05 April 2022 - NW695

Profile picture: Basson, Mr LJ

Basson, Mr LJ to ask the Minister of Water and Sanitation

What (a) is the new timeline for completing the Clanwilliam Dam project and (b) will the new cost be?

Reply:

a)  The raising of Clanwilliam Dam project will be completed by April 2026 as per the current approved programme.

b) The revised cost is R 3 920 000 000 as per current project cost estimate.