Question NW1131 to the Minister of Land Reform and Rural Development
28 November 2024 - NW1131
Dugmore, Mr C to ask the Minister of Land Reform and Rural Development
(1) With regard to claims lodged by claimants in terms of the Restitution of Land Rights Act, Act 22 of 1994, before the deadline of 1998 in each province, what total number of (a) claims were timeously lodged and (b) the specified claims were settled. (2) what total number of the settled claims were (a) settled via (i) financial compensation and/or (ii) returning the land to the relevant claimants and (b) not settled. (3) whether he will provide a comprehensive list of all the claims which have not yet been settled; if not, why not; if so, what are the relevant details; (4) whether he will provide a short description of the cause of the delay in settling each of the specified claims; if not, why not; if so, what are the relevant details. (5) what is the proposed time frame to settle each outstanding claim? NW1380E
Reply:
(1)(a) Please refer to the table below.
Province |
Total Lodged |
Eastern Cape |
16,716 |
Free State |
2,682 |
Gauteng |
13,162 |
KwaZulu-Natal |
16,394 |
Limpopo |
3,489 |
Mpumalanga |
3,400 |
North West |
3,902 |
Northern Cape |
3,852 |
Western Cape |
16,099 |
TOTAL |
79,696 |
(b) Please refer to Annexure A.
(2)(a)(i) 56 040
(ii) 8 314
(b) 5755
3. Yes. Please refer to Annexure B.
4. There are various challenges amongst others such as conflict amongst the beneficiaries, landowners challenging the validity of the claims and land invasions which caused the delays in the settlement of claims.
Due to the declining budget, the Commission on Restitution of Land Rights reduced its APP targets. Cognisant of the increased value of settlements and the declining budget, the Commission has aligned the settlement and finalisation targets with the allocated budget. There is need for increased budget and human resources capacity in order for the Commission to accelerate the fast-tracking of land claims.
5. Due to above mention reasons no specific time frame can be indicated as each claim has different challenges.
END
Source file
Documents
- RNW1131-2024-11-28-ANNEXURE-EC.xlsx
- RNW1131-2024-11-28-ANNEXURE-GP.xlsx
- RNW1131-2024-11-28-ANNEXURE-FS.xlsx
- RNW1131-2024-11-28-ANNEXURE-KZN.xlsx
- RNW1131-2024-11-28-ANNEXURE-L.xlsx