Question NW2531 to the Minister of Tourism

Share this page:

17 July 2015 - NW2531

Profile picture: Whitfield, Mr AG

Whitfield, Mr AG to ask the Minister of Tourism

(1)Whether, in view of the lack of project management skills and controls, poor workmanship and in some cases no value for money associated with the implementation of the Expanded Public Works Programme projects in the tourism industry, his department has devised a plan to complete the poorly implemented projects; if not, why not; if so, what are the relevant details;

Reply:

  1. Yes, forensic investigations were conducted in relation to non-compliance with the contractual agreements and suspected mismanagement of funds by project implementers. The department has decided on legal recourse in such cases. Where projects could not be completed due to cost escalations related to the changes in the built environment, the department will provide support for completion of such facilities based on availability of funds.

Page 2

  1. Yes, the department has undertaken a review of the Social Responsibility Implementation’s (SRI) planning, implementation, monitoring and reporting processes in relation to infrastructure projects to ensure closer alignment with the built environment requirements. SRI also undertakes continuous improvement based on annual audits and monitoring of project implementation.

(3) No, the department did not revise the method of appointment of project implementers. The appointment of implementers is governed by the public finance management requirements as contained in the Public Finance Management Act and its regulations.

(4) Thirteen projects have been subjected to forensic auditing.