Question NW1825 to the Minister of Tourism

Share this page:

31 May 2023 - NW1825

Profile picture: Ismail, Ms H

Ismail, Ms H to ask the Minister of Tourism

Whether, in order to better understand the financial implications and underlying reasons for the non-completion of the tourism projects, she will (a) furnish Ms H Ismail with a detailed analysis of the initial financial allocations to each contractor, (b) disclose the specific reasons behind the failure to complete each specified project within the original scope, budget and timeline, (c) specify the additional funds allocated to the Development Bank of Southern Africa for the completion of each project and (d) outline any measures taken to mitigate such issues in future tourism-related contracts; if not, why not, in each case; if so, what are the relevant details in each case?

Reply:

Prov

 

Project Name

(a) Initial allocation to each contractor

(b) Reasons behind the failure to complete each project within the original scope, budget and timeline

(c) Additional funds allocated to the DBSA for completion of each project (construction value)

EC

1

Qatywa Lodge

Budget:

R 23,750,000

Exp: R 23,288,668

Incomplete chalets, restaurant and conference centre due to budget depletion.

R 32,802,163.00

 

2

Western Tembuland Lodge

Budget:

R 10,449,156

Exp: R 10,382,358

Incomplete chalets, entrance guard house due to budget depletion

R 23,437,638.25

 

3

Maluti Hiking and Horse Trail

Budget:

R 4,750,000

Exp: R 4,749,987

Poor workmanship on the river crossing bridges

R 18,160,388.15

 

4

Mthonsi Lodge

Budget:

R 28,215,000

Exp: R 27,531,883

Incomplete chalets, restaurant and conference centre due to budget depletion.

R 31,072,567.60

 

5

Nyandeni

Budget:

R 7,600,000

Exp: R 7,546,800

Chalets completed however not furnished. Lack of maintenance over time.

R19,023,014.80

FS

1

Qwa Qwa Guest House

Budget:

R 34,234,974

Exp: R 34,001,662

Incomplete chalets due to budget depletion.

R21,120,795.06

 

2

Vredefort Dome Interpretation Centre

Budget:

R 3,009,453

Exp: R 2,927,652

Interpretation Centre completed however there were structural defects due to geotechnical instability.

R24,160,892.96

 

3

Monontsha Access Road

Budget:

R 12,629,500

Exp: R 12,548,922

Incomplete access road due to budget budget depletion.

R6,726,894.01

KZN

1

Muzi Pan

Budget:

R 12,447,480

Exp: R 11,887,690

Chalets completed however with some defects/ poor workmanship.

Contractor not yet appointed

 

2

Isibhubhu

Budget:

R 15,000,000

Exp: R 14,889,708

The project was completed however it could not be handed over without occupation certificate.

R29,918,570.53

LP

1

Phiphidi Waterfall

Budget:

R 29,477,099

Exp:

R 23,264,771.67

Incomplete chalets. Contractual disputes with the Implementing Agent whose contract lapsed.

Contractor not yet appointed

 

2

The Oaks

Budget:

R 26,550,216

Exp: R 25,483,869

Incomplete chalets and restaurant due to Contractual disputes with the Implementing Agent whose contract lapsed.

R25,807,207.29

 

3

Ngove

Budget:

R 20,133,951

Exp: R 19,993,013

Some chalets not completed due to budget depletion.

R29,988,483.30

 

4

Tisane

Budget:

R 18,810,000

Exp: R 18,299,799

Incomplete chalets due to budget depletion

R27,463,083.70

 

5

VhaTsonga

Budget:

R 9,185,000

Exp: R 9,068,064

Incomplete rondavels and poor workmanship and budget depletion.

Contractor not yet appointed

NC

1

Kamiesburg

Budget:

R 5,100,000

Exp: R 4,815,074

Incomplete ablution facilities, campsite and chalets due to budget depletion.

Contractor not yet appointed

 

2

Platfontein

Budget:

R 32,206,320

Exp: R 32,072,057

 

Chalets and kitchen completed. Structural defects post completion due in part to geotechnical issues and drainage.

Contractor not yet appointed

NW

1

Manyane Lodge

Budget:

R 48,465,113

Exp: R 47,884,114

Incomplete restaurant. Conference centre not done. Damages on the completed chalets from a fire and vandalism. And budget depletion.

Contractor not yet appointed

 

2

Lehurutshe Bird and Trophy Hunting

Budget:

R 2,827,500

Exp: R 2,809,808

Completed, not ready to be handed over due to lack of Occupation Certificate .

Contractor not yet appointed

(d) Measures taken to mitigate such issues in future tourism related contracts

I have been informed that the Department has aligned its processes to the Framework for Infrastructure Delivery and Procurement Management (FIPDM), and also partnered with the Development Bank of South Africa (DBSA) which has requisite built environment capacity and is assisting the Department with the following:

a) Provision of infrastructure delivery, including planning, design and construction through a multi-disciplinary team of professionals and technical specialists and

b) Exercising effective project controls, monitoring and reporting in line with applicable norms and standards.

c) I have met with DBSA to discuss the poor performance and advised the Department to establish a project management unit to conduct oversight.

 