Question NW2601 to the Minister of Water and Sanitation

Share this page:

31 August 2015 - NW2601

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

(1)(a) When was the nine boreholes and package plant with a reservoir completed in Hoedspruit, Limpopo, and (b) what was the total cost of the project; (2) whether the plant is currently in use; if not, why not; if so, what are the relevant details; (3) what is the capacity of the plant in mega litres per day?

Reply:

(1)(a) The Hoedspruit Package Plant with an elevated tank (which is used as a reservoir) and seven boreholes and not nine, as per the question raised, were constructed and commissioned on 28 May 2014 by the Mopani District Municipality to augment the supply of water from the Drankensig Water Treatment Plant owned by the National Department of Public Works. The initiative emanated from the 2011/2012 Maruleng Flood Disaster.

(1)(b) The total cost of the project was R11 972 303.00.

(2) The Package Plant is in use, however; the clear water pump has currently burnt out and the Mopani District Municipality has issued an order for repairs which will be installed by the end of August 2015.

(3) The capacity of the plant is 0.35Ml/d.

---00O00---

Source file