts of climate change.

7. Corporate Governance

 

Outcome 12 - An efficient, effective and

development oriented public service and an empowered, fair and inclusive citizenship.

Good corporate governance for effective and efficient service delivery.

 

 

 

 

 

4.2.4. Programmes of the Department of Energy

 

The Department has six programme areas: Administration; Energy Policy and Planning; Petroleum and Petroleum Products Regulation; Electrification and Energy Programmes and Project Management, Nuclear Energy and Clean Energy.

 

4.2.4.1. Programme 1:  Administration

The purpose of the programme is to provide corporate, executive, financial management and accounting, information and communication technology, supply chain, asset management support to the Department, to ensure good corporate governance and compliance by Department and/or the Energy Sector.

 

4.4.4.2. Programme 2: Energy Policy and Planning

The purpose of the programme is to ensure evidence based planning, policy setting  and investment decisions in the energy sector to improve the security of energy supply, regulation and competition.

 

4.4.4.3. Programme 3: Petroleum and Petroleum Products Regulation

The purpose of the programme is to manage the regulation of petroleum and petroleum products to ensure the optimum and orderly functioning of the petroleum industry to achieve government’s development goals.

 

4.4.4.4. Programme 4: Electrification and Energy Programme and Project Management

The purpose of the programme to manage, coordinate and monitor programmes and projects focused on access to energy.

 

4.4.4.5. Programme 5: Nuclear Energy

The purpose of the programme is to manage the South African nuclear energy industry and control nuclear materials in terms of international obligations, and nuclear energy legislation and policies to ensure the peaceful use of nuclear energy.

 

4.4.4.6. Programme 6: Clean Energy

 

The purpose of the programme is to manage and facilitate the development and implementation of clean and renewable energy initiatives, as well as energy efficiency and demand side management initiatives.

 

 

 

4.2.5. Department of Energy - Total Budget Allocations since 2010

 

Table 1: DoE Budget Allocations

R million

2010/11

2011/12

2012/13

2013/14

2014/15

Administration

121.6

192.7

216.8

212.8

244.1

Energy Policy & Planning

1607.2

1 541.9

1 545.3

45.0

52.6

Petroleum and Petroleum Products Regulation

24.1

27.2

44.4

69.3

82.7

Electrification & Energy Programme and Project Management

2 772.1

3 274.5

3 116.0

3 946.2

4 199.2

Nuclear Energy

612.3

642.3

643.2

730.8

850.5

Clean Energy

368.0

495.7

1 093.3

1 483.1

1 986.5

Total

5 505.4

6 174.3

6 659.0

6 487.2

7 415.6

Source: National Treasury (2014). Estimates of National Budget (pg 666)

 

 

5.     REFLECTION OF THE PORTFOLIO COMMITTEE ON ENERGY PERFORMANCE (PCE)

 

Vision of the Portfolio Committee on Energy

The vision of the PCE is defined as:

To become a vibrant and effective Portfolio Committee that legislates and conducts oversight over the implementation of   departmental programmes and related entities to improve service delivery, achieve universal access to electricity and a transformed energy sector.

 

 

 


5.1. Mandate and functions of the Portfolio Committee on Energy

 

The Portfolio Committee on Energy is established by the rules of the National Assembly as enshrined in Section 57(2) (a) of the Constitution of the Republic of South Africa, Act 108 of 1996. The Committee is therefore an extension of the National Assembly and derives its mandate from Parliament. 

 

 

5.1.1. The Portfolio Committee on Energy, as a Committee of the National Assembly, has as its mandate, in respect to the DoE, to:

 

·         Consider, amend, approve or reject legislation;

·         Consider and approve budgets and monitor expenditure of  department and entities;

·         Consider progress reports from the line function department,  and entities on their respective mandates 

·         Ensure that all appropriate executive organs of state are held accountable for their actions; and Conduct oversight of the national executive authority and of any organ of state

 

5.1.2. The mandate of the Committee fulfils the following functions (derived from Parliament’s strategic objectives):

·         Pass legislation.

·         Scrutinise and oversee executive action

·         Facilitate public participation and involvement in the legislative and other processes.

·         Participate in, promote and oversee co-operative government.

·         Engage in, participate and oversee international relations.

 

Furthermore the Portfolio Committee on Energy fulfils its mandate by discharging its oversight role over the Department of Energy and its entities.  The Committee also conducts oversight visits and hold public hearings to ensure public participation and corporative governance as enshrined in the Constitution. 

 

 

 

 

 

 

5.2. Method of work of the committee

 

5.2.1. Committee category

 

Committee meetings were predominantly scheduled on a Tuesday, as the committee was in the A-group (committees are grouped into A, B, C and D – to avoid clashes). Being part of the Group A, meant that the committee could meet on a Tuesday morning (09:00 -13:00) and on a Thursday afternoon and Friday  if there are no plenaries (approval for the meetings on a Thursday and Friday need to be sought from the Office of the House Chairperson: Committees)

 

During the committee weeks, the Portfolio Committee on Energy were allowed to meet on a Tuesday afternoon (14:00 – 17:00) and Wednesday morning (09:00 – 13:00). Meetings could also be scheduled on a Thursday and/or Friday (with the approval of the Office of the House Chairperson)

 

5.2.2. Processing legislation

 

When processing legislation, where needed the committee meetings were scheduled on Tuesday, Wednesday, Thursday and Friday (with the approval of the Office of the House Chairperson). This also depended on the amount of work which had to be done during the deliberation stages of the Bill.

 

Also, when processing legislation the committee conducted placed advertisements in national newspapers and regional newspapers calling for written submissions (stakeholders have to indicate request for oral submission. Subsequent to the “call for written submissions” the PCE will schedule public hearings, where the different stakeholders can make oral presentations on their written submissions to the committee. Besides placing the advert the PCE will In certain cases also invite stakeholders to make a submission (written and verbal).

 

In certain circumstances the committee will conduct workshops on the legislation, to enhance its understanding thereof (this is very important as some of the legislation in the energy sector is very technical and complex.

 

5.2.3. Oversight visits

 

Oversight visits to various projects and programmes are three pronged. The visits will be scheduled as follows:

 

·         Visit the targeted project

·         Meet the service provider/s

·         Meet the local community

 

PS: Oversight work was done directly on the DoE provincial/regional offices as well as the SOEs. Some of the oversight visits integrated study tour aspects as well.

 

5.2.4. Study tours

 

Study tours have been conducted by either the committee as a whole, a delegation of PCE MPs or individuals both inside and outside.

 

5.2.5. Media Networking Sessions

 

The main purpose for the media networking session is to build and foster strong relations with journalists that report about issues affecting Parliament. This event was usually scheduled after hours on a Thursday evening (18:00 – 20:00). During the period under review the committee scheduled 2 media networking sessions, one (1) at the parliamentary precincts and one (1) outside.

 

5.2.6. Expert testimonies – inviting experts/specialists

 

The Portfolio Committee on Energy would also invite experts/specialists in a specific area (depending on what the Portfolio Committee on Energy is dealing with) to attend the meetings and/or accompany the delegation on an oversight visit. The aim of this is to get that expert/specialist view on the area under discussion.

 

Expert testimonies by various experts have been presented by the PCE as a new practice and such were immensely beneficial to members of the PCE. In most cases the PCE has made use of the various tertiary institutions, who does work in the energy sector to provide this service. The aim is also to foster relations with the various tertiary institutions (see list below).

 

 


5.2.7. Energy Stakeholder Meetings

 

The Portfolio Committee on Energy further scheduled Energy Stakeholder Meetings (ESMs). The aim of these Energy Stakeholder Meetings is to create a platform for public discourse in the energy sector by facilitating structured discussions on various topics on energy issues. These meetings are usually scheduled on a specific Thursday afternoon (at 5pm).

 

The format of this forum is that the Portfolio Committee on Energy will invite 3-4 departments/entities/private companies to present on a specific topic, where after the Chairperson will open up the floor to all present for questions, clarity seeking and comments. A report is compiled for consideration and adoption of these Energy Stakeholder Meetings. These Energy Stakeholder Meetings are usually well attended, depending on the topic (around 70 - 80 people on average). For the period under review three (4) ESMs was conducted at Parliament and two (2) outside.

 

5.2.8. Roundtable discussions

 

The roundtable discussions are more or less like the Energy Stakeholder Meetings, but the groups invited are smaller (20 -30 people). Discussions are also more informal.

 

5.2.9. Extra-Parliamentary Meetings

 

The PCE held at least one meeting outside Parliament annually for the past 3 years. Such is according to directives from the Speaker’s Office. 

5.2.10. Public hearings – excluding legislation

In certain circumstances the committee will conduct public hearings on a topical issue, where some of the items included:

 

 

 

5.2.11. Mailing list  

 

The committee has mailing list, consisting of about 500 people (their e-mails). This mailing list covers most of the respective sectors within the energy sphere (liquid fuels, electricity, renewable energy etc).

 

The mailing list receives the various notices and invites of the Portfolio Committee on Energy. Portfolio Committee on Energy meetings are well attended and stakeholders are informed of the activities undertaken by the Portfolio Committee on Energy.

 

5.3. Committee focus areas during the fourth term

 

During the 4th Parliament, the PCE focused on some keys areas of activity.

 

·         Oversight over the DoE and the SOE’s activities and programmes. This included financial as well as operational oversight. The PCE also assessed the progress made on Millennium Development Goals (MDGs), Government Outcomes and the Strategic Outcomes-Orientated Goals (SOGs) and the Strategic Integrated Projects (SIPs), including directives from SONA on energy issues.

·         The PCE also focused on the Energy Policy of the DoE, focusing on the ISMO Bill, outstanding legislation and policy documentation with regard to energy planning in general e.g. IRP and IEP and sector specific e.g. Electricity and Hydrocarbon policies.

·         The PCE assessed Petroleum Regulation and looked at petroleum licensing, pricing and compliance to policies e.g. liquid fuels charter.

·         The PCE also focused on Electrification programmes including INEP, REIPPP, the industry transformation, infrastructure and community uplift programmes including IEC’s.

·         Another area assessed regularly was nuclear energy including the envisaged 9600MW nuclear roll out programme, nuclear safety, waste management including the National Radioactive Waste Disposal Institute and nuclear policy.

·         The PCE also focused on clean energy including energy efficiency, renewable energy and climate change issues.

 

 

 

 


5.4. Reflection on the PCE performance as guided by its strategic objectives

 

The Portfolio Committee on Energy met these objectives in the following way:

 

I.        Promote the design and implementation of broad based sector or industry empowerment programmes with clearly defined targets based on agreements between stakeholders. In this regard the Portfolio Committee on Energy held the following engagements

 

·         In 2010, the Portfolio Committee on Energy held public hearings on the Liquid Fuels Charter and energy industry transformation and this was followed with an engagement with the Deputy Minister of Trade & Industry, PetroSA, National Energy Regulator of South Africa (NERSA), Transnet and the DoE.

·          In terms of the Liquid Fuels Charter, the Portfolio Committee on Energy conducted oversight on the Liquid Fuels Charter audit outcomes in 2012 to gain insights on progress and challenges identified.

·         The Portfolio Committee on Energy also, in November 2012, held an Energy Stakeholder Meeting on Transformation in Petroleum Industry.

·         Further, the Portfolio Committee on Energy conducted oversight on the downstream liquid fuels sector with input by wholesalers, storage sub-sectors and retailers.

·         The Portfolio Committee on Energy held an Energy Stakeholder Meeting on the upstream oil and gas industry early in 2014 where industry players were given the opportunity to air their views and one of the key outcomes of this Energy Stakeholder Meeting was that there needs to be clear policy directives from government. Such included issues regarding BBBEE.

·         In terms of Biofuels, the Portfolio Committee on Energy received an Industrial Strategy update on Biofuels in 2013. The PCE also requested that the DoE brief the Committee on the 200 odd small biofuel producers and how the DoE is managing this. Biofuels was a regular topic of discussion, with the DoE whenever they presented their annual or strategic plans to the Portfolio Committee on Energy.

·         In terms of electricity, there were engagements that the Portfolio Committee on Energy initiated. The Portfolio Committee on Energy assessed the Industrial Development Corporation (IDC) implementation of New Growth Path and Industrial Policy Action Plan (IPAP2) with special reference to the green economy and renewable energy. This was followed up by a Panel discussion for Independent Power Producers on Renewable Energy Procurement (Window 1).

·         In terms of the Renewable Energy programme, the Africa Institute of SA & Standard Bank discussed Investment Flows for Change with the Portfolio Committee on Energy also during this period and the Portfolio Committee on Energy held a Meeting of stakeholders in the renewable energy sector, entitled Exploring solutions to the challenges of financing and certification of locally produced renewable energy products. The Portfolio Committee on Energy ensured it received regular updates on the Renewable Energy Independent Power Producer Procurement Programme (REIPPP) by the DoE. Finally, it appears as if the next major Independent Power Producer procurement drive by the DoE will be in the area of co-generation and hence in 2013, the Portfolio Committee on Energy held Cogeneration public hearings and this was followed up with a round table discussion early 2014 where issues and challenges were trashed out with all stakeholders present. One of the key recommendations that came out of the round table was that there is a need for a national conference where issues are carefully unpacked and dealt with. The PCE did conduct oversight on skills and technology transfer and BBBEE procurement.

 

II.        Assess the impact of the Energy Efficiency Strategy of 2005.

 

·         The Portfolio Committee on Energy on a regular basis conducted oversight on energy efficiency with regular briefings by the DoE. It further conducted oversight on such projects in SA, including green buildings and industrial energy efficiency projects. As part of this the Portfolio Committee on Energy reviewed a Committee report on  the Workshop on Renewable Energy Policies for Sustainable African Development in Ghana. Some other interactions were as follows; in 2010, the Portfolio Committee on Energy was briefed by the DoE on International Renewable Energy Agency and soon thereafter on the Memorandum of South Africa's membership to International Renewable Energy Agency (IRENA) & Report on International Climate Change and Energy Excess Hearings. This was followed up in 2011 where the Portfolio Committee on Energy was briefed by South South North Africa, Green Building Council of South Africa, PEER Africa, and Council for Built Environment & Council for Scientific & Industrial Research on Energy Efficiency.

·         The Portfolio Committee on Energy also regularly was briefed on the solar water heater programme by the DoE and conducted oversight visits to such sights, engaging with the communities on issues and challenges. This included visits to the South African Bureau of Standards on energy efficient standards and the assessment and testing of energy efficient equipment, and Council for Scientific and Industrial Research on energy efficiency programmes in late 2012.

·         The Portfolio Committee on Energy was also regularly briefed on Energy Efficiency by the DoE during the regular quarterly report updates and annually during their presentations of their annual reports and five year strategic plans.

 

III.        Monitor restructuring of the fragmented electricity distribution industry.

 

·         With regard to distribution, the Portfolio Committee on Energy conducted oversight on this topic with briefings by the DoE and other players including South African Local Government Association and Municipal Infrastructure Support Agency. The Portfolio Committee on Energy found key issues to be addressed included (a) financial constraints at Municipal level, (b) lack of appropriate skills, especially at the smaller municipalities and (c) lack of maintenance in the case of some Municipalities. In terms of oversight, in 2010, the DoE briefed the Portfolio Committee on Energy on the Electricity Distribution Industry & Regional Electricity Distributors on the Electricity Distribution Industry Holdings. This was followed up by briefings by the Department of Energy & South African Local Government Association (SALGA) on Electricity Distribution Industry Goals in 2011 and this topic was again visited by the Portfolio Committee on Energy with the DoE in early 2012 with four days of public hearings being held in mid of 2012.

·         The Portfolio Committee on Energy also regularly conducted oversight on the pilot programme ADAM and received input by Department of Energy, South African Local Government Association, Municipal Infrastructure Support Agency & Financial and Fiscal Commission in 2013; however independent of these dedicated meetings, there were a lot of discussions and guidance from the Portfolio Committee on Energy, with the DoE on the topic of distribution in general.

·         The Portfolio Committee on Energy was also regularly briefed on the electricity distribution industry by the DoE during the regular quarterly report updates and annually during their presentations of their annual reports and five year strategic plans.

 

IV.        Achieving universal access to electricity

 

·         The Integrated National Electrification Programme (INEP) was one of the key programmes the Portfolio Committee on Energy exercised oversight over. During this Parliament, the percentage households that are electrified in SA went up from 74.9% in 2010 to 85% in 2013, with over 900 000 households being electrified during this Parliament. The Portfolio Committee on Energy regularly conducted oversight on this topic and also conducted oversight visits, interrogating the topic and guiding the DoE where necessary.

·         The Portfolio Committee on Energy was also regularly briefed on the Integrated National Electrification Programme by the DoE during the regular quarterly report updates and annually during their presentations of their annual reports and five year strategic plans.

 

V.        Monitor promotion and progress on the utilization of Liquefied Petroleum Gas as well as transforming the sector.

 

·         The Portfolio Committee on Energy engaged the DoE on this topic numerous times in the 4th Parliament. They also looked at this topic in numerous ways to ensure a clear understanding of the fundamentals at play in the Liquefied Petroleum Gas industry. In 2010 the Portfolio Committee on Energy looked at Liquefied Petroleum Gas regulation with the DoE. This was followed up with a progress meeting with the DoE on Implementation of the Liquefied Petroleum Gas (LPG) Regulations and on the Two Pilot Projects implemented in Atteridgeville & Tweefontein. Safety issues were also interrogated by the Portfolio Committee on Energy during a meeting with the Liquefied Petroleum Gas Safety Association. In 2012, the DoE also briefed the Portfolio Committee on Energy on Liquefied Petroleum Gas Options for Expansion’

·         This topic was also interrogated by the Portfolio Committee on Energy with the DoE and South African Local Government Association as part of the Free Basic Alternative Energy discussions. The Portfolio Committee on Energy also conducted oversight on equipment used, and availability of equipment and Liquefied Petroleum Gas, especially for the indigent communities and further, distribution infrastructure in particular and entire Liquefied Petroleum Gas value chain in general, e.g. during the oversight visit to informal settlements in Stellenbosch in July 2013

·         The Portfolio Committee on Energy further conducted oversight on indigent households using Liquefied Petroleum Gas for cooking purposes and further visited gas distribution companies to gain some insights into the issues related to gas distribution in SA, e.g. during the oversight visit to industrial sites in August 2013.

·         The Portfolio Committee on Energy was also regularly briefed on the above aspects related to Liquefied Petroleum Gas by the DoE during the regular quarterly report updates and annually during their presentations of their annual reports and five year strategic plans.

 

VI.        Assessing the extent of investment and progress on the utilization of clean energy sources

 

·         The Portfolio Committee on Energy, for the duration of the 4th Parliament, monitored the solar water heater programme carefully. The Portfolio Committee on Energy was also regularly briefed on the utilization of clean energy sources including the solar water heater programme by the DoE, during the regular quarterly report updates and annually during their presentations of their annual reports and five year strategic plans

·         The PCE conducted oversight on installations and programmes. This was during oversight visits to Khayalitsha in 2010, Ivory Park in 2014 and SABS (in terms of quality) in 2012. Comments and concerns were communicated to the DoE for further action.

·         The Portfolio Committee on Energy conducted oversight on the various aspects of the Renewable Energy Independent Power Procurement Programme and received regular updates on this programme from the DoE.

·         The Portfolio Committee on Energy also was briefed on the International Renewable Energy Agency by the DoE in 2010; assessed the National Climate Change Response Green Paper and Conference of the Parties (COP) 17 in 2011.

·         The Portfolio Committee on Energy also engaged with the Industrial Development Corporation (IDC) on implementation of New Growth Path and Industrial Policy Action Plan (IPAP2) with special reference to the green economy and renewable energy later that year. The Committee was also briefed on the Renewable Energy Policies for Sustainable African Development in Ghana; and at the South Africa Renewable Energy Initiative with SANEDI in 2012. In August 2012, the Portfolio Committee on Energy also held a meeting of stakeholders in the renewable energy sector; Exploring solutions to the challenges of financing and certification of locally produced renewable energy products.

