Question NW673 to the Minister of Transport

Share this page:

23 April 2018 - NW673

Profile picture: De Freitas, Mr MS

De Freitas, Mr MS to ask the Minister of Transport

What are the (a) plans, (b) time frames, (c) deadlines, (d) milestones in each province and (e) monitoring mechanisms with regard to the new rail infrastructure and its integration onto the existing rail infrastructure and network?

Reply:

Key programmes on the rail infrastructure network is reflected in the table below. All of these projects are multi-year projects and dates indicated on current projects are as per contracts.

Plans/Programme

Region

d)

Key Milestones

b &c)

Projected Completion Date

e)

Monitoring Mechanism

Re-Signalling Programme

KwaZulu/Natal (KZN)

 

25 Jun 2021

Project Progress meetings;

Monthly report;

APP;

Quarterly Report DOT

   

Phase 1: Pinetown line

20 Jul 2018

 
   

Phase 2: New Rossborough Centralised Traffic Control Centre (CTC)

16 May 2019

 
   

Phase 3A: Kwa Mashu to Temple

30 Nov 2018

 
   

Phase 3B: Avoca to Springfield

27 May 2020

 
   

Phase 4: Umlazi to Umbogintwini

23 Sep 2019

 
   

Phase 5: Clairwood to Crossmoor

05 Jun 2020

 
   

Phase 6: Berea to Congella

15 Oct 2020

 
   

Phase 7: Durban station

11 May 2021

 
 

Western Cape (WC)

 

30 Jun 2020

Project Progress Meeting ; Monthly report;

APP

Quarterly report to DOT

   

Regional Monitoring and Train Control Centre (RM&TCC)

30 June 2018

 
   

Phase 1.2: Wynberg – Simonstown, Crawford – Diep River

30 Apr 2018

 
   

Phase 1.4: Koeberg – Maitland - Hazendal

31 May 2018

 
   

Phase 1.3: Salt River - Kenilworth

31 Jul 2018

 
   

Phase 3.1: Cape Town - Woodstock (South)

30 Sep 2018

 
   

Phase 3.2: Cape Town - Woodstock (North)

31 Oct 2018

 
   

Phase 2.3: Esplanade - Ysterplaat

31 Jan 2019

 
   

Phase 1.1: Philippi - Kaptiensklip, Chris Hani

28 Feb 2020

 
   

Phase 2.2: Woltemade – Parow

31 Mar 2020

 
   

Phase 2.1: Langa - Nyanga, Bontheuwel – Sarepta

30 Apr 2020

 
   

Phase 4.1: Tygerberg – Bellville

31 May 2020

 
   

Phase 4.2: Kuils River - Strand, Eerste River - Muldersvlei

30 Jun 2020

 
 

Gauteng

 

28 Feb 2021

Project Progress meetings;

Monthly report;

APP;

Quarterly Report DOT

   

Gauteng Nerve Centre (GNC)

Apr 2016 - Completed

 
   

Phase 1: Midway – Residentia

31 Mar 2016 – Completed

 
   

Phase 2: Kaalfontein – Leralla, Olifantsfontein – Irene

28 Nov 2016 – Completed

 
   

Phase 3: Randfontein – Roodepoort

15 May 2017 – Completed

 
   

Phase 4: Boksburg East – Springs, Daveyton – Alliance

15 Dec 2017 – Completed

 
   

Phase 5: George Goch – Geldenhuys, Benrose – Kaserne West, Booysens – Crown

03 Apr 2018

 
   

Phase 6: Rissik – Koedoespoort – Eerste Fabrieke

15 Dec 2019

 
   

Phase 7: Jeppe – Johannesburg – Braamfontein

25 Sep 2018

 
   

Phase 8: Centurion – Pretoria, Mitchell Street – Saulsville

07 Jan 2019

 
   

Phase 9: Kempton Park – Knights

11 Mar 2019

 
   

Phase 10: Langlaagte – Florida, Croesus

20 May 2019

 
   

Phase 11: New Canada – Naledi, Orlando – Kliptown

14 Oct 2019

 
   

Phase 12: Hercules – Belle Ombre, Capital Park East and West, Pretoria North – Mabopane, Rosslyn

23 Jun 2020

 
   

Phase 13: De Wildt

06 Jul 2020

 
   

Phase 14: Driehoek – Germiston, Angelo – Oosrand, Kutalo – Elsburg – Kwesine, India

01 Feb 2021

 

Blue Downs Rail Extension

Western Cape: Cape Town

Preliminary Design and EIA

Detail Design

Construction

Operations

Aim to commence Preliminary Design in 2018/19, thereafter timeframes can be confirmed with greater accuracy.

Allow for 4-6 month procurement process for phases leading up to Operations

12 – 15 months

6 months

  1. – 30 months

Programme Management office

Cape Town Intermodal Planning Committee

Depot Modernisation

Wolmerton

Gauteng North

Phase 1 complete

Phase 2 in testing & commissioning scheduled for completion by end March 2018

Phase 3 Consultants appointed

Designs complete

Contractor appointed

All construction complete

February 2019

February 2020

November 2021

March 2026

 

Depot Modernisation

Braamfontein

Gauteng South

Will be done in phases

Phase 1 awaiting appointment of contractor by PRASA Board. 12 month design and construction period envisaged

Phase 2

Consultants appointed

Designs complete

Contractor appointed

All construction complete

June 2019

March 2020

December 2021

June 2024

Project Progress meetings;

PRASA Tech Management Committee;

Monthly report;

APP;

Quarterly Report DOT

Depot Modernisation

Salt River

Western Cape

Will be done in Phases

Phase 1 will be advertised by June 2018 and construction will be complete by June 2021

Phase 2

Consultants appointed

Designs complete

Contractor appointed

All construction complete

December 2019

December 2020

December 2021

June 2025

PRASA Tech Management Committee;

Monthly Report;

APP

Quarterly Report DOT

Depot Modernisation

Durban Yard and Springfield

KZN

Consultants appointed

Designs complete

Contractor appointed

All construction complete

January 2019

January 2020

November 2021

March 2026

PRASA Tech Management Committee;

Monthly Report;

APP

Quarterly Report DOT

 

Source file