Question NW2156 to the Minister of Water and Sanitation
31 October 2016 - NW2156
Basson, Mr LJ to ask the Minister of Water and Sanitation
With reference to the five contracts regarding the progress of Phase II of the Lesotho Highlands Water Scheme that were awarded, what is, in each case, the (a) nature of the work completed, (b) particulars of the parties to the contract, (c) expected date of completion and (d) projected total value of the contract?
Reply:
Refer to Annexure A regarding the progress of the five contracts of Phase II of the Lesotho Highlands Water Scheme.
ANNEXURE A
Contract # |
Description |
Company |
Date of completion |
Tender price (Rand) |
Cost to date (Rand) |
Water Transfer Contracts being implemented |
|||||
2223 |
Project Management Unit |
CDM Smith and Partners |
Dec-2025 |
349 889 571 |
131 625 324 |
3009 |
Professional Services for the Urban Planning, D&S Project Housing & Associated Infrastructure |
Polihali Infrastructure Consultants |
Apr-2021 |
79 365 621 |
14 019 480 |
3014 |
D&S Polihali North Eastern Access Road |
SMEC FMA Joint Venture |
Sep-2016 |
28 453 705 |
4 936 235 |
3015 |
Professional services for the Evaluation, Optimisation, and Site Supervision of Geotechnical investigations |
Jeffares and Green Joint Venture |
Sep-2017 |
19 750 472 |
7 026 482 |
6013 |
RAP PNEAR and site establishment area(in house) |
Inhouse by LHDA |
Jun-2017 |
1 500 000 |
- |
4016 |
Geotechnical investigations-Polihali Tunnel-drilling contractor |
Diabor Pty Ltd |
Aug-2017 |
49 238 075 |
12 515 273 |
Totals |
528 197 444 |
170 122 794 |
D&S = Design and Construction supervision
RAP = Resettlement Action Plan
PNEAR = North East Access Road
D&S = Design and Construction supervision
ESIA = Environmental Social Impact Assessment
RAP = Resettlement Action Plan