·         The Portfolio Committee on Energy also conducted oversight visits on the renewable energy programme by visiting various wind and solar projects in SA, e.g. Drling Wind Farm in 2011 and a solar project in 2014 in Bloemfontein

·         The Portfolio Committee on Energy also assessed the biofuels industry of South Africa and received numerous updates from the DoE on the Biofuels strategy.

·         The Portfolio Committee on Energy further assessed co-generation and tri-generation and further not only received updates from the DoE, but further held public hearing in 2013 on co-generation and followed this up with a round table in early 2014 where the interested and affected parties were given the opportunity to raise comments and concerns on this topic. This information was relayed to the DoE as they were also present at these engagements. The Portfolio Committee on Energy also visited companies that co-generate power from these technologies e.g. ABSA and MTN.

·         The Portfolio Committee on Energy was also briefed on the Electric Vehicle Research Project by Eskom and Nissan in 2013.

 

VII.        Facilitate the formulation and review of the Energy policies

 

·         The Liquid Fuels Charter of the DoE. Here the Portfolio Committee on Energy assessed this policy with the DoE on a regular basis over the 4th Parliament. This includes the outcome of the Audit on the Charter. To ensure the Portfolio Committee on Energy had a clear picture in its guidance to the DoE; the Portfolio Committee on Energy further held public hearings and an energy stakeholder meeting where both issues related to the upstream and downstream sector were assessed with the relevant stakeholders. The Portfolio Committee on Energy also assessed related policies e.g. the liquid fuels infrastructure roadmap, the basic fuel price, the biofuels strategy and in some cases actual implementation e.g. the New Multipurpose Product Pipeline (for the transport of liquid fuels). The above topics were well interrogated with multiple meetings over the 4th Parliament.

·         The Portfolio Committee on Energy engaged with NERSA more than once a year on pricing related issues. The PCE conducted oversight on electricity pricing and the Multi Year Price Determination (MYPD), but the Portfolio Committee on Energy was also regularly briefed by NERSA (and the DoE), on this topic, when they presented their annual reports and strategic plans. The Portfolio Committee on Energy also attended the public hearings on the MYPD 3 determination to gain first hand information on the concerns of the public, related to electricity pricing policy in SA. One other policy area interrogated by the Portfolio Committee on Energy was that of the energy efficiency strategy. Here the Portfolio Committee on Energy held meetings with the DoE on this topic annually. The Portfolio Committee on Energy also held public hearings on this topic in 2012 and further conducted a few oversight visits to assess how industry was addressing this topic. 

·         The other key focus area of the Portfolio Committee on Energy was policies of the DoE related to gender, youth and people within the energy sector. In 2011 the Portfolio Committee on Energy had a meeting on the topic of “Mainstreaming Gender, Youth and People with Disabilities in the Energy Sector” and this was followed up with numerous engagements where this was addressed with the DoE. The Portfolio Committee on Energy further requested regular updates from the DoE on the status of women, youth and people with disabilities in the energy sector.

·         Finally, two other policies the Portfolio Committee on Energy also focused on were the Integrated Resource Plan (IRP) and the Integrated Energy Plan (IEP). These are two key policies that guide the roll out of energy resources for SA. The Portfolio Committee on Energy was briefed numerous times on this topic by the DoE, during the 4th Parliament

·         In 2012 was also briefed on the outcome of the public hearings into the Integrated Resource Plan. During this Parliament, both the Integrated Resource Plan and the Integrated Energy Plan were revised and were released for public comment. The Portfolio Committee on Energy also extensively debated the Independent System Market Operator (ISMO) Bill. This bill is aimed at creating a competitive electricity market and hence promotes the involvement of private players in the generation space. This was sent to the House for adoption but was not adopted during the 4th Parliament.

·         The Portfolio Committee on Energy was also regularly briefed on the formulation and review of the Energy policies by the DoE during the regular quarterly report updates and annually during their presentations of their annual reports and five year strategic plans.

 

VIII.        Assess the extent of transformation in the nuclear industry including assessment of Nuclear Policy

 

·         The Portfolio Committee on Energy regularly engaged with the DoE on nuclear issues including policy. These engagements were during the presentation of annual reports and strategic plans of both the South African Nuclear Energy Corporation (NECSA) and the National Nuclear Regulator (NNR), but further during the presentations of the DoE on their reports and plans, including the quarterly reporting.

·         Additional to the above, some areas visited in detail by the Portfolio Committee on Energy included, nuclear skills where the NNR and NECSA briefed the Portfolio Committee on Energy in 2010 on this topic.

·         With regard to public acceptance of nuclear: the Portfolio Committee on Energy assessed international experience and in 2011, Électricité de France (EDF) briefed the Portfolio Committee on Energy on stakeholder engagement and experiences on nuclear power and public acceptance thereof. The Portfolio Committee on Energy also looked at radioactive waste contamination at the mine dump near the Tudor Shaft Informal Settlement and discussed with the NNR, in 2011 the relocation of the Settlement, a topic still not closed due to a legal issue. Nuclear safety was a key issue the Portfolio Committee on Energy dealt with and in 2012 held a discussion with a victim of the Fukushima Nuclear Disaster that occurred in Japan. The Portfolio Committee on Energy also attended numerous conference and engagements on the envisaged 9600MW nuclear programme and in 2013 held a stakeholder meeting entitled, Nuclear energy as an option for sustainable supply of energy.

·         The Portfolio Committee on Energy was also regularly briefed on the nuclear industry by the DoE during the regular quarterly report updates and annually during their presentations of their annual reports and five year strategic plans.

 

IX.        Monitoring safety practices and legislation in the energy sector, including assessment of the safety levels of electrical installation

 

·         The Portfolio Committee on Energy conducted oversight on safety in energy and was briefed numerous times in Committee meetings by the DoE and the relevant stakeholders. It was also brought up during some of the public hearings and energy stakeholder meetings held by the Portfolio Committee on Energy. This ensured the Portfolio Committee on Energy had a good understanding of safety issues.

·         In 2011 the Portfolio Committee on Energy received two presentations on Liquefied Petroleum Gas, one on implementation of regulations and the other on issues related to Liquefied Petroleum Gas.

·         In June 2012, the Portfolio Committee on Energy held a meeting to discuss Energy Safety Issues with briefings by Eskom, Paraffin Safety Association of Southern Africa, Liquefied Petroleum Gas Safety Association of South Africa and the National Union of Metalworkers of South Africa.

·         As indicated above the Portfolio Committee on Energy was briefed on nuclear safety, numerous times during their engagements with the DoE, Necsa and the NNR and specifically focused on the radioactive waste contamination at the mine dump near the Tudor Shaft Informal Settlement and the Fukushima Nuclear disaster. In 2011, the Portfolio Committee on Energy also conducted an oversight visit to Koeberg Power Station to gain an assessment of the safety measures employed at the station in light of the nuclear incident in Japan.

·         The Portfolio Committee on Energy also conducted oversight visits e.g. the visits in 2013 to Liquefied Petroleum Gas distribution companies and to households that utilize Liquefied Petroleum Gas as well as that were electrified by the Integrated National Electrification programme.

 

X.        Monitor promotion of private sector participation in the electricity industry (Independent Power Producers)

 

·         The Renewable Energy Independent Power Procurement Programme allows for private sector participation in energy generation in South Africa. The Portfolio Committee on Energy exercised oversight on this programme and in 2012 held a panel discussion for Independent Power Producers on Renewable Energy Procurement (Window 1). This was followed up with a meeting of stakeholders in the renewable energy sector: Exploring solutions to the challenges of financing and certification of locally produced renewable energy products. There was also a follow-up meetings held in relation to Renewable Energy Independent Power Procurement Programme, with the DoE in November 2013. The Portfolio Committee on Energy also conducted oversight visits to this project and visited the Letsatsi Solar Project, near Bloemfontein in early 2014, a few weeks before it was to be connected to the grid.

·         The Portfolio Committee on Energy also held public hearings on the Electricity Distribution Industry over four days in July 2012 assessing the various mechanisms, available to the state to address the challenges associated with this industry.

·         The Portfolio Committee on Energy also assessed an additional area where there could be substantial private sector participation in the electricity industry and that was the area of co-generation. Here, not only was the Portfolio Committee on Energy briefed by the Department, but also held public hearings in late 2013 and convened a round table in Johannesburg in early 2014.

·         The Portfolio Committee on Energy also monitored the rollout of solar water heaters and conducted oversight on the aspect of 70% local content and further conducted oversight visits to gain firsthand experience of the compliance testing at the South African Bureau of Standards and visited communities that were beneficiaries of this programme in Touwsriver in 2012 and Ivory Park in 2014.

 

XI.        Monitor the implementation of the Energy Act, 2008, particularity Integrated Energy Plan and Integrated Resource Plan 2010

 

Majority of the engagements of the Portfolio Committee on Energy stems from the Energy Act of 2008 as it encompasses the objectives of the state to ensure energy security and diversity for economic growth and poverty alleviation. In this regard this Act looks at;

 

·         Energy Supply, Optimisation and Utilization – In this regard the Portfolio Committee on Energy engaged with the DoE on numerous occasions, assessing the programmes and alignment of the programmes to the Energy Act. All energy carriers including, liquid fuels, gas and electricity, were assessed. With liquid fuels, the issue of security of supply and mechanisms to address risks was extensively explored with the DoE. Alternative supplies including biofuels and gas-to-liquid/coal-to-liquid options were also looked at. In terms of liquid fuel utilization, the electric vehicle as an alternative to liquid fuel powered vehicles was also assessed. With regard to gas, the Portfolio Committee on Energy explored various options of supply with the DoE. In terms of supply, the Portfolio Committee on Energy also looked at off shore exploration (of both gas and liquids) and shale gas. They also extensive visited the topic of infrastructure and explored mechanisms with the DoE to ensure increased utilization. One of the findings of the Portfolio Committee on Energy was that there needs to be increased gas in the Integrated Resource Plan to ensure there is a key customer that drives demand. With regard to electricity. The Portfolio Committee on Energy regularly looked at the topic of diversity of supply with the DoE and discussed options available. This included in-depth scrutiny of the renewable energy programme and co-generation as alternative sources of electricity. The Portfolio Committee on Energy also regularly engaged with Eskom on the topic of security of supply and the new build. The Portfolio Committee on Energy also looked at optimisation and utilization options with the DoE and Eskom e.g. the retrofit programme, Solar Water Heater programme and 49M. The Portfolio Committee on Energy also exercised oversight over distribution and transmission in South Africa with numerous meetings with the various stakeholders. The pricing aspects of all carriers was also assessed and the Portfolio Committee on Energy received regular updates from the various stakeholders including the DoE, NERSA and SALGA

·         Integrated Energy Planning – The Portfolio Committee on Energy also regularly focused on the Integrated Resource Plan (IRP) and the Integrated Energy Plan (IEP). The Portfolio Committee on Energy was briefed numerous times on this topic by the DoE, during the 4th Parliament and in 2012 was also briefed on the outcome of the public hearings into the Integrated Resource Plan. During this Parliament, the Integrated Resource Plan was revised and this and the Integrated Energy Plan were released for public comment.

·         South African National Energy Development Institute – the Portfolio Committee on Energy exercised oversight on the research activities of SANEDI and offered guidance where necessary. This was not limited to the briefings on the annual report and strategic plan but also on specific research areas, e.g. SANEDI’s “Working for Energy Programme” and as an Energy Efficiency Champion in 2013.

·         The Portfolio Committee on Energy was also regularly briefed on the formulation and review of the Energy policies by the DoE during the regular quarterly report updates and annually during their presentations of their annual reports and five year strategic plans.

 

XII.        Climate change and Millennium Developmental Goal pillars (focus on the one relevant to energy issues)

 

·         The Portfolio Committee on Energy addressed climate change in the following ways. The Portfolio Committee on Energy was briefed by the Department of Environmental Affairs (DEA) on the National Climate Change Response Green Paper and by the DoE on Conference of the Parties 17 in 2011, and a progress report was submitted in 2012. The Portfolio Committee on Energy also received a briefing on a Report on International Climate Change and Energy Hearings in 2010.

·         In terms of climate change, the next area that the Portfolio Committee on Energy focused on was that of renewable energy as utilization of renewable energy results in reduced carbon emissions. In 2010, the Portfolio Committee on Energy was briefed by the DoE on the International Renewable Energy Agency including its programmes. Further in 2011 the Industrial Development Corporation also briefed the Portfolio Committee on Energy on the implementation of New Growth Path and Industrial Policy Action Plan (IPAP2) with special reference to the green economy and renewable energy. The Portfolio Committee on Energy also looked at international experience when they assessed a report on a Workshop on Renewable Energy Policies for Sustainable African Development in Ghana. From 2012, the focus shifted to the Renewable Energy Independent Power Producer Procurement Programme as this was the flagship programme of the DoE that not only addressed SA’s energy needs but also looked at climate change issues by addressing green energy. The Portfolio Committee on Energy also held a panel discussion on this topic the same year and also held a meeting of stakeholders in the renewable energy sector to explore solutions to the challenges of financing and certification of locally produced renewable energy products. The Portfolio Committee on Energy also, in 2012 assessed SANEDI’s involvement in the South Africa Renewable Energy Initiative, ensuring that there is focused Research and Development to benefit SA in terms of renewable energy.

·         The activities of the DoE speak to all the Millennium Development Goals in some form or the other. Hence the Portfolio Committee on Energy ensured compliance to these when conducting oversight and monitored the DoE in terms of their activities; in this regard, the Portfolio Committee on Energy received a briefing from the DoE on the Department of Energy’s contributions to government outcomes and Millennium Development Goals in August 2011. The DoE also briefed the PCE on updates to this during their presentations of their annual reports to the PCE.

·         The first goal, “to eradicate extreme poverty and hunger”, here the Portfolio Committee on Energy monitored the Integrated National Electrification Programme that is in place to ensure universal access to electricity and more specifically the Free Basic Energy and Free Basic Alternative Energy programmes of the DoE. This is a key programme that speaks to eradicating poverty and the Portfolio Committee on Energy monitored implementation with the DoE and South African Local Government Association. The INEP programme also speaks to the issues of “universal primary education” as the Portfolio Committee on Energy also monitored electricity roll out, including distribution, in communities, including schools. The Portfolio Committee on Energy also visited this topic during oversight visits. It can be noted that one of the areas that the Portfolio Committee on Energy conducted oversight over, was the area of non-grid electrification, of which there are already 66 000 connections.

·         In terms of “gender equality and empower women”, the Portfolio Committee on Energy regularly monitored the DoE and the SoE’s with regard to compliance, but further conducted oversight on gender equality and empowerment of women on the Renewable Energy Independent Power Procurement Programme and the Oil and Gas industry.

·         Another area assessed was the role out of the solar water heater programme which speaks to the health issues in the Millennium Development Goals and here the DoE monitored this programme closely over the years to the current state of almost 400 000 geysers rolled out.

·         “Environmental sustainability” issues were addressed by the DoE via the Renewable Energy Independent Power Procurement Programme and the energy efficiency programmes. As indicated above, this was carefully scrutinised by the Portfolio Committee on Energy during the 4th Parliament, but one area needing acknowledgement is that of Carbon Tax. The Portfolio Committee on Energy held a stakeholder discussion on the Likely Impact of Carbon Tax on Energy Supply in South Africa (and SADC) in July 2013 with the aim of allowing stakeholders to address this topic with the Portfolio Committee on Energy and National Treasury.

·         Finally in terms of “developing a global partnership for development the Portfolio Committee on Energy monitored the Renewable Energy Independent Power Procurement Programme to ensure there is local participation and that there is skills and technology transfer. The Portfolio Committee on Energy also monitored the international programme of the DoE to ensure sustainable partnerships are built. In this regard, the Portfolio Committee on Energy, in August 2013, engaged with the Pan African Parliament Committee on Transport, Industry, Communications, Energy, Science and Technology in a Joint Workshop on “Improvement of the Energy Industry in Africa for Sustainable Development- The Role of Parliaments”. Some of the outcomes included, a need for harmonization of legislation and Pan African Parliament (PAP) initiatives with New Partnership for Africa’s Development (NEPAD) projects, the need for capacity building, strengthening of institutions and access to data. There was an agreement between the two Parliaments that there will be future engagements.

 

 5.5. Reflection on the PCE oversight performance on annual basis and on whether the objectives of its programmes were achieved

 

Below is a reflection on the PCE oversight performance on annual basis and on whether the objectives of its programmes were achieved. The programmes were guided by the Key objectives of the PCE which are as follows:

 

  1. Promote the design and implementation of broad based sector or industry empowerment programmes with clearly defined targets based on agreements between stakeholders.
  2. Assess the impact of the Energy Efficiency Strategy of 2005.
  3. Monitor the restructuring the fragmented electricity distribution industry.
  4. Achieving universal access to electricity/Integrated National Electrification Programme.
  5. Monitor promotion and progress on the utilization of Liquified Petroleum Gas as well as transforming the sector.
  6. Assessing the extent of investment and progress on the utilization of clean energy sources.
  7. Facilitate the formulation and review of the Energy policies.
  8. Assess the extent of transformation in the nuclear industry including assessment of Nuclear Policy.
  9. Monitoring safety practices and legislation in the energy sector, including assessment of the safety levels of electrical installation
  10. Monitor promotion of private sector participation in the electricity industry (Independent Power Producers).
  11. Monitor the implementation of the Energy Act, 2008, particularly Integrated Energy Plan and Integrated Resource Plan 2010)
  12. Climate change and MDG. 4 pillars (focus on the one relevant to energy issues)

 

Hence below is a Reflection on the PCE oversight performance on annual basis;

5.5.1.     2009 to 2010

 

In 2009, the PCE conducted oversight on the electricity industry. They were briefed on the electricity distribution industry twice, including the Regional Electricity Distributors. They also conducted oversight on electricity pricing with Nersa and Eskom. The PCE also conducted oversight on liquid petroleum gas pricing and conducted oversight on the aviation fuel shortages with the DoE and the Airports Company SA.

The PCE also conducted oversight on the annual activities of DoE, Nersa, NNR, EDI and Necsa when they presented their annual reports to the PCE.

 

In terms of oversight trips undertaken, The PCE conducted an oversight trip to PetroSA’s Gas-to-Liquids (GTL) Refinery in Mossel Bay in the Western Cape.

 

The PCE also undertook a study tour to Mozambique in 2009 to discuss how the growing demand for energy in an age of rising fuel prices can most effectively be met, whilst simultaneously addressing the growing dangers of climate change and ensuring that the poor have adequate access to energy

 

In conducting the above oversight activities, key oversight objectives 3, 4, 5, 7 and 11 of the PCE were met. However it can be noted that all key oversight objectives of the PCE were met, as although the PCE may not have held dedicated meetings to conduct oversight over each object listed above, comprehensive oversight was conducted over all the listed key objectives above, by the PCE, when the DoE presented their annual report. Hence the objectives of the PCE programmes were achieved.

 

 

5.5.2.     2010 to 2011

 

In 2010, the PCE started the programme by paying tribute to Mr. C. Schmidt. The PCE also conducted oversight on Liquid Petroleum Gas (LPG) regulation and was briefed by the DoE. There was also an update on LPG pricing, by the DoE later that year. The DoE also presented their budget and strategic plans to the DoE early in the year. The PCE conducted oversight on the Integrated Resource Plan twice that year with briefings by the DoE. The PCE also conducted oversight on renewable energy and was briefed by the DoE on the International Renewable Energy Agency and also received a briefing on the  Memorandum of South Africa's membership to IRENA & Report on International Climate Change and Energy Excess Hearings. The PCE also was briefed on the Energy Efficiency Strategy 2005 by the DoE. In this regard, the DoE presented the Solar water heating programme to the PCE. The PCE also conducted oversight on training with a briefing by the   Energy Sector Education and Training Authority (ESETA) and nuclear skills by DoE, NNR and Necsa. In terms of nuclear the DoE briefed the PCE on Amendments to Articles VI & XIV.A of Statute of the IAEA. The PCE also conducted oversight on the DoE when they were present with the DoE performance review April to September. The DoE also presented the Integrated Energy Plan to the PCE. The PCE also held two days of public hearing in September on Liquid Fuels Charter & Energy Industry transformation. In terms of the Liquid fuels Charter, there was also an Engagement with Deputy Minister of Trade & Industry, PetroSA, National Energy Regulator of South Africa (NERSA), Transnet & Department of Energy - follow-up briefings to public hearings. The PCE once again conducted oversight on annual reports and CEF, PetroSA, Necsa, DoE, NNR and EDI presented theirs. The PCE also dealt with the 2010/2011 Budget Review and Recommendation Report.

