18 May 2022 - NW1406

Profile picture: Motsepe, Ms CCS

Motsepe, Ms CCS to ask the Minister of Human Settlements

(1)What (a) are the reasons that the Reconstruction and Development Project which was initiated by her department in 2009-10 financial year at Tiyani and/or Magoro Village in the Collins Chabane Local Municipality has been abandoned and (b) total amount of the allocated budget was spent by her department?

Reply:

1. (a) The total number of units allocated to Tiyani/Magoro Village in Collins Chabane Local Municipality was 77. The number of units completed is 76 and the remaining one unit is at a wall plate level. The contractor is currently at a final stage for completion and the project is not abandoned.

(b) The total budget allocated was R 6,366,849.92. The total budget spent by the Department is R 6,317,529.47. The remaining amount of R49,320.45 will be paid after the completion of the outstanding unit.