Question NW2155 to the Minister of Water and Sanitation

Share this page:

31 October 2016 - NW2155

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

With reference to 16 completed contracts regarding the progress of Phase II of the Lesotho Highlands Water Scheme, what is, in each case, the (a) nature of the work completed, (b) particulars of the parties to the contract, (c) date the contract was entered into, (d) date the work was completed and (e) total amount (i) paid and/or (ii) still payable in terms of the contract

Reply:

Refer to Annexure A regarding progress of the 16 completed contracts of Phase II of the Lesotho Highlands Water Scheme.

Annexure A

 

Contract #

Description

Company

Date of Award

Date

completed

Contract price (Rand)

Cost

at completion (Rand)

Water Transfer Awarded Contracts : Completed

 

 

 

 

2222A-C

Interim PMU-

JB Barry and Partners (Ireland)

12-Aug-11

Jan-14

19 459 612

19 459 612

             

2222D

Interim PMU-

Dr S Turner - Individual Service Contract

12-Aug-11

Jan-14

4 295 015

4 295 015

4002

Construction of Access Road to Polihali Weir

MOPS Civil Contractors Pty Ltd (- Lesotho company)

Nov-11

31-Mar-12

4 136 254

4 136 254

4001

Construction of Polihali Downstream Weir

LSP Construction (Lesotho company)

14-May-12

17-Oct-13

21 714 123

21 686 529

4014

Tlokoeng Housing Renovations

LSP Construction

Jan-14

Mar-14

1 171 385

1 171 385

3000

Design and Supervision of PolihaliWeir

AECOM and sub consultants

07-Dec-10

Oct-13

2 492 652

2 493 236

3003

LidarSurvey1

CK Aerial Surveys

12-Jun-12

31-Mar-13

1 771 250

1 771 250

3011

LidarSurvey2

CK Aerial Surveys

12-Jun-12

30-Sep-13

514 298

514 298

3017

Demarcation of Reservoir Boundary

Maleka, Ntsihlehle, Putsoa ( MNP)

May-14

30-Nov-15

7 950 100

8 215 930

6001

Baseline Study-Water Quality and IFR

Institute of Natural Resources

14-Jan-13

31-Aug-14

9 206 025

9 225 230

6002

Baseline Study - Biological, Archeological & Heritage

Coastal and Environmental Services (CES)

27-Nov-12

31-Mar-14

2 599 230

2 599 230

6008

Baseline Study - Public Health

NonyanaHoohlo and Associates

Dec-13

09-Jul-15

6 740 575

6 045 475

6000

Baseline Study - Socio-Economic

Coastal and Environmental Services (CES)

27-Nov-12

Oct-14

4 817 998

6 167 998

6000

Baseline Study-Socio-Economic

LHDA Inhouse

Inhouse

Dec-14

1 480

1 480

6031

Re-configuration of socio-economic database

GK Consulting

Jan-16

Feb-16

91 256

91 256

9006

Financing Strategy Consultant

Delloitte&Touche

Sep-14

Mar-15

1 335 907

1 335 907

 

TOTAL

 

 

88 297 160

89 210 085