 

In terms of oversight trips undertaken, The PCE conducted an oversight trip to Khayelitsha, Cape Town to assess the progress made and do oversight on the Kuyasa Energy Efficiency Project, Kuyasa is South Africa’s first registered Clean Development Mechanism project activity which aims to retrofit existing low-income houses with solar water heaters.

 

The PCE also undertook a study tour to

·         Mozambique - To gain further understanding of the international clean energy sources scene and utilization thereof

·         Botswana - To honour an invitation by the University of Botswana to the IASTED Conference on renewable energy and gasses

·         France - To learn about the French Energy Mix and in Particular their Nuclear Energy Programmes

 

In conducting the above oversight activities, all key oversight objectives of the PCE were met, although the PCE may not have held dedicated meetings to conduct oversight over each object listed above, comprehensive oversight was conducted over all the listed key objectives above, by the PCE, when the DoE presented their annual report. Hence the objectives of the PCE programmes were achieved.

 

5.5.3.     2011 to 2012

 

In January, the PCE was briefed on the Integrated Resource Plan 2 (IRP2) public hearings outcomes by the DoE. The Minister and the DoE also briefed the PCE on the Integrated National Electrification Programme. The DoE also reported on progress on Implementation of the Liquefied Petroleum Gas (LPG) Regulations and the Two Pilot Projects implemented in Atteridgeville & Tweefontein and the NNR reported to the PCE on relocation of Tudor Shaft Informal Settlement from mine dump contaminated with nuclear radioactive material. The PCE was also briefed on the declining feedstock at the Mossgas Gas Field project by PetroSA and thereafter looked at the Eskom Capital Expansion programme. there was also an update on LPG issues by the DoE later that year.

The PCE then conducted oversight on the strategic plan, 3rd Quarter performance and the budget of the DoE. In terms of electricity, the PCE conducted oversight on the Electricity Distribution Industry Goals with the Department of Energy & SALGA. The PCE was briefed by the DoE on the Independent Systems Market Operator (ISMO) Draft Bill. With regard to climate change issues, the National Climate Change Response Green Paper was presented by the by Department of Environmental Affairs and COP 17 Progress Report by Department of Energy. The PCE was also briefed by the DoE on Energy Efficiency and Energy Saving. Focus on Energy Efficiency: briefing by South South North Africa, Green Building Council of South Africa, PEER Africa, Council for Built Environment & Council for Scientific & Industrial Research. There was also a briefing by the Industrial Development Corporation (IDC) on implementation of New Growth Path and Industrial Policy Action Plan (IPAP2) with special reference to the green economy and renewable energy

 The PCE also conducted oversight on the Multi-Products Pipeline Project, Wind Energy & REFIT tariffs with the DoE. There was a briefing by Électricité de France (EDF) on stakeholder engagement and experiences on nuclear power and public acceptance thereof.

In terms of annual reports, the following entities presented theirs; CEF, DoE, NNR, Nersa, Necsa and PetroSA. In this regard the PCE was briefed on the Performance of Department of Energy by Department of Performance Monitoring & Evaluation. The PCE also dealt with the Budgetary Review and Recommendations process and was also briefed by the Auditor General in this regard.

Finally the PCE also dealt with Mainstreaming Gender, Youth and People with Disabilities in the Energy Sector with the DoE.

 

In terms of oversight trips undertaken, The PCE conducted an oversight trip to

 

·         Cape Town – Department of Energy regional offices to assess operations of the regional offices of the Department of Energy in the Western Cape.

·         Koeberg Power Station to get an understanding of safety measures employed at the station in view of the nuclear accident in Fukushima nuclear plant in Japan

·         Darling Wind Farm where the oversight visit was aimed at giving the Committee an insight into the progress made on efforts to incorporate wind energy into the energy mix of the country.

·         CEF Offices in  Johannesburg to get an understanding of the affairs of the Central Energy Fund (CEF), including all its projects, subsidiaries

 

In conducting the above oversight activities, all key oversight objectives of the PCE were met, although the PCE may not have held dedicated meetings to conduct oversight over each object listed above, comprehensive oversight was conducted over all the listed key objectives above, by the PCE, when the DoE presented their annual report, Strategic plan and presentation of their quarterly reports. Hence the objectives of the PCE programmes were achieved.

 

5.5.4.     2012 to 2013

 

In 2012, the PCE conducted oversight on legislation and was briefed on the National Energy Regulator Amendment & Electricity Regulation Second Amendment Draft Bill by the DoE. The other piece of legislation handled by the PCE was the Independent System and Market Operator (ISMO) Bill. Here the PCE held public hearings in May and received the department’s response to submissions and received a report back from the task team in August and later in September where they presented scenario building.

 

The DoE also presented their response to the State of the Nation Address and Budget speech, their international programmes and later in the year on an update on international agreements and participation in international bodies, their third quarter and fourth 2011/2012 performance, their strategic plan and their annual report. The DoE also undated the PCE on the Integrated Energy plan. With regard to the entities, the year started with a Presidential Review SOE Committee on State-Owned Entities, reporting to Department of Energy. The entities also presented their strategic plans as well as their annual reports later in the year. There was also a briefing by the Energy Minister on Service Delivery Agreement Outcomes & Department of Performance Monitoring & Evaluation input and by Auditor-General on Department of Energy 2011/12 Annual Report & CPUT Energy Institute review and finally with regard to annual reports, Evaluation on Management Performance of Department of Energy: briefing by Department of Performance Monitoring and Evaluation. In terms of PetroSA, the department also briefed the committee on PetroSA “Outlook 2012 to 2016”, Integrated Energy Centre Programme.

 

The DoE also updated the PCE on Renewable Energy Independent Power Producer Procurement and in June held Panel discussion for Independent Power Producers on Renewable Energy Procurement (Window 1).  The PCE also held a Meeting of stakeholders in the renewable energy sector: Exploring solutions to the challenges of financing and certification of locally produced renewable energy products. The Department of Energy & World Wildlife Fund briefed the PCE on Energy outcomes of COP 17 and in February Committee Report on Workshop on Renewable Energy Policies for Sustainable African Development in Ghana. The PCE also held public hearings on energy efficiency in September.

 

Energy safety was also an issue that the PCE conducted oversight over with briefings by Eskom, Paraffin Safety Association of Southern Africa, Liquefied Petroleum Gas Safety Association of South Africa & National Union of Metalworkers of South Africa. The PCE also conducted oversight on nuclear safety with a discussion with a victim of Fukushima Nuclear Disaster in Japan

 

In terms of electricity distribution, the PCE was briefed by the Department and later held public hearings on Restructuring of Electricity Distribution Industry in July and in terms of electricity, the PCE conducted oversight on Electricity Pricing Policy and Impact of Multi-Year Price Determination with Nersa and the DoE and also received an update on the Eskom led new build programme and on Eskom Multi-Year Price Determination (MYPD3) application to NERSA. Related to this the PCE conducted oversight on Free Basic Electricity / Alternative Energy and Electrical Power Interruptions: solutions and strategies and later in  April the Department of Energy, Eskom & Cennergi updated the PCE on the Solar Water Heater programme

 

The PCE also conducted oversight on the oil and gas sector. The DoE presented the progress on the Cleaner Fuels 2 programme in March and The Liquid Fuels Charter audit outcomes were presented to the PCE in August and also the Liquefied Petroleum Gas Option for Expansion by Department of Energy. In November the PCE held a Energy Stakeholder Meeting on Transformation in Petroleum Industry. The DoE also briefed the PCE on Liquid Fuels Infrastructure Roadmap and Basic Fuel Price.

 

In terms of skills development, the DoE presented the skills development in the energy sector to the PCE in September and in November conducted oversight on Energy Sector skills development with briefings on Local Government SETA, Construction SETA, Chemical Industries SETA, Wholesale & Retail SETA input.

 

Two additional areas the PCE conducted oversight over was Investment Flows for Change

 

With briefings by Africa Institute of SA & Standard Bank and the Budgetary Review and Recommendation process

 

In terms of oversight trips undertaken, The PCE conducted an oversight trip to

·         Hluleka and eLucingweni (Eastern Cape) and Durban (KwaZulu-Natal) to visit to refineries and meeting with community around the refineries; visit Hybrid energy Systems; conduct an Energy Public meeting and visit the Marianhill Landfill site

·         Oversight visit to Touwsriver Solar Park Power project:. The Committee wanted to to engage the Community of Touwsriver, with the view of doing an oversight in order to gain an understanding of how the project is evolving, including understanding the challenges faced by ordinary people and ways of addressing such challenges if any exist. The aim of the visit is to try and understand the impact of this development project on matters of climate change.

·         Businesses in Cape Town - The committee undertook the visit to ascertain what businesses are doing with regard to energy efficiency initiatives as the committee envisage undertaking public hearings to address energy efficiency issues, during the 3rd Term 2012.

·         Century City – Aurecon Engineers and Epping – St Gobain The committee undertook the visit to ascertain what businesses are doing with regard to energy efficiency initiatives as the committee envisage undertaking public hearings to address energy efficiency issues, during the 3rd Term 2012. The visits to these projects will provide the committee the necessary information when deliberating on energy efficiency issues not only during its deliberations and engagements during the public hearings, but at other forums as well. This trip can also be considered a study tour.

 

The PCE also undertook a study tour to PetroSA Synthetic Fuel Centre at UWC to investigate and learn what the PetroSA Synthetic Fuel Centre does, which focuses on improving the efficiency of the COD process and the possibility of using alternative feed stocks such as alcohols and naphthas.

 

In conducting the above oversight activities, all key oversight objectives of the PCE were met, although the PCE may not have held dedicated meetings to conduct oversight over each object listed above, comprehensive oversight was conducted over all the listed key objectives above, by the PCE, when the DoE presented their annual report, Strategic plan and presentation of their quarterly reports. Hence the objectives of the PCE programmes were achieved.

 

5.5.5.     2013 to 2014

 

In 2013, the PCE focused on legislation this year also, and held deliberations on the Independent System Market Operator (ISMO) Bill at a few meetings, including deliberations on public comments and the impact study on the transfer of transmission.

The DoE presented their legislative programme to the PCE in February, thereafter the implications of the State of the Nation address on the DoE; they also presented their Strategic and Annual Performance Plan 2013; their 3rd and 4th quarter performance reports and their annual reports; the 1st and 2nd quarter performance report for 2013/4 in October. The entities CEF and subsidiaries, Nersa, NNR, Necsa and SANEDI presented their strategic plans in April and their annual reports later in the year to the PCE. The AG presented the audit outcome with regard to the DoE and their entities to the PCE and the Financial and Fiscal Commission briefed the PCE on its recommendations related to energy. The PCE was also updated on Energy Strategic Integrated Projects (SIPs) by the DoE.

In terms of electricity, the PCE conducted oversight on Free Basic Alternative Energy/Free Basic Electricity with presentations by the DoE. The DoE also presented an update on the Integrated National Electricity Programme. With DoE, Nersa, Eskom and SALGA on Eskom’s multiyear price determination application. The PCE also conducted oversight on . the PCE also conducted oversight on Free Basic Electricity with Department of Cooperative Governance & Municipal Infrastructure Support Agent (MISA) briefings, Electricity Sector restructuring & draft Integrated Energy Plan with the DoE and Municipal Tariff Determinations: National Energy Regulator, National Treasury, SALGA briefings; Working for Energy: SA National Energy Development Institute updates. The PCE also conducted oversight on electricity sector regulation with Nersa. The PCE also received a briefing from IDC & SA Calcium Carbide on co-generation and held public hearings into co-generation in July. In September an energy stakeholder meeting was held on Nuclear energy as an option for sustainable supply of energy and the PCE received an update on the Renewable Independent Power Producer Procurement Programme by the DoE. The PCE als received an Update on pilot Approach to Distribution Asset Management (ADAM) with input by Department of Energy, SALGA, Municipal Infrastructure Support Agency & Financial and Fiscal Commission

In terms of oil and gas, Nersa updated the PCE on Transnet pipeline tariff and Sasol gas prices. The PCE conducted oversight on the downstream liquid fuels sector with input by wholesalers, storage sub-sectors and retailers; Liquid fuels pricing briefing by Department of Energy. The DOE also presented Industrial Strategy update on Biofuels & Transformation of the Gas Industry.

The PCE also received a briefing from Eskom and Nissan on the Electric Vehicle Research Project, held a second day of public hearings on energy efficiency in January and in September conducted oversight over the National Energy Efficiency Strategy and South African National Energy Development Institute as Energy Efficiency Champion. The PCE also held a stakeholder discussion on Likely Impact of Carbon Tax on Energy Supply in South Africa (and SADC) and finally a media briefing session was held in 2013 also in terms of administrative functions, the Budgetary Review and Recommendation process.

 

In 2014, the PCE conducted oversight on energy efficiency with a presentation by the DoE on the Energy Efficiency Strategy. The PCE was also briefed by the Department of Energy on its 3rd Quarter Performance Report for 2013/14. The PCE also held an energy stakeholder meeting on the Assessment of the Upstream Sector in the Oil and Gas Industry. Public hearings on the ‘Possible transformation of the gas sector through partnerships’ was held in January at the University of Johannesburg. The PCE also held a round table discussion on co-generation at the SANEDI headquarters in Johannesburg. This was to allow stakeholders, who normally cannot come to Cape Town, an opportunity to air their views.

 

The PCE, in August 2013, engaged with the Pan African Parliament Committee on Transport, Industry, Communications, Energy, Science and Technology in a Joint Workshop on “Improvement of the Energy Industry in Africa for Sustainable Development- The Role of Parliaments”. Some of the outcomes included, a need for harmonization of legislation and PAP initiatives with NEPAD projects, the need for capacity building, strengthening of institutions and access to data. There was an agreement between the two Parliaments that there will be future engagements.

 

In terms of oversight trips undertaken in 2013, The PCE conducted an oversight trip to

·         Paarden Eiland – BPSA and Easigas – Bellville-South Portfolio Committee on Energy visited industrial and commercial sites as well as household supply facilities that use LPG . This can also be considered to be a study tour.

·         SA Breweries - Newlands Portfolio Committee on Energy will visit project that generate energy from waste. This can also be considered to be a study tour.

 

In terms of study tours, as part of the PAPSAEI Joint Workshop, the Members of the PAP Committee on Transport, Industry, Energy, Communication, Science and Technology as well as the Members of the South African Portfolio Committee on Energy visited three Energy projects in the Gauteng area, focusing on waste to energy and co-generation and tri-generation undertaken by SA entities. These were The Johannesburg Metro Municipality Landfill Gas to Energy Project; the MTN 2MW Tri-generation Plant; and the ABSA Towers West Energy Centre Project.

In terms of oversight trips undertaken in 2014, The Portfolio Committee on Energy conducted oversight on various energy related projects in a number of provinces. The Committee plans to firstly visit solar home systems that have been implemented in KZN. Further, the committee will visit areas in KZN where the Renewable Energy Independent Power Producer Procurement Programme (REIPPP) are or are being implemented, In Gauteng, the Portfolio Committee on Energy will be holding public hearings on transforming the gas industry through partnerships and will further focus on cogeneration and trigeneration power initiatives and partnerships. The week will end with a visit to Integrated National Electrification Programmes (INEP) (and solar water heater programmes) in Gauteng.

 

In conducting the above oversight activities, all key oversight objectives of the PCE were met, although the PCE may not have held dedicated meetings to conduct oversight over each object listed above, comprehensive oversight was conducted over all the listed key objectives above, by the PCE, when the DoE presented their annual report, Strategic plan and presentation of their quarterly reports. Hence the objectives of the PCE programmes were achieved.

 


5.6. Other activities the committee undertook in the period under review

 

5.6.1. Public Hearings

 

5.6.2. Energy Stakeholder Meetings

·         November 2011 – Parliament, Cape Town - Topic: “Prospects of job creation to local manufacturing in the renewable energy sector”.

·         January 2012 – Durban University of Technology (DUT), Durban (KZN) - Topic: “Management of strategic fuel stocks – options for SA”

·         June 2012 – Parliament, Cape Town - Topic: Panel discussion on Renewable Energy Procurement for Independent Power Producers Bidding: Window 1

·         August 2012 – Parliament, Cape Town – Topic: “Exploring solutions to challenges on financing and certification of locally produced renewable products”

·         12 September 2013 – Parliament, Cape Town - Topic: “Nuclear energy as an option for sustainable supply of energy”

·         20 February 2014 – Parliament, Cape Town – “Assessment of Upstream Sector in oil and gas industry

 

5.6.3. Roundtable discussions

 

5.6.4. Workshops

 

5.6.5. Legislation

 

Year

Name of Legislation

Tagging

Objectives

Completed/Not Completed

2009/10

N/A

N/A

N/A

N/A

 

 

 

 

 

2010/11

N/A

N/A

N/A

N/A

 

 

 

 

 

2011/12

1

S75

To provide for the establishment of an Independent System and Market Operator as a state-owned entity which will provide an independent system operation to ensure safe, secure and efficient operation of the integrated power system, trading of electricity at wholesale level

Completed (reported on the bill to the House)

 

 

 

 

 

2012/13

N/A

N/A

N/A

 

 

 

 

 

 

2013/14

1 (recommitted)

S76

To provide for the establishment of an Independent System and Market Operator as a state-owned entity which will provide an independent system operation to ensure safe, secure and efficient operation of the integrated power system, trading of electricity at wholesale level

Completed (reported on the Bill to the House)

 

a)     Challenges emerging

 

The following challenges emerged during the processing of legislation:

 

·         Technical/operational challenges that may have delayed legislation and/or complicated the processing thereof

ISMO Bill [B9 – 2012] - The Department took a long time to introduce the Bill to Parliament. The introduction of the Bill was firstly mooted in 2010, but the Bill was eventually tabled during March 2012. The bill was initially tagged as a Section 75, but after processing the bill, the bill was retagged as a Section 76. During 2013, the Bill was recommitted to the committee on which we revised the report on the Bill, which was subsequently ATCd.

 

The Department’s legal unit, especially the unit responsible for the drafting of legislation, needs to be beefed up, considering that more legislation will be tabled in Parliament during the 5th Parliament.  

 

Further to the above the DoE has been extremely slow in introducing bills to Parliament.

 

 

5.6.6. Oversight trips undertaken

 

The following oversight trips were undertaken:

 

Date

Area Visited

Objective

Recommendations

Responses to Recommendations

Follow-up Issues

Status of Report

05 - 07 October 2009

PetroSA’s Gas-to-Liquids (GTL) Refinery in Mossel Bay, Western Cape

During the deliberations at the committee’s Introductory Workshop [13-13 august 2009], PetroSA invited the Portfolio Committee to visit the Port Elizabeth plant of its latest oil investment with the Coega Industrial Development Zone, so as to witness the progress made there.

Need to collect information  from former Committee Secretaries

A full feasibility study had been launched into the proposed Project Mthombo refinery on March 26th 2013, following the signing of a two year framework agreement with Sinopec

The outcome of this study needs to be presented, including the next phase of the project to the Portfolio Committee on Energy

Adopted

17 August 2010

Khayelitsha, Cape Town

To assess the progress made and do oversight on the Kuyasa Energy Efficiency Project, Kuyasa is South Africa’s first registered Clean Development Mechanism project activity which aims to retrofit existing low-income houses with solar water heaters.

