What (a) is the new timeline for completing the Clanwilliam Dam project and (b) will the new cost be?
Reply:
a) The raising of Clanwilliam Dam project will be completed by April 2026 as per the current approved programme.
b) The revised cost is R 3 920 000 000 as per current project cost estimate.
NW833E