Question NW286 to the Minister of Cooperative Governance and Traditional Affairs

Share this page:

26 June 2018 - NW286

Profile picture: Boshoff, Ms SH

Boshoff, Ms SH to ask the Minister of Cooperative Governance and Traditional Affairs

What number of housing projects have been (i) undertaken and (ii) completed in the Thaba Chweu Local Municipality in Mpumalanga (aa) in each of the past three financial years and (bb) since 1 April 2017 and b) What was the (i) budget allocation, (ii) commencement date and (iii) completion date for each housing project?

Reply:

Housing projects are implemented by the Department of Human Settlements in the Municipalities in the Province. The Department of Human Settlements in the Mpumalanga Province was contacted and confirmed the information below as correct.

The Thaba Chweu Local Municipality was contacted to assist with the response to the question. The response is as follows: (Annexure A)

No.

Project Name

Financial

Total Units

Start Date

Status

Budget

 

No Allocation

2014/15

n/a

n/a

n/a

n/a

 

No Allocation

2015/16

n/a

n/a

n/a

n/a

 

Chryselda

2016/17

200

01/11/2016

In progress

R20 600 000

 

Mgugwana

2016/17

100

01/11/2016

Completed (08/12/2017)

R10 300 000

 

Lwakhiti JV

2017/18

150

22/09/2017

In progress

R15 450 000

 

Fenekwane

2017/18

100

22/09/2017

In progress

R10 900 000

As per the comments of the Deputy Minister to provide background/ explanatory notes to the matter, the following additional information was obtained.

Housing projects are implemented by the Department of Human Settlements in the Municipalities in the Province. The Department of Human Settlements in the Mpumalanga Province was contacted and confirmed the above information as correct. As implementers of the housing projects, the Department allocates the budget, appoints Service Providers and monitors them in collaboration with the affected Municipality. The Municipality’s responsibilities include the identification of beneficiaries.

2016/17 financial year includes the following:

  • The Chryselda housing project experienced challenges as it is reported that about 24 houses were invaded. Municipality still engaging with the affected individuals to vacate the affected properties.
  • Mgugwana Housing Project was completed but the units are not yet occupied as the programme to service the completed units is still ongoing.