Need to collect information from former Committee Secretaries

The Portfolio Committee on Energy regularly engaged with the DoE on the topic of SWH and the challenges and rollout thereof. The DoE focused on efforts and to date 390 000 homes have had SWH installed.

The Portfolio Committee on Energy still needs to follow-up that the DoE ensures it accelerates this programme to ensure delivery of the 1 million SWH and also addresses issues of community involvement, quality and service contracts

Adopted

28 June 2011

Cape Town – Department of Energy regional offices

Assessing operations of the regional offices of the Department of Energy in the Western Cape

 

The regional offices were restructured to make them more effective. The Portfolio Committee on Energy regularly engaged with the DoE on the functioning of the regional offices and specifically on the issues of interactions between the different offices.

The effectiveness of the regional offices, now that they are restructured needs to be assessed.

Adopted

29 June 2011

Cape Town - Koeberg Power Station

Getting an understanding of safety measures employed at the station in view of the nuclear accident in Fukushima nuclear plant in Japan

·         Need to target public representatives in terms of raising awareness as these public representatives would in turn communicate with people on the ground.

·         The Committee would engage the department in order to ensure that something was done to avail more funds that would be dedicated towards public education around nuclear programmes in the country.

 

The DoE, NNR and Necsa indicated that there are regular forums with communities that live around nuclear facilities, and issues are dealt with.

The DoE indicated that they are busy with public awareness campaigns around nuclear including radio and TV) and further, Necsa has the visitors centre to educate the public about nuclear

Feedback from communities living around these facilities as to, how are their concerns being addressed.

Adopted

29 June 2011

Cape Town - Darling Wind Farm

The oversight visit was aimed at giving the Committee an insight into the progress made on efforts to incorporate wind energy into the energy mix of the country.

·         There was a need to gather more information that will assist in the intervention of what seemed to be a stand-off between the Community and investors of the darling wind farm.

·         Certain allegations about the origins of BEE partners who took 33% and that they did not come from the darling Community needed to be probed.

·         The Committee promised to use its interest (emanating from the 48% stake belonging to CEF) to get to the bottom of what had caused such huge dissatisfaction from the community.

·         The Committee promised to channel other social concerns which emanated from the meeting to relevant government departments and committees in parliament.

The Portfolio Committee on Energy has engaged with the DoE and requested that they deal with community related issues on all REIPPP projects. The DoE indicated that there are some issues on some projects

The DoE to address the Portfolio Committee on Energy on progress in this area and if they are using lessons learnt on some projects to assist others that are having challenges

Adopted

01 – 05 August 2011

CEF Offices – Sandton, Johannesburg

Oversight exercise to get an understanding of the affairs of the Central Energy Fund (CEF), including all its projects, subsidiaries.

 

·         There was a need for continued interaction and sharing of strategic activities between the Department, of Energy, Central Energy Fund, its divisions, subsidiaries, and associates and the Portfolio Committee for Energy.

·         The Committee expects a briefing about the outcomes of the upcoming refinery manager’s forum expected to take place as organised by SASDA.

·         Committee expressed an interest to get a briefing about the profiles of new employees who may be hired to head strategic projects under CEF.

·         Department of Energy was encouraged to lend more support to CEF, especially regarding clean energy projects.

·         Energy efficiency in government buildings seen as important intervention and CEF was therefore requested to consider getting involved in such intervention.

·         The situation surrounding Phillips Trading Company needed to be re-negotiated.

·         The committee stressed the importance of job creation in every project. Maximising profits should not be the sole aim of initiating projects and the committee would measure the success of every project based on its viability financially as well as job creation

·         CEF was urged to be biased towards promoting local manufacturing as this would play a key role in contributing to job creation.

·         For future interactions and sharing of information, CEF was encouraged to make use of Parliamentary Library Services for any reading material that could be relevant for Committee members.

The refitting of government is being spearheaded by the Department of Public Enterprises.

CEF is currently in a restructuring phase where one of the options being considered is greater involvement in the renewable energy sector. There were regular interactions between the DoE, CEF and the Portfolio Committee on Energy on issues affecting CEF.

 

The restructuring of CEF needs to be monitored, to ensure it is a viable stand alone entity.

Adopted

16 – 20 January 2012

·         Hluleka and eLucingweni (Eastern Cape)

·         Durban (KwaZulu-Natal)

·         Visit to refineries and meeting with community around the refineries

·         Visit to Hybrid energy Systems

·         Energy Public meeting

·         Visit to the Marianhill Landfill site

·         The Department of Energy is to encourage the Council for scientific and Industrial Research (CSIR) and the SA National Energy Development Institute (SANEDI) to salvage whatever is left of the hybrid energy system at eLucingweni and establish a joint project with the Walter Sisulu University for local schools in the area.

·         The Department of Energy to add focus on the development of hybrid mini-grid or off-grid energy systems to address rural development.

·         With regard to adverse effects from refineries in eThekweni, the Department of Environmental and Water Affairs to revive the joint initiative with the eThekweni Metro to address environmental issues in the vicinity around the refineries.

 

There has been substantial investment in the off-grid electrification programme, by the DoE and to date 66 000 homes have received off grid electricity.

In terms of landfill sites, there has been some progress in extracting methane from these sites for the generation of electricity.

There was a take up of 18 of the allocated 25MW for landfill gas on the REIPP programme, hence the Portfolio Committee on Energy needs to monitor that there is greater take up of landfill gas in the upcoming windows.

Adopted

09 March 2012

Touwsriver, Western Cape

Oversight visit to Touwsriver Solar Park Power project:

The Committee wanted to to engage the Community of Touwsriver, with the view of doing an oversight in order to gain an understanding of how the project is evolving, including understanding the challenges faced by ordinary people and ways of addressing such challenges if any exist. The aim of the visit is to try and understand the impact of this development project on matters of climate change.

The Portfolio Committee on Energy recommends that the Minister of Energy should:

·         Engage extensively with the communities of De Doorns and Touwsriver on their concerns on the project and more specifically about the 5% stake the community has in the project.

·         Engage with the contractors and Soitec to address concerns raised by the local communities.

·         Explore opportunities to expand this project jointly with the Minister of Trade and Industry.

·         Ensures that public participation be implemented as a process distinct from but linked to processes such as Environmental Impact Assessment.

 

The DoE indicated that there are challenges with the involvement of communities in the REIPP programmes but this is being addressed. The PCE did visit a successful project near Bloemfontein in 2014 with this regard.

The PCE is to conduct oversight over the involvement of communities in the REIPP programme and ensure that challenges identified with regard to community involvement be addressed by the DoE

The PCE conduct oversight as to how the DoE has addressed the concerns identified in De Doorns

Adopted

21 – 22 June 2012

Cape Town

The committee undertook the visit to ascertain what businesses are doing with regard to energy efficiency initiatives as the committee envisage undertaking public hearings to address energy efficiency issues, during the 3rd Term 2012. The visits to these projects will provide the committee the necessary information when deliberating on energy efficiency issues not only during its deliberations and engagements during the public hearings, but at other forums as well.

·         Promotes Kuyasa Clean Development Mechanism Pilot Project and facilitates its replication in the rest of the country;

·         In partnership with the relevant Ministers, ensure that policy development for all new public buildings to be environmentally sensitive with energy efficient designing;

·         Ensure promotion of Industrial Energy Efficiency Improvement Project and increased resourcing of the National Cleaner Production Centre

·         Promotes gas as an alternative source for industrial use and reviews policy to facilitate such.

 

The DPW indicated that they are busy with the retrofit programme.

There are new regulations with regard to buildings in South Africa. This will result in more EE designs.

The DoE is revising the gas policies currently

Strong incentives exist for energy efficiency improvement in the South African industry, namely increased profit, reduction of GHG emissions, and the need to maintain economic competitiveness. Several case study assessments of industry leaders in South Africa suggest that South African industry has an even higher potential for energy cost saving.

 

The establishment of a fuels innovation centre at pilot-plant scale represents a new venture as far as technology development partnerships between industry and academia in South Africa are concerned.

Adopted

27 November 2012

·         Century City – Aurecon Engineers

·         Epping – St Gobain

·         The committee undertook the visit to ascertain what businesses are doing with regard to energy efficiency initiatives as the committee envisage undertaking public hearings to address energy efficiency issues, during the 3rd Term 2012. The visits to these projects will provide the committee the necessary information when deliberating on energy efficiency issues not only during its deliberations and engagements during the public hearings, but at other forums as well.

·         Promotes Kuyasa Clean Development Mechanism Pilot Project and facilitates its replication in the rest of the country;

·         In partnership with the relevant Ministers, ensure that policy development for all new public buildings to be environmentally sensitive with energy efficient designing;

·         Ensure promotion of Industrial Energy Efficiency Improvement Project and increased resourcing of the National Cleaner Production Centre

·         Promotes gas as an alternative source for industrial use and reviews policy to facilitate such.

 

The DPW indicated it is in the process of retrofitting all public buildings in SA.

SANEDI indicated that it need to evolve as a EE champion of South Africa

The DoE indicated that the Gas policy is being ing revised in SA and they are in discussions with Mozambique to access more gas. The IRP with a larger gas footprint is also being revised, spurring on investment

The PCE needs to conduct oversight over the rollout of the retrofit programme in public buildings and at municipal level.

The PCE needs to conduct oversight that the DoE puts in place mechanisms for the creation of a EE champion in SA.

The PCE needs to conduct oversight on the revised Gas policies.

 

31 July 2013

Stellenbosch,  Klapmuts and Blue Downs

·         Portfolio Committee on Energy visited identified INEP projects in the Western Cape

·         Portfolio Committee on Energy will visit Enkanini to witness utilisation of cost effective building material that is environmentally sound including energy efficiency and solar energy

·         The City of Cape Town to be written a formal letter and request to address issues raised

·         The PC on Energy to arrange its own meeting with the Gas Users group to get insight of its programmes, proposals and concerns.

·         The Committee would require a clarification on how the proposed changes on the Stellenbosch Municipality Indigent Policy would affect the Free Basic Electricity (FBE), Free Basic Alternative Energy (FBAE) subsidies and the R100 monthly fee which the community is currently paying for solar electricity.

·         Furthermore the Committee noted the idea of investing on bio-digester toilets through collaboration with the Stellenbosch Municipality in order to improve household access to sanitation, which would ultimately improve household access to gas electricity.

·         The Committee recommended the Sustainability Institute to collaborate with the Department of Human Settlements and the Department of Health.

·         The Sustainability Institute indicated that an “incremental approach” to electrification appeared to be a good approach for informal settlements.

·         It was suggested that the Department of Energy visits the Institute and discuss options available regarding projects of this nature.

·         The Director of the Sustainability Institute, Mr Mark Swilling suggested that the Committee hold Public Hearings on Incremental Approach to Energisation.  

 

A public hearing was held with the gas industry that included the DoE so that they become aware of the challenges.

The DoE has been requested to assess the grid and non-grid electrification programmes and ensure all stakeholders form part of the process

The PCE follow up with City of Cape Town and Stellenbosch Municipality on issues raised

The PCE evaluate if it wishes to hold  Public Hearings on Incremental Approach to Energisation

 

01 August 2013

·         Paarden Eiland – BPSA

·         Easigas – Bellville-South

·         SA Breweries - Newlands

·         Portfolio Committee on Energy will visit industrial and commercial sites as well as household supply facilities that use LPG

·         Expert testimony on LPG industry will be invited will be invited to the oversight visit

·         Portfolio Committee on Energy will visit project that generate energy from waste

·         Expert testimony on waste to energy technology  will be invited to the oversight visit

The Minister of Energy to address the following:

·         SAB indicated that they are willing to partner with government in terms of skills development, investment in energy projects and job creation (SAB sees great opportunity in clearing alien vegetation).

·         Institutional arrangements in project management of electrification projects at municipal level, between the Department of Energy, ESKOM and a municipality be reviewed and improved.

·         Technical and financial approvals for electrical installations be rationalised.

·         Reviewal of the modus operandi of payment for electrification projects by the Department of Energy and ESKOM including exploration of guarantees and improved formalisation.

·         Installation of solar water heaters in Nuwe Begin with a priority on the old and disabled.

·         Arranges a meeting between the Department of Energy and the gas industry to address all gas related issues raised in the report.

·         Arranges a meeting with the Gas Users Group to address their proposals and concerns.

 

The DoE indicated that the NERA amendment bill is in the process of being revised and the PCE has requested that the role of Nersa in terms of municipalities be assessed.

The DoE acknowledged that there are issues with regard to the current rollout of SWH and this will be addressed in conjunction with all the relevant stakeholders to accelerate rollout.

Public hearings were held with the gas industry. The DoE indicated it is reviewing the gas policies

Skills development in the energy sector. The DoE to present their mechanism to involve industry

The working relationship between the various stakeholders in electrification programmes needs some attention from the DoE

The Gas related policies need to be reviewed by the PCE once updated by the DoE

Adopted

27 – 31 January 2014

·         Pietermaritzburg - KwaZulu-Natal,

·         Bloemfontein - Free State

·         Johannesburg (Ivory Park) - Gauteng

The Portfolio Committee on Energy conducted oversight on various energy related projects in a number of provinces. The Committee plans to firstly visit solar home systems that have been implemented in KZN. Further, the committee will visit areas in KZN where the Renewable Energy Independent Power Producer Procurement Programme (REIPPP) are or are being implemented, In Gauteng, the Portfolio Committee on Energy will be holding public hearings on transforming the gas industry through partnerships and will further focus on cogeneration and tri-generation power initiatives and partnerships. The week will end with a visit to Integrated National Electrification Programmes (INEP) (and Solar water heater programmes) in Gauteng

·         Policy reviewal on non-grid electricity system including budget allocation as well as the technology to accommodate increase of power be initiated as matter of urgency.

·         The Department of Energy  to upgrade non/off-grid systems and also make them scalable to accommodate those who may express additional need and appropriately address energy poverty

·         The Department of Energy  to explore “ permanency” or long term approach on the non/off-grid electricity system in the rural areas

·         Strong coordination between various stakeholders especially Department of Energy, ESKOM, and the municipalities be addressed as a matter of urgency

·         Intensive public education  and mass communication with the help of SABC, GCIS, local community media especially community radio stations and municipal communications units on non/off-grid electricity system including Solar Home Systems

·         Grid electrification programme be accelerated in both Msinga and Ndwedwe Municipalities

·         Address the huge backlog in terms of general service delivery in Msinga Municipality

·         Improve customer care especially for the sickly and elderly particularly at pay points

·         Explore micro-insurance arrangements for damaged or stolen equipment

·         Department of Energy to explore jointly with the Department of Basic Education introduction of appropriate electrification of schools

·         Integration of FBE and municipalities to be consistent in their allocation of subsidy – such be done through the support of SALGA

·         A socio-economic impact study of the programme to be conducted

·         Issues below be referred to relevant departments and/or spheres of government for their consideration:

o    Lack of potable water  NOTE: Water is the main challenge and need in Msinga Municipality

    • Lack of roads
    • Need for houses

 

The DoE indicated that the non-grid electrification programme was still in its infancy but efforts will be made to accelerate it and deal with concerns raised.

The DoE indicated the non-grid solar home systems were upgraded but does not include heating

The DoE indicated it will address the issue of the working relationship between the different stakeholders

Mechanisms of communication used by the DoE to inform communities of non-grid electrification systems

The DoE, with other Department, accelerate the rollout of grid electrification and basic services in the Msinga and Ndwedwe areas

Follow up with  Eskom and service providers on service contracts and damaged/stolen equipment

Adopted

 

The following challenges emerged during the oversight visit:

 

·         Technical/operational challenges

1.     Logistics at times posed a challenge. Vehicles were not available to transport members when required or the drivers were not briefed as to what was required of them

2.     Some area the PCE conducted oversight over required special (4x4) vehicles to transport members in due to the terrain

3.     In some locations, presentation equipment was required which was not available.

4.     In some cases, experts joined the PCE on oversight trips and hence transport arrangements need to incorporate this

·         Content-related challenges

1.     In some cases, translation services may have been needed.

2.     In some cases not enough information was available on the sites being visited

3.     In the case of experts accompanying the PCE, in some cases, the experts are not always easy to find

4.     More time and resources needs to be allocated to allow Committees to conduct more detailed oversight in areas of concern

 

a)     Issues for follow-up

 

The 5th Parliament should consider following up on the following concerns that arose:

1.     In terms of Project Mthombo, the PCE needs to exercise oversight over the following. The outcome of the feasibility study into the proposed Project Mthombo refinery needs to be presented, including the next phase of the project to the Portfolio Committee on Energy

2.     The Portfolio Committee on Energy still needs to conduct oversight that the DoE ensures it accelerates the Solar Water Heater programme to ensure delivery of the 1 million SWH and also addresses issues of community involvement, quality and service contracts

3.     The DoE needs to present to the PCE on the effectiveness of the DoE regional offices, now that they are restructured.

4.     Further, the mechanisms used by the DoE to incorporate the Regional offices into National DoE office activities needs to be demonstrated to the PCE by the DoE

5.     The PCE should conduct oversight on the communities living around nuclear facilities as to, how are their concerns being addressed by the DoE, the NNR and Necsa.

6.     The DoE to address the Portfolio Committee on Energy on progress in this area and if they are using lessons learnt on some projects to assist others that are having challenges

7.     The PCE needs to conduct oversight on the restructuring of CEF, to ensure it is a viable standalone entity

8.     The PCE needs to conduct oversight on the REIPPP programme to ensure the DoE is doing all necessary to ensure take up of landfill gas as part of the programme in the upcoming windows.

9.     The PCE needs to conduct oversight on the energy challenges faced by ordinary South Africans and how these are being addressed by the DoE

10.  The DoE needs to demonstrate what it is doing, going forward in terms of energy efficiency in South Africa

11.  The PCE (in conjunction with other Portfolio Committees) needs to conduct oversight on Energy efficient buildings in South Africa that save energy

12.  The PCE needs to conduct oversight on the rollout of LPG for domestic use, especially for indigent communities

 

 

5.6.7. Study tours undertaken

 

The following study tours were undertaken:

 

Date

Places Visited

Objective

Lessons Learned

Status of Report

17–21 September 2009

Mozambique

The objectives of the hearing encompassed the following;

  • To provide and opportunity for the legislators to question experts and discuss how the growing demand for energy in an age of rising fuel prices can most effectively be met, whilst simultaneously addressing the growing dangers of climate change and ensuring that the poor have adequate access to energy.
  • The hearing would focus on how to provide electricity to poor rural communities distant from the national grid, as well as issues relating to gender and energy.
  • The focus would be on the impacts of climate change and the energy situation in the Southern Africa region. It would also look at the possibilities for providing energy to the rural poor and options for tapping into the region’s huge potential for renewable energies, such as solar, biomass, wind and hydro. In particular, focus would also be on the question of whether mini-grid systems powered by renewable energy sources could be a solution for rural electrification.
  • The hearing would be action-oriented; focusing on concrete steps that MPs can take there and then in their own parliaments.

This was the fifth International parliamentary hearing in a series of nine organized by the e-Parliament for African, Caribbean and Pacific legislators between 2008 and 2010.

 

·         There is a need for widespread awareness of gender differences when designing energy policies. Men and women have different energy needs and these differences have to be accounted for when providing a rural community with electricity. Gender audits, like the one developed in Botswana, can help identify gender gaps in energy policies and suggest ways to address them.

·         When planning rural electrification, the characteristics and the needs of communities need to be surveyed to assess whether a certain community can have grid electricity in the near future. If extending the grid is not economically feasible it needs to be determined which off-grid options - stand alone systems or mini-grids - are the most suitable.

·         The legislators unanimously agreed on the importance of building capacity within Southern Africa and stimulating the local production of renewable technologies (such as solar panels) instead of relying on expensive imports. This would not only increase access to these systems and accelerate the deployment of renewables, but would also create jobs in the region.

