Question NW756 to the Minister of Water and Sanitation

Share this page:

05 May 2022 - NW756

Profile picture: Komane, Ms RN

Komane, Ms RN to ask the Minister of Water and Sanitation

Which measures has his department put in place to ensure that the residents of Makolokwe in Rustenburg Local Municipality have clean, drinkable water, as they have been without such water since last year?

Reply:

The Department of Water and Sanitation has allocated R15 million, through Water Services Infrastructure Grant (WSIG), for the Makolokwe Water Supply Project. This project is intended to connect to the water supply pipeline from Glencor Mines, which is still under negotiation.

The design of the pipeline and connection is completed, and tender document is ready for the construction. The anticipate commencement of construction is May 2022, the projected completion date is August 2022.

---00O00---

Source file