Question NW1665 to the Minister of Water and Sanitation

Share this page:

14 August 2017 - NW1665

Profile picture: Baker, Ms TE

Baker, Ms TE to ask the Minister of Water and Sanitation

What is the (a) nature, (b) cost, (c) location and (d) commencement date of each (i) Accelerated Community Infrastructure project and (ii) Water and Sanitation Implementation Committee project currently under construction.

Reply:

(i) In the 2017/18 financial year, the Accelerated Community Infrastructure Programme (ACIP) will implement 3 projects in the KwaZulu-Natal Province. Refer to the table below for the nature, cost, location and commencement date of each project.

Project Name

(a) Project Nature

(b) Project cost

(c) Location

(d) Commencement date

Manguzi WWTW

Refurbishment of a Waste Water Treatment Work (WWTW)

R 9,710,000

Umhlabuyalingana Local Municipality (LM) under uMkhanyakude District

October 2017

Hluhluwe WWTW

Refurbishment of WWTW

R3,450,000

The Big Five False Bay LM under uMkhanyakude DM

October 2017

Ingwavuma WWTW

Refurbishment of WWTW

R13,679,916

Jozini LM under uMkhanyakude DM

January 2017 (Under Construction)

Total

 

R26,839,916

   

(ii) There is no programme within my Department’s Branch: National Water Resources Infrastructure implemented as “Water and Sanitation Implementation Committee Projects”.