·         Feasibility studies on the potential for solar thermal power should be conducted, especially in the countries with the highest solar irradiation levels such as Namibia, Botswana and South Africa. Furthermore, possibilities for sharing this and other renewable sources through regional HVDC links should also be assessed.

·         A number of options were discussed regarding the financing of renewable energies in the region. As has been demonstrated in some African countries, Feed-in tariffs can help encourage the uptake of on-grid renewable energies. Given that the European-style FIT scheme may not always be suitable for off-grid rural electrification, the “Renewable Energy Premium Tariff” - that combines the key aspects of a FIT with government or international funding – was discussed as a promising way to promote mini-grids in remote areas.

·         Introducing a charge on grid-connected users, encouraging financial institutions to offer soft-loans for RE projects and offering tax breaks and lower import tariffs for RE technologies and necessary materials were other financing options discussed by MPs and experts.

 

 

 

Adopted

18 – 21 July 2010

Mozambique

To gain further understanding of the international clean energy sources scene and utilization thereof.

Need to collect information from former Committee Secretaries

Adopted

04-08 Sep 2010

Botswana

To honour an invitation by the University of Botswana to the IASTED Conference on renewable energy and gasses

Need to collect information from former Committee Secretaries

Adopted

03-10 November 2010

France

To learn about the French Energy Mix and in Particular their Nuclear Energy Programmes

·      Clean electricity from renewables, that is, solar, wind, biomass and geothermal power, deserves strong support. Government should consider investing heavily in these forms of energy in the long run in order to embrace viable energy mix.

 

·         Today, governments around the world are embracing nuclear power as fundamental to their strategies of national energy security and global environmental responsibility.

 

Adopted

27 November 2012

Century city – Aurecon Engineers (building)

City of Cape Town initiatives

Epping – St Gobain

 

Visiting energy efficiency initiatives  undertaken by Aurecon, City of Cape Town and St Gobain

·      South African businesses are undertaking energy efficiency initiatives which are beneficial to their operations.

Report compiled and to be adopted.

27 November 2012

PetroSA Synthetic Fuel Centre - UWC

To investigate and learn what the PetroSA Synthetic Fuel Centre does, which focuses on improving the efficiency of the COD process and the possibility of using alternative feed stocks such as alcohols and naphthas.

·      The establishment of a fuels innovation centre at pilot-plant scale represents a new venture as far as technology development partnerships between industry and academia in South Africa are concerned. The Committee wish to congratulate the PetroSA for its vision in funding this important enterprise, as well as the University of the Western Cape in housing on its campus a pilot plant facility that is dedicated to technological innovation in the national interest.

Report compiled and to be adopted.

01 August 2013

·         Paarden Eiland – BPSA

·         Easigas – Bellville-South

·         SA Breweries - Newlands

·         Portfolio Committee on Energy visited industrial and commercial sites as well as household supply facilities that use LPG

 

·         Address complaints that have been received about the current regulations and rules relating to Maximum Refinery Gate Price [MRGP] (LPG pricing must be at a level that encourages importation). Maximum Retail Price for residential customers must be in line with MRGP/import price;

·         Enable the industry to build import facilities; and

·         Promulgate regulated prices in line with current supply/demand situation in the country.

 

Report compiled and to be adopted.

10 August 2013

The Johannesburg Metro Municipality Landfill Gas to Energy Project;

The MTN 2MW Tri-generation Plant; and

The ABSA Towers West Energy Centre Project.

 

As part of the PAPSAEI Joint Workshop, the Members of the PAP Committee on Transport, Industry, Energy, Communication, Science and Technology as well as the Members of the South African Portfolio Committee on Energy visited three Energy projects in the Gauteng area, focusing on waste to energy and co-generation and tri-generation undertaken by SA entities.

The site visits have set a solid base for an enhanced role and contribution of PAP on continental energy programmes and the proposed PAP-SA Parliament Energy Initiative [PAPSAPEI] in advancing the African Agenda for a better life for all in Africa.

 

Report compiled and to be adopted.

The following challenges emerged during the study tours:

 

·         Technical/operational challenges

1.     Logistics at times posed a challenge. Vehicles were not available to transport members when required or the drivers were not briefed as to what was required of them

2.     Some area the PCE conducted oversight over required special (4x4) vehicles to transport members in due to the terrain

3.     In some locations, presentation equipment was required which was not available.

4.     In some cases, experts joined the PCE on oversight trips and hence transport arrangements need to incorporate this

5.     Facilities provided need to be conducive to learning

·         Content-related challenges

1.     In some cases, translation services may have been needed.

2.     In some cases not enough information was available on the sites being visited

3.     In the case of experts accompanying the PCE, in some cases, the experts are not always easy to find

4.     More time and resources needs to be allocated to allow Committees to conduct more detailed oversight in areas of concern

 

b)    Issues for follow-up

 

The 5th Parliament should consider following up on the following concerns that arose:

1.     The PCE needs to conduct oversight on the energy needs of the different genders as there are differences and further on the energy needs of rural communities to guide the policies of the DoE in these areas.

2.     The PCE also needs to conduct oversight on the rollout of grid electrification vs. non-grid electrification. That there is careful planning that has gone into it with the involvement of all stakeholders

3.     The PCE needs to conduct oversight on possible feasibility studies into greater solar projects for other African countries and the possibility of power sharing

4.     Governments around the world are embracing nuclear power and the PCE needs to conduct oversight that the DoE is tracking developments and lessons learnt to the benefit of South Africa

5.     South African businesses are taking Energy Efficiency initiatives that are beneficial to their business. The PCE needs to conduct oversight on this activity to ensure this is a sustainable trend.

6.     The PCE needs to conduct oversight on the energy research centres in South Africa, to ensure that they are not only producing beneficial research outputs but also are activity involved in training students and staff with the required skills to grow the energy expertise of South Africa

 

 

5.6.8. International work

 

5.6.8.1. General international work

The PCE has engaged with various MP’s through the Chairperson as well as other MP’s from time to time. Such includes countries such as China, US, Germany, etc. Various members participated in international conferences both within and outside the country.

5.6.8.2. Engagement with international bodies

·         The Chairperson had several engagements with various embassy representatives. These include: China, Russia, France, Germany, Netherlands, Iraq, Iran, UK, Japan, US etc.

·         The PCE also undertook study tours to Mozambique, Botswana and France

·         During the PAPSAEI workshop in August 2013, the International Energy Association (IEA) and Nepad briefed the workshop.

 

5.6.8.2.1. Joint workshop with the Pan African Parliament

The establishment of PAP-SA Parliament Energy Initiative is in line with the strategic focus of Parliament of Republic of South Africa. This initiative will provide a platform for Parliamentarians dealing with energy issues to share information on the best practices to foster oversight and legislate laws in their respective countries to attain universal access to energy and energy security.

 

The ultimate goal of this initiative is to achieve the energy security among African countries and to ensure this, partnerships among legislators is critical in order to have a common understanding of the African energy agenda. In order to achieve energy security in Africa, there is a need to partner with each other through regional energy integration, electricity power pool and sharing technical knowledge on new energy.

 

5.6.7.3. International agreements

NB: Agreements were submitted to Parliament but never tabled to the Portfolio Committee on Energy

 

a)     Challenges emerging

 

The following challenges emerged during the processing of international agreements:

 

·         Technical/operational challenges

 

One of the challenges relates to the fact that a number international agreements have been concluded by the South Africa government through DoE and were deposited into the Office of the Clerk of Papers. The PCE was however not notified. The PCE has not addressed any specific agreement that has been signed by the DoE. Furthermore the PCE has not been informed about any other government to government agreements that have implications on energy. 

 

·         Content-related challenges

 

b)    Issues for follow-up

 

The 5th Parliament should consider following up on the following concerns that arose:

 

·         More emphasis should placed on tracking these international agreements and that the Portfolio Committee on Energy be updated on these on a regular basis, at least once every term (if any during that period). These updates can either take the form of briefings or forwarding these agreements (hard or soft copies) to the Portfolio Committee on Energy for information purposes.

 

5.6.8. Statutory appointments

 

The following appointment processes were referred to the committee and the resultant statutory appointments were made:

 

Date

Type of appointment

Period of appointment

Status of Report

N/A

N/A

N/A

N/A

 

a)     Challenges emerging

 

The following challenges emerged during the statutory appointments:

 

·         Technical/operational challenges

 

During the 4th Parliament the Portfolio Committee on Energy found that it has minimum oversight over the appointment of Board members of the entities. The result is that the Portfolio Committee on Energy were unable to test whether the processes followed was done correctly or not. The Portfolio Committee on Energy is also of the view that its participation in these appointments can either be active or re-active.

 

·         Content-related challenges

 

b)    Issues for follow-up

 

The 5th Parliament should consider following up on the following concerns that arose:

 

·         That the Portfolio Committee on Energy play a more vigorous role with regard to appointments of Board members and senior managers in DoE and SOEs as guided by current statutes and procedures.

·         Regular engagements with Boards at least once every 6 months.

 

5.6.9.     Interventions

 

The following interventions were referred to and processed by the committee:

 

Title

Date referred

Current status

N/A

N/A

N/A

 

c)     Challenges emerging

 

The following challenges were experienced during the processing of interventions:

 

·         Technical/operational challenges

·         Content-related challenges

 

d)    Issues for follow-up

 

The 5th Parliament should consider following up on the following concerns that arose:

 

·          

 

 

5.6.10.Petitions

 

The following petitions were referred to and considered by the committee:

 

Title

Date referred

Current status

N/A

N/A

N/A

 

NB: The Chairperson, Hon SJ Njikelana did receive a petition from the Office of the Speaker relating to concerns/challenges raised by the community of Matatiele Local Municipality (KZN) focusing on inter alia, energy issues. The petition was however not formally referred to the committee.

 

 

e)     Challenges emerging

 

The following challenges were experienced during the processing of petitions:

 

·         Technical/operational challenges

·         Content-related challenges

 

f)      Issues for follow-up

 

The 5th Parliament should consider following up on the following concerns that arose:

 

·          

 

5.6.11. Obligations conferred on committee by legislation:

 

5.6.11.1. Budget Review Process

 

The PCE has used the BRP as the new form of oversight on the DoE as directed by the NA since 2010. Members underwent training on the process at various stages. Reports have been generated and submitted timeously to the House. The PCE did its best to work according to the 6 stages of the Budget Cycle and also engaged with the Office of the Auditor General, Department of Performance Monitoring and Evaluation, Finance and Fiscal Commission, as well as Audit and Risk Committees of the Doe and its entities.

 

According to Section 5 of the Money Bills Amendment Procedure and Related Matters Act, the National Assembly, through its committees, must annually assess the performance of each national department. The Committee must submit an annual Budgetary Review and Recommendations Report (BRRR) for each department that falls under its oversight responsibilities for tabling in the National Assembly. These should be considered by the Committee on Appropriations when it is considering and reporting on the Medium Term Budget Policy Statement (MTBPS) to the House.

 


5.6.11.2. Various recommendations from the BRR Reports.

 

Recommendation from the 2009/2010 BRRR

 

The Portfolio Committee on Energy recommended the following:

 

·         That the Department of Energy should closely monitor its expenses and carefully implement cost containment measures to avoid over spending on the allocated budget for Programme 1.

·         That Committee on Appropriations should look at ways to align reporting cycles and engage with Department of Cooperative Governance and Traditional Affairs to align and synchronise national, provincial and local spheres of government planning, budgeting and implementation of programmes. This systemic governance issue is impeding planning and implementation of programmes and should be seriously looked at and joint committee meeting between Portfolio Committee on Cooperative Government and Traditional Affairs and Portfolio Committee on Energy need to be convened to examine this matter.

·         That the Department of Energy should consider the establishment of a designated Monitoring and Evaluation Unit that will oversee the State-Owned Enterprises reporting to the department.

·         That the Department of Energy should strengthen its oversight mechanisms over its State-Owned Enterprises in order to determine if they are fulfilling their strategic mandates and identify operational inefficiencies.

 

Recommendation from the 2010/11 BRRR

 

The Portfolio Committee on Energy recommended the following:

 

·         Minister of Finance in conjunction with the Minister of Public Service and Administration (DPSA) and the Minister of Energy should address appropriate resourcing of the Department of Energy in both the forthcoming Medium Term Budget Policy Statement Processes well as Budget Vote for Energy for 2012/13. Particular reference is made to human resource, regional offices and international activities.

·         Continental activities of the Department of Energy should be expanded and intensified by the Minister of Energy. A comprehensive plan on this area should be submitted to Parliament by the end of the first quarter of 2012.

·         The Minister of Energy should address the challenges in the distribution of electricity as a matter of urgency. These include a restructuring of the electricity distribution industry, as well as reviewing the legislative and regulatory environment throughout 2012. Progress of addressing the challenges should be submitted to Parliament by the end of June 2012.

·         Progress reporting by the Minister of Energy on Solar Water Heaters should be improved. The Minister of Energy should provide Parliament with quarterly progress reports as well as provide a briefing, early in 2012 on the proposed new plan regarding the roll-out of this programme.

·         The Minister of Energy should consider establishing a special directorate that would oversee the performance of the State-Owned Enterprises. Alternatively an upgrade of any existing office in this regard should also be considered by the end of the first term of 2012.  

·         Central Energy Fund (CEF) should, as part of its restructuring process, satisfy the Portfolio Committee on Energy on how it will raise requisite capital for its future initiatives. A report thereon should be submitted to Parliament by the end of the first term of 2012.  

·         That the campaign around changing consumer behaviour on usage of energy (energy saving lifestyle), as one of the objectives of the Minister of Energy, should be intensified and strengthened as a matter of urgency.

·         Local manufacturing and beneficiation of products (focusing on, inter alia, solar photovoltaic and renewable energy technology) in the green economy should be prioritized by the Minister of Energy. Due consideration should include the consideration of urban waste as a source of energy.

·         The Renewable Energy Technology Policy and Programme should be developed in line with the conventional grid infrastructure by the Minister of Energy and progress on such be shared with Parliament by end of June 2012.

·         The Minister of Energy should ensure that electrical appliances should be labelled to indicate their energy in/efficiencies. A report thereon should be submitted by the end of June 2012 to Parliament.

·         Fiscal incentives to address Renewable Energy Technologies (RET’s) should be introduced by the Minister of Finance.

·         The Department of Science and Technology should introduce standardisation of solar PV-units to ascertain quality materials used to manufacture the units as early as is practically possible.

·         The Minister of Energy should develop regulations for handling, disposal and recycling of power batteries by the end of the third quarter of 2012.

·         Establishment of an African Technology Test Centre, in partnership with NEPAD, should be explored by the Minister of Energy in order to standardize materials used to manufacture photovoltaics and associated products. Progress thereon should be shared with Parliament by end of 2012. 

·         The Minister of Energy should emphasize education focused on nuclear technology used for nuclear energy, as part of its public education programme on energy issues. This is an effort that should be executed in collaboration with other spheres of government. The Minister of Energy should share the programme with Parliament by end of first quarter of 2012.

·         The Minister of Trade and Industry should ensure that Intellectual Property Rights on Renewable Energy Technologies be developed in a manner that it does not undermine knowledge transfer and capacity building.

·         Optimization of Muela and Cahora Bassa hydropower facilities should be favourably considered in the context of a South African Development Community Regional Energy Power Pooling Programme by the Minister of Energy. The outcome of such consideration should be integrated into the review of Integrated Resource Plan2010 during 2012. 

·         The Minister of Energy, in conjunction with the Minister of Science and Technology, should review South Africa’s nuclear disaster preparedness – a comprehensive, inter-sectoral and collaborative approach which should include municipalities and provincial governments should be embarked on by 2012.

·         The Minister of Energy should ensure functions and competencies on nuclear and nuclear-related programmes and activities be rationalized and harmonized amongst various Ministers and their respective government departments and entities, e.g. Health, Science & Technology, Mineral Resources, Water and Environmental Affairs. A report thereon should be submitted by October 2012 to Parliament.

·         Minister of Energy should address the need for a comprehensive radioactive waste management system through public private partnerships and include universities and similar institutions. A report thereon to be submitted by the end of June 2012 to Parliament.

·         Minister of Energy should, through the National Nuclear Regulator, explore creative ways and means of strengthening Africa’s regulatory capacity through the Forum of Nuclear Regulatory Bodies in Africa (FNRBA).  A plan thereof should be shared with Parliament by September 2012.

·         Development Bank of Southern Africa (DBSA) should, in conjunction with other partners in the Darling Wind Energy Project, submit a report regarding challenges on the project to Parliament by the end of the fourth term 2011.

·         Minister of Finance should submit a report to the Portfolio Committee on Energy about Section 54 challenges regarding State Owned Enterprizes (SOEs) roles and status in the Renewable Energy Feed-In Tariff (REFIT) or similar initiatives. Such report should indicate whether there are any alternatives or likely solutions on such challenges. Such report should be done within the first term of 2012.

·         Central Energy Fund (CEF) should compile a proposal/plan and brief the Portfolio Committee on Energy on its strategy regarding its decisions to embark on projects and how it will conduct feasibility studies for such projects. Such must include future strategy on pioneer projects.

·         Minister of Energy in partnership with the Minister of Higher Education and Training should arrange an Indaba on Skills Development in the Energy Sector with the aim of producing a strategy and programme on skills development in the energy sector by the third term of 2012. Such should be done in partnership with the business sector.

·         A Budget Review Facilitation Unit or dedicated personnel, located in the Office of the Speaker to assist all parliamentary committees in the budget review processes as well as monitoring and evaluating the budget review processes, be established as a unit and personnel be appointed as a matter of urgency

·         Minister of Performance Monitoring and Evaluation should ensure presentation of its plan regarding the Department of Energy for 2012-2013 financial year (or MTEF whichever is applicable) and regular briefings on its assessment of the Department of Energy on a quarterly basis to the Portfolio Committee on Energy as from the Phase 1 of the forthcoming Budget Review Cycle (i.e. November 2011)

·         Minister of Finance should consider allocating additional resources for the forthcoming Budget Vote for the Department of Energy for the Clean Energy Programme in order to allow for implementation of renewable energy projects.

·         The Department of Energy should report to the Parliament on the recruitment of appropriate personnel for the Clean Energy Programme. The latter report should be submitted to the Portfolio Committee on Energy every six months for the three coming years.

·         The Minister of Energy should examine the adequacy of the Strategic Fuel Fund’s (SFF)’s funding received from the fiscus. Such effort should include a comprehensive review of fuel stocks reserves which are currently 21 days. A report should be submitted to the Parliament by end of the first term of 2012.

·         Minister of Energy should ensure that further engagements be undertaken with the Mozambican authorities to explore and scale up hydro electricity opportunities to supply South Africa with additional renewable energy.

·         Establishment of the UN-sponsored observatory should be explored jointly by the Minister for the National Planning Commission (NPC), Minister of Finance and Minister for Performance Monitoring and Evaluation (DPME) in partnership with the UN Habitat.

·         Minister of Energy should embark on a comprehensive restructuring programme for both Central Energy Fund and PetroSA, specifically with the aim of positioning them as strategic national entities in the energy sector. .A report thereof should be submitted by conclusion of the Budget Review Process of 2011/2012 i.e. October 2012.

·         The Minister of Energy should submit a brief plan on how the Department of Energy intends to improve its strategic coherence in programmes where it is the lead department, to the Committee by the end of the second term of 2012.

 

Recommendation from the 2011/12 BRRR

 

Having assessed the performance of the Department of Energy, the Portfolio Committee on Energy recommended that the Minister of Energy should ensure the following:

 

·         The Department of Energy expedites the conclusion of outstanding policy strategies and programmes in order to position itself in the forefront of energy policy and planning. These strategies and programmes should include the following:

o    Strategic Fuel Policy,

o    Energy Efficiency Strategy,

o    Approach to Distributions Asset Management (ADAM),

o    Restructuring of the electricity industry,

o    Electricity Pricing Policy,

o    Bio-Fuels Policy,

o    Replacement of Regional Electricity Distributors (REDs),

o    Free Basic Alternative Energy (FBEA),

o    Cost Recovery Mechanism for Cleaner Fuels,

o    Review of the Integrated Resource Plan (IRP),

o    Review of the Renewable Energy White Paper,

o    Integrated Energy Plan, and

o    Household Energy strategy.

