Question NW2119 to the Minister of Water and Sanitation

Share this page:

03 July 2015 - NW2119

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

(1)What amount was spent by her department on environmental rehabilitation due to sewage spills in each province (a) in the (i) 2013-14 and (ii) 2014-15 financial years and (b) since 1 April 2015; 2) (a) what was the location, (b) cause and (c) nature of the rehabilitation for each spillage?

Reply:

  1. Table 1 below reflects the amount that was spent by the Department on environmental rehabilitation due to sewage spills in each province (a) in the (i) 2013-14 and (ii) 2014-15 financial years and (b) since 1 April 2015:

Table 1

(a)Province

(a)(i) 2013-14

(a)(ii) 2014-15

(b) since 1 April 2015

Eastern Cape

N/A

N/A

N/A

Free State

R15 850 000 (ACIP)

R42 850 000 (ACIP)

R18 968 000 (Planned to be spent under ACIP)

 

R5 000 000 (RBIG)

R47 000 000 (RBIG)

R90 474 000 ((Planned to be spent under RBIG)

Gauteng

N/A

N/A

N/A

KwaZulu-Natal

N/A

N/A

N/A

Limpopo

N/A

N/A

N/A

Mpumalanga

R9 000 000 (ACIP)

R13, 7m (ACIP)

R47m (RBIG)

Northern Cape

N/A

N/A

N/A

North West

N/A

N/A

N/A

Western Cape

N/A

N/A

N/A

(2)(a) Refer to the table below for the (a) location, (b) cause and (c) nature of the rehabilitation for each spillage within the Free State and Mpumalanga provinces.

 

FREE STATE PROVINCE

2013/14 (ACIP)

Location (2) (a)

Cause (2) (b)

Nature of Rehabilitation (2) (c)

Municipality

Clocolan

Non-functional sewer pump stations due to ageing infrastructure

Replaced all pumps, motors & electrical infrastructure

Setsoto LM

Ficksburg

Collapsed old sewer pipes

Unblocked sewer lines and replaced defective ones

Setsoto LM

Kroonstad

Collapsed 1,2 km old asbestos sewer line from Gelukwarts polluting the Vals river

Replaced 1,2km of sewer line.

Moqhaka LM

Wepener

Non-functional sewer pump station & waste water treatment works

Refurbished all pumps, motors & electrical infrastructure.

Naledi LM

2013/14 (RBIG)

Location (2) (a)

Cause (2) (b)

Nature of Rehabilitation (2) (c)

Municipality

Vredefort

Non-functional sewer pump station & waste water treatment works

Refurbished all pumps, motors & electrical infrastructure.

Ngwathe LM

2014/15 (ACIP)

Location (2) (a)

Cause (2) (b)

Nature of Rehabilitation (2) (c)

Municipality

Theunissen

Collapsed old asbestos line

Replaced a length of 500 meters

Masilonyana LM

Brandfort

Non-functional two sewer pump stations due to old infrastructure

Refurbished and upgraded the two pump stations.

Masilonyana LM

Winburg

Non-functional one sewer pump station due to old infrastructure

Refurbished and upgraded the one pump station.

Masilonyana LM

Vrede

Non-functional pumps & motors and electrical infrastructure

Replaced pumps and motors and refurbished electrical infrastructure

Phumelela LM

Waden

Non-functional pumps & motors and electrical infrastructure

Replaced pumps and motors and refurbished electrical infrastructure

Phumelela LM

Koffiefontein

Non-functional pumps & motors and electrical infrastructure

Refurbished pumps and motors and refurbished electrical infrastructure

Letsemeng LM

2014/15 (RBIG)

Location (2) (a)

Cause (2) (b)

Nature of Rehabilitation (2) (c)

Municipality

Wesselsbron

Non-functional electrical and mechanical components at waste water treatment plant.

Replaced all non functional electrical & mechanical components.

Nala LM

Kroonstad

Collapsed asbestos sewer pipe line in Hill street

Collapsed Boitumelo Marabastad asbestos sewer pipeline

Non-functional sewer treatment plant

Multi-year projects. Replacing and upgrading the Hill Street sewer pipeline.

Replacing and upgrading the sewer pipeline.

Upgrading of the sewer treatment plant to meet the demands

Moqhaka LM

Vredefort

Non-functional sewer treatment plant and old sewer line

Refurbished and upgraded the waste water treatment plant and replaced the sewer line

Ngwathe LM

2015/16 (ACIP Projects under implementation)

Location (2) (a)

Cause (2) (b)

Nature of Rehabilitation (2) (c)

Municipality

Koppies

Non-functional electrical and mechanical components at waste water treatment plant.

Replace all non-functional electrical & mechanical components.

Ngwathe LM

Reitz and Lindley

Non-functional of electrical and mechanical components in pump station

Refurbishment of non-functional of electrical and mechanical components

Nketoana LM

Koffiefontein

Non-functional electrical and mechanical components at waste water treatment plant.

Replace all non-functional electrical & mechanical components.

Letsemeng LM

Odendalsrus

Collapsed old sewer lines

Replacement of collapsed old sewer pipeline

Matjhabeng LM

Mamahabane

Oxidation ponds not lined and the sewerage seeps through the nearby environment.

Rehabilitation of oxidation ponds

Matjhabeng LM

Wepenar

Collapsed old asbestos sewer pipeline and non-functional of two sewer pump station.

Replace the collapsed sewer line and refurbish the two sewer pump stations.

Naledi LM

 

2015/16 (RBIG Projects under implementation)

Location (2) (a)

Cause (2) (b)

Nature of Rehabilitation (2) (c)

Municipality

Kroonstad

Collapsed asbestos sewer pipe line in Hill street

 

Collapsed Boitumelo Marabastad asbestos sewer pipeline

Non-functional sewer treatment plant

Multi-year projects. Replacing and upgrading the Hill Street sewer pipeline.

Replacing and upgrading the sewer pipeline.

Upgrading of the sewer treatment plant to meet the demands

Moqhaka LM

Vredefort

Non-functional of electrical and mechanical components in pump station

Refurbishment of non-functional of electrical and mechanical components

Nketoana LM

MPUMALANGA PROVINCE

2013-14

Location (2) (a)

Cause (2) (b)

Nature of Rehabilitation (2) (c)

Municipality

Mhlatikop and Komatipoort

Ageing Infrastructure, operating beyond design capacities, poor operation and maintenance

Refurbishment of the WWTW and pump stations Phase 1

Nkomazi

2014-15

Location (2) (a)

Cause (2) (b)

Nature of Rehabilitation (2) (c)

Municipality

Mhlatikop and Komatipoort

Ageing Infrastructure, operating beyond design capacities, poor operation and maintenance

Refurbishment of the WWTW and pump stations Phase 2

Nkomazi

Leandra

 

Refurbishment of the WWTW

Govern Mbeki

2015-16

Location (2) (a)

Cause (2) (b)

Nature of Rehabilitation (2) (c)

Municipality

Balfour

Ageing Infrastructure, operating beyond design capacities, poor operation and maintenance

Upgrade of the WWTW

Dipaleseng

Delmas

   

Victor Khanye LM

Botleng

     

---00O00---