Question NW139 to the Minister of Justice and Correctional Services

Share this page:

16 March 2022 - NW139

Profile picture: Horn, Mr W

Horn, Mr W to ask the Minister of Justice and Correctional Services

What is the status of all the infrastructure projects of his department aimed at (a) adding additional bed spaces to correctional facilities and (b) building of new correctional centres?

Reply:

a) Currently, DCS has one upgrade project in execution at Parys for the construction of additional bed spaces. This project is underway and scheduled for completion during the 2022/23 financial year. The project is implemented by the Development Bank of Southern Africa (DBSA). The construction is at 85% completion.

b) Building of new correctional centres can be summarised as follow:

Projects: Construction of new correctional centre

Status

Burgersdorp

Tender advertised for the appointment of a construction contractor. Bid Adjudication stage with DPWI. Construction contractor appointment scheduled for the 2022/2023 financial year.

Lichtenburg

Project in design stages. Site clearance finalised, Construction contractor appointment scheduled for the 2022/2023 financial year. The project is in the process to be adopted from the DPWI, due to delays during the planning and design stages.

Thohoyandou

Site clearance stage: Project deferred due to budget constraints.

Kirkwood

Site identified. The feasibility studies are 80% complete. Project deferred due to budget constraints.

Richards Bay

Feasibility study stage. Project deferred due to budget constraints.

Nigel

Appointment of consultants to conduct Environmental Impact Assessments finalised. Project deferred due to budget constraints.

Leeuwkop

Appointment of consultants to conduct Environmental Impact Assessments finalised. Project deferred due to budget constraints.

George

Project deferred due to budget constraints.

Voorberg

Project deferred due to budget constraints.

Klerksdorp

Feasibility study and site clearance processes finalised. Project deferred due to budget constraints.

Khayelisha

Project deferred due to budget constraints. Site identification report completed.

Bergville

Project deferred due to budget constraints. Site identification report was completed.

Potchefstroom

Project deferred due to budget constraints. Site clearance processes not initiated.

Losperfontein

Project deferred due to budget constraints. Site clearance processes not initiated.

Polokwane

Project deferred due to budget constraints. A Township Establishment was approved by the Municipality in 2011.

Port Shepstone

Site clearance outstanding.

Mouth Ayliff

Project deferred due to budget constraints. Site clearance processes not initiated.

Engcobo

Project deferred due to budget constraints. Site clearance processes not initiated.

Queenstown

Project deferred due to budget constraints. Site clearance processes not initiated.

East London

Project deferred due to budget constraints. Site clearance processes not initiated.

Durban

Project deferred due to budget constraints. Site clearance processes not initiated.

END