·         The Department of Energy mobilises at least 30 percent of the needed funding for the infrastructure backlog in conjunction with the National Treasury, by the end of the 2012/13 financial year.

·         The Department of Energy ensures that the restructuring process of the Central Energy Fund is concluded within the 2012/13 financial year.

·         The Department of Energy submits an update on how it has addressed recommendations of the Budgetary Review and Recommendations report of both 2010 and 2011 by the end of the 2012 calendar year.

·         The Department of Energy submits a report to the Committee relating to the Internal Audit Control strategies and plans on how to achieve clean audits for both the Department of Energy and its entities.

·         The Department of Energy submits a strategy and plan on its role and contribution in responding to climate change and based COP 17 resolutions. This strategy/plan should be submitted within three months after the adoption of this Report by the House.

·         The Department of Energy mobilises for skills development in the energy sector by ensuring a definite review and rollout of non-grid electrification policy and programmes within the 2012/13 financial year.

·         The Department of Energy extends the Household Energy Strategy to include efficiency and access to household appliances.

·         The Department of Energy and its entities develops a strategy on synergy between the itself and its entities within 2012/13 financial year. Such a strategy should include monitoring and evaluation of funds transferred to entities including municipalities.

·         The Department of Energy formulates policy and develops a strategy on energy data management especially collection including measurement of use of Renewable Energy reporting in order to track progress. This should be done within the 2012/13 financial year.

·         The Department of Energy addresses outstanding issues with the Independent Power Producers (IPPs) that have received Renewable Energy Independent Power Producer Programme (REIPPP) contracts by the end of the calendar year.

·         The Department of Energy develops skills development programmes in the energy sector especially the liquid fuels sector and the electricity sector within the 2012/13 financial year.

·         The Department of Energy develops a plan on smart-grid policy and strategy is developed within the 2012/13 financial year.

·         The Department of Energy ensures corporate services especially skills development, legal services and monitoring and evaluation have adopted plans by the end of the 2012 calendar year.

·         The Department of Energy develops a plan relating to Public Participation Programme through partnerships, especially with municipalities to be adopted within this financial year.

·         The Department of Energy ensures that an independent verification mechanism is in place to determine the quality of liquid fuels within this financial year.

·         The Department of Energy ensures the readiness of South African Nuclear Energy Corporation and the National Nuclear Regulator for the New Nuclear Build Programme is visibly geared up within this financial year.

·         The Department of Energy ensures the full utilization of the National Multi-Purpose Pipeline (NMPP) for various liquid fuel products by end of current financial year.

·         The South African Nuclear Corporation works out a turnaround strategy to avert further retrenchments.

·         The Department of Energy formulates an exit strategy for the African Exploration and Financing Corporation by the end of the year, including compensation for its establishment by the Central Energy Fund within the 2012/13 financial year.

·         The Department of Energy facilitates financing mechanisms for Clean Development Mechanism by the end of the financial year.

·         The Department of Energy submits a report on the Ogies Mines environment challenges within the 2012/13 financial year.

·         The Department of Energy builds internal capacity to generate policies and legislation as a priority by end of the 2012/13 financial year

·         The Department of Energy formulates a strategy and develops a plan on how to maintain targets on universal access on electricity whilst shifting deadline from 2014 to 2025. These strategy and plan to be finalized before the end of the 2012/13 financial year.

·         The Department of Energy develops a funding and implementation plan in order to reduce the electricity distribution infrastructure maintenance backlog of R27.4 billion to R15 billion by 2014. This plan to include the following:

o    Funding and implementation plan in place by March 2011,

o    Report detailing a map of distribution asset status for 50% of all Municipalities by 2012/13

o    Initiate interventions, monitor rehabilitation projects and reduce backlog by R8bn in 2012/13

·         The Department of Energy develops a plan that will ensure that household access to electricity would be 92 per cent by 2014. This plan should be completed before end of the 2012/13 financial year.

·         The Department of Energy formulates a strategy and develops a plan to regain momentum on solar water heating installation programme schedule. This strategy and plan should be completed before end of the 2012/13 financial year

·         The Department of Energy develops a plan on how reporting on demand-side savings will be improved. This plan should be finalized before end of the 2012/13 financial year

·         The Department of Energy formulates a strategy and develops a plan on how better mapping and targeting of indigent households needed for Free Basic Electricity, Compact Fluorescent Light Bulbs and solar geysers, for Inclined Block Tariffs.

·         The Department of Energy presents an intervention strategy and plan which  is required on Upington Solar Park Project and to clear obstacles to enable the rapid realisation of the Renewable Energy Independent Power Producer Programme (REIPPP) construction by end of this calendar year

·         The Department of Energy formulates an intervention strategy and plan how to expedite the SARi programme, by end of the current financial year

·         The Department of Energy presents an intervention strategy and develops a plan on how 12 per cent energy efficiency  improvement target by 2015 will be achieved

·         The Department of Energy submits, during the 2012/13 financial year, a report on the New Nuclear Build Programme. This report should articulate the following:

o    Funding model of, the New Nuclear Build Programme,

o    Eskom’s role, and

o    The Department’s role.

·         The Department of Energy ensures that programme and requisite resource mobilization plans are in place before end of the 2012 calendar year.

 

Recommendation from the 2012/13 BRRR

 

The Portfolio Committee on Energy recommended that the Minister of Energy should address the following:

 

·         The Grand Inga Hydro Power Project be handled as one of the priority projects of the Department and an update be presented to the Portfolio Committee on Energy by the 3rd term of 2014-15.

·         Energy efficiency be addressed by empowering SANEDI in engaging in energy efficiency programmes. The strategy and plan thereof to be presented to the Portfolio Committee on Energy by the 3rd term of 2014-15.

·         The rate of delivery of Integrated Energy Centres be increased and the Department builds at least three in the current financial year, with special focus on rural areas.

·         Skills development in the energy sector, in partnership with the relevant government entities and higher education institutions be intensified and report back to the Portfolio Committee on Energy by the end of the 3rd term of 2014-15.

·         Not only co-ordination of research, within the entities it oversees, should be enhanced but assistance for the entities be increased to ensure full value chain to commercialization of research and development projects is maximised. Such enhanced support should be linked improved allocation of funds. The strategy and plan thereof to be presented to the Portfolio Committee on Energy by end of the 4th term of 2014-15.

·         Robust oversight over Energy Efficient Demand Side Management Programme Municipalities and Eskom is intensified. The Minister to update the Portfolio Committee on Energy by the 3rd term of 2014-15.

·         Transformation of the gas industry is firmly in place by concluding the refinement of policy on gas and substantial investments are mobilised as well as encouraging new entrants into the gas industry. The Minister to present the update on strategic interventions by the 3rd term of 2014-15.

·         Ensure replication of the Kuyasa CDM project throughout SA on a mass scale. The Minister is to update the Portfolio Committee on Energy by the 4th term of 2014-15.

·         In conjunction with other sectors of Government to ensure all future designs, retrofitting and construction of government property are energy and resource efficient and such be extended to all built environment as a matter of urgency. The Minister of Energy, in conjunction with the Minister of Public Works to, prepare a plan to be presented to the Portfolio Committee on Energy by the 2nd term of 2014-15.

·         In terms of the Renewable Energy Independent Power Producers Procurement Programme, the Minister of Energy to:

o    Urgently address challenges of the complex and expensive bidding process, job creation, skills transfer in partnership with other departments;

o    Reverse the lack of initiatives to take advantage of the emerging opportunities and ensure the establishment of a local manufacturing renewable energy industry to achieve the 60 percent target on local content;

o    To closely monitor skills transfer to emerging businesses;

o    To ensure the 2.1 percent of project costs that are earmarked for socio-economic development are strictly adhered to – such must include clear guidelines on how this money should be spent;

o    Develop mechanisms to ensure South African bidders have a higher number of local participants during subsequent phases beyond Windows 1,2 and 3 of the REIPPPP;

o    To mobilize provincial Financial Development Institutions to enhance their contribution on the renewable energy programmes by the 4th term of 2014-15.

·         The Minister should include updates on the above mentioned (a-f), to the Portfolio Committee on Energy, when updating the committee on the Integrated Resource Plan.

·         In terms of “exploring solutions to challenges on financing and certification of locally produced renewable products”, the Minister of Energy to:

o    Engage with the Banking Association of SA (BASA), the Industrial Development Corporation (IDC) and other financing entities as well as the SABS to explore solutions to problems faced by the renewable energy sector.

o    Engage with the National Treasury and the Department of Cooperative Governance and Traditional Affairs (COGTA) to explore ways of resolving the issue of local government authorities being prevented from purchasing energy from IPP’s.

·         Formulate a compensation strategy for the establishment of the African Mining Exploration and Financing Corporation by the Central Energy Fund through conversion of the loans into equity.

·         In partnership with the Minister of transport develop a green transport strategy and programme as part of the Green Energy Strategy by the 3rd term of 2014-15.

·         Institutionalise research into fossil fuels and present the plan to the Committee by 4th term of 2014-15

·         Explore mechanisms in addressing enhanced funding to SANEDI

·         Explore mechanisms to enhance CEF’s manufacturing capacity in the energy sector

·         Update the Committee on the following investigations (once they are finalised);

o    Allegations that State employees are involved in the procurement processes

o    Investigations relating to employees allegedly having interest and/or performing remunerative work without approval.

o    Investigation relating to irregular expenditure in supply chain management and one relating to employee costs.

·         Remove the reference to REDS in the ADAM policy and programme as well as replace it by an appropriate policy directive

·         Intensify efforts on non-grid electrification, especially in rural areas and report by 3rd term of 2014-15.

·         The Minister should, once again, ensure that staffing is prioritised - particular reference is made on legislative capacity as well as personnel for regional offices, international relations and oversight unit on entities.

·         Appointment of permanent Chief Financial Officers at entities must be urgently addressed within six months from submission of this report.

·         Ensure that when determining the rate that municipalities charge their customers for electricity, NERSA also meticulously assesses the components of the rate and regularly audit the actual expenditure of municipalities.

·         With regard to establishment of “end user forums” ensure that NERSA, in conjunction with South African Local Government Association and the Department of Energy to continue establish appropriate mechanisms to roll out this programme once the relevant legislation is in place.

·         Ensure that NECSA intensify its transformation and present an update to the Portfolio Committee on Energy by the 3rd term 20140-15

·         With regard to Pelchem, ensure that NECSA must make every endeavour to ensure it is a financially viable entity and strong focus on investing in the fluorspar industry by the 3rd term 20140-15.

·         Ensure that the NNR intensify its public awareness campaigns as well as efforts to demystify nuclear energy.

·         Ensure NNR makes pay more attention on “ownerless legacy sites” especially the mine dumps with radioactive waste with the assistance of the Department of Energy and other relevant sectors of government. The Minister should update the Committee by the 3rd term of 2014-15.

·         Enhance the role of SANEDI on the “Working for Energy Programme”.  Update the Committee on the above three points by the 4th term of 2014-15.

·         Ensure that research and development projects that are developed in SANEDI are commercialised within the shortest possible time frames whenever possible. Update the Committee on the above three points by the 4th term of 2014-15.

·         Ensure that funding for research and development, not only in renewable energy technology but also on the development of new products in the energy sector be enhanced including working with SANEDI, universities and the renewable energy industry to minimize the critical research gap that requires funding. Update the Committee on the above three points by the 4th term of 2014-15.

·         Ensure there is proper management of procurement at some of the entities of CEF. The Minister is to regularly update the Committee on this matter.

 

5.6.12. Role and contribution of the PCE on areas of non-achievement by the DoE

The PCE has consistently identified areas, tasks and programmes that the DoE was under achieving on. Such was brought to the attention of the Department during meetings or through the Budget Review Process. Some issues of non achievement have not been picked up as a tracking and monitoring model has not been developed to allow this. 

5.6.13. Summary of outstanding issues

Below is a list of ALL issues that were resolved in the regular meetings of the PCE:

 

5.6.13.1. Outstanding issues from the minutes of the PCE

 

Date of meeting

Agenda

Resolutions

11 February 2014

  • Briefing by the Department of Energy on its 3rd Quarter Performance Report for 2013/14
  • Consideration and adoption of minutes and reports

 

o    The Committee requested that the DoE should brief the PCE on campaigns and events.

o    The Department of Energy should forward their MPAT report to the committee within two weeks of this meeting.

o    The committee requested that the DoE should focus on its consultant reduction plan and present it to the committee (the Committee will identify a date).

o    The DoE should negotiate with National Treasury for funds for training.

o    The Committee further requested that the DoE brief the committee on the impact of the Regulatory Accounting System (RAS) as some concerns were raised.

 

Tuesday 15 October 2013

·         Briefing by the NERSA on their Annual Report of 2012/13

·          

·         The committee will schedule a follow-up meeting with NERSA to address the BHP Billiton contract.

·         NERSA should forward more detailed information on small scale embedded generation to the Committee

·         NERSA should provide the Committee with information on the research it conducted on alternative energy sources.

 

Wednesday 09 October 2013

 

·         Briefing by the Department of Energy on their Annual Reports of 2012/13

 

·         ESKOM should forward the list of all stakeholders who form part of the committee on nuclear.

·         The DoE should forward the new Household Electrification Strategy to the Committee.

 

Tuesday 20 August2013

Briefing by the Department of Energy on

  • the restructuring of the electricity sector
  • the Integrated Energy Plan (IEP)
  • Consideration and adoption of minutes

 

  • The Chairperson undertook to follow-up with the State Law Advisors the status/latest developments regarding the ERA and NERA Bills.

 

Tuesday 13 August 2013

  • Briefing by the Department of Energy on the bio-fuels and biomass programmes in South Africa
  • Update by the Department of Energy on the transformation of the gas (LPG/LNG) industry and related matters

 

  • The Department of Energy must forward a detailed report on the Saldana tender to the committee, within four (4) weeks to the committee.

 

Tuesday 06 August 2013

Briefing by the Department of Energy on:

  • Pricing on liquid fuels
  • Electricity pricing

 

 

  • Further engagements on the Fuel prices need to be scheduled, due its complexities
  • The PCE requested the Department to develop a household energy policy

Wednesday 24 July 2013

Briefing on the liquid fuels sector by the Department of Energy, wholesalers and retailers

 

  • There is a need for further engagement on the downstream liquid fuels sector – the committee will explore the possibility of conducting public hearings.

 

Tuesday 18 June 2013

  • Update by the Department of Energy on the Integrated National Energy Plan, Free Basic Electricity and Free Basic Alternative Energy
  • Briefing by the National Treasury on Free Basic Electricity and Free basic Alternative Energy
  • Briefing by the Financial and Fiscal Commission on Free Basic Electricity and Free basic Alternative Energy
  • Consideration and adoption of outstanding minutes

 

  • The Department of Energy must brief the committee during the fourth term of 2013 on the New Master Plan.
  • At the next engagement on INEP, FBE and FBAE the SALGA and COGTA (with reference to MISA) must share their experiences on the afore-mentioned.

 

Tuesday 11 June 2013

09:00 – 11: 00               Briefing by the ESKOM and Nissan SA on the three (3) year research project on the Nissan Leaf electronic vehicle

 

11:00 – 12:50                Briefing by the Industrial Development Corporation (IDC) and the SA Calcium Carbide (SACC) on the co-generation project in Newcastle.

 

12:50 – 13:00                Consideration and adoption of outstanding minutes

 

 

  • The committee must explore the possibility of scheduling public hearings on co-generation during the 3rd term of 2013.
  • The consideration and adoption of minutes was deferred to the next meeting.

 

Wednesday, 27 February 2013

  • Briefing by the Department of Energy on the Independent System and Market Operator Bill [B9 – 2012]

 

  • The committee resolved that the Department of Energy consider convening another energy summit.

 

Tuesday 26 February 2013

  • Review of the performance of the Portfolio Committee on Energy for 2012
  • Deliberations on the ISMO Bill [B9 – 2013]

 

  • Members noted the report on the PC on Energy’s performance for 2012.
  • Members resolved that the committee must be updated on a quarterly basis regarding the committee budget.
  • Members resolved that the Department of Energy must brief the committee in the near future on its role in some of the Strategic Infrastructure Programmes (SIPs)

 

Tuesday 19 February 2013

  • Update by the Department of Energy (DoE) on its legislative programme
  • Consideration and adoption of the Impact study report on the possible transfer of the transmission sector to the ISMO
  • Overview of the performance of the PC on Energy during 2012
  • Consideration and adoption of outstanding minutes

The Chairperson requested that the Department articulate precise reasons for the delay, for each and every bill, and also the impact of these delays, and to forward this report to the committee.

 

Friday 01 February 2013

Briefing by the Task Team on the further due diligence on the possible transfer of the transmission sector to the ISMO

 

  • That the Task Team forwards the Barclays/ABSA report to the committee.
  • That the more detailed report on the due diligence be forwarded to the committee.

 

Wednesday, 30 January 2013

Briefing by the Department of Energy on:

  • Update of Free Basic Alternative Electricity (FBAE)
  • Update of the Bio-fuels strategy

 

  • The Department of Energy should forward the list of municipalities which do not have Indigent Registers to the committee within a month.

 

Tuesday, 23 October 2012

- Consideration and adoption of the Budgetary Review and Recommendations Report (BRRR) 2012

- Consideration and adoption of minutes

 

  • Members must forward their proposed recommendations to the Committee Secretary before the end of business on Tuesday 23 October 2012.
  • At the next briefing by the Department of Energy on the SA Renewable Initiative (SARi), National Treasury should form part of the meeting.

 

Friday, 17 August 2012

  • Briefing by the Department of Energy on the Liquefied Petroleum Gas (LPG) Industry

 

  • Members are encourage to visit  the pilot projects in Gauteng.
  • The DoE should forward a summary of the status quo across the sector.
  • The committee would explore the possibility of conducting public hearings on the LPG sector once the Roadmap on the sector is finalised by the DoE.

 

Tuesday, 07 August 2012

  • Report back from the DoE on the scenario building exercise and further due diligence on the future of the transmission sector vis-à-vis  ISMO Bill.
  • Consideration and adoption of minutes

 

With regard to the scenario building and further due diligence on the ISMO Bill, the committee resolved as follows:

·         That the Task Team update the committee within one (1) month of this meeting on the scenario building exercise of the ISMO Bill.

·         The Task Team updates the committee within two (2) months of this meeting on the further due diligence on the ISMO Bill.

·         That the Task Team on a two (2) weekly basis updates the Chairperson on the latest developments regarding the above-mentioned issues.

 

Tuesday, 17 April 2012

·         Briefing by Exxaro and Tata on their clean-energy joint venture, namely Cennergi;

·         Briefing by the Department of Energy on the status of the Solar Water Heater (SWH) programme

 

  • The committee resolved that Cennergi must forward more information on their five (5) projects currently underway.
  • The committee need to schedule a meeting during the Third term with the various Sector Education and Training Authorities (SETAs) applicable to

 

Tuesday, 06 March 2012

  • Briefing by the Department of Energy on the Cleaner Fuels 2 Programme:
    • Status of the promulgation of specifications for refineries,
    • Progress on drafting the Cost Recovery Mechanism,
    • Comparative Analysis between Euro 5 specifications and South African specifications as well as implications thereof.
  • Briefing by the Department of Energy on the Independent Systems & Market Operator (ISMO) Bill

 

  • Once finalised the Department should forward the KPMG report on the state of refineries to the Portfolio Committee on Energy. 
  • Members resolved that the Department should brief the committee on comparing other countries’ approaches to cleaner fuels,  to the approach taken by South Africa.

 

Tuesday, 28 February 2012

  • Report of the Portfolio Committee on Energy attending the, World Future Council Workshop on Renewable Energy Policies for Sustainable African Development, in Oboadaka, Ghana.
  • Consideration and adoption of outstanding minutes

 

  • The labelling of appliances is also and important issue and the Committee should invite the SABS on the quality and the standards of the appliances
  • The Members agreed that they should look at and research on other areas where there are hybrids of energy or areas using solar, bio-mass, wind energy etc. The South African National Energy Development Institute (SANEDI) as a researching institute ought to look into areas of alternative energy source.

 

Friday, 17 February 2012

·         Briefing by the Department of Energy on the outcomes of COP 17

·         Briefing by the World Wildlife Fund for Nature on the Outcomes of COP 17

 

  • The Department should provide the committee with more information relating to CDM projects.
  • The Department should forward the Energy Efficiency Strategy to the committee once finalised in May 2012.

 

 

Tuesday, 14 February 2012

·         Briefing by the Department of Energy on its international programmes including power pooling and energy trade in SADC

 

  • The Department of Energy should forward more information on energy efficiency initiatives in Mexico to the committee.
  • The Committee need a schedule a meeting with the Minister of Energy to brief the committee on the outcomes of the Africa Energy Ministers Conference held in September 2011.
  • The Department should invite the committee to the EU Africa Energy conference scheduled for May 2012 (date to be confirmed).

 

Tuesday, 15 November 2011

o    Briefing by the Department of Energy on their:

o    2nd Quarter Performance Report for 2011/12

o    Public Participation Programme

o    Consideration and adoption of minutes

 

o    The Department should forward the list of municipalities that fail to comply to the committee.

o    Members noted that the new Department of Energy, after the split from the former Department of Minerals and Energy is struggling with the current funding allocation and it is expected that the new Department is to operate effectively and efficiently. The Committee resolved that it must endeavour to find solutions and address the funding shortcomings of the Department.

o    The Committee resolved that the DoE must brief the committee on the outcome of the African Energy Minister’s Conference of 2011 during 2012.

o    The committee further resolved that in future the Department should include more details on expenditure projections and the reports also need to contain the reasons as to why transfers was not processed.

o    The Department must forward the reports on the Eskom issues and the quality of water to the committee. 

o    The committee reiterated the importance of public participation and highlighted that quarterly reports on the progress of the programme should be made to the Committee.

 

Friday, 11 November 2011

  • Briefings by the Departments of Energy, Labour and Women, Children and Persons with Disabilities, respectively on:
  • Progress reports (updates) and future plans on mainstreaming of gender, youth and persons with disabilities relating to energy

·         Briefing by Ms K Omari (Sustainable Development Programme Manager: Heinrich Boell Stiftung Foundation)  on gender mainstreaming in the energy sector, with a focus on the Botswana experience

 

·         The members resolved that the “Learner focus week” of the Department of Energy need to be reviewed as it only focuses on a few individuals.

  • Members resolved that it will be very helpful in the future that Departments include statistics on the type of jobs occupied by women and persons with disabilities from both Departments and state owned entities like PertoSA. These statistics will assist Parliament to monitor how those departments and entities address these issues.

·         Members further resolved that the MoUs signed between the DWCPD and the various departments be presented and made available to the applicable parliamentary committees.

·         Members encouraged the DWCPD to ensure that all processes and programmes are driven progressively and vigorously and that all relevant stakeholders are onboard (buy-in), and that proper coordination takes place.

 

 

Tuesday, 01 November 2011

  1. Briefing by the National Energy Corporation of SA (NECSA) on their Annual Report 2010/11

 

·         Necsa should forward the 31 innovation disclosures to the committee within 2 weeks.

·         The committee resolved that Necsa should forward their marketing campaign on nuclear awareness to the committee within 2 weeks. 

 

Tuesday, 25 October 2011

  1. Briefing by the Central Energy Fund and PetroSA on their Annual Report 2010/11, respectively

 

·         PetroSA should forward their list of products to the committee.

·         PetroSA should forward their list of subsidiaries to the committee.

·          

Tuesday, 18 October 2011

Briefing by the National Nuclear Regulator and the National Energy Regulator of SA on their Annual Report 2010/11

  •  

o    The Madibeng Local Municipality’s nuclear disaster preparedness needs to be addressed. The committee needs to identify a strategy on how it is going to address this issue.

o    The committee needs to address the NNR’s budget allocation, which has been decreasing over the past two years.

o    The committee resolved that a follow-up meeting be scheduled during the 1st Term of 2012 with the NERSA on the price path of electricity.

·          

Friday, 14 October 2011

  • Briefing by the Department of Energy on their Annual Report  and financial statements 2010/11

·         The committee resolved that a workshop in terms of pricing be scheduled, to determine what the correct methodology would be.

  • The Department should forward a copy of their Energy Efficiency Awareness Campaign to the committee.
  • The Department should forward their full Human Resource Plan to the committee.
  • The Committee resolved that a “Mini-Indaba” on the backlog of energy infrastructure, be scheduled during 2012.

·          

Wednesday, 13 October 2011

  • Identification of recommendations in oversight visit report undertaken during 2010/11 to be included in the Budgetary Review and Recommendations Report
  • Training by the Auditor-General of SA on the analysis of the Annual Reports of departments

 

·         The committee resolved to continue with the report on the committee oversight visit recommendations, but that the Committee Secretary needs to obtain the necessary reports in order for the committee to consider those recommendations to form part of the 2011 BRRR.

·         A follow-up meeting need to be rescheduled for the committee to consider the other oversight visit recommendations.

 

Wednesday, 12 October 2011

Briefing by the Department of Performance,Monitoring and Evaluation on the performance of the Department of Energy as reported in their annual report 2010/11 focussing on service delivery;

 

·         The Department of Performance Monitoring & Evaluation should forward the performance & progress reports of the Department of Energy to the committee on a quarterly basis.

 

Wednesday, 21 September 2011

Briefing by the Financial and Fiscal Commission on their recommendations relating to energy

  • Recommendations emanating from the meeting should be consolidated and a consensus reached at a later stage.
  • Joint sessions with the FFC and other Parliamentary Committees need to be scheduled.

 

Tuesday, 13 September 2011

Briefing by the Department of Energy on the following:

  • 3rd and 4th Quarterly Performance Report of 2010/11
  • 1st Quarter Performance Report 2011/12.

 

·         The committee resolved that quarterly performance report briefings by the Department will be scheduled on a quarterly basis by the Portfolio Committee on Energy.

·         There is a need for the committee to schedule a workshop on the Budgetary Review and Recommendations Report processes.

 

Tuesday, 13 October 2009

Briefing by the Airports Company of South Africa (ACSA) and the Department of Energy on the Jet Fuel Shortage and the state of readiness for the 2010 FIFA Soccer World Cup

  • There should be cooperation between all stakeholders involved to ensure a successful World Cup in particular Transnet. The Committees would have a follow up meeting with the Portfolio Committee on Public Enterprise in facilitating the required intervention.
  • Both ACSA and DOE should address the fuel supply challenges and it not only affects OR Tambo but remains a challenge in all airports. Therefore focus should be directed to all airports.
  • ACSA should engage Transnet to ensure they have a clear undertaking from Transnet for the 76 additional Rail Tank Carts required for 2010 World Cup.
  • ACSA would brief both Committees on the final plans in preparation of the World Cup early next year.
  • There was a need for a long term intervention that would include a long term role of government in the fuel industry.
  • The Committees would facilitate the reporting mechanism of the established task team to report to Parliament on its work.

 

Wednesday, 10 June 2009

Briefing by the Department of Minerals and Energy on the Strategic Plan and               Budget Vote 28 of 2009/10

 

The meeting resolved that the Department would brief the Committee in a workshop on a number of these issues and others.

 

 

Additional items outstanding

The following key issues are outstanding from the committee’s activities during the 4th Parliament:

 

Issue(s)

Responsibility

Briefing on progress on Medupi, Kusile and Ingula power stations by ESKOM, organised labour and business community involved in the 3 power stations

 

DoE, ESKOM and NUMSA

Shale gas

Mineral Resources, Energy, Water and Environmental Affairs, Trade & Industry, Science & Technology

Legislation to be tabled to Parliament

PCE/DoE

Update by the DoE, NNR on the IAEA report on SA readiness regarding NNBP

 

DoE and NNR

audit report on oil refineries  as well as the revised 20-year security plan liquid fuels;

DoE

Public hearings: Liquid Fuels downstream sector

DoE

Briefing  on power programmes in the SADC and Africa

 

DoE, NEPAD and SADC (Executive and PF)

Biofuels Strategy

 

DoE/DAFF

Colloquim: Green Economy accord in the context of industrialization

DoE/DTI/EDD/IDC

Progress reviewal of Liquid Fuels Charter in keeping with the BBBEE Codes of Good Practice

 

DoE

Training

·         Municipal revenues, vis-a-vis electricity, FBE and FBAE

·         Rural energy – concept, practice, lessons learnt and case studies

·         Exploring household energy options

·         Energy poverty and electrification

 

PCE

Training

·         Carbon tax – overview and implications

·         Policy alignment and the National Development Plan on low carbon economy and energy

·         Integrated Energy Plan

·         MYPD – concept and practice

 

PCE

There various pieces of legislation and policy documents that are still outstanding and these need to be presented to the PCE for deliberation and comment. These include, among others, the Electricity Regulation Act and National Energy Regulator Act, the Biofuels Strategy and the Household Energy Strategy. The DoE has a new draft IEP and IRP and these needs to be finalized.

 

DoE

The Independent System Market Operator (ISMO) Bill was deliberated in the Committee and submitted to the House for Adoption. This was not adopted in the 4th Parliament and 5th Parliament needs to follow up on this.

 

PCE

From the Energy Stakeholder Meeting on the upstream sector, it emerged that policy challenges that need to be addressed as clear policy directives are needed and the DoE is to formulate a plan on identifying the challenges and a mechanism to address them.

 

DoE

The REIPPP Programme is a success story for the South Africa Energy Sector. However it is still in its infancy stages as construction on most projects have just begun. The 5th Parliament needs to monitor the successes and challenges of this programme and ensure the DoE builds on this. This includes the area of localization and skills transfer.

 

PCE

The transformation of the petroleum industry and compliance to the Liquid Fuels Charter is another area that requires some attention as progress has been less than satisfactory.

 

DoE

The transformation of the gas industry is another area needing attention and substantial investments are needed to encourage new entrants into the gas industry.

 

DoE

With reference to Indigent communities, the aspect of access to clean energy is critical. Areas needing attention here is access to Free Basic Services including energy. This includes access to electricity, be it grid or non-grid. Solar water heating and clean forms of heating e.g. LPG. In this regard price and accessibility are important. So too is safety aspects in terms of handling these energy sources. There has been progress here but the progress made by the DoE in this regard needs to be monitored.

 

PCE

The DoE is to present their Biofuels strategy to the PCE. There are concerns about food security and empowerment of small farmers and the issue of management of subsidies to this industry.

 

DoE

In terms of the solar water heater (SWH) programme, to date, over 350 000 units of the envisaged 1 million units have been rollout. There is still a long way to go as issues local content, the involvement of all spheres of government, maintenance of units are some of the challenges arising. The 5th Parliament also needs to assess with the DoE mechanisms to accelerate rollout of the units.

 

PCE

Energy research programmes at universities including SANEDI’s “working for energy programme” should be monitored and co-ordinated, especially in the energy sector. The maturity of some of these programme through to commercialization is also important and so too the training aspect. The 5th Parliament needs to monitor this space to ensure at least some of this research work results in commercial benefit for South Africa.

 

PCE

The National Electrification programme is one of the biggest programmes of the DoE. Currently 85% of South African homes have electricity. The 5th Parliament needs to monitor that universal access to electricity is achieved, be it via grid or non-grid electrification programmes. The two need to complement each other and all spheres of government need to work together in this regard. Issues of distribution (especially the infrastructure) need to be addressed. This includes funding and the skills deficit and a replacement for Regional Electricity Distributors needs to be found.

 

PCE/DoE

The National Electrification programme is one of the biggest programmes of the DoE. Currently 85% of South African homes have electricity. The 5th Parliament needs to monitor that universal access to electricity is achieved, be it via grid or non-grid electrification programmes. The

DoE/PCE

Energy Efficiency initiatives needs to be monitored including meeting the 12% energy efficiency improvement target by 2015. Further, EE programmes and initiatives are fragmented and plans to address this needs to be explored. In this regard, the establishment of an Energy Efficiency champion for South Africa is needed that monitors and co-ordinates all activities in this area.

DoE/PCE

The involvement of Women, Youth and People with Disabilities in the Energy Sector has to be monitored on a regular basis by the 5th Parliament. Numerous opportunities are being created in the REIPPP and related programmes and it is important that this sector of the population is also empowered by the opportunities being created.

 

DoE/PCE

One area of concern of the 4th Parliament was that of the “ownerless legacy sites” and one in particular is the Tudor Shaft mine dump contamination issues. The 5th Parliament needs to monitor this going forward.

 

DoE/PCE/NNR

Numerous challenges were identified with the Free Basic Energy / Free Basic Alternative Energy Policy. These include the indigent register, inconsistency in execution of the policy at municipal level and the annual adjustment of the amount allocated. The 5th Parliament needs to assess the actions the DoE is following to manage this.

 

DoE/SALGA/COGTA/PCE

The DoE’s international programme including the Grand Inga project needs to be monitored. So too the South African Development Community Regional Energy Power Pooling Programme, the initiatives with the Pan African Parliament and developments at NEPAD. Regional development is important for the stability and growth of the region and the DoE’s contribution to these needs to be monitored.

 

PCE

In terms of energy carriers, the nuclear power programme will be the biggest infrastructure programme of the state. The PCE needs to monitor all aspects of this, especially the preparedness of SA to meet the localization component. Skills development is also critical and progress on plans needs to be communicated to the 5th Parliament. The National Radioactive Waste Disposal Institute was just established and the maturity thereof needs to be monitored.

 

DoE/NNR/NECSA/ESKOM

Shale gas and other oil and gas exploration ventures need to be monitored to ensure it is well managed.

 

PCE

 

5.6.13.2. Outstanding issues from the ESMs

Date

Topic

Outstanding issues

11 November 2011

Prospects for job creation in local manufacturing in the renewable energy sector

  • Local people need to be the beneficiaries of the local projects;
  • Rural development to be part of the focus in  job creation since energy plays an important role in economic development;
  • Advocacy campaigns and interventions need to be strengthened and reinforced to inform people of the advantages of SWH;
  • New funding models are being explored where the fiscus is strained; Land acquisition, civil works and construction should not form part of local content;
  • Higher percentage levels of local content need be addressed as a matter of urgency;
  • Long term visibility be considered including committing to compute strategy and plans over a long period 20 - 30 years;
  • Opportunities for renewable energy in rural areas, where municipalities need assist as well are facilitated;
  • Micro businesses must not be excluded in the renewable sector;
  • Regional markets need to be explored as well.

19 January 2012

Management of strategic fuel stocks – options for SA

·         Facilitate access to storage facilities including leasing of tanks as well as third party access to such facilities to black owned companies.

·         Also ensure there is appropriate business empowerment in transportation of petroleum products;

·         Ensure adequate (and expansion of) buffer stock and tankages to store strategic stock and such should  include buffer stock as well;

·         Encourage tertiary institutions to assist in developing the necessary skills to address the skills shortages in the petroleum sector;

·         Address concerns that the same processes and procedures applies to both international oil companies and local BBBEE companies;

·         Ensure that itself, the State Owned Companies (SOCs) – PetroSA, Transnet, SFF etc, align their programmes, etc., with regards to the petroleum industry;

·         Mobilise more investments that are needed to address some of the challenges experienced in this sector;

·         Facilitate industry coordination such that all relevant stakeholders; i.e. oil companies, government etc. work together;

·         Ensure the oil majors take cognizance that new players are entering the market and that transformation is therefore essential.

 

07 June 2012

Independent Power Producers Renewable Energy Procurement Bidding: Window 1

·         The Department of Energy to urgently consider challenges of the complex and expensive bidding process, BBBEE policies, job creation, skills transfer and work with other departments to address such challenges;

·         The Department of Energy to try and reverse the lack of initiatives to take advantage of the opportunities to increase local content had to be addressed as a matter of urgency;  The Department of Energy to ensure focus must be on the establishment of a local manufacturing renewable energy industry particularly achieve a 60 percent local content target;

·         The Department of Energy to closely monitor skills transfer which is also paramount;

·         The Department of Energy to ensure the 2.1 percent of project costs that are earmarked for socio-economic development are strictly adhered to – such must include clear guidelines on how this money should be spent;

·         The Department of Energy should motivate South African bidders such that there are more local participants during subsequent phases beyond windows 1 and 2;

·         The Department of Energy to work more intensively with Department of Economic Development and the Department of Trade and Industry on the job creation aspect of the programme;

The Department of Energy to mobilize provincial Development Financiers to enhance their contribution on the renewable energy programme; The Department of Energy to ensure that spending on research and development, not only in renewable energy technology but also on the development of new products be enhanced including working with SANEDI, universities and the renewable energy industry to minimize the critical research gap that requires funding.

19 September 2012

Nuclear energy as an option for sustainable supply of energy

·         The Portfolio Committee on Energy needs to monitor all aspects of this, especially the preparedness of SA to meet the localization component.

·         Skills development is also critical and progress on plans needs to be communicated to the 5th Parliament.

·         The National Radioactive Waste Disposal Institute was just established and the maturity thereof needs to be monitored

20 February 2012

Assessment of the Upstream Sector in oil and gas industry

·         Oil and gas exploration ventures need to be monitored to ensure it is well managed

 

 

 

 

 

5.6.13.3. Outstanding issues on engagements such as Climate Change, MDGs

 

a.     The PCE addressed climate change in the following ways. The PCE was briefed by the Department of Environmental Affairs (DEA) on the National Climate Change Response Green Paper in 2011 and by the DoE on COP 17 in 2011, with a progress report in 2012. The PCE also received a briefing on a Report on International Climate Change and Energy Hearings in 2010.

b.    In terms of climate change, the next area that the PCE focused on was that of renewable energy and in 2010, the PCE was briefed by the DoE on the International Renewable Energy Agency. Further in 2011 the Industrial Development Corporation also briefed the PCE on the implementation of New Growth Path and Industrial Policy Action Plan (IPAP2) with special reference to the green economy and renewable energy. The PCE also looked at international experience when they assessed a report on a Workshop on Renewable Energy Policies for Sustainable African Development in Ghana. From 2012, the focus shifted to the Renewable Energy Independent Power Producer Procurement (REIPPP) programme as this was the flagship programme of the DoE that not only addressed SA’s energy needs but also looked at climate change issues by addressing green energy. The PCE also held a panel discussion on this topic the same year and also held a meeting of stakeholders in the renewable energy sector to explore solutions to the challenges of financing and certification of locally produced renewable energy products. The PCE also, in 2012 assessed SANEDI’s involvement in the South Africa Renewable Energy Initiative, ensuring that there is focused Research and Development to benefit SA in terms of renewable energy.

 

Regarding the Millennium Development Goals, the DoE has responded to almost all the goals. The eight MDGs are:

·         To eradicate extreme poverty and hunger

·         To achieve universal primary education

·         To promote gender equality and empower women

·         To reduce child mortality

·         To improve maternal health

·         To combat HIV/AIDS, malaria and other diseases

·         To ensure environmental sustainability

·         To develop a global partnership for development

c.     The activities of the DoE speak to all these goals in some form or the other. Hence the PCE ensured compliance to these and monitored the DoE in terms of their activities; in this regard, the PCE received a briefing from the DoE on the Department of Energy’s contributions to government outcomes and Millennium Development Goals in August 2011.

d.    The first goal, “to eradicate extreme poverty and hunger”, here the PCE monitored the Integrated National Electrification Programme that is in place to ensure universal access to electricity and more specifically the Free Basic Energy and Free Basic Alternative Energy programmes of the DoE. This is a key programme that speaks to eradicating poverty and the PCE monitored implementation with the DoE and SALGA. The INEP programme also speaks to the issues of “universal primary education” as the PCE also monitored electricity roll out, including distribution, in communities, including schools. The PCE also visited this topic during oversight visits. It can be noted that one of the areas that the PCE conducted oversight over, was the area of non-grid electrification, of which there are already 66 000 connections.

e.     In terms of “gender equality and empower women”, the PCE regularly monitored the DoE and the SoE’s with regard to compliance, but further looked at the REIPPP programme and the liquid fuel charter. This was visited regularly over the 4th Parliament.

f.     Another area assessed was the role out of the solar water heater programme which speaks to the health issues in the MDG’s and here the DoE monitored this programme closely over the years to the current state of almost 400 000 geysers rolled out.

g.    “Environmental sustainability” issues were addressed by the DoE via the REIPPP programme and the energy efficiency programmes. As indicated above, this was carefully scrutinised by the PCE during the 4th Parliament, but one area needing acknowledgement is that of Carbon Tax. The PCE held a stakeholder discussion on the Likely Impact of Carbon Tax on Energy Supply in South Africa (and SADC) in July 2013 with the aim of allowing stakeholders to address this topic with the PCE and National Treasury.

h.     Finally in terms of “developing a global partnership for development the PCE monitored the REIPPP programme to ensure there is local participation and that there is skills and technology transfer. The PCE also monitored the international programme of the DoE to ensure sustainable partnerships are built. In this regard, the PCE, in August 2013, engaged with the Pan African Parliament Committee on Transport, Industry, Communications, Energy, Science and Technology in a Joint Workshop on “Improvement of the Energy Industry in Africa for Sustainable Development- The Role of Parliaments”. Some of the outcomes included, a need for harmonization of legislation and PAP initiatives with NEPAD projects, the need for capacity building, strengthening of institutions and access to data. There was an agreement between the two Parliaments that there will be future engagements.

 




6. Miscellaneous

6.1. Media

 

·         With regard to Media Networking Sessions, the media fraternity is informed of the activities which have been undertaken by the PC on Energy. The Media Networking Sessions has also provided the PC on Energy the opportunity to build and foster relations with the media fraternity.

·         When undertaking oversight visits, representatives from the Parliamentary Media Unit accompany the delegation to the various sites to be visited. The aim of this practice is for the Portfolio Committee on Energy to inform the media of its findings during these visits. This usually takes the form of media statements, interviews with national, regional and local radio stations, newspapers (regional and local).

 

7. Key challenges emerging

 

Ø  Effective utilisation of the Budget Reviewal Process and Oversight and Accountability Model has not been optimised

Ø  Monitoring of budget expenditure of the PCE needs improvement

Ø  Engagement with the National Treasury and the Standing Committee on Appropriations on BRRR has almost not been done ever since the BRP was introduced

Ø  The role and authority of the PCE in the ratification of international agreements has been non-existent. Event the submission of the agreements to the PCE has not been formally done save for submission to the Clerk of Papers.

Ø  Engagement between support staff and Chairpersons has been rather terse and, at times, less beneficial.

Ø  The role of MP’s on performance management of staff is unclear and yet poor practice of such has a negative effect on the work of the PCE.

Ø  Cooperative government, as one of the strategic objectives of Parliament, has not been fully activated albeit working relations with SALGA are quite visible

Ø  Communication protocol between the Office of the Chairperson and the stakeholders and members of the public has been compromised several times

Ø  Technical and administrative support has not been up to standard viz.:

o    Late submission of minutes and reports

o    Repeated corrections of minutes and reports

o    Limited research work due to staff limitations

o    Alleged work overload of staff

o    Consistency in working according to job description

Ø  Information on the PCE activities does not seem to centralised i.e. the PCMS is underutilised

Ø  Training and mentoring of support  staff is rather limited – such can be observed on the quality of support given

Ø  Monitoring and tracking by the PCE especially follow up in issues identified as well as those decided on

Ø  The practice of including recommendations for the consideration by the DoE and even the NA has been recent and intermittent

Ø  An overall assessment is needed to establish if the DoE is correctly funded to deliver on all the areas that need attention for energy resource development in SA. There are challenges in aging and required energy infrastructure to ensure economic growth.

Ø  The development of key and critical skills in the various areas of energy including, among others, engineering, nuclear and electricity distribution. This area has to be carefully interrogated and managed and the 4th Parliament proposed an indaba on skills development be held.

Ø  Electricity distribution proved to be a major challenge and the 5th Parliament may have to assess with the DoE, the possibility of restructuring the distribution sector including a review of the relevant legislative and regulatory environment.

Ø  The issue of meeting departmental targets emerged as an area the DoE is grappling with and this must be carefully interrogated with the DoE to understand the challenges and mechanisms that will be employed to address them

Ø  The issue of transformation in the liquid fuels sector is progressing at a slow pace. The DoE has put in some initiatives to help accelerate this but this must be carefully interrogated.

Ø  The issue of data collection and management appeared to be a problem at the DoE. The DoE indicated that this has now largely been addressed with the recruitment of additional skills to manage this. The 5th Parliament however needs to exercise strict oversight over this as national policies and legislation is based on this.

Ø  The roll out of Integrated Energy Centres is critical, and these are being rolled out albeit at a slow pace. This has proven to be a critical resource especially for indigent communities and the Portfolio Committee on Energy needs to, with the DoE, find mechanisms to accelerate this programme.

Ø  The DoE exercises oversight over the SOE’s that account to it. The 4th Parliament noted gaps in the oversight modus operandi utilized by the DoE and the 5th Parliament needs to interrogate this topic thoroughly with the DoE to ensure a robust oversight model.

Ø  The 5th Parliament needs to monitor the area of Public Participation Programmes especially with regard to energy issues and at a municipal level. End user forums are critical to identification of problem areas and clear communication of this back to the DoE will result in these being addressed.

 

7.     Key areas for future work

 

·         There various pieces of legislation and policy documents that are still outstanding and these need to be presented to the Portfolio Committee on Energy for deliberation and comment. These include, among others,

·          The Department of Energy expedites the conclusion of outstanding policy strategies and programmes in order to position itself in the forefront of energy policy and planning. These strategies and programmes should include the following:

o    Strategic Fuel Policy,

o    Energy Efficiency Strategy,

o    Approach to Distributions Asset Management (ADAM),

o    Restructuring of the electricity industry,

o    Electricity Pricing Policy,

o    Bio-Fuels Policy,

o    Replacement of Regional Electricity Distributors (REDs),

o    Free Basic Alternative Energy (FBAE),

o    Cost Recovery Mechanism for cleaner fuels,

o    Review of the Renewable Energy White Paper,

o    Household Energy strategy.

The DoE has a new draft Integrated Energy Plan and Integrated Resource Plan and these needs to be finalized.

·         The Independent System Market Operator (ISMO) Bill was deliberated in the Committee and submitted to the House for Adoption. This was not adopted in the 4th Parliament and 5th Parliament needs to follow up on this.

·         From the Energy Stakeholder Meeting on the upstream sector, it emerged that policy challenges e.g. with some of the amendments of the proposed Minerals and Petroleum Resources Development (MPRDA) bill to the upstream sector, that need to be addressed as clear policy directives are needed and the DoE is to formulate a plan on identifying the challenges and a mechanism to address them.

·         The Renewable Energy Independent Power Procurement Programme is a success story for the South Africa Energy Sector. However it is still in its infancy stages as construction on most projects have just begun. The 5th Parliament needs to monitor the successes and challenges of this programme and ensure the DoE builds on this. This includes the area of localization and skills transfer, greater take up of some technologies, among others.

·         The Co-generation independent power procurement programme by the DoE which may form part of the revised integrated Resource Plan.

·         The transformation of the petroleum industry and compliance to the Liquid Fuels Charter is another area that requires some attention as progress has been less than satisfactory.

·         The transformation of the gas industry is another area needing attention and substantial investments are needed to encourage new entrants into the gas industry as a few big (or base) customers are needed to increase the investment in infrastructure that can be utilized also by the new entrants.

·         With reference to Indigent communities, the aspect of access to clean energy is critical. Areas needing attention here is access to Free Basic Services including Free Basic Electricity and Free Basic Alternative Energy. This includes access to electricity, be it grid or non-grid. Solar water heating and clean forms of heating e.g. Liquefied Petroleum Gas. In this regard price and accessibility are important. So too is safety aspects in terms of handling these energy sources. The DoE is experiencing challenges with the rollout of the above listed services. There has been progress here but the progress made by the DoE in this regard needs to be monitored.

·         The DoE is to present their Biofuels strategy to the Portfolio Committee on Energy. There are concerns about food security and empowerment of small farmers and the issue of management of subsidies to this industry.

·         In terms of the solar water heater (SWH) programme, to date, over 350 000 units of the envisaged 1 million units have been rollout. There is still a long way to go as issues local content, the involvement of all spheres of government, maintenance of units are some of the challenges arising. The 5th Parliament also needs to assess with the DoE mechanisms to accelerate rollout of the units.

·         Energy research programmes at universities including SANEDI’s “working for energy programme” should be monitored and co-ordinated, especially in the energy sector. The maturity of some of these programme through to commercialization is also important and so too the training aspect. The 5th Parliament needs to monitor this space to ensure at least some of this research work results in commercial benefit for South Africa.

·         The National Electrification programme is one of the biggest programmes of the DoE. Currently 85% of South African homes have electricity. The 5th Parliament needs to monitor that universal access to electricity is achieved, be it via grid or non-grid electrification programmes. The two electrification programmes (grid and non-grid) need to complement each other and all spheres of government need to work together in this regard. Issues of distribution (especially the infrastructure) need to be addressed. This includes funding and the skills deficit and a replacement for Regional Electricity Distributors needs to be found by the DoE.

·         Energy Efficiency initiatives needs to be monitored including meeting the 12% energy efficiency improvement target by 2015. Further, EE programmes and initiatives are fragmented and plans to address this needs to be explored. In this regard, the establishment of an Energy Efficiency champion for South Africa is needed that monitors and co-ordinates all activities in this area. The DoE needs to indicate to the 5th Parliament, its plans in this sector. In this regard, one area needing attention is that of public awareness and Consumer behaviour in terms of usage of electricity. Mechanisms to move to energy saving lifestyles needs to be explored. Another area is that of the green transport strategy and execution especially at Government level. Also the retrofitting of government buildings needs also to be monitored.

·         The involvement of Women, Youth and People with Disabilities in the Energy Sector has to be monitored on a regular basis by the 5th Parliament. Numerous opportunities are being created in the Renewable Energy Independent Power Procurement Programme and related programmes and it is important that this sector of the population is also empowered by the opportunities being created.

·         One area of concern of the 4th Parliament was that of the “ownerless legacy sites” and one in particular is the Tudor Shaft mine dump contamination issues.

·         Numerous challenges were identified with the Free Basic Energy / Free Basic Alternative Energy Policy. These include the indigent register, inconsistency in execution of the policy at municipal level and the annual adjustment of the amount allocated.

·         In terms of energy carriers, the nuclear power programme will be the biggest infrastructure programme of the state. The Portfolio Committee on Energy needs to monitor all aspects of this, especially the manufacturing of components locally. Skills development is far from adequate also critical and progress on plans needs to be communicated to the 5th Parliament. The National Radioactive Waste Disposal Institute was just established and the maturity thereof needs to be monitored.

·         Shale gas and other oil and gas exploration ventures need to be monitored to ensure it is well managed.

 

9. Recommendations

 

Ø  As a way to improve effective utilisation of the Budget Review Process (BRP) and Oversight and Accountability Model the following aught to be considered:

 

ü  Emphasis on the 6 stages of the BRP as well as intensified engagement with OAG, DPME, FFC, Audit and Risk Committees, Internal Audit Services, Quarterly Performance Reports

ü  Interaction with the National Treasury and the Standing Committee on Appropriations on BRRR be ensured and closely monitored

ü  Establishment of the Joint Parliamentary Oversight and Government Assurance Committee

ü  Introduction and/or intensification of joint oversight

1.     With other parliamentary committees in NA

2.     Between NA and NCOP parliamentary committees

3.     With international bodies such as PAP, IPU, SADC-PF, etc has to be intensively explored

ü  Oversight on international work including international agreements

ü  Linkage with Parliamentary Democracy Offices

ü  Tracking, monitoring and advice

ü  Inputs on constituency issues be made a matter of practice

ü  Individual member oversight

Ø  Legislative Impact Assessment on each statute has to be introduced as a compulsory practice

Ø  The PCE has to as matter of practice monitor data and information management regarding all its activities

Ø  Preparations of processing of Bills

ü  The sponsor of any Bill must be emphatic on the policy context of the proposed more than ever before.

ü  An all-embracing workshop, involving the PCE and DoE in the main, must be an obligation before the said Bill is processed. Focus aught to be on the Bill as well as the environment or sector within which it will be operating. Such must include a vivid elaboration for its introduction.

ü  Expert testimony must be encouraged to empower those engaged in processing the Bill.

ü  Extended public hearings may have to be considered for certain Bills viz.:

ü  Extra-Parliamentary public hearings;

ü  Public hearings held through electronic means i.e. video conferencing

ü  Elaborate research, including comparative analysis with other countries, must be a matter of practice.

ü  Testing of a Bill that is introduced against government policy and the constitution must reported to the PCE as a matter of practice

ü  The PCE should consider broadened engagement when preparing to process a Bill – such may include visiting other countries, institutions of research and training depending on the nature of the need and/or challenge at the time

Ø  Enhancement on capacity-building and empowerment of members of the PCE and support staff:

ü  Exchange programmes with countries where we have formal partnerships should be facilitated during constituency period;

ü  Internship Programme, especially on the legislative, research, media, communication and information services, should be considered to bolster such services;

ü  Holiday programme for post-graduate students has to be introduced especially for the above areas;

ü  Partnerships with other countries as well as other international support must be exploited too

Ø  There must be a paradigm shift on international work – engagements with counterparts from other Parliaments aught to include various forms viz.:

ü  Joint programmes including empowerment, research, video conferencing as another form of communication

Ø  Personnel in the following sectors has to be appropriately increased:

ü  Legislative services

ü  Media and communication services

ü  Library and information services

Ø  Task Assignment Strategy

ü  Members of the PCE aught to be given assignments as groups in order to share the load of work and enhance its effectiveness

ü  Such practice has to be accompanied with fast-track empowerment

Ø  The Office of the Chairperson be established as a distinct office with a public status and profile as well as getting the requisite resources for its functioning

Ø  The status and category of the PCE has to be upgraded to a B category

Motivation:

ü  The need to address challenges in the supply of electricity

ü  A lot of processing of legislation is expected during the 5th Parliament – such will be due to legislation that was not processed in this 4th Parliament as well as anticipated due to policy refinement and other identified gaps

ü  There is a lot of reviewal and refinement that will be done in the regulatory environment

ü  The upsurge in the oil and gas exploration needs more attention

ü  Oil and gas trade has not been given the attention it deserves despite the growing challenges in this sector

ü  Shale gas will be another matter that will demand intensive attention during the 5th Parliament.

Ø  PCE Budget and Financial Report System

The following areas must be addressed and improved:

ü  Budget planning

ü  Engagement between finance support staff and the Chairpersons

ü  Expenditure monitoring, evaluation and reviewal has to be enhanced

Ø  The PCE has to intensify its engagement with the public, including the public education on its role and contribution on the energy sector, through the support of the appropriate unit in Parliament

Ø  Preparations for the compiling reports be resumed at least 6 months before the end of each term of parliament

ü  Such preparations must be preceded by workshops for both support staff and the PCE

ü  Such preparations must also be preceded by research work and consultation

Ø  Cooperative government, as one of the strategic objectives of Parliament, be given the attention it deserves including appropriate resourcing

Ø  The practice of including recommendations for the consideration by the DoE and even the NA has to be a matter of practice as much as is possible

Ø   Some issues of non achievement have not been picked up as a tracking and monitoring model has not been developed to allow this.

Ø  In terms of the BRP the PCE is to assess the inclusion of comments from the Standing Committee on Appropriations, National Treasury and the Parliamentary Budget office.

Ø  Security of electricity supply, in the short term, is made a priority during the 5th Parliament and such includes a plan of action to prevent load shedding which will be presented to the PCE at the early stages of the 5th Parliament.

Ø  Outstanding legislation and policies be made a priority and tracked, some of the outstanding legislation include:

1. The Gas Amendment Bill

2. National Nuclear Regulator Amendment Bill

3. Electricity Regulation Second Amendment Bill

4. National Energy Regulator Amendment Bill

5. Radioactive Management Fund Bill

6.    Nuclear Energy Amendment Bill

 

Ø  Furthermore the 5th Parliament should ensure expeditious processing of the bills whilst empowering all stakeholders.

Ø  The 5th Parliament ensures that the Minister of Energy:

a) Conducts a due diligence study in order to determine the feasibility and implications of the transfer of transmission assets and to submit a final report to the National Assembly

b) Conducts a cost benefit analysis of the possibility of incorporating the transmission assets into the Independent System and Market Operator (ISMO)

c) Further conducts a cost benefit analysis of establishing a Transmission System Operator (TSO), or any other arrangement suitable to the South African situation.

d) Ensures that the restructuring of the entire electricity sector be addressed as matter of urgency.

Ø  Particular emphasis is the articulation of the end-state for each of the sub-industries in the electricity sector. The 5th Parliament must ensure a comparative analysis including drawing lessons from other countries through, inter alia, study tours, workshops, etc., be facilitated for the future PCE.

Ø  The 5th Parliament ensures that the Department of Energy expedites the conclusion of outstanding policy strategies. These strategies and programmes include, inter alia, the following:

·         Strategic Stocks Fuel Policy,

·         Energy Efficiency Strategy,

·         Approach to Distributions Asset Management (ADAM),

·         Restructuring of the electricity industry,

·         Electricity Pricing Policy,

·         Bio-Fuels Policy,

·         Replacement of Regional Electricity Distributors (REDs),

·         National Household Energy Safety Policy

·         Mandatory National Energy Efficiency Programme

·         Comprehensive National Infrastructure Maintenance Strategy

·         Comprehensive policy framework on alternative energy

·         Rationalisation of the regulatory environment in the energy sector

·         Free Basic Electricity (FBE)

·         Free Basic Alternative Energy (FBEA),

·         Cost Recovery Mechanism for Cleaner Fuels,

·         Review of the Renewable Energy White Paper,

·         Household Energy Strategy,

·         Gas Utilisation Master Plan

·         Roll-out of Gas Infrastructure

 

Ø  The 5th Parliament closely tracks and monitors the current reviewal of the IRP as well as ensuring that subsequent reviewals are done timeously.

Ø  The 5th Parliament, with regard to the DoE, needs to pay careful attention to the areas of; funding allocation to the DoE from National Treasury to ensure it is empowered financially to execute its mandate; skills availability for the various energy projects in South Africa and the timely delivery of outstanding legislation by the DoE. Further the area of oversight of financial control by State Owned Companies/Entities and ensuring they meet their objectives needs careful scrutiny by the 5th Parliament.

Ø  In terms of the entities, the 5th Parliament needs to monitor the restructuring of CEF and PetroSA and empowering them to meet future energy demands of SA.

Ø  Explore and promote mechanisms to assist Necsa to become financially independent of the state eventually

Ø  Ensure that NNR has the requisite skills and resources able to manage the nuclear new build programme.

Ø  Assess the legislative framework regarding Nersa comprehensively and ensure that they are empowered to execute their duties.

Ø  Nersa, in conjunction with the DoE and Salga, needs to redefine its role in terms of ensuring greater compliance of municipalities to Nersa’s determinations. The 5th Parliament needs to monitor this.

Ø  SANEDI, needs to ensure that it has the mechanisms in place to convert Research and Development projects into commercial ventures and explore its role SANEDI as an Energy Efficiency Champion for South Africa, with the DoE. The 5th Parliament needs to monitor this.

Ø  The Department of Energy needs to expedite the conclusion of outstanding policies and legislation.  The 5th Parliament needs